Location via proxy:   [ UP ]  
[Report a bug]   [Manage cookies]                

308

Download as pdf or txt
Download as pdf or txt
You are on page 1of 112
At a glance
Powered by AI
The document discusses foundation installation for overhead power lines, including different foundation types, design considerations, and installation methods.

The aim of the brochure is to provide an overview of the methods and procedures adopted for the installation of different types of support foundations for overhead power lines.

There are many factors which potentially influence the installation of overhead line support foundations including support type, foundation type, geotechnical conditions, and whether the installation is permanent or temporary.

308

FOUNDATION INSTALLATION

AN OVERVIEW

Working Group
B2.07

December 2006
Copyright 2006
Ownership of a CIGRE publication, whether in paper form or on electronic support only infers right of use for
personal purposes. Are prohibited, except if explicitly agreed by CIGRE, total or partial reproduction of the
publication for use other than personal and transfer to a third party; hence circulation on any intranet or other
company network is forbidden.
Disclaimer notice
CIGRE gives no warranty or assurance about the contents of this publication, nor does it accept any responsibility,
as to the accuracy or exhaustiveness of the information. All implied warranties and conditions are excluded to the
maximum extent permitted by law.
Study Committee B2 Overhead Lines

Working Group 07 Foundations

Foundation Installation An Overview

May 2006

C:\CIGRE\WG07\Foundation Installation\Section0_Final i May 2006


Study Committee B2 Overhead Lines

Working Group 07 Foundations

Foundation Installation An Overview

May 2006

During the preparation of this report, WG07 comprised the following members:

N R Cuer (Convenor), E O Connor (secretary), M B Buckley (IE), J P Chouteau (CA),


W Combrinck (SA), J Dufour (FR), E Dembicki (PL), A M DiGioia Jr (USA), A Haldar (CA),
M Leva (IT), G Paterson (AU), M Pietske (DE), J-P Sivertsen (NO) and B Zadnick (SI).

Keywords

Overhead line support, foundations, Foundation design, Foundation installation, Interaction


between design and installation, Quality assurance, Health and safety, Environmental
impacts and mitigation measures, Foundation costs, Method of measurement and payment.

C:\CIGRE\WG07\Foundation Installation\Section0_Final ii May 2006


Executive Summary

Introduction

Overhead line foundations are the interlinking component between the support and the in-
situ soil and/or rock. However, unlike the other major components of an overhead line, they
are constructed wholly or partly in-situ, in a natural medium whose characteristic properties
may vary between support locations and possibly between adjacent footings. Consequently,
both the design and the subsequent performance of the foundations, and hence to a degree
that of the complete overhead line, is significantly influenced by the methods and practices
used during the installation process.

Aim of the Brochure

The aim of the Brochure is to provide an overview of the methods and procedures adopted
for the installation of the different types of support foundations. To achieve this overall aim,
an extensive literature review has been undertaken to identify how the influences described
above interact with the installation process.

Factors influencing foundation installation

There are many factors which potentially influence the installation of overhead line support
foundations: support type, base size and applied loadings; foundation type; geotechnical
conditions; permanent or temporary installation; primary installation, refurbishment or
upgrading of existing foundations; environmental factors, e.g. topography; resources;
constraints due to environmental impact; health and safety requirements and quality
management requirements.

Although for convenience the design of overhead line support foundations has been
considered in Cigre technical brochure 206 [Cigr 2002], there should not be any artificial
boundaries between the design and installation process, i.e. the design and installation
activities should be seamless, with a continuous exchange of information between all parties.
In addition to the obvious interaction between the design and installation process, the
interaction with respect to: environmental constraints, health and safety, quality and resource
management, must all be taken into account and continuously evaluated throughout the
design and installation process.

The serious consequences of failing to verify the assumed geotechnical design parameters
during foundation installation are shown in Figure 1.

Reasons for Failure

< Failure due to a combination of circumstances:

< Tower failure precipitated by high Santa Ana wind


prior to commissioning of the line;
< Based on geology of line route the foundation
designer assumed cohesive soil and decided to use
drilled shaft foundation with an under-ream (bell) at
the base;
< No inspection undertaken during construction and no
one noticed the soil was granular;
< During concreting the side walls of the shaft
collapsed, especially at the bottom;
< Installation contractor did not measure quantity of
concrete poured, therefore no check against
theoretical volume of concrete.

Figure 1 Failure of a 500 kV Suspension Tower Drilled Shaft Foundation

C:\CIGRE\WG07\Foundation Installation\Section0_Final iii May 2006


Interaction with the design process

As previously stated, the foundation design process and the foundation installation activities
cannot be considered in isolation, but are mutually dependant on each other. Section 2 of the
Brochure considers how the foundation installation activities can have an adverse effect on
the design process, taking into consideration not only changes in the actual geotechnical
conditions, but also errors or mistakes during the actual foundation installation.

For the principal types of foundations considered, the site activities that are likely to affect the
foundation design can be summarised as: failure to recognise changes in the geotechnical
conditions, inappropriate installation, concreting and backfilling techniques, and variations in
foundation dimensions.

For each of the foundation types considered an interaction diagram and associated table
detailed the relationship between the installation activities and their potential effect on the
foundation design has been prepared. A typical interaction diagram for a helical screw
anchor foundation and associated table is shown in Figure 2.

Effect on foundation
Key Parameter Installation activities
design
4 Actual soil/rock Change in foundation
Soil/rock
properties or ground geotechnical design
properties
water level encountered may affect foundation
1 and/or
5 during foundation design strength and/
ground
excavation differs from or long term durability.
water level
G.L. design assumptions.
Failure to use correct
Installation installation torque and Reduction in anchor
2
torque maintain constant design strength.
2
6 rotational speed.
Possibly increase in
foundation design
3 Misalignment of the loading and/or
3 Alignment
anchor shaft. reduction in
1
foundation design
strength.
Torsional buckling
4 Downthrust Excessive downthrust.
failure of anchor shaft.
Foundation Incorrect anchor setting. Increased foundation
5
setting loading.
Changes in ground Reduction in
Ground
6 profile adjacent to foundation design
profile
foundation. strength.

Figure 2 Helical screw foundations interaction between installation and design

Foundation installation activities

Section 3 of the Brochure provides an overview of accepted good practice with respect to
foundation installation, such that the adverse effects can be eliminated or at least reduced to
a minimum. Foundation installation can be considered as a series of discreet interrelated
activities, which for convenience can be divided between the pre-site activities i.e. the
activities that are undertaken prior to the commencement of the contract foundation
installation and those undertaken as part of the main works. The pre-site activities including
the preparation of foundation installation drawings, the concrete mix design, the preliminary
foundation design tests and the preparation of the foundation installation criteria schedule
which lists the type of foundation to be installed for each support location.

Of particular importance is the concrete mix design, which must ensure that the fresh
concrete has the required workability, to enable a, dense, void-free concrete to be placed,
such that the hardened concrete has the required strength and durability for the intended
service life of the foundations. Further details of the factors to be considered in achieving
C:\CIGRE\WG07\Foundation Installation\Section0_Final iv May 2006
these aims are given in the Brochure, together with the effects of changing the mix
proportions on the properties of the concrete.

The main works activities encompass: setting out of the foundations, excavation including the
control of ground water, the installation of drilled shafts and piles, stub setting, concrete
production, delivery and placing, backfilling of the excavation, and site reinstatement.
Although details of all these activities are given in the Brochure, particular emphasis is
placed on the key activities, i.e. excavation, stub setting and concrete placing and
subsequent curing.

All excavations should be adequately supported on forming to ensure the stability of the
sides, prevent damage to the surrounding ground or adjacent structures and ensure the
safety of all personnel; a typical close sheeted excavation is shown in Figure 3.

To ensure the support structure can be erected without inducing additional stresses, the stub
steelwork should be accurately set within the permitted tolerance level; Figure 4 shows the
lower portion of a lattice steel tower utilized in setting the foundation stubs.

Of crucial importance in ensuring that the concrete achieves its intended service life is the
curing regime adopted after placing. The setting and hardening of cement depends on the
presence of water, drying out, if allowed to take place to soon, results in low strength and
porous concrete. The curing regime should ensure that: premature drying particularly due to
solar radiation or wind is prevented; rapid cooling does not occur in the first few days after
placing, the concrete is protected against low temperatures, high internal thermal gradients,
vibration and impacts do not occur.

Figure 3 - Foundation excavation Figure 4 Stub setting

Quality management

Overhead transmission line construction is undertaken effectively on a long linear site with
isolated areas of activity. Since the overhead line support foundations are installed in a
variable natural medium, quality management should form an integral part of the construction
activities. The common European Standard for the design of overhead lines requires that
>The systems and procedures, which the designer and/or installation contractor will use to
ensure that the project works comply with the project requirements, shall be defined in the
designer=s and/or installation contractor=s quality plan for the project works=. Section 4 of the
Brochure considers various aspects of the quality management activities undertaken during
the foundation design and installation, together with the associated Hold and Notification
points.
C:\CIGRE\WG07\Foundation Installation\Section0_Final v May 2006
For simplicity the quality management requirements have been divided between pre-project
foundation installation activities and project foundation installation activities. Pre-project
foundation installation activities include the foundation design process, the concrete mix
design, the quality auditing of proposed suppliers and/or subcontractors and, the installation
and full-scale testing of any test foundations. A diagrammatic representation of this process,
together with an indication of the documentation required and the corresponding hold and
notification points is shown in Figure 5.

Design Foundation Foundation test


Foundation
calculations drawings programme
Design

Suppliers Suppliers
Cement, Rebar,
QA/QC
Concrete,
etc.

Foundation
Installation &
Testing

Trial mix Concrete


Concrete mix
results specification
design
Foundation Test
results

Foundation Installation
Foundation Installation Method
Design Review criteria statement

Foundation
Key: Process or activity Design
Hold point

Document submission Design Notification point


calculations

Figure 5 Diagrammatic representation of pre-project foundation QA & QC


arrangements

Project foundation installation activities include setting out of the foundations, verification of
the foundation geotechnical design parameters, inspection prior to concreting, concrete
placing, concrete identity tests, foundation setting dimensions, foundation proof and integrity
tests.

While this section of the Brochure mainly concentrates on the Quality Assurance activities, it
is an inherent responsibility of the installation contractor to instigate his own internal quality
control procedures and verification methods.

Health and safety

Foundation installation can be a hazardous operation both to the site operatives and
members of the general public, if due care and attention is not paid to the health and safety
(H&S) aspects of the work. Consequentially, there is a need to consider H&S aspects of
foundation installation activities; since the H&S legislation varies between countries, the
information contained in Section 5 of the Brochure is indicative only and is based on current
UK practice.

Within this section of the Brochure consideration is given both to the initial design
assessments and on-site risk assessments, whereby the foundation design or the installation
process are reviewed for their inherent hazards and by a process of hierarchical risk control
the risks are eliminated or at least reduced to an acceptable level. Preparation of health and
safety plans both at the pre-tender and construction phases are also considered, together
with the associated method statements and checklists.

The foundation designers should apply a hierarchy of risk control, i.e. the designers need to
C:\CIGRE\WG07\Foundation Installation\Section0_Final vi May 2006
identify the hazards inherent in undertaking the construction work and where possible alter
the design to eliminate them. If the hazards cannot be removed by design changes, the
designers should minimise the risks and provide information about the risks that remain.
Information regarding these residual risks is then contained in the pre-tender health and
safety plan. Possible mitigation measures considered are the use of alternative foundation
types, which require smaller and shallower excavations and the use of driven piles on
brownfield (contaminated) sites.

Good health and safety practices can be summarised as: the adoption of good working
practices; provision of adequately trained and motivated site operatives; ensuring that design
assessments and pre-tender health and safety plans concentrate on the hazardous
operations that a competent contractor could not foresee; that for hazardous operations site
specific risk assessments and method statements are prepared; the site is kept tidy, simple
checklists are used and adequate inspections are undertaken; there is effective
communication between all parties to the work and that timely action is taken if the
assumptions made in the design regarding the ground conditions are not found on-site.

Environmental impacts and mitigation measures

Section 6 of the Brochure deals specifically with the environmental impacts and the
associated mitigation measures related to installation of support foundations and the affect of
the access route construction on the environment.

Potential environmental impacts, which may occur, during access construction and
foundation installation activities include: increase in traffic on local roads; impact of access
tracks on the environment; disturbance of land and vegetation management; vegetation and
tree removal; noise, dust and vibrational pollution; soil erosion and pollution of water courses;
disturbance to birds and fauna and the dispersion of contaminated soil or ground water.

While it is not possible to completely remove all of the potential impacts, described above, it
is possible to at least reduce their impact and therefore to a degree, the publics and/or
landowners perception of the affect of overhead transmission line construction on the
environment.

Irrespective of whether it is new build, the refurbishment and/or upgrading of existing


overhead transmission lines an initial desk-top study and site assessments should be
undertaken to establish which of the support sites and associated access tracks are likely to
be affected by environmental and/or archaeological constraints.

Support sites, which are located in designated areas of importance under international
conventions or by national regulations, will require specific studies to be undertaken in
consultation with the appropriate statutory bodies. Once the studies outlined above have
been completed and depending on their outcome in terms of the environmental and
archaeological impacts, it may be necessary to prepare a site environmental plan, detailing
the mitigation measures required.

With regards to the actual design of the foundation, mention has been previously made of the
use of alternative foundation types, which may lessen the overall environmental impact.
Where foundations are located in contaminated sites, there will be a need to control the
migration of pollutants to the surrounding area and particularly aquifers, especially when
piled foundations are being considered.

As alternative to the use of existing access tracks consideration should also be given to the
use of special temporary access systems, i.e. aluminium track way panels or temporary
stone roads, (see Figure 6.1). Other potential methods of alleviating the environmental
impact are the use helicopters to transport materials, equipment and site operatives, (see
Figure 6.2). The use of helicopters may be a condition of the planning consent of the
overhead transmission line route, if the route crosses sensitive ecological areas or as an
economic alternative to the construction of long and expensive access tracks from the
C:\CIGRE\WG07\Foundation Installation\Section0_Final vii May 2006
nearest public highway.

Figure 6.1 - Aluminium track way panels Figure 6.2 Transportation of concrete
by helicopter

Foundation costs

The support foundations represents between 14 and 23 percent of the total cost of an
overhead line, with an average value of 19 percent [Cigr 1991]. This average value remains
reasonably constant and is not affected by changes in the transmission line voltage, circuit
configuration and support type. Similarly, the percentage breakdown between material
supply and installation also remains reasonably constant at 65 percent to 35 percent.

The factors which have the greatest influence on the foundation cost are: the support type,
the magnitude of the applied loadings, the foundation type and the geotechnical conditions.

With respect to support foundation costs there are no universal rules that can be developed
and this to a degree is a reflection of the difference in costs in relation to different foundation
types which in itself is a reflection of the variability of the ground conditions. Other factors
which may influence the selection of foundation type and hence its cost are: environmental,
resource limitations and health and safety requirements.

The price or rate for the foundation will in addition to the factors described above, depend on
the method of measurement and payment plus the allocation of risk between the client and
the installation contractor. Details of typical methods of measurement and payment are given
in the section 7 of the Brochure.

Conclusions

The installation of overhead line support foundations can not be viewed in isolation but must
be considered as on going process, with a seamless transition between design and
construction, if the adverse effects outlined in section 2 of this Brochure are to be avoided.
Similarly, to ensure that the intended service life is achieved, quality management
requirements must also be integrated within the installation process. Since foundation
installation is also hazardous both to site operatives and the environment, mitigation
measures must also be considered from the outset of the project.
C:\CIGRE\WG07\Foundation Installation\Section0_Final viii May 2006
References

Cigre [1991], >An International Survey of Component Costs of Overhead Transmission Lines=,
Cigre, Electra No.137, August 1991.

Cigre [2002], Technical Brochure No.206 >The Design of Transmission Line Support
Foundations - An Overview=, Cigre WG 22-07.

C:\CIGRE\WG07\Foundation Installation\Section0_Final ix May 2006


Foundation Installation An Overview

Contents

1 Introduction 1
1.1 General 1.1
1.2 Aims and Objectives 1.1
1.3 Interaction 1.2
1.4 Foundation Categories 1.4
1.4.1 General 1.4
1.4.2 Applied foundation loadings 1.6
1.5 Foundation types 1.6
1.5.1 Separate foundations 1.6
1.5.2 Anchor foundations 1.10
1.5.3 Compact foundations 1.11
1.6 Liability 1.12

2 Interaction with the Design Process 2


2.1 General 2.1
2.2 Separate foundations 2.1
2.2.1 Spread footings 2.1
2.2.2 Drilled shaft foundations 2.3
2.2.3 Piled foundations 2.6
2.3 Anchor foundations 2.8
2.3.1 Micropiles and ground anchors 2.8
2.3.2 Block anchors 2.9
2.3.3 Helical screw anchors 2.9
2.3.4 Deadman and spread plate anchors 2.10
2.4 Compact foundations 2.11
2.4.1 General 2.11
2.4.2 Direct embedment 2.11
2.5 Conclusion 2.11

3 Foundation Installation Activities 3


3.1 General 3.1
3.2 Pre-site activities 3.2
3.2.1 General 3.2
3.2.2 Foundation installation drawings 3.2
3.2.3 Concrete mix design 3.4
3.2.4 Preliminary foundation design tests 3.6
3.2.5 Foundation installation criteria 3.7
3.3 Setting out 3.7
3.4 Excavation 3.8
3.5 Reinforcement 3.10
3.6 Drilled shaft and piled foundations 3.12
3.7 Micropile and ground anchor installation 3.12
3.8 Stub setting 3.13
3.9 Concrete production and delivery 3.14
3.9.1 General 3.14
3.9.2 Concrete production 3.14
3.9.3 Concrete transportation 3.15
3.9.4 Concrete placing 3.15
3.9.5 Construction joints 3.17
3.9.6 Compaction 3.17
3.9.7 Curing 3.17
3.9.8 Working in cold weather 3.18
3.9.9 Working in hot weather 3.19
3.10 Backfilling 3.19
3.11 Protective coatings 3.20
3.12 Installation activities 3.20
3.13 Summary 3.21
Annex 3A Foundation Installation - Photographs illustrating different aspect of the 3A.1
foundation installation process Figures 3A.1 to 3A.13

C:\CIGRE\WG07\Foundation Installation\Section0_Final x May 2006


4 Quality Assurance and Quality Control 4
4.1 General 4.1
4.2 Quality control 4.2
4.3 Pre-project foundation installation 4.2
4.3.1 General 4.2
4.3.2 Suppliers 4.2
4.3.3 Concrete mix design 4.3
4.3.4 Concrete specification 4.4
4.3.5 Foundation design tests 4.4
4.3.6 Foundation installation criteria and method statement 4.4
4.4 Project foundation installation 4.5
4.4.1 General 4.5
4.4.2 Setting out 4.6
4.4.3 Verification of foundation design soil /rock parameters 4.6
4.4.4 Inspection prior to concreting and site bending of reinforcement 4.8
4.4.5 Concrete placing 4.9
4.4.6 Concrete identity tests 4.9
4.4.7 Concrete returns 4.10
4.4.8 Concrete curing compounds 4.10
4.4.9 Imported backfill 4.10
4.4.10 Foundation setting dimensions 4.11
4.4.11 Foundation proof and identity tests 4.11
4.4.12 Early age concrete strength assessment 4.11
4.5 Foundation installation records 4.12
4.6 Final records 4.12
4.7 Conclusions 4.13
Annex 4A Verification of rock suitability 4A.1

5 Health and Safety 5


5.1 General 5.1
5.2 Design assessment 5.2
5.3 Health and safety plan 5.2
5.3.1 General 5.2
5.3.2 Pre-tender health and safety plan 5.2
5.3.3 Construction phase health and safety plan 5.3
5.4 Method statements and risk assessments 5.3
5.4.1 Risk assessments 5.3
5.4.2 Method statements 5.5
5.4.3 Supporting calculations 5.6
5.5 Site access 5.6
5.6 Foundation installation 5.6
5.6.1 General 5.6
5.6.2 Excavation health and safety checklist 5.6
5.7 Summary 5.8

6 Environmental Impact and Mitigation 6


6.1 General 6.1
6.2 Environmental impact 6.1
6.3 Environmental mitigation 6.2
6.3.1 Design phase 6.2
6.3.2 Site access 6.3
6.3.3 Helicopters 6.5
6.3.4 Foundation installation 6.6
6.3.5 Site reinstatement 6.7
6.4 Conclusions 6.7

7 Foundation Costs 7
7.1 General 7.1
7.2 Allocation of risk 7.1
7.3 Method of measurement and payment 7.2
7.4 Conclusions 7.3

8 Summary 8
8.1 General 8.1
8.2 Foundation design 8.2
C:\CIGRE\WG07\Foundation Installation\Section0_Final xi May 2006
8.3 Interaction with the design process 8.2
8.4 Foundation installation 8.2
8.5 Quality management 8.3
8.6 Health and safety 8.3
8.7 Environmental impact and mitigation 8.3
8.8 Foundation costs 8.4
8.9 Conclusions 8.5

9 Bibliography 9

Acknowledgements:

Acknowledgements are given to the Danish representative of SC B2 and the Convenor of


WG06, for their time in reviewing this report and for helpful comments and suggestions.

Acknowledgements are also are given to the following organisations:

Westpile Ltd. for permission to reproduce Figure 1.7;

NorPower Limited for permission to reproduce Figures 3.5, 3.9 and 3.11.

AMEC Power Ltd. for permission to reproduce Figures 3A.1, 3A.2 and 3A.3;

Eve Transmission for permission to reproduce Figure 3A.4;

C:\CIGRE\WG07\Foundation Installation\Section0_Final xii May 2006


1 Introduction

1.1 General

Overhead line foundations are the interlinking component between the support and the in-
situ soil and/or rock. However, unlike the other major components of an overhead line, they
are constructed wholly or partly in-situ, in a natural medium whose characteristic properties
may vary between support locations and possibly between adjacent footings. Consequently,
both the design and the subsequent performance of the foundations, and hence to a degree
that of the complete overhead line, is significantly influenced by the methods and practices
used during the installation process.

This report is a guide to the methods and procedures adopted for the installation of the
common types of overhead line support foundations used in practice.

There are many factors which potentially influence the installation of overhead line support
foundations:

< Support type, base size or diameter and applied loadings;


< Foundation type, e.g. drilled shaft, pad and chimney, direct embedment, steel grillages,
etc.;
< Geotechnical conditions, e.g. soil or rock type, ground water level, etc.;
< Permanent or temporary installation;
< Primary installation, refurbishment or upgrading of existing foundations;
< Environmental, e.g. topography, climatic, contamination, etc.;
< Resources, e.g. foundation materials, labour, construction plant, programme and financial;
< Constraints, e.g. environmental impact, client requirements, third parties with respect to
access, use of the surrounding land, etc.;
< Health and safety requirements;
< Quality management requirements.

The interaction between the primary influences, i.e. design, installation, environmental,
resources, quality and health and safety, is discussed further in section 1.3 of this report.

1.2 Aims and Objectives

The aim of this report is to provide a guide/overview of the methods and procedures adopted
for the installation/construction of the different types of overhead line support foundations. To
achieve this overall aim, an extensive literature review has been undertaken to identify how
the influences described in Section 1.1 of this report interact with the installation process.

Section 2 of this report considers the influence of the installation process on the design of the
foundation, i.e. how changes in the design geotechnical conditions, use of inappropriate
installation techniques or mistakes during construction can adversely effect the foundation
design strength and/or the long term durability of the foundation and hence its design life.

The actual installation process, e.g. site access, setting out, excavation, concreting,
backfilling, etc., for various types of foundation is discussed in Section 3, while Section 4
considers the associated quality assurance issues including the quality control test
requirements both on the foundations constituent materials and the complete foundation.

Section 5 of the report considers the health and safety issues related to the foundation
installation process
C:\Cigre\WG07\FoundationInstallation\Section1_Final 1.1 May 2006
The environmental impacts of the foundation installation process together with possible
mitigation measures are discussed in Section 6; while, Section 7 provides a brief review of
the relative cost of the foundation and the associated foundation price and the factors which
influence them. An overall summary of the report is given in Section 8 and Section 9
contains a comprehensive bibliography.

For details of the life cycle assessment for overhead line foundations, reference should be
made to Cigr Technical Brochure No. 265 [Cigr 2004].

1.3 Interaction

Although for convenience the design and installation of overhead line support foundations
have been considered in two separate Cigre technical brochures, there should not be any
artificial boundaries between the design and installation process, i.e. the design and
installation activities should be seamless, with a continuous exchange of information
between all parties, e.g. the client, the foundation designer and the installation contractor. In
addition to the obvious interaction between the design and installation process, the
interaction with respect to: environmental constraints, site access, health and safety, quality
and resource management, must all be taken into account and continuously evaluated
throughout the design and installation process. The overall interaction is shown
diagrammatically in Figure 1.1, while a detailed diagrammatic representation of the
foundation design and installation process is shown in Figure 1.2.

Design Resources

Installation Quality

Environment Health & Safety

Figure 1.1 - Interaction Process

As stated above, good communications between the respective parties to contract, i.e. the
client, the clients representatives, the foundation designers and the installation contractor
form an essential part of the overall design and installation process and will have a marked
influence on the successful outcome of the project, in terms of quality, safety and the
environmental impact.

The client and/or his representatives should ensure that their technical requirements are
clearly stated in the specification and that for any work on existing support foundations the
existing foundation drawings, calculations and associated health and safety information (pre-
tender health and safety plan) are made available at the earliest opportunity to both the
foundation designers and the installation contractor.

The foundation designers should ensure that all the information used in the design and
especially any assumptions made regarding the installation contractors method of working
are made available to the client, the clients representative and the foundation installation
contractor. The information should include the foundation design calculations, installation
drawings, the geotechnical report and the initial design risk assessment.
C:\Cigre\WG07\FoundationInstallation\Section1_Final 1.2 May 2006
The foundation installation contractor should ensure that all the appropriate information is
considered in the preparation of his construction health and safety plan, site risk assessment
and proposed foundation installation method statements. Critically, the foundation installation
contractors site staff and operatives should ensure that if there are any changes in the
ground conditions from those assumed in the foundation design, e.g. variations in ground
water level or soil properties, the foundation designers are immediately informed and, if
necessary, work on-site suspended until a reassessment of the design has been made and,
if appropriate, a revision to the method statement undertaken.

The serious consequences of failing to verify the assumed geotechnical design parameters
during foundation installation are shown in Figure 1.3; which emphasis the need for effective
communications between the foundation designer and the installation contractor.

For specific details of the foundation design process, reference should be made to Cigr
Technical Brochure No.206 [Cigr 2002].

Geotechnical Support type Customer Programme &


Conditions Applied loadings, requirements Budget
Base size, etc. Technical, Q.A.
Soil/rock type,
G.W. level, etc.

Labour &
plant resources

Material resources

Foundation
design

Foundation
Third party Access & site Material Plant & labour
installation
constraints requirements quantities resources
drawings

Installation
Access & site Health & safety
Method
development requirements
statement
Environmental
constraints &
mitigation
measures
Foundation Q.C. & Q.A.
installation requirements

Foundation
tests

Site
reinstatement

Figure 1.2 Diagrammatic representation of Foundation Design / Installation Process

C:\Cigre\WG07\FoundationInstallation\Section1_Final 1.3 May 2006


Figure 1.3 Failure of a 500 kV Suspension Tower Drilled Shaft Foundation

< Tower failure precipitated by high Santa Ana wind prior to


Failure due to a combination commissioning of the line;
of circumstances: < Based on geology of line route the foundation designer
assumed cohesive soil and decided to use drilled shaft
foundation with an under-ream (bell) at the base;
< No inspection undertaken during construction and no one
noticed the soil was granular;
< During concreting the side walls of the shaft collapsed,
especially at the bottom;
< Installation contractor did not measure quantity of
concrete poured, therefore no check against theoretical
volume of concrete.

1.4 Foundation categories

1.4.1 General

For simplicity three basic categories of foundation are considered in this report, i.e. spread,
anchor and compact foundations. The use of any particular category of foundation, and
specifically an individual foundation type, will depend to a degree on both the support type
and the geotechnical conditions present. This subsection of the report considers the
relationship between the support type and foundation category, and between the foundation
type and the geotechnical conditions: the geotechnical conditions influencing both the
foundation design and the foundation installation. A diagrammatic representation depicting
the relationships between the support type, the basic foundation category, the foundation
type and the geotechnical conditions, is shown in Figure 1.4.

C:\Cigre\WG07\FoundationInstallation\Section1_Final 1.4 May 2006


Support Narrow Base Lattice Towers H - Frames Broad Base Lattice Towers Guyed Towers
Type Single Poles

Predominant Moment Moment Uplift / Compression Compression or Uplift


Foundation Uplift / Compression
Load Mast Base
Uplift / Compression
Weak Soil

Principal
Foundation COMPACT SEPARATE ANCHOR

C:\Cigre\WG07\FoundationInstallation\Section1_Final
Category
Uplift Foundations

1.5
Foundation
Monoblock Drilled Shaft Direct Raft Pad or Pyramid Steel Drilled Helical Screw
Types
Embedded & Chimney Grillage Shaft
(Normal soil)
Pole

Ground Anchor Dead


Men

Foundation
Pile Raft
Types
(Weak soil)

Displacement Non-Displacement

Figure 1.4 Diagrammatic Representation of Interrelationship between Support Type and Principal Foundation Category

May 2006
Note: Weak Soil defined as soil with an SPT value of less than 10 blows per 300 mm, or an undrained shear strength of less than 35 kN/m 2
1.4.2 Applied foundation loadings

Prior to describing the various foundation types, a resume of the principal support types and
their primary applied foundation loadings is given below:

a) Single poles and narrow base lattice towers


The foundation loads for single poles and narrow base lattice towers with compact
foundations consist of overturning moments in association with relatively small horizontal,
vertical and torsional forces.

b) HFrame supports
HFrame supports are basically structurally indeterminate. The foundation loads may be
determined either by making assumptions that result in a structurally determinate structure,
or by using computerised stiffness matrix methods. The foundation loads for H-frame
supports consist of overturning moments in association with relatively small horizontal,
vertical forces and torsional moments. If the connection between the supports and
foundations are designed as pins or universal joints, theoretically, the moments acting upon
the foundations will be zero.

c) Broad base lattice towers


Lattice tower foundation loads consist principally of vertical uplift (tension) or compression
forces and associated horizontal shears. For intermediate and angle towers with small
angles of deviation, the vertical loads may either be in tension or compression. While, for
angle towers with large angles of deviation and terminal towers under normal climatic
loadings, two legs will normally be in uplift with the other two legs in compression. Under all
loading combinations, the distribution of horizontal forces between the individual footings will
vary, depending on the bracing arrangement of the tower.

d) Externally guyed supports


For all types of externally guyed supports, the guy anchor will be in uplift, while the mast
foundations will be in compression with relatively small horizontal forces.

1.5 Foundation types

1.5.1 Separate foundations

Separate foundations may be defined as those specifically designed to withstand the loads
transmitted by each leg of a support. Generally, separate foundations are used for lattice
towers or H-frame structures when the face width exceeds 3 m, provided that the
geotechnical conditions are suitable, or where there are no specific requirements to limit the
differential settlement between adjacent foundations. The connection between the leg of the
support and the foundation is normally provided by stubs encased in the foundations or by
the use of anchor bolts.

Under the classification separate, the following types of foundations have been considered:

< spread footings;


< drilled shafts;
< piles.

a) Spread footings
Spread footings considered in this report are: concrete pad and chimney foundations
including stepped block foundations, concrete pyramid and chimney including normal non
reinforced concrete pyramids, shallow reinforced pyramids and pyramids with extended

C:\Cigre\WG07\FoundationInstallation\Section1_Final 1.6 May 2006


pads, and steel grillage foundations. A diagrammatic representation of the various types of
spread footings is shown in Figure 1.5 and a typical grillage foundation in Figure 1.6.

G.L. G.L. G.L.

Upper
Excavation pad if
line for required Included Extended
undercut angle 45 Pad
- 70 deg.

Pad and Chimney Stepped Block Pyramid and Chimney


(a) (b) (c)

G.L. G.L. G.L.

Shear
Key

Included Grillage
angle Bearers
25 deg.

Braced Tretrapod Single Leg


Shallow Pyramid and Chimney Steel grillage
(d) (e)
Figure 1.5 Spread footings

Figure 1.6 Typical grillage foundations

C:\Cigre\WG07\FoundationInstallation\Section1_Final 1.7 May 2006


b) Drilled shaft foundations
A drilled shaft or augered foundation is essentially a cylindrical excavation formed by a power
auger and subsequently filled with reinforced concrete. The shaft may be straight or the base
may be enlarged by under-reaming or belling. Although this type of foundation is effectively a
bored pile, the American Concrete Institute [ACI 1993] defines them as drilled shafts (piers)
when their diameter is greater than 760 mm.

For broad base lattice towers drilled shafts may be installed vertically or inclined along the
hip slope of the leg as shown in Figure 1.7. The shaft shear load is greatly reduced for drilled
shafts inclined along the tower leg hip slope. For H-frame supports the shaft would be
installed vertically.

Under-reaming of the base can be undertaken in non-caving soils to increase both the
bearing and uplift capacities of the drilled shaft.

Leg
Hip slope

G.L.
G.L.

Under-ream
(Bell)

Vertical Inclined

Figure 1.7 - Drilled shaft foundations

c) Piled foundations
Pile foundations can comprise either a single pile or a group of piles connected at or just
below ground level by a reinforced concrete cap, i.e. a piled foundation.

Piles may be classified as driven (displacement) where the soil is moved radially as the pile
enters the ground, or bored (non-displacement) when little disturbance is caused to the soil
as the pile is installed. Driven displacement piles may comprise a totally preformed section
from steel, pre-cast concrete or timber. Alternatively, where hollow steel or pre-cast concrete
sections are used these are normally subsequently filled with concrete, or for steel H-
sections post grouted. Non-displacement piles are cast-in-situ using either concrete or grout;
the pile section is formed by boring or drilling.

Typical driven pre-cast concrete and steel tube piles, and bored and continuous flight auger
piles are shown in Figure 1.8.

Micropiles are defined as non-displacement piles with a diameter of 300 mm or less and for
the purpose of this report have been included within the section related to anchors and
anchor foundations.

C:\Cigre\WG07\FoundationInstallation\Section1_Final 1.8 May 2006


Driven pre-cast concrete piles Driven steel tube piles

Bored piles Continuous flight auger piles

Figure 1.8 Typical pile types

C:\Cigre\WG07\FoundationInstallation\Section1_Final 1.9 May 2006


1.5.2 Anchor foundations

Anchors may be used to provide tension resistance for guys of any type of guyed support
and to provide additional uplift resistance to spread footing type foundations in which case
various types of anchors can be used.

a) Ground anchors
Ground anchors and micropiles consist of a steel tendon (either reinforcing steel, wire or
steel cable) placed into a hole drilled into rock or soil which is subsequently filled with a
cement or resin based grout usually under pressure (Figure 1.9a)

Ground anchors can be grouped together in an array and connected by a concrete cap at or
below ground level to form a spread footing anchor foundation (Figure 1.9b).

b) Block anchors
Block anchors comprise a pad and chimney spread type footing whereby the concrete is cast
directly against the face of the excavation possibly with an undercut at the base (Figure
1.9c).

G.L. G.L. G.L.


Soil

Anchor
Ground Rock
Tendon Anchors or
Mirco-piles
Grout

Spread Footing type Foundation


Ground Anchor using ground anchors Block Anchor Foundation
(1.9a) (1.9b) (1.9c)

G.L. G.L. G.L.

Anchor rod

Helical Screw Anchor Helical Srew Anchor Foundation Deadman / Spread Plate Anchor
(1.9d) (1.9e) (1.9f)

Figure 1.7 Anchor foundations

c) Helical screw anchors


A helical screw anchor comprises a steel shaft which is screwed into the ground (Figure
1.9d). Helical screw anchors can also be connected together at or above ground level by a
steel grillage or concrete cap to form a helical screw anchor foundation (Figure 1.9e).

C:\Cigre\WG07\FoundationInstallation\Section1_Final 1.10 May 2006


d) Deadman/Spread anchors
Typically these anchors consist of a timber baulk, a pre-cast concrete block/pad or deformed
steel plate installed in the ground by excavating a trench or augering a hole, placing the
anchor against undisturbed soil and backfilling the excavation (Figure 1.9f). The anchor rod
may be installed by cutting a narrow trench or drilling a small diameter hole.

1.5.3 Compact foundations

Compact foundations have been defined as those specifically designed to resist the applied
overturning moment from the support. Generally this type of foundation is used for single
poles, for lattice towers with narrow base widths (less than 3 m) and for H-frame supports
with a predominant moment loading. In addition, they may be used to replace separate
footings for wide base lattice towers when there is a specific need to limit the differential
settlement between adjacent footings, i.e. raft foundations. The connection between the
support and the foundation is normally provided by anchor bolts, by a section of the pole
directly encased in the foundation, or by stubs encased in the foundation.

Under the classification of compact, the following types of foundations have been
considered: Monoblock, Drilled shaft, Direct Embedded Pole, Raft and Piled. Both drilled
shaft and piled foundations for compact foundations are similar to those described for
separate foundations.

a) Monoblocks
Concrete monoblock foundations in their simplest form, comprises a cast-in-situ reinforced
concrete block. A typical one for a single pole is shown in Figure 1.10a. A monoblock
foundation for a narrow base width tower is shown in Figure 1.10b; alternatively they can be
cast in-situ using prefabricated formwork or pre-cast, Figure 1.10c.

G.L G.L G.L

Block cast Block cast Backfill Precast Block


in-situ in-situ

Pole Lattice Tower Lattice Tower


(1.10a) (1.10b) (1.10c)

Figure 1.10 Monoblock foundations

b) Direct embedment
Originally used for the direct embedment of relatively lightly loaded wood poles, this type of
foundation is now also used for steel and concrete poles subjected to high overturning
moments. However, for steel and concrete poles the size of the excavation, the type of
backfill material, e.g. imported granular or weak mix concrete and the compaction of the
backfill material are carefully controlled.

c) Raft foundations
Under the general classification of raft foundations, the following types of foundations have
been considered: concrete raft foundations and steel grillage raft foundations.

C:\Cigre\WG07\FoundationInstallation\Section1_Final 1.11 May 2006


Concrete raft foundations in their simplest form comprise a cast-in-situ reinforced concrete
pad at or below ground level as shown in Figure 1.11a and Figure 1.12.

Steel grillage raft foundations as shown in Figure 1.11b, are normally only used for narrow
base lattice steel towers, and basically consist of steel angle section grillage members which
are connected to two steel angle or channel section bearers orientated at 90E to the grillage
members. Depending on the fabrication process used, the grillage members are either bolted
to, or slotted in the bearers. In the latter case it is common practice to spot weld the grillage
members to the bearers prior to installation. The connection of the grillage to the support is
by means of an extension of the tower body.

G.L. G.L.
Backfill

Backfill

Concrete Steel Grillage


(1.11a) (1.11b)
Figure 1.11 Raft foundations

Figure 1.12 Reinforced concrete raft (slab) foundation for a 110 kV lattice steel tower

1.6 Liability

This report is not intended to be a standard nor a textbook but only a guide to good practice.
The material presented has been collected from a number of sources and is based on
recognized engineering practices. The information contained in this report should not be
used without first securing competent advice with respect to its suitability and application for
any general or specific use. This is especially important in respect of complying with any
statutory requirements relating to health and safety and/or the environment.
C:\Cigre\WG07\FoundationInstallation\Section1_Final 1.12 May 2006
2 Interaction with the Design Process

2.1 General

The foundation design process and the foundation installation activities cannot be considered
in isolation, but are mutually dependant on each other. This section of the report considers
how the foundation installation activities can have an adverse effect on the design process,
taking into consideration not only changes in the actual geotechnical conditions, but also
errors or mistakes during the actual foundation installation.

Although environmental and third party constraints and the effect of resource constraints can
influence both the foundation design process and the foundation installation activities, these
have been dealt with separately.

For simplicity, the interaction has been considered for each major type of foundation
separately.

2.2 Separate foundations

2.2.1 Spread footings

Spread footings as previously stated in section 1.5; include concrete pad and chimney
foundations, concrete pyramid foundations and steel grillage foundations. To illustrate how
the foundation installation activities interact with the foundation design process a composite
concrete pad/pyramid and chimney foundation is shown in Figure 2.1.

9 4

G.L.

Stub
5A
Backfill

Excavation Reinforcement
Support
3B
6
1

3
5 Concrete

8 6 3A

6A Blinding
concrete

2 2A 7

Figure 2.1 Spread foundations interaction diagram

Detailed in Table 2.1 are the relevant construction activities and the affect they have on the
C:\CIGRE\WG07\Foundation Installation\Section2_Final 2.1 May 2006
overall foundation design:

Table 2.1 Interaction installation activities and foundation design Spread footings

Possible changes during Adverse effect on foundation


Key Parameter
installation activities design
Actual soil/rock properties or Changes in foundation
Soil/rock properties
ground water level encountered geotechnical design may affect
1 and/or ground water
during foundation excavation foundation design strength and/
level
differs from design assumptions. or long term durability.
Failure to remove soft spots Possible reduction in
below setting level of foundation foundation design bearing
Soil/rock beneath base
2 or premature removal of bottom pressure and/or the cause of
of foundation
layer of cohesive soil prior to differential settlement of
placing blinding concrete. adjacent footings.
In cohesive soils possible
reduction in bearing capacity
due to softening of the soil. In
2A Blinding concrete Failure to place blinding concrete.
soils with high concentration of
sulfates or chlorides, reduction
in the long term durability.
Reduction in foundation design
uplift strength.
Backfill bulk density lower than
3 Backfill
assumed in design calculations. Reduction in foundation design
lateral resistance to shear
loads.
3A Undercut No undercut or reduced undercut. Reduction in foundation design
uplift strength.
Failure to remove excavation Change in design basis for
3B Excavation support
support. foundation uplift resistance.
Incorrect stub setting dimensions
4 Stub setting Increase in foundation loading.
or stub alignment.
Foundation dimensions smaller Reduction in foundation design
5 Foundation dimensions
than design values. strength.
Changes in ground profile Reduction in foundation design
5A Ground profile
adjacent to foundation uplift and shear strength.
Reinforcement cover less than
6 Reinforcement cover
specified.
6A Stub cover Stub cover less than specified.
Reduction in foundation design
7 Construction joint Inadequate construction joint.
strength and/or long term
Concrete strength, Reduced concrete strength and/or durability.
8 workability and poor workability insufficient
compaction compaction.
9 Concrete curing Inappropriate concrete curing.

In addition, to the parameter outlined in Table 2.1, the following additional considerations are
also applicable in respect of spread footings:

< Key 3 Backfill, failure to adequately compact the backfill may also result in either ponding
of rainwater above the foundation or a change in backfill densities from dry to partially or
fully saturated, both likely to result in a potential reduction in the foundation design
strength and /or long term durability;
< Key 3A Undercut, failure to provide an undercut, or failure to cast the foundation directly
against the side of the excavation for a specified height, will again alter the basic design
principles of the foundation uplift resistance;
< Key 5 and 6A Foundation dimensions and Stub cover, failure to install the foundation at
the correct depth could either result in the stub cleats being located in foundation chimney
C:\CIGRE\WG07\Foundation Installation\Section2_Final 2.2 May 2006
and not in pyramid/pad (as required) if the foundation is set too deep, or the stub may
project below the base of the foundation with insufficient punching shear resistance for the
cleats and without the required concrete cover to the embedded steel, if the foundation is
set shallower than required.
< With respect to spread foundations in rock, formed foundations, i.e. those cast in
formwork should not be used without additional anchoring to the rock, because under
uplift conditions there is effectively no shear resistance developed between the backfill
material and the sides of the rock excavation.
< Although not shown in the Figure 2.1, the failure to adequately restore any in-situ drainage
or, if appropriate, to improve the overall site drainage during the reinstatement activities
could lead to the foundation excavation acting as a sump, with the consequential
reduction in both the soil strength properties and the foundation strength.

Similar construction activities would also be applicable for both non-reinforced concrete
stepped block foundations and steel grillage foundations. For the former, key points 1, 2, 2A,
3, 3B, 4, 5, 5A, 6A, 7, 8 and 9 would apply, while for the latter, key points 1, 2, 3, 3B, 4 and
5A would apply and, if appropriate, the failure to provide a non-cohesive bedding layer.

Figure 2.2 Separate foundations poor compaction of concrete at the chimney


pyramid joint (Key 8)

2.2.2 Drilled Shaft foundations

Within the overall category of separate foundations are drilled shaft or augered foundations,
which essentially consist of cylindrical excavations with or without an under-ream (bell)
formed by a power auger and subsequently filled with reinforced concrete. To illustrate how
the foundation installation activities interact with the foundation design process a composite
drilled shaft (with and without an under-ream) is shown in Figure 2.3.

If short, relatively shallow, drilled shaft foundations are installed with the stub projecting to
the base of the foundation, then reference should be made to section 2.2.1 regarding the
location of the stub relative to the base of the foundation. In addition, failure to adequately
restore any in-situ drainage or, if appropriate, to improve the overall site drainage during the
reinstatement activities could lead to a change in the soil properties and a consequential
reduction in the foundation strength.

C:\CIGRE\WG07\Foundation Installation\Section2_Final 2.3 May 2006


12 9

G. L.
Temporary / permanent
casing
3A 4
Stub

Concrete

5 2

3 1
Reinforcement

9 6

Under-ream 10

7A
11

7 5

Figure 2.3 Drilled shaft foundation interaction diagram

Table 2.2 Interaction installation activities and foundation design drilled shafts

Possible changes during installation Adverse effect on foundation


Key Parameter
activities design
Change in foundation
Actual soil/rock properties or ground
Soil/rock properties geotechnical design may
water level encountered during
1 and/or ground water affect foundation design
foundation excavation differs from
level strength and/ or long term
design assumptions.
durability.
Possibly increase in
2 Alignment of shaft Misalignment of shaft. foundation loading and/or
reduction in strength.
Incorrect depth and/or diameter,
Reduction in foundation
3 Foundation dimensions under-ream and/or insufficient
design strength.
penetration into bearing stratum.
Changes in ground profile adjacent Reduction in foundation
3A Ground profile
to foundation design strength.
Incorrect installation techniques
with respect to temporary and/or
Temporary/permanent
4 permanent casing.
casings
Incorrect length of permanent Reduction in foundation
casing. design strength and/or long
Incorrect installation techniques term durability.
with respect to the control of ground
Ground water
5 water penetration causing shaft
penetration
instability, reduction in c.s.a. or
contaminated concrete.

C:\CIGRE\WG07\Foundation Installation\Section2_Final 2.4 May 2006


Possible changes during installation Adverse effect on foundation
Key Parameter
activities design
Incorrect installation techniques
with respect to the use of stabilizing
Stabilizing fluids or
6 fluids or drilling muds, causing shaft
drilling muds
instability, reduction in c.s.a. or
contaminated concrete.
Failure to remove loose or disturbed Reduction in foundation
Base cleaning or soil from shaft base causing design strength and/or long
7
forming inadequate bearing material or term durability.
contaminated concrete.
Incorrect dimensions and/or partial
7A Under-ream
collapse of under-ream.
Misalignment of reinforcement
Reinforcement
8 and/or reinforcement cover less
alignment and/or cover
than specified.
9 Stub setting Incorrect stub setting or alignment. Increase in foundation
loading.
Inappropriate concreting techniques
causing concrete to segregate,
concrete contamination, voids, etc.
10 Concrete placing Delays in placing concrete after Reduction in foundation
completion of excavation, failure to design strength and/or long
check actual against theoretical term durability.
concrete volumes.
Concrete strength Reduced concrete strength and/or
11
and/or workability poor workability.
Inappropriate concrete curing Reduction in long term
12 Concrete curing
techniques. durability.

Figure 2.4 Drilled shaft foundations failure to adequately remove all of excavation
material during concrete placing (Key 7 & 10)

C:\CIGRE\WG07\Foundation Installation\Section2_Final 2.5 May 2006


2.2.3 Piled foundations

Although, piled foundations are included in the general category of both separate and
compact foundations, for simplicity they have been included in this section of the report. Pile
foundations can either comprise a single pile or a group of piles connected at or just below
ground level by a reinforced concrete cap, i.e. a piled foundation.

The following types of piles have been considered in this section of the report:

< Bored cast in-situ piles;


< Continuous flight auger piles (CFA-pile);
< Driven cast-in-place piles;
< Pre-cast reinforced and pre-cast reinforced concrete segmental piles;
< Steel bearing piles.

Bored piles can be constructed dry employing temporary casing to seal the pile bore
through water-bearing or unstable strata overlying suitable stable material. Upon reaching
the design depth a reinforcing cage is introduced, and concrete is placed in the bore to the
required level. The casing is then withdrawn. Wet boring also employs a temporary casing
through unstable ground and is used when the pile bore cannot be sealed against water
ingress. Boring is then undertaken using a digging bucket to drill through the underlying soils
to the design depth. The reinforcing cage is lowered into the bore and the concrete placed by
tremie pipe and subsequent removal of the temporary casing. In some cases there may be a
need to employ drilling fluids to maintain a stable shaft.

Continuous flight auger piles (CFA-pile) are formed by screwing a continuous auger into the
ground to the required depth. Concrete is then pumped under pressure down the hollow
stem of the auger to the bottom of the bore. Once pumping starts the auger is progressively
withdrawn bringing the excavated soil to the surface. Once the auger is finally removed the
reinforcement is placed in the concrete pile.

Pre-cast reinforced piles are normally manufactured off-site, the use of mechanical
interlocking joints means that the individual units can be rapidly coupled together during the
driving.

Steel bearing piles can either H-section or tubular steel piles, the latter now being extensively
used for overhead transmission line support foundations. Prefabricated stub connectors can
be cast into the top of the tubes for direct connection of the tower leg.

Although, timber piles have been used previously for transmission line support foundations,
their current use is not extensive and as such they have not been included in this report.

Because of the variety of pile types considered and the fact that the piles can be installed
singularly or in a group, it has not been possible to produce a piled foundation interaction
diagram; consequentially, only a review of the installation activities and their affect on the
overall foundation design is given in Table 2.3.

Note: The following key has been used to identify the different piles types, B - Bored cast
in-situ, C - Continuous flight auger, D - Driven cast-in-place, P Pre-cast reinforced
and pre-cast reinforced concrete segmental piles and S - Steel bearing piles.

Unless noted otherwise, details pertaining to the use of bored cast in-situ piles are covered in
the preceding subjection for drilled shaft foundations.

C:\CIGRE\WG07\Foundation Installation\Section2_Final 2.6 May 2006


Table 2.3 - Interaction installation activities and foundation design - piled foundations

Pile Possible changes during Adverse effect on foundation


Parameter
type installation activities design
Actual soil/rock properties or Change in foundation
Soil/rock properties
ground water level encountered geotechnical design may affect
All and/or ground water
during foundation excavation foundation design strength and/
level
differs from design assumptions. or long term durability.
Possibly increase in pile design
All Alignment of pile Misalignment of pile. loading and/or reduction in
strength.
Incorrect depth and/or diameter,
Reduction in pile design
All Pile dimensions and/or insufficient penetration into
strength.
bearing stratum.
Changes in ground profile Reduction in foundation design
All Ground profile
adjacent to foundation. strength.
Insufficient distance between
Damage to or increased
All Adjacent piles piles or time elapse before
installation of adjacent piles. loading of adjacent piles.
B, C Inappropriate pile trimming/cutting
Pile trimming
&P techniques causing pile cracking.
B, C Inadequate construction of
Placing of reinforcement
&D reinforcement cage.
Reduction in pile design
Misalignment of reinforcement
B, C Reinforcement strength and/or long term
and/or reinforcement cover less
&D alignment and/or cover durability.
than specified.
Inappropriate concreting
B, C
Concrete placing techniques causing concrete
&D
segregation.
Reduction in pile design
B, C Concrete strength Reduced concrete strength and/or
&D and/or workability poor workability. strength and/or long term
durability.
B, C Inappropriate concrete curing Reduction in long term
Concrete curing
&D techniques. durability.
Pile construction Failure of automated monitoring
C
monitoring system system.
Inappropriate installation
techniques with respect to the
C Non-cohesive soils
advance and rate of rotation of Reduction in pile design
the auger. strength and/or long term
Misalignment between the rate of durability.
removal of the auger and the rate
C Concreting of supply of concrete, causing
changes in c.s.a. or contaminated
concrete.
Inappropriate installation
D, P Damage to pile and reduction
Pile driving techniques with respect to pile
&S in pile design strength.
driving.
D, P
Pile joints Misalignment of pile joints.
&S Reduction in pile design
D, P Inappropriate techniques used to strength.
Pile set
&S measure pile set.
D& Stub setting or anchor Incorrect stub setting or
S bolt placing* alignment. Increase foundation loading.
Reduction in pile and hence
Incorrect techniques with respect reduction foundation design
D Temporary casing
to removal of temporary casing. strength and/or long term
durability.
Inappropriate techniques with Damage to pile and hence
P& Pile transportation,
respect to pile transportation, reduction in foundation design
S lifting and pitching
lifting and pitching. strength.
C:\CIGRE\WG07\Foundation Installation\Section2_Final 2.7 May 2006
Note: Stub setting or anchor bolt placing* - only applicable to single piles with no pile cap.

Where pile caps and ground (tie) beams are required, the interaction between the
construction activities and the design process will be similar to that described in section 2.2.1
for spread footings. In particular, key points 1, 2, 2A, 3, 4, 5, 5A, 6, 6A, 7, 8 and 9 will apply.
For pile caps and/or ground beams constructed above ground level, additional interaction
between the strength of the formwork and the overall foundation design will also apply.

2.3 Anchor foundations

2.3.1 Micropiles and ground anchors

Since there are a variety of different types of micropiles and ground anchors and
corresponding installation techniques, the parameters identified in figure 2.5 and described in
Table 2.4, have been generalised and may not be applicable to a specific type and/or
method of installation. The parameters described in the following table are equally applicable
to ground anchors.

9
3

G.L.

Temporary
casing 4
10
Grout Tendon
2
7 1
5

7A
6

8 8A

Figure 2.5 Micropiles and ground anchors interaction diagram

Table 2.4 Interaction installation activities and foundation design micropile &
ground anchors

Possible changes during Adverse effect on foundation


Key Parameter
installation activities design
Actual soil/rock properties or Change in foundation
Soil/rock properties
ground water level encountered geotechnical design may affect
1 and/or ground water
during foundation excavation foundation design strength and/
level
differs from design assumptions. or long term durability.
Incorrect depth and/or diameter
Reduction in micropile design
2 Micropile dimensions and/or insufficient penetration into
strength.
bearing stratum.
Possibly increase in foundation
3 Alignment Misalignment of micropile. design loading and/or reduction
in foundation design strength.
C:\CIGRE\WG07\Foundation Installation\Section2_Final 2.8 May 2006
Possible changes during Adverse effect on foundation
Key Parameter
installation activities design
Incorrect installation techniques
Temporary/permanent with respect to temporary and/or
4
casings permanent casing. Incorrect
length of permanent casing.
Drilling and hole Inappropriate drilling techniques,
5
stabilisation hole collapse.
Inappropriate hole flushing
6 Hole flushing techniques, failure to remove all
soil/rock particles. Reduction in micropile design
strength and/or long term
Inappropriate tendon handling
Tendon placement durability.
7 technique, causing damage to
(homing)
tendon.
Tendon alignment Misalignment of tendon and/or
7A
and/or cover cover less than specified.
Grout strength and/or Reduced grout strength and/or
8
workability poor workability.
Delay between hole drilling and/or
8A Grouting
incorrect grouting techniques.
9 Foundation setting Incorrect micropile setting. Increased foundation loading.
Changes in ground profile Reduction in foundation design
10 Ground profile
adjacent to foundation. strength.

For details with respect to the micropile and ground anchor caps, reference should be made
section 2.2.3.

2.3.2 Block anchors

For details of the interaction between installation activities and the foundation design strength
for block anchors, reference should be made to section 2.2.1 for spread footings.

2.3.3 Helical screw anchors

Although helical screw anchors are relatively simple to install, there are a number of key
installation activities which have a direct influence on the foundation design strength; these
are shown diagrammatically in Figure 2.6 and described in Table 2.5.

G.L.

2
6

Figure 2.6 Helical screw anchors interaction diagram

C:\CIGRE\WG07\Foundation Installation\Section2_Final 2.9 May 2006


Table 2.5 Interaction installation activities and foundation design helical screw
anchors

Possible changes during Adverse effect on foundation


Key Parameter
installation activities design
Actual soil/rock properties or Change in foundation
Soil/rock properties
ground water level encountered geotechnical design may affect
1 and/or ground water
during foundation excavation foundation design strength and/
level
differs from design assumptions. or long term durability.
Failure to use correct installation
Reduction in anchor design
2 Installation torque torque and maintain constant
strength.
rotational speed.
Possibly increase in foundation
3 Alignment Misalignment of the anchor shaft. design loading and/or reduction
in foundation design strength.
Torsional buckling failure of
4 Downthrust Excessive downthrust.
anchor shaft.
5 Foundation setting Incorrect anchor setting. Increased foundation loading.
Changes in ground profile Reduction in foundation design
6 Ground profile
adjacent to foundation. strength.

If multiple helical screw anchors are interconnected with a reinforced concrete cap, similar
interactions to those described in section 2.2.3 for pile caps would apply.

2.3.4 Deadman and spread plate anchors

Deadman and spread plate anchors can be used as alternative to helical screw anchors,
especially in soils which contain boulders. A diagrammatic representation of the interaction
between the installation activities and the foundation design is shown in Figure 2.7 and
described in Table 2.6

7
2

G.L.

Backfill
8 2
6 Anchor rod

5
1
3
Installation slot

Anchor block

Figure 2.7 Deadman anchors- Interaction diagram

C:\CIGRE\WG07\Foundation Installation\Section2_Final 2.10 May 2006


Table 2.6 Interaction installation activities and foundation design deadman
anchors

Possible changes during Adverse effect on foundation


Key Parameter
installation activities design
Actual soil/rock properties or Change in foundation
Soil/rock properties
ground water level encountered geotechnical design may affect
1 and/or ground water
during foundation excavation foundation design strength and/
level
differs from design assumptions. or long term durability.
Possible increase in foundation
2 Alignment Misalignment of the anchor rod. design loading and/or reduction
in foundation design strength.
3 Anchor depth Incorrect anchor depth.
Failure to locate anchor block Reduction in anchor design
4 Block installation
against undisturbed soil. strength.
Inappropriate techniques used to
5 Rod installation
install anchor rod.
Backfill density lower than Reduction in foundation design
6 Backfill
assumed in design calculations. uplift strength.
7 Foundation setting Incorrect anchor setting. Increased foundation loading.
Changes in ground profile Reduction in foundation design
8 Ground profile
adjacent to foundations. strength.

2.4 Compact foundations

2.4.1 General

The interaction between the installation activities and the foundation design process for both
monoblock and raft foundations is similar to that described for spread footings, and reference
should be made to sections 2.2.1. For raft foundations constructed above ground level,
additional interaction between the strength of the formwork and the overall foundation design
will also apply.

For drilled shafts and piles used as compact foundations, similar interactions to those
described in sections 2.2.2 and 2.2.3, respectively will apply.

2.4.2 Direct embedment

The installation activities associated with the direct embedment of monopoles are similar in
certain respects to those for drilled shaft foundations; the major difference is the absence of
concrete and the presence of a backfill material. Both the width of the annulus between the
pole and the surrounding soil/rock and the degree of compaction of the backfill will have a
major influence on the foundation design strength. In addition, the key points 1, 2, 3, 3A, 5
and 7 for drilled shaft foundations, will also apply.

2.5 Conclusions

This section of the report has considered how the foundation installation activities can
potentially influence both foundation design strength and its long term durability. For the
principal types of foundations considered, the site activities that likely affect foundations can
be summarised as:

< Failure to recognise changes in the geotechnical conditions;


< Inappropriate installation techniques;
< Variations in foundation dimensions;
< Inappropriate concreting methods;
C:\CIGRE\WG07\Foundation Installation\Section2_Final 2.11 May 2006
< Inappropriate backfilling techniques.

The consequences of these failings in the foundation installation activities has been shown in
Figure 1.3, but in a less dramatic manner in figure 2.8, which illustrates the reduction in the
long term durability of the foundation due to a failure to provide an adequate construction
joint between the foundation and muff concrete.

Section 3 of the report outlines the recommended site installation methods and procedures
that should be employed to ensure that the deficiencies described in this section of the report
do not occur.

Figure 2.8A Corrosion of stub


& tower bracing member

Note poor compaction of muff


concrete and failure to effectively
seal between double angle
bracing members, thereby
permitting ingress of aggressive
agents.

Figure 2.8B Corrosion of


tower bracing member after
removal of the muff concrete.

C:\CIGRE\WG07\Foundation Installation\Section2_Final 2.12 May 2006


3 Foundation Installation Activities

3.1 General

The previous section of this report has considered how the foundation design can be
adversely influenced both by changes in the geotechnical properties and the use of
inappropriate foundation installation techniques. This section of the report provides an
overview of accepted good practice with respect to foundation installation, such that the
adverse effects can be eliminated or at least reduced to a minimum.

Foundation installation can be considered as a series of discreet interrelated activities


commencing with the initial foundation design and associated installation drawings, site
access preparation, setting out, excavation, etc., through to the site reinstatement, although
completion of the latter does normally occur until after the end of construction activities. A
diagrammatic flow chart of the foundation installation activities is shown in Figure 3.1.

Environmental
Foundation Geotechnical Programme &
& 3rd Party
Design Investigation Resources
Constraints

Installation
Pre-site Formwork Concrete mix Access
Method
activities Drawings design development
procedures

Setting up
Setting out Excavation or Concreting &
Stub setting Backfilling
primary installation curing
template

Formwork
Reinforcement
& Stub fixing

Setting up
Setting out Concreting &
Excavation Stub setting Backfilling
secondary curing
template

Formwork
Reinforcement
& Stub fixing

Foundation
proof tests

Site
reinstatement

Figure 3.1 - Diagrammatic representation of foundation installation activities

Note: Primary activities refer to main foundation installation, i.e. for piled foundations the
installation of the piles themselves, while the secondary activities refer to the
construction of the pile cap.
C:\Cigre\Foundation Installation\Section3_Final 3.1 May 2006
3rd Parties include Landowners, Grantors, Regulatory Agencies, etc.

This section of the report does not cover the specific requirements for foundation installation
in areas subject to mining subsidence caused by the extracting of coal and other minerals by
shallow, deep or opencast mining. For details of procedures to be adopted reference should
be made to CIRIA Report 32 [CIRIA 1984] and to Jones, Deal and Paisley [1988].

For details of the quality control and quality assurance, and health and safety activities
associated with foundation installation, reference should be made to sections 4 and 5 of this
report respectively.

3.2 Pre-site activities

3.2.1 General

For the purpose of this report, pre-site activities are defined below and assume that the
foundation design and associated geotechnical investigation have already been undertaken,
that any client, environmental and/or third party constraints have been considered and the
requirements of both the programme and financial budgets have been taken into account.

< Preparation of the foundation installation drawings;


< Manufacture of the foundation formwork (shuttering) and the stub or anchor bolt setting
templates. If the lower portion of a lattice tower is used to set the stubs, then the
associated erection and rigging drawings also must be available;
< Preparation of the foundation installation method statement and associated hazard
identification/risk assessment;
< If the excavation method proposed differs from the installation contractors normal
practice, consideration should be given to the preparation of foundation excavation
support drawings and associated calculations (if appropriate);
< Site access development (accommodation works) has been undertaken, taking into
consideration any client, environmental and/or third party constraints, the size and weight
of the installation equipment, the transportation of site personnel and materials. If the use
of helicopters is required for the transportation of equipment/materials/site personnel, all
the appropriate planning and off-site activities have been completed.
< The concrete mix(es) has been finalised and approved, if appropriate;
< Details of the support type, extension and location have been agreed/approved and the
support centre peg fixed on site;
< Any preliminary foundation design tests have been undertaken, unless the tests are going
to be undertaken on working foundations and subsequently incorporated into the final
work;
< The foundation installation criteria schedule has been prepared and approved, if
appropriate.

Although, not stated above, it is assumed that all materials, installation plant/equipment and
personnel, site offices/welfare facilities and stores are available.

3.2.2 Foundation installation drawings

Foundation installation drawings may include some or all of the following:

< Foundation general arrangement / construction drawings


< Concrete reinforcement bar bending and cutting schedules;
< Foundation formwork (shuttering) drawing;
< Stub setting or anchor bolt assembly template drawings.
C:\Cigre\Foundation Installation\Section3_Final 3.2 May 2006
a) Foundation general arrangement / construction drawings
Foundation installation drawings should typically show the elevation, plan and cross sections
(if appropriate) of the foundation complete with all the appropriate dimensions. Stub details or
holding down bolt assembly details, excavation dimensions, concrete mix design details,
concrete reinforcement details, bar bending schedule, stub or anchor bolt assembly setting
dimensions, installation tolerances and cross-references to all the appropriate foundation
design documentation including the Site Investigation (SI) report, should also be included. As
a minimum and where appropriate, the key foundation design data should be included on the
general arrangement / construction drawing e.g. soil/rock profile, ground water level,
assumed bearing pressure, frustum angle, density of backfill, etc. Typical foundation general
arrangement/construction drawings for a reinforced concrete spread footing (pyramid and
chimney); single driven steel tube pile foundation and a multiple driven steel tube piled
foundation complete with a reinforced concrete pile cap are shown in Figures 3A.1, 3A.2 and
3A.3 respectively.

For the reinforcement bar bending and cutting schedule, care should be taken to ensure that
both bending and cutting tolerances are taken into consideration when determining the
overall bar length and that the specified concrete cover is not infringed. The clear spacing
between the reinforcement should take into consideration both the maximum aggregate size
and the diameter of the vibrator. In addition, the location of concrete spacers, especially
chairs to support the upper layers of reinforcement, should be clearly shown on the
foundation construction drawing.

b) Formwork
The following parameters should be considered in the design of formwork:

< The formwork should be sufficiently rigid and tight to prevent the loss of grout or mortar
from the fresh concrete;
< The formwork and its supports should maintain their correct position and ensure the
correct shape and profile of the concrete;
< The design of the formwork should take into account any safety considerations applicable,
including manual handling;
< The formwork should be capable of being dismantled and removed from the cast concrete
without shock, disturbance or damage;

If standard foundations are required for a specific geotechnical condition for a range of
different support types, e.g. suspension, light, medium and heavy angle, and terminal,
normal UK practice is to undertake the design and manufacture of a standard range of steel
formwork (shutters). The key requirement is to achieve the highest interchangeability
between different support types, without compromising the foundation design. A typical steel
shuttering general arrangement drawing is shown in Figure 3A.4 and the actual shutters in
Figure 3.10; an alternative arrangement using disposal shuttering is shown in Figure 3.11.
The use of timber formwork is shown in Figures 3A.11 and 3A.12.

c) Stub setting and anchor bolt assembly templates


Stub setting or anchor bolt assembly templates may be provided by the support
manufacturer or by the foundation installation contractor. Stub setting templates may
comprise a complete frame such that all four stubs can be set at once or alternatively a
single template such that individual stubs are set in turn. The critical features are, that the
stub setting template should be accurate such that the setting tolerances can easily be met,
support the weight of the stub without causing the frame to distort, easily extendable for
different support extensions and capable of setting hillside leg extensions. A typical stub
setting template is shown in Figures 3.9 and, an alternative approach in Figure 3A.7c and an
anchor bolt template in Figure 3A.5.
C:\Cigre\Foundation Installation\Section3_Final 3.3 May 2006
3.2.3 Concrete mix design

a) General
The primary objective of the concrete mix design is to ensure that the fresh concrete has the
required workability, to enable a dense, void-free, concrete to be placed such that the
hardened concrete has the required strength and durability for the intended service life of the
foundation. For the majority of overhead line support foundations, the durability of the
concrete and not the strength is the key requirement.

To achieve these aims, the concrete mix design, should take into account the following
factors:

< The design strength in terms of the 28-day characteristic strength, strength grade or
compressive strength grade;
< The durability required, taking into consideration the intended service life of the
foundation, the chemical aggressiveness of the surrounding soil or ground water (static or
mobile), whether the site is a greenfield or a brownfield location and whether the concrete
is prone to freeze-thaw attack;
< The workability required, taking into consideration the delivery time to site from the
batching plant, the proposed method of transporting and placing the concrete, the method
of compaction, environmental conditions, e.g. cold or hot weather, etc.;
< The type of cement available and whether a combined cement, e.g. Portland cement
combined with pulverised fly ash (pfa) or ground granulated blast furnace slag (ggbs), can
be used,
< The type and size of the coarse aggregate, taking into account the proposed method of
placing, e.g. rounded aggregates are preferred for concrete placed by tremie or pumping,
the clear spacing between reinforcement and the diameter of the concrete vibrator;
< The permitted use of admixtures;
< Whether a design mix or a standardised mix in accordance with a national standard is
required;
< The relevant requirements of the clients technical specification and/or
national/international standards;
< Whether the concrete is going to be supplied from an external ready-mix supplier or
batched on-site;
< Whether the external supplier is accredited to an approved quality assurance scheme;
< For site batched concrete, the source and types of aggregates and the quality of water.

Note: A brownfield site is defined as a site or part of a site that has been subject to industrial
development, storage of chemicals or deposition of waste, and which may contain
aggressive chemicals in residual surface materials or ground penetrated by leachates.
[BRE 2001]

Similar details to those listed above will also need to be considered in respect of the design
of cementious grouts for anchor foundations.

With regards to durability, the concrete and especially the cover to the reinforcement
undertakes a series of functions, i.e.:

< Provides a high alkaline environment which passivates the reinforcement, thereby
inhibiting corrosion;
< Provides a low permeability physical barrier (of sufficient depth) to the chemical agents
that would otherwise promote corrosion in embedded steel items, e.g. chloride attack on
concrete reinforcement;
< Forms an outer shell to protect the foundation from physical attack, e.g. freeze-thaw
damage.
C:\Cigre\Foundation Installation\Section3_Final 3.4 May 2006
The achievement of the desired level of durability requires the correct cover to the
reinforcement, the appropriate concrete mix, good compaction (i.e. reduction of voids and
low permeability), correct curing, and possibly the use of admixtures in appropriate
applications and quantities.

The effect of altering (increasing) the proportions and/or properties of the concrete mix
constituents, i.e. cement, aggregates and water, on the workability, cohesiveness and
stiffening time of the mix, are shown in Table 3.1.

Table 3.1 - Effect of increasing the proportions and/or properties of the mix
constituents

Mix constituents Effect on


Workability Cohesiveness Stiffening time*
Water Increase N/A N/A
Portland cement N/A Increase Reduce
pfa Increase Increase Increase
ggbs Increase Increase Increase
Aggregate
max. aggregate size Increase Reduce N/A
angularity Reduce N/A N/A
fine aggregate content Reduce Increase N/A

Notes: * Stiffening time is time beyond which reworking the concrete would be detrimental.
Details taken from Table 4.6 of CIRIA report R165 [CIRIA 1977a].

For further information reference should be made to the appropriate standards, e.g. EN 206-
1 [BSI 2000a], BS 8500 [BSI 2002]. Reference should also be made to section 3.6 of this
report, for specific requirements for concrete mixes for drilled shaft foundations and piles.

b) Aggressive ground or ground water conditions


Concrete in the ground is prone to attack by a variety of different chemicals either in the soil
and/or the ground water, with a corresponding reduction in both its long term strength and
durability. The chemical constituents of aggressive ground and groundwater are: sulfates and
sulfides, acids, magnesium ions, ammonium ions, aggressive carbon dioxide, chloride ions
and phenols. For further details regarding concrete in aggressive ground conditions and
recommendations regarding the design of resistant concrete mixes, reference should be
made to BRE Special Digest 1 [BRE 2001]. In addition, details of reinforced concrete
construction in hot-wet and hot-dry environments are given in CIRIA Report C577 [CIRIA
2002a].

Concrete can also suffer from internal degradation from alkali-aggregate reaction, normally in
the form of alkali-silica reaction, for further details reference should be made to BS 8500 [BSI
2002].

c) Combined cements
Portland cement combined with either pfa or ggbs can provide adequate protection against
sulfate attack and enhanced protection against chloride attack, and these combinations are
suitable alternatives to Sulfate-resisting Portland cement, when this is not available. Care
should be taken when using a ggbs combination due to its slower rate of gain of strength and
tendency to bleed more than concrete made from Portland cement.
C:\Cigre\Foundation Installation\Section3_Final 3.5 May 2006
d) Admixtures
Admixtures are a useful way of modifying or improving the concrete mix in respect of the
workability or durability. All admixtures should be used in accordance with the manufacturers
instructions, especially where multiple admixtures are used in combination for their
compatibility and in accordance with the relevant standard, e.g. EN 934 [BSI 2001a]. The
range of admixtures available includes: accelerators, retarders, air-entraining agents, water
reducers, plasticisers and pumping aids.

< Accelerators reduce the setting/stiffening time and increase the rate of strength gain;

< Retarders retains workability thereby offsetting the effects of high ambient
temperatures, slower/strength time response and hence prevention of
cold joints between pours;
< Air-entraining increase the durability of concrete to resist freeze-thaw attack;
agents however, the use of this admixture can cause a reduction in the
concrete strength and may require a change in the mix design;
< Water reducers higher workability for a given water content hence denser concrete,
& plasticisers higher strength for a reduced water content at a maintained workability
therefore stronger concrete, same strength at a reduced cement
content whilst maintaining the same w/c ratio hence lower permeability;
< Superplasticisers very high workability at given water content thereby assisting placing in
difficult situations, time and energy saving no compaction necessary,
non-shrink/non-bleed grouts.

The effect of altering (increasing) the admixture proportions on the workability, cohesiveness
and stiffening time of the concrete mix are shown in Table 3.2.

Table 3.2 - Effect of increasing the admixture proportions on the mix properties

Admixture Effect on
Workability Cohesiveness Stiffening time
Accelerators N/A N/A Reduce
Retarders N/A N/A Increase
Water reducers / plasticisers Increase Increase N/A
Air-entrainer Increase Increase N/A
Superplasticisers Increase Increase N/A
Pumping aids Increase Increase N/A

For further details regarding concrete technology for cast in-situ foundations, reference
should be made CIRIA Report C569 [CIRIA 2002b].

3.2.4 Preliminary foundation design tests

Full-scale foundation design tests are normally undertaken in advance of the main site
activities and are usually carried out on specially installed foundations, with one or more of
the following objectives:

< To verify design parameters or methodologies;


< To verify installation procedures;
< To establish geotechnical design parameters and/or design methodologies for a specific
application;
C:\Cigre\Foundation Installation\Section3_Final 3.6 May 2006
< To verify compliance of the foundation design(s) with the clients specification;
< To determine the average failure load and coefficient of variation of the foundation design
in specified geotechnical conditions.

A typical full-scale foundation uplift loading test arrangement is shown in Figure 3.2. For
further details regarding full-scale foundation design requirements, reference should be
made to IEC 61773 [IEC 1996] and Cigre Brochure No. 81 [Cigre 1994].

Figure 3.2 Full-scale foundation uplift loading test arrangement

3.2.5 Foundation installation criteria

Foundation installation criteria are detailed in a schedule which categorises for each support
location, the soil and/or rock type, ground water level, the type of foundation to be installed
and the concrete mix to be used. The schedule is prepared by the foundation designer and
should demonstrate the basis for the selection, taking into account the following items:

< The results of the site investigation;


< The results of any preliminary foundation design tests;
< The design criteria, i.e. a summary of the design parameters including the theoretical
basis for the design, the applicable design standards or codes of practice used, etc.

3.3 Setting out

Prior to commencing any work on-site apart from site clearing, main and auxiliary line pegs
both transverse and longitudinal to the direction of the overhead line should be established,
such that, the centre peg of the support can be re-established, if necessary. The pins used,
should be of steel with a minimum length of 300 mm and a minimum diameter of 12 mm,
located outside the proposed area of working and driven to ground level.

Pins used for marking out the foundation excavation should be of a similar type. Setting out
pins for piles should be similar and for raking piles due account should be taken of the
horizontal offset required, to allow for any difference in elevation between the piling platform
C:\Cigre\Foundation Installation\Section3_Final 3.7 May 2006
and the cut-off level of the pile. In addition, for raking piles an alignment pin will be required
to indicate the direction of the rake. If appropriate, the pins should be clearly tagged with the
pile reference number.

Permitted installation tolerances for piles are given in both EN 1536 [BSI 2000b] and the
Specification for Piling and Embedded Retaining Walls [ICE 1996].

3.4 Excavation

Excavations should be adequately supported or formed to ensure stability of the sides,


prevent any damage to the surrounding ground or adjacent structures and ensure the safety
of all personnel. Where sheet piling and/or timbering is used for the support of the foundation
excavation, this should be in accordance with a recognised standard or code of practice, e.g.
BS 8004 Section 5 [BSI 1984] or HSG185 [HSE 1999].

Unless the excavation is battered or stepped, excavations in non-cohesive loose sand and
gravel, soft clays and silts will require close sheeting to prevent ground movement. The use
of steel trench sheeting or timber boards driven prior to excavation commencing may be
necessary in many cases. For details of safe slope angles for battered back sides of
excavations reference should be made to HSG185 [HSE 1999]. Typical excavations with
side support are shown in Figures 3.3, 3.4, 3.5 and 3.6.

Steel trench sheeting driven below base of excvation or


alternatively use of timber runners
Safety
chain

G. L. Timber or steel
whalings

Close sheeting
Sole
Puncheons plates
Open sheeting Base of excavation

Figure 3.3 - Typical foundation excavation

Note: Safety barriers and/or guard rails, stop blocks omitted for clarity.

Excavations in cohesive soil and weak rock may stand unsupported; however, there is
always a risk that excavations in these ground conditions will collapse without warning.
Cohesive stiff or very stiff clays may be adequately supported by open trench sheeting where
alternate sheets/boards are omitted. Care is necessary when excavating rock which may
fracture, to ensure that loose blocks do not fall from the excavation face.

The risk of the collapse of the excavation side is influenced by the following factors:

< Loose uncompacted soils, especially fill materials or made-up ground;


< Excavations through different strata;
C:\Cigre\Foundation Installation\Section3_Final 3.8 May 2006
< Presence of groundwater or surface water running into the excavation;
< Proximity of earlier excavations;
< Loose blocks of fractured rock;
< Weathering, rain and freeze/thaw effects;
< Vibration from plant and equipment;
< Surcharging by spoil;
< Proximity of loaded foundations.

Excavated material suitable for reuse as a backfill should be stored within the working area,
but in such a location so as not to cause an increase in loading (surcharge) on the face of the
excavation (minimum distance from excavation face of 1.5 m or the depth of the excavation,
if greater). Excavated top soil should be stored separately.

For excavation in cohesive soil, the final 150 mm above the formation level should only be
removed prior to placing the blinding concrete, thereby preventing softening of the exposed
formation layer. Normal practice is to use a concrete blinding layer 75 mm thick, although in
chemically aggressive soils it may be necessary to use an impermeable membrane between
the blinding concrete and the soil. Similar requirements may be required for certain weak
rocks that deteriorate due to the presence of moisture, e.g. uncemented mudstones.

No water should be permitted to accumulate in the excavation; any water arising from the
excavation or draining into it, should be drained to an approved location, clear of the
excavation area and in a manner that does not cause erosion, silting or contamination of
existing drains and watercourses. Adequate steps should be taken to prevent the adjacent
ground being adversely affected by the loss of fines in any groundwater control process. The
water removal system may include conventional pumping from a sump in the corner of the
excavation or alternatively in soils with a high permeability using well pointing de-watering
techniques. For further details regarding groundwater lowering, e.g. de-watering, reference
should be made to BS 8004 [BSI 1984]. The design of the groundwater control system
should ensure that any upward flow of water is not sufficient to cause piping at the base of
the excavation, whereby the soil cannot support any vertical load.

Figure 3.4 Foundation excavation open sheeting

C:\Cigre\Foundation Installation\Section3_Final 3.9 May 2006


Figure 3.5 Foundation excavation close sheeting using steel trench sheeting

Figure 3.6 Foundation excavation side support using netting frame

3.5 Reinforcement

The necessity for adequate concrete cover has been previously discussed in section 3.2.3
with respect to the overall durability of the foundation. With regards to the storage, cutting,
bending, fixing and site bending of the reinforcement, the following points should be taken
into consideration:
C:\Cigre\Foundation Installation\Section3_Final 3.10 May 2006
< All reinforcement should be adequately stored to prevent contamination or damage.
< Cutting and bending should be undertaken in accordance with the appropriate standard,
e.g. BS 8666 [BSI 2000c] and should be clearly identified with securely fixed durable tags.
< The welding of reinforcement cages or the welding of handling steelwork to the cage
should be undertaken in accordance with appropriate standards. Care should be taken to
ensure that the reinforcement is of weldable quality.
< The reinforcement should be property supported and maintained in position by the
adequate use of chairs, concrete block spacers, plastic wheel spacers and tying wire (see
Figures 3.7, 3.8, 3A.7 and 3A.8).
BS 7973 [BSI 2001b], requires that spacers and chairs for horizontal mat reinforcement,
e.g. for pile caps should be spaced at 50 x reinforcement diameter, but not exceeding
1000 mm and should be staggered in plan. Similarly, spacers for vertical reinforcement
should be positioned at similar spacings.
< The reinforcement should be free of all loose rust, scale or contamination of any kind.
< Site bending of reinforcement, or bending and subsequent straightening of reinforcing
bars projecting from existing concrete, should be undertaken at a reinforcing bar
temperature greater than 6C and in accordance with recognised practices.
< Where heating is required, the heat should be applied as uniformly as possible over a
length of bar equal to 10 x reinforcement diameter. The centre of the heated length should
be at the centre of the completed bend. The temperature should be maintained constant
during bending and straightening operations and should not exceed 100C. Temperature
measuring crayons or a contact pyrometer should be used to determine the temperature.
Care should be taken to prevent quenching of the heated bars either by application of
water, or by a high volume of air.
< Straightened bars should be visually inspected before and after straightening to determine
whether they are cracked or otherwise damaged.

Where possible the site bending of reinforcement should be avoided by the use of bar
couplers.

For further details regarding the care and treatment of steel reinforcement on site, reference
should be made to CIRIA Report 147 [CIRIA 1995]. ISO 14654 [BSI 1999] contains
guidelines on site practice with respect to the use of epoxy-coated steel reinforcement.

Figure 3.7 Foundation reinforcement Figure 3.8 - Foundation reinforcement


showing concrete block spacers complete with plastic wheel spacers

C:\Cigre\Foundation Installation\Section3_Final 3.11 May 2006


3.6 Drilled shaft and pile installation

To avoid the problems and their effect on the foundation design outlined in section 2 of this
report, all drilled shaft foundations and piles should be installed in accordance with the
appropriate standards or recognized codes of practice.

Details of the design requirements, installation techniques including methods of excavating


or forming the pile, methods of dealing with unstable ground conditions or ground water
infiltration, use of temporary and/or permanent casings or other means of excavation
support, e.g. use of stabilizing fluids, concrete mix design, placing of reinforcement and
concrete or grout, installation tolerances, inspection requirements and associated records,
and testing requirements are contained in the following standards and codes of practice:

< ACI 543-74 [ACI 1974] - Concrete piles;


< ACI 336.3R-93 [ACI 1993] - Drilled shaft foundations;
< EN 1536 [BSI 2000b] - Drilled shaft foundations, Bored cast in-situ piles and c.f.a piles;
< EN 12699 [BSI 2001c] - Displacement piles;
< Specification for Piling and Embedded Retaining Walls [ICE 1996] - All pile types, for
drilled shaft foundations see bored cast in-situ piles.

Further information regarding pile installation is contained in the following reports:

< CIRIA Report PG2 [CIRIA 1977b] - Cast-in-place piles;


< CIRIA Report PG3 [CIRIA 1977c] - Use and influence of bentonite in bored pile
construction;
< CIRIA Report SP12 [CIRIA 1979] - Piling in chalk;
< CIRIA Report PG8 [CIRIA 1980] - Problems associated with the installation of
displacement piles.
< IEEE Guide to Installation of Foundations for Transmission Line Structures [IEEE 1991]

3.7 Micropile and ground anchor installation

To avoid the problems and their effect on the foundation design outlined in section 2 of this
report, all micropiles and ground anchors should be installed in accordance with the
appropriate standards or recognized codes of practice.

Details of the design requirements, installation techniques including methods of drilling or


forming the micropile/ground anchor, methods of dealing with unstable ground conditions or
ground water infiltration, use of temporary and/or permanent casings or other means of
excavation support, e.g. use of grout, grout mix design, placing of reinforcement and grout,
installation tolerances, inspection requirements and associated records, and testing
requirements are contained in the following standards and codes of practice:

< BS 8081 [BSI 1989] - Ground anchors relevant in part to micropiles;


< EN 1537 [BSI 2000d] - Ground anchors;
< EN 14199 [BSI 2005] Micropiles.

For a general introduction on the use of micropiles for overhead line support foundations,
reference should be made to Cigre Brochure 281 [Cigre 2005].

C:\Cigre\Foundation Installation\Section3_Final 3.12 May 2006


3.8 Stub setting

The key points for consideration in respect of stub setting or holding down bolt assemblies
are:

< Stubs should be held firmly in position by a stub setting template (see Figures 3.9 and
3.14) or other device including the bottom panel of a tower (see Figure 3.10), while the
concrete is placed.
< The support should be maintained until backfilling of the foundation is complete, or for
drilled shaft, anchor and pile caps, compact and raft foundations until a minimum period of
48 hours have elapsed after concreting.
< Where individual templates are used (i.e. per footing), as opposed to an overall frame
template, additional care should be taken to ensure the stub setting dimensions and the
level, rake and orientation of the stubs are correct and within any specified setting
tolerance.
< Where the lower section of the support is used, as an alternative to a stub setting
template, adequate measures should be taken to ensure the stability of the support;
< When large heavy stubs are used, care should be taken to ensure the effect of the
suspended stubs does not cause the stub setting template to distort. The use of concrete
blocks to support the lower end of the stub and assist in the leveling of the stubs will
overcome this. Where concrete blocks are used, they should have similar strength and
durability to the surrounding concrete;
< Where holding bolt assemblies are used for separate foundations, setting templates
should be used and retained in position for a minimum of 48 hours after concreting.

Figure 3.9 Stub setting template,

Note only two foundations being excavated at one time.

C:\Cigre\Foundation Installation\Section3_Final 3.13 May 2006


Figure 3.10 Stub setting using the bottom panel of the tower

3.9 Concrete production, delivery and placing

3.9.1 General

The following recommendations with respect to the production, delivery both to and on site,
and placing are for guidance only and reference should be made to the applicable standards,
e.g. BS 5328 Part 3 [BSI 1990a], EN 206-1 [BSI 2000a], BS 8500 [BSI 2002], for specific
requirements.

3.9.2 Concrete production

a) Material storage
The key requirements for material storage are:

< Provision of separate storage for cement, ggbs, pfa and each nominal size and type of
aggregate;
< Silos used for bulk storage of cement, ggbs and pfa should be weatherproof and control
dust pollution;
< Bagged cement should be stored to prevent it becoming damp and used in the same
order as delivered;
< Cement that is adversely affected by damp should not be used;
< Aggregate storage areas should have adequate drainage;
< Water should be protected against contamination.

b) Batching
Concrete batching should be undertaken taking into account the following points:

< Cement, ggbs and pfa should be measured by mass, using a separate weighing device
from that provided for the aggregates;
< For bagged cement use whole bags;
< Aggregate(s) should be measured by mass, using a weighing device, with due allowance
C:\Cigre\Foundation Installation\Section3_Final 3.14 May 2006
for the mass of the water in the aggregate(s);
< Water may be measured by volume or mass;
< The accuracy of the measuring equipment should be within "3% for all constituent
materials, except admixtures where "5% is acceptable;
< The weighing devices should be zeroed daily, checked for accuracy monthly and
calibrated every 3 months;
< In cold weather, the mixing plant, aggregates and mixing water should be free from snow,
ice and frost. If steam heating of aggregates is used, allowance for the increased moisture
content should be made;
< In cold weather if the water and aggregates are heated, the water should not be heated
above 80EC, and if the water is heated above 60EC, it should be mixed with the aggregate
before coming into contact with the cement;
< In hot weather, the most effective means of reducing the concrete temperature is the
addition of crushed ice to the mix water [BRE 1971]. However, the mass of crushed ice or
ice chips should not exceed 50% of the total mass of water [BSI 2000b].

3.9.3 Concrete transportation

Concrete should be transported from the mixer to the point of placing as rapidly as
practicable, by methods that will maintain the required workability and will prevent
segregation, loss of any constituents or ingress of foreign matter, significant loss or gain of
water and loss of air entrainment. No additional water should be added to the mix before
placing, unless where required to permit the correct mixing of admixtures just before placing;
however, no changes to the design water-cement ratio are permitted. In addition, the mode
of transportation should take into consideration the terrain and the required rate of supply.

3.9.4 Concrete placing

Normally, concrete should be placed within two hours after the initial loading in a truck mixer
or agitators, or within one hour if non-agitating equipment is used. These periods may be
extended or shortened, depending on climatic conditions and whether ggbs, pfa, accelerating
admixtures or retarding admixtures have been used.

Concrete chutes suitable for high workability concrete should have an adequate constant
slope to permit continuous flow without segregation and should be fitted with end baffle
plates to prevent segregation or impact with the reinforcement or other embedded items.

Where it is intended to place the concrete by pumping, careful attention should be paid to the
concrete mix design, i.e. the workability, with particular reference to the fine aggregate
grading, type and size of coarse aggregate, the use of replacement cementious material
(pfa), the water cement ratio and the use of suitable admixtures, to ensure that segregation
and bleeding does not occur.

Before the concrete is placed, all rubbish should be removed from the formwork and the
faces of the forms in contact with the concrete should be cleaned and treated with a suitable
release agent. The release agent should be applied to provide a uniform coating to the forms
without contaminating the reinforcement. Figure 3.10 illustrates the setting up of steel
formwork prior to concreting, while Figures 3.13, 3.14, 3A.6 and 3A.13 all show concrete
being placed.

For further details regarding the placing of concrete in general and especially the use of
tremie pipes, reference should be made section 3.6 of this report and CIRIA report R165
[CIRIA 1997a].

C:\Cigre\Foundation Installation\Section3_Final 3.15 May 2006


Figure 3.11 Steel formwork
Concreting using chutes

Note timber props to resist uplift force of


wet concrete
Figure 3.12 Disposable formwork

Figure 3.14 Placing of concrete in a drilled


shaft foundation.

Note: The use of an alternative type of stub


setting template

Figure 3.13 Concreting using chutes

C:\Cigre\Foundation Installation\Section3_Final 3.16 May 2006


3.9.5 Construction joints

Although, it is preferable to have an integrally cast foundation, this may not be possible due
to the foundation type or connection between the tower bracings and the stub member. To
ensure that the joint between the two concrete pours are acceptable the following procedure
is recommended:

< The surface of the first pour should be roughened to increase the bond strength and to
provide aggregate interlocking;
< For horizontal joints, this can be achieved by spraying the joint surface approximately 2 to
4 hours after the concrete is first placed with a fine spray of water and/or brushing with a
stiff brush;
< If it is not possible to roughen the joint surface until the concrete has hardened, the large
aggregate particles near the surface should be exposed by sand blasting;
< The joint surface should be cleaned immediately before the fresh concrete is placed and if
necessary the surface should be slightly wetted to prevent excessive loss of mix water by
absorption.
< Particular care should be taken in placing the fresh concrete close to the joint to ensure it
has adequate fines content and is fully compacted and dense.

3.9.6 Compaction

Unless a self-compacting concrete mix is used, all concrete should be thoroughly compacted
by vibration, or other means, and worked around the reinforcement, embedded items, e.g.
stubs and into corners of the formwork to form a solid void-free mass. When vibrators are
used, vibration should be applied until the expulsion of air has practically ceased and in a
manner that does not promote segregation. Over-vibration should be avoided to minimize the
risk of forming a weak surface layer or excessive bleeding.

3.9.7 Curing

The setting and hardening of cement depend on the presence of water; drying out, if allowed
to take place too soon, results in low strength and porous concrete. At the time of concrete
placing, there is normally an adequate quantity of water present for full hydration; however, it
is necessary to ensure that this water is retained so that the chemical reaction continues until
the concrete has thoroughly hardened. Correspondingly, curing and protection should start
immediately after compaction of the concrete and should ensure adequate protection from:

< Premature drying out, particularly by solar radiation and wind;


< Leaching out by rain and flowing water;
< Rapid cooling during the first few days after placing
< Low temperatures or frost until the concrete has reached an adequate maturity;
< High internal thermal gradients;
< Vibration and impact which may disrupt the concrete and interfere with its bond to the
reinforcement or other embedded items.

Although, normal formwork, e.g. steel shutters for concrete spread footings, provides
adequate protection to the concrete in normal climatic conditions, extra measures may be
required during cold or hot weather conditions. As an approximate guide, for concrete with a
characteristic strength of between 25 N/mm and 35 N/mm, a minimum period before
stripping of 24 hours should be allowed for Portland cement or combined cements, except for
combined cements containing ggbs when a minimum period of 48 hours should be allowed.
For further information regarding minimum curing periods, reference should be made to BS
8110 section 6 [BSI 1997].
C:\Cigre\Foundation Installation\Section3_Final 3.17 May 2006
For horizontal surfaces, e.g. upper surfaces of pile caps or raft foundations, effective curing
can be achieved by covering the surface with an impermeable membrane, e.g. polyethylene,
which should be well sealed and fastened, or by using a sprayed curing membrane.

3.9.8 Working in cold weather

The concrete setting time and gain in strength are delayed at low temperatures and if the
partly set concrete is allowed to freeze, serious damage can occur. Consequentially, in cold
weather consideration should be given to:

< Prevention of freezing of the immature concrete, e.g. by insulating the fresh concrete
using thermal blankets, etc. (see Figure 3.15);
< The extended stiffening times of fresh concrete, which lead to increased formwork
pressures and finishing times;
< The low rate of concrete strength development, which can lead to delays in subsequent
operations;
< Increasing the cementious content of the mix, thereby increasing the heat of hydration and
early strength gain;
< Using admixtures that reduce the setting time and/or increase the rate of strength gain;
< Specifying a minimum temperature of fresh concrete higher than the norm of 5EC.

The key requirement of winter working is planning, taking into consideration weather
forecasts, and keeping records of maximum and minimum temperatures, thereby assisting in
the assessment of the concrete maturity and formwork striking times.

The rate of gain of strength is related to the concrete maturity, which is the product of the
concrete temperature above -10EC and the number of hours at that temperature. For
concrete with a characteristic strength of 25 N/mm, the requisite pre-hardening period is 52
hours if the concrete temperature is 5EC reducing to 26 hours at 20EC. For further details
reference should be made to Concrete Practice [C & CA 1975].

For conventional reinforced concrete spread footings, the early backfilling of the foundation
will assist in the prevention of damage to the concrete by frost action, provided that the
backfill material is not frozen.

Figure 3.15 Cold weather concreting, note use of thermal insulation


C:\Cigre\Foundation Installation\Section3_Final 3.18 May 2006
3.9.9 Working in hot weather

In hot weather the main difficulties in concreting are caused by reductions in the working life
of fresh concrete due to loss of mix water by evaporation and accelerated hydration, and
early-age thermal cracking arising from a high temperature rise in the concrete.
Consequentially, in hot weather consideration should be given to:

< Using admixtures to retard the hydration and/or to increase the initial workability;
< Using a cement or cement combination that has a low heat evolution;
< Specifying a maximum temperature of fresh concrete lower, than the norm of 30EC.

As previously noted, the key requirements for concreting in hot weather are planning and the
need to protect the fresh concrete from drying out by sun and/or wind action.

3.10 Backfilling

As previously mentioned in section 2 of this report, failure to adequately compact the backfill
is one of the prime reasons for a foundations actual uplift strength, being less than its
theoretical design strength. Correspondingly, the following recommendations should be
taken into consideration:

< Backfilling should be compacted in 300 mm layers to achieve a bulk density equivalent to
that assumed in the geotechnical design model;
< Backfilling should be undertaken progressively over the whole foundation plan area, with
particular emphasis on the area adjacent to the inner face of the chimney (see Figure
3.16);
Stub setting template
Foundation
excavation Stub

Note: Excavation Concrete pyramid & chimney


support omitted for foundation
clarity

Backfill to spread
uniformly

Difficulty of placing
backfill on inner face

Figure 3.16 - Foundation backfilling

< During backfilling, the side support sheeting to the excavation should, wherever possible,
be progressively withdrawn such that the toe of the sheeting is never more than 600 mm
below the surface of the compacted material;
< Extreme care should be taken during compaction to ensure that the foundation is not
damage nor displaced out of position;
< The compaction plant should be selected to achieve the required bulk density. The actual
C:\Cigre\Foundation Installation\Section3_Final 3.19 May 2006
method of compaction selected will depend on the type of material to be compacted, the
difficulty in accessing areas within the excavation and the safety of the site operatives.

For spread footing foundations in soils subjected to permafrost and frost forces,
consideration should be given to backfilling with non frost susceptible materials, e.g. granular
fill with less than 8% silt content and passing through a 200 sieve. For further
recommendations regarding the use of insulating materials and the application of a lubricant
to steel foundation members, reference should be made to Cigre Brochures No.141 [Cigre
1999a] and No. 206 [Cigre 2002].

Compaction of the backfill around steel grillage foundations is shown in Figure 3A.9.

3.11 Protective coatings

Where appropriate, consideration should be given to the application of protective coatings to


the foundation or foundation components, e.g. steel bearing piles, guy anchor rods, etc., to
improve their long term durability.

Normal practice is to coat, as a minimum, all exposed concrete surfaces above ground level
and 300 mm below ground level, although in very aggressive conditions, it may be necessary
to coat all concrete surfaces below ground level. Similarly, all support steelwork should be
treated for a minimum distance of 300 mm above the top of the concrete. Where steel
bearing piles or driven cast-in-situ piles with permanent casings are used, a combination of
sacrificial steel and protective coatings, may be used as alternative to a pure protective
coating system.

Coatings may take the form of waterproof membranes or surface coatings. Surface coatings
include cementious mortars, polysulphides, resins and silicones, silanes and siloxanes for
concrete and coal tar epoxy paint for steelwork. Although, historically two coats of heavy duty
bituminous paint (with a density of 1 kg/litre and applied at a rate of 1.7 to 2.1 m/litre) has
performed satisfactorily in the UK, care should be taken in its use owing to its tendency to
crack under high temperature conditions. Coal tar epoxy coatings to buried steelwork should
have a minimum dry film thickness of 300 :m.

Prior to the application of any external coating, the concrete should be allowed to cure for at
least 28 days and all surface laitance, dirt and other contaminants should be removed.
Where applicable, the concrete surface should be treated with a proprietary filling compound,
compatible with the coating system.

If it is necessary to bury the support steelwork (excluding directly embedded steel poles),
consideration should be given to protecting the buried steelwork using an approved medium,
e.g. mastic impregnated tape or coal tar epoxy coating. The use of concrete to protect
buried support steelwork, especially lattice tower bracing members is not recommended, due
to the difficulty of ensuring a homogenous concrete covering and the possibility of damaging
or distorting the steelwork.

3.12 Installation activities

Reference should be made to section 3A, where photographs of both foundation installation
equipment and sequences in the installation of different types of foundations are shown.

C:\Cigre\Foundation Installation\Section3_Final 3.20 May 2006


3.13 Summary

The foundation installation activities considered in this section of the report have
encompassed the general pre-site activities, e.g. preparation of foundation installation
drawings, concrete mix design, preliminary foundation design tests, the foundation setting
out, excavation, the placing of the reinforcement, concrete production, delivery and placing,
backfilling, and protective coatings.

To ensure that activities described in this section are performed satisfactory such that the
foundation achieves its intended service life, the next section of the report considers the
quality management requirements in respect of foundation installation.

C:\Cigre\Foundation Installation\Section3_Final 3.21 May 2006


Figure 3A.7a Auger-pile foundations before concreting of the individual auger-piles

Figure 3A.7b Auger-pile foundations after concreting of the individual auger-piles

C:\CIGRE\WG07\Foundation Installation\Section3A_Finala 3A.7 May 2006


Figure 3A.7c Auger-pile foundations before concreting of the pile cap

Note: The use of a cast-in-situ concrete block to support the stub vertically and the use of a
simple adjustable prop system to form the stub setting template.

Figure 3A.8 - Foundation Installation - Driven steel tube piles - pile cap

Note: Pile cap ready for concreting, concrete cast directly against the surrounding soil, use
of pre-cast concrete block below stub and reinforcement welded to steel tube piles
(starter bars).

C:\CIGRE\WG07\Foundation Installation\Section3A_Finala 3A.8 May 2006


Figure 3A.9a Assembly of steel grillage foundations for 230 kV OHL - Newfoundland

Figure 3A.9b Compaction of the backfill around the steel grillage foundations

C:\CIGRE\WG07\Foundation Installation\Section3A_Finala 3A.9 May 2006


Figure 3A.9c Completion of the backfilling for the nearest tower legs and
excavation for the far two legs.

Figure 3A.9d Detail of the plate vibrator used for the backfill compaction

C:\CIGRE\WG07\Foundation Installation\Section3A_Finala 3A.10 May 2006


Figure 3A.10 Details of bored pile installation equipment ~ 1.3 m diameter piles
Germany

C:\CIGRE\WG07\Foundation Installation\Section3A_Finala 3A.11 May 2006


Figure 3A.11a Bored pile 1.3 m diameter Figure 3A.11b Bored piles 2 x 1.3 m
single pile per leg 380 kV diameter per leg, detail of
lattice steel tower pile cap and chimney.

Figure 3A.11c Bored pile 2 x 1.2 m diameter per leg, details of pile cap and chimney
extension 110 kV lattice steel towers ~ Germany

C:\CIGRE\WG07\Foundation Installation\Section3A_Finala 3A.12 May 2006


Figure 3A.12 Details of cruciform foundation for 330 kV lattice steel tower
located in Hunter Valley coalfield, N.S.W. Australia

Note: Cruciform foundation used instead of a raft foundation to ensuring no differential


settlement between footings in the event of subsequent subsidence due to deep
mining activities.

C:\CIGRE\WG07\Foundation Installation\Section3A_Finala 3A.13 May 2006


Figure 3A.13 Installation of pad and chimney foundations for 220 kV lattice steel tower
Western Australia

Note: The overlapping of adjacent footings prevent individual excavations, resulting in a major
excavation and backfilling operation.

C:\CIGRE\WG07\Foundation Installation\Section3A_Finala 3A.14 May 2006


4 Quality Assurance and Quality Control

4.1 General

Overhead transmission line construction is undertaken effectively on a long linear site with
isolated areas of activity. Since overhead line support foundations are installed in a variable
naturally occurring medium, quality assurance and quality control should form an integral part
of the construction activities. Consequentially, the majority of overhead line technical
specifications or design standards require that all activities are undertaken in accordance
with the relevant requirements of ISO 9001 [BSI 2000e]. The common European Standard
EN 50341-1 [BSI 2001d], requires that The systems and procedures, which the designer
and/or installation contractor will use to ensure that the project works comply with the project
requirements, shall be defined in the designers and/or installation contractors quality plan
for the project works.

This section of the report considers various aspects of the quality assurance and quality
control activities undertaken during the foundation design and installation.

The following definitions are used throughout this section of the report:

< Quality Assurance - Part of the quality management, focussed on providing confidence
that quality requirements are fulfilled. Quality Assurance has both internal and external
aspects, which in many instances may be shared between the contractor (1st party), the
customer (2nd party) and any regulatory body (3rd party) that may be involved.

< Quality Control - The operational techniques and activities that are used to fulfil
requirements for quality. Quality control is considered to be the contractors responsibility.

< Hold Point - A stage in the material procurement or workmanship process beyond which
work shall not proceed without the documented approval of designated individuals or
organisations.

< Notification Point - A stage in the material procurement or workmanship process for
which advance notice of the activity is required to facilitate the witnessing of the activity.

Normally, the clients written acceptance is required to authorise work to proceed beyond a
Hold Point. With regards to notification points, if the client does not attend after receiving
document notification, the work may normally proceed. Note that the term client includes his
representative, if appropriate.

For simplicity sake, the quality requirements have been divided between pre-project
foundation installation activities, i.e. the design phase including the foundation type testing, (if
appropriate, of the proposed project foundations) and project foundation installation activities.

Within the pre-project activities consideration has been given to possible Hold and
Notification points, concrete mix design and specification, foundation installation criteria and
foundation installation method statements. For the project foundation installation phase of the
work, consideration has again been given to possible Hold and Notification points, setting out
tolerances for the support and the actual foundations, verification of the foundation
geotechnical design parameters, inspection prior to concreting, concrete identity tests,
foundation proof and/or identity tests and foundation installation records.

C:\CIGRE\WG07\Foundation Installation\Section4_Final 4.1 May 2006


4.2 Quality control

While this section of the report mainly concentrates on the Quality Assurance activities, it is
an inherent responsibility of the installation contractor to instigate his own internal quality
control procedures and verification methods. Without these procedures and activities
including the appropriate level of internal auditing in-place, the overall quality assurance
requirements of the project will be difficult to achieve.

Identified below are examples of quality control activities that may be applicable during the
foundation installation:

< Verification of all foundation installation drawings, technical specifications for sub-
contracted goods and services, e.g. concrete, foundation test programmes, installation
method statements, concrete mix design, etc.;
< Auditing of proposed material supplier(s) or sub-contractor(s);
< Verification of the concrete trial mix results;
< Verification of the foundation type test results;
< Verification of the support and foundation setting out;
< Verification of the foundation geotechnical design parameters during the foundation
installation process, if this is not undertaken as part of the project quality assurance
activities;
< Verification of concrete identity test results and concrete returns;
< Verification of the backfill density;
< Verification of the foundation setting dimensions;
< Verification of the proof and integrity test results;
< Verification of the as constructed foundation drawings and associated records.

4.3 Pre-project foundation installation

4.3.1 General

Pre-project foundation installation activities include the foundation design process, the
concrete mix design, the quality auditing of proposed suppliers and/or subcontractors, the
installation and full-scale testing of any test foundations and the preparation of the foundation
installation criteria and the associated foundation installation method statement(s). A
diagrammatic representation of this process, together with an indication of the documentation
required and the corresponding hold and notification points is shown in Figure 4.1.

4.3.2 Suppliers

All materials used in the foundation installation should, where possible, be purchased from a
supplier operating a quality management system in accordance with a recognised standard;
where this is not possible, the installation contractor should instigate his own quality control
requirements with respect to the materials purchased, e.g. all materials should be regularly
tested in accordance with the appropriate standards. Similar comments would also apply to
any subcontractor engaged for the foundation installation.

C:\CIGRE\WG07\Foundation Installation\Section4_Final 4.2 May 2006


Design Foundation Foundation test
Foundation
calculations drawings programme
Design

Suppliers Suppliers
Cement, Rebar,
QA/QC
Concrete,
etc.

Foundation
Installation &
Testing

Trial mix Concrete


Concrete mix
results specification
design
Foundation Test
results

Foundation Installation
Foundation Installation Method
Design Review criteria statement

Foundation
Key: Process or activity Design
Hold point

Document submission Design Notification point


calculations

Figure 4.1 - Diagrammatic representation of pre-project foundation installation QA &


QC

4.3.3 Concrete mix design

Before any concrete is supplied (assuming off-site ready mix), the recommended procedure
is for the purchaser (the foundation installation contractor) to request the proposed producer
to provide the following information:

< The nature and source of all constituent materials, including water and admixtures;
< The proposed quantity of each constituent, per cubic metre of fully compacted concrete;
< Evidence of the suitability of the proposed mix proportions to meet the specified
requirements;
< The suppliers quality assurance certification.

Where evidence is requested of the adequacy of the proposed mix proportions to meet the
specified strength, this generally can be obtained from previous productions of concrete
using similar materials and equipment to that proposed or using trial mixes.

Where concrete is produced on-site, the constituent materials should be obtained from a
recognised source and the relevant quality control test undertaken. The evidence of the
suitability of the mix design would be based on the results from trial mixes.

Acceptance of the trial mix is usually based on the results of both workability and

C:\CIGRE\WG07\Foundation Installation\Section4_Final 4.3 May 2006


compressive strength tests, in accordance with the appropriate standards. Typically, for the
compressive strength test, three concrete cubes or cylinders would be made from each batch
of concrete and tested at twenty-eight days, with the average compressive strength of the
three cubes tested exceeding the specified characteristic strength by a stated value, normally
10 N/mm.

In certain cases, where standardised mixes are used and are supplied from plants having a
product conformity certificate, the certification body is responsible for checking the suitability
of the mix proportions.

Typical details on specifying concrete, together with the respective quality assurance
requirements are given in BS 5328 [BSI 1990b], EN 206-1 [BSI 2000a], BS 8500 [BSI 2002].

4.3.4 Concrete specification

Once the source of supply of the concrete has been decided and the adequacy of concrete
mix proportions agreed, it is frequently a requirement that the installation contractor should
submit to the client, a concrete specification detailing:

< Details of the proposed mix proportions and the relevant standards used;
< The source of supply, including if necessary all the constituent materials;
< Detail of the trial mixes undertaken and works test results;
< Quality assurance and quality control procedures instigated.

The submission of this specification is normally a Hold Point.

4.3.5 Foundation design tests

Prior to undertaking any full-scale foundation design tests, it would be normal practice for the
installation contractor to submit his proposed foundation test programme, e.g. test
arrangement, loading regime, etc., to the client for agreement. This again would be Hold
Point, although the actually testing of the foundation would usually only be a Notification
Point.

4.3.6 Foundation installation criteria and method statement

The final, two written submissions that are normally required before work can commence on-
site are the foundation installation criteria and the foundation installation method
statement(s). For details of the foundation installation criteria, reference should be made to
section 3.2.5 of this report.

The foundation installation method statement(s) should include, as appropriate, the following:

< The proposed method of foundation installation (for all foundation types), including
proposals regarding the removal of water from the excavation and methods of verifying
the foundation soil / rock parameters assumed in the foundation design (e.g. soil type,
depth and ground water level) ;
< The proposed method of site bending or welding of concrete reinforcement;
< The proposed method of placing concrete, including grouting;
< The proposed method of installing permanent casings, including backfilling or grouting
behind the casings;
< The proposed method of backfilling the excavation and backfill compaction;
< Quality assurance and quality control procedures;
< Risk assessments including cross-reference to design checks undertaken on the
foundations under temporary construction loadings or during refurbishment and/or
upgrading activities.

C:\CIGRE\WG07\Foundation Installation\Section4_Final 4.4 May 2006


Both of these submissions would constitute Hold Points, i.e. as a general requirement no
foundation installation could commence before agreement is given by the client.

4.4 Project foundation installation

4.4.1 General

Assuming that agreement has been given for the installation contractor to commence work
on-site, the relationship between the various foundation installation activities and the
associated QA/QC requirements can be represented diagrammatically, as shown in Figure
4.2.

Setting
Out

Confirmation of Excavation
Excavation or
geotechnical Support details
Installation
parameters
For two stage process, e.g installation of individual piles/anchors and separate caps

Formwork
stub and
reinforcement

Inspection prior Site bending of


to concreting reinforcement

Concrete Concrete curing


Concrete
placing and details
conformity tests
curing

Concrete
returns

Details of Stub setting


Remedial
Backfilling imported backfill dimensions
measures

Foundation Foundation test Foundation Test Foundation


proof/integrity programme results installation
tests records

Key:
Process or activity Backfilling Hold point

Concrete
Document submission Notification point
returns

Figure 4.2 - Diagrammatic representation of project foundation installation QA & QC

C:\CIGRE\WG07\Foundation Installation\Section4_Final 4.5 May 2006


Note: The actual sequence of installation activities will depend on the foundation type and
whether it is a one or two-stage process. The installation of spread footings is normally a one
stage process, while piled foundations are normally a two-stage process; with the piles
installed first and the pile cap constructed subsequently.

4.4.2 Setting out

Typical requirements would be for the centre-peg of the support to be located along the line
route within 2000 mm of the location shown on the overhead line profile. The perpendicular
displacement transverse to the line route would be 50 mm relative to a theoretical route
centre-line joining the adjacent angle support points.

Where angle supports have asymmetrical length crossarms, the route centre line and the
support centre-peg will not be coincident (see Figure 4.3) and this should be taken into
account when setting out the foundations.

Offset

Tower centre peg

Route peg
Route centre-line

Figure 4.3 - Angle support setting out

4.4.3 Verification of foundation design soil / rock parameters

The serious consequence of failing to verify the assumed foundation geotechnical design
parameters during the foundation installation is shown in Figure 1.3. This sub-section of the
report considers what practical methods / techniques are available to verify the geotechnical
parameters assumed in the foundation design.

The on-site verification process obviously assumes that the basic design parameters are
shown on the foundation installation drawing (reference section 3.2.2(a)) or that a copy of SI
report is available on-site. Details of common geotechnical design parameters and possible
verification methods are given in Table 4.1 and Figure 4.4 shows a typical foundation
installation record sheet.

Table 4.1 - Verification methods geotechnical design parameters

Geotechnical parameter Verification method


Soil strata Visual during excavation
Soil type Visual / tactile
Ground water level Visual / measurement
Base resistance Penetrometer / Shear vane

C:\CIGRE\WG07\Foundation Installation\Section4_Final 4.6 May 2006


Figure 4.4 Foundation Installation Record Sheet

C:\CIGRE\WG07\Foundation Installation\Section4_Final 4.7 May 2006


Details of visual / tactile identification of soil types are given in ASTM D2488 [ASTM 1984]
and BS 8004 [BSI 1984].

For details of the Norwegian practice in respect of on-site verification of the suitability of rock
for transmission tower foundations, reference should be made to Appendix 4A of this report.

4.4.4 Inspection prior to concreting and site bending of reinforcement

Common practice is for the installation contractor to inform the client of his intention to
commence concreting; thus allowing the client to undertake an inspection if so desired
(Notification Point). Similarly, if the installation contractor needs to undertake site bending of
reinforcement, e.g. the bending of the pile reinforcement into a pile cap, this activity would
also be a Notification Point.

Points to be considered in the inspection prior to concreting:

< Cleanliness of the foundation, e.g. ensuring that any rubbish has been removed and the
formwork is coated with a release agent;
< Stub or anchor bolt setting dimensions;
< Rigidity of the stub setting or anchor bolt template;
< Reinforcement cover and rigidity of any reinforcement cage or mat;
< Fixity of formwork to ensure it had adequate stiffness and support to prevent movement or
displacement during concreting;
< Availability of stand by vibrators;
< Site health and safety aspects as appropriate (see Section 5).

The failure by both the installation contractor and the client to undertake an adequate
inspection prior to concreting is shown in Figure 4.5.

Segregated concrete

Bricks to support
concrete
reinforcement

Depression in base
of concrete pyramid

Base of stub, should


be 100 mm above
base of foundation

Exposed concrete
reinforcement should
have 50 mm cover

Figure 4.5 Base of concrete pyramid foundation

C:\CIGRE\WG07\Foundation Installation\Section4_Final 4.8 May 2006


4.4.5 Concrete placing

Although this is a quality control activity, it is imperative to ensure that the concrete is placed
strictly in accordance with the specified requirements, thereby insuring that the problems
identified in section 2, e.g. concrete segregation, honeycombing, formation of cold joints,
necking of cast-in-situ piles, etc., do not occur.

Figure 4.6, illustrates potential segregation of concrete due to the failure to use adequate
concrete chutes.

Figure 4.6 Concrete placing

4.4.6 Concrete identity tests

Concrete identity tests normally comprise workability, air content (if appropriate) and
compressive strength tests.

Workability tests either slump or flow tests, as appropriate, should be undertaken on spot
samples obtained after the initial discharge of 0.3 m of concrete, from the producers
delivery vehicle or alternatively at the point of placing into the foundation. Slump and flow
tests should be undertaken in accordance with the appropriate standards, e.g. EN 12350-2
[BSI 2000f] and EN12350-5 [BSI 2000g], with the acceptance criteria in accordance with
BS 8500 [BSI 2002].

Air content identity tests should be undertaken on composite samples and tested in
accordance with the appropriate standards, e.g. EN12350-7 [BSI 2000h], with the
acceptance criteria in accordance with BS 8500 [BSI 2002].

Compliance with the specified characteristic strength is normally based on tests made on
cubes or cylinders (test specimens) at twenty-eight days. Normal practice is for four test
specimens to be taken from each pour or footing. If the footing requires more than one pour,
a set of test specimens should be taken from each pour. Samples should be taken in a
similar manner to that described for workability tests. Test specimens should be made, cured
and details recorded in accordance with the appropriate standard, e.g. EN 12390-2 [BSI
C:\CIGRE\WG07\Foundation Installation\Section4_Final 4.9 May 2006
2000j] and compressive strength or density in accordance with EN 12390-3 [BSI 2000k] and
EN 12390-7 [BSI 2000m] respectively. Usually, the following procedure is adopted:

< One specimen is tested at seven days to provide an early indication as to whether the
twenty-eight day strength is likely to be achieved;
< Two specimens are tested at twenty-eight days;
< One specimen held in reserve for further testing if required.

Should the twenty-eight day compressive strength criteria fail to be met, then there are a
number of actions that could be undertaken, e.g.:

< Validating the sampling procedure adopted;


< Validating the testing procedure adopted;
< Establishing the location and the extent of non-conformity;
< Considering the degree of non-conformity and its influence on the required strength and
durability of the foundation;
< Considering the scope and the consequences of the proposed remedial action;
< Implementation of measures to prevent reoccurrence of the non-conformity.

The determination of the location and extent of the non-conformity may involve undertaking
either some or all of the following tests:

< Penetration resistance or surface hardness tests;


< The drilling of test cylinders in the suspect concrete and testing of the samples to
destruction by compression.

All testing should be undertaken in accordance with the appropriate standard.

However, the usual cause of failure of a test specimen(s) is poor workmanship in the making,
curing and transporting the test specimen: it should also be noted that in the majority of
cases, the characteristic strength is not the most important feature of the concrete but its
durability, e.g. cement content and the water-cement ratio. Since it is difficult to determine
either the cement content or the water-cement ratio directly, reliance has to be placed on an
indirect measure, i.e. the compressive strength of the concrete.

4.4.7 Concrete returns

The installation contractor should maintain and when requested make available to the client,
a record of the daily returns of the quantity, concrete mix, location and identity test results for
all of the concrete placed.

4.4.8 Concrete curing compounds

Where the installation contractor proposes to use a proprietary concrete curing compound to
protect exposed surfaces of the concrete from solar radiation or to improve moisture
retention, normal practice is for agreement to be requested from the client for its use, e.g. a
Hold Point.

4.4.9 Imported backfill

If it is necessary to import backfill material either due to the unsuitability of the existing soil,
e.g. large boulders or lumps of clay, or where it is necessary to use a flowable material for
directly embedded steel poles, the installation contractor should submit details of his
proposed backfill material, source of supply, the relevant standard(s), if appropriate, and if
necessary his proposed method of backfilling / compaction. This would normally be a Hold
Point.

C:\CIGRE\WG07\Foundation Installation\Section4_Final 4.10 May 2006


Checks on the backfill soil bulk density to ensure that the minimum value assumed in the
design is achieved, could be undertaken using a lightweight dynamic penetrometer or by
undertaking in-situ density tests, in accordance with the appropriate standard, e.g. BS1377-9
[BSI 1990c].

4.4.10 Foundation setting dimensions

The relevant stub setting or anchor bolt dimensions, e.g. back to back of the stubs (face and
diagonal), stub levels and rakes, should be measured prior, during and after concreting.
Records of these measurements should be retained by the installation contractor and made
available to the client upon request.

Where the dimensions, levels or rakes are outside the permitted tolerance values, the
installation contractor should propose the relevant remedial measures to the client. These
might vary from redesign of the splice connection between the stub and the support leg to
removal and reinstallation of one footing. This would normally be a Hold Point.

For details of permitted stub setting tolerances, reference should be made to table 4.2 of this
report.

For guyed supports, typical permitted installation tolerances would be:

< Guy anchor foundations nominal distance from the support centre line " 15 mm or 0.15%
of the guy lane dimension (whichever is greater);
< Guy anchor alignment " 2.5E of the specified guy angle;
< H-poles nominal centre to centre dimensions " 0.1 % of the nominal centre to centre
dimensions.

4.4.11 Foundation proof and integrity tests

Foundation proof tests are undertaken on project foundations or individual elements of a


foundation, e.g. individual piles or ground anchors.

Proof tests should be undertaken on all foundations where the resistance of the foundation is
dependant upon the geotechnical properties of the soil, or where there is doubt of the
reliability of the theoretical design model used. The number of foundations subject to proof
testing will depend on the soil type, the extent of the ground investigation, the heterogeneity
of the subsoils, the type of the foundation and the reliability of the design. Where proof tests
are considered necessary, it is recommended that a least 5 percent of the relevant number of
foundation types or foundation elements should be proof tested. For further details, reference
should be made to IEC 61773 [IEC 1996] and EN 1537 [BSI 2000d].

For drilled shaft, bored cast-in-situ, continuous flight auger or similar types of piled
foundations, low-strain integrity tests should be undertaken on all piles to ensure a
satisfactory level of workmanship is achieved especially during concreting. For further details
reference should be made to ICE Specification for Piling and Embedded Retaining Walls
[ICE 1996], CIRIA Report 144 [CIRIA 1997] and ASTM D 5882 [ASTM 1996].

4.4.12 Early age concrete strength assessment

Occasionally it may be necessary to erect a support on the foundations earlier than the
normal time allowance of seven days after placing. Reliance on cube testing for early-age
strength assessment is usually unsatisfactory because:

< Generally the results come too late;


< The test specimens taken are not necessarily representative of the concrete in-situ;
< The making, storing, transporting, testing of test specimens is non-productive, liable to
C:\CIGRE\WG07\Foundation Installation\Section4_Final 4.11 May 2006
error and is usually impractical for very early-age strength assessment.

In these circumstances, consideration should be given to the use of pull-out inserts cast into
the concrete. The principle behind the test method is that the force required to pull out an
insert cast into the concrete can be correlated with the concretes compressive strength. For
further details, on the use of the Lok-test, reference should be made BCA report Early age
strength assessment on site [BCA 2000].

4.5 Foundation installation records

As part of the overall quality management requirements a foundation installation record sheet
should be prepared for each support location by the foundation installation contractor and,
where appropriate, should be agreed and signed by the client.

The installation report sheet should contain the following information, as appropriate:

< Project and overhead line route reference;


< Support type and number;
< Foundation type;
< Details of the verification of the support location setting out;
< Details of the confirmation of the basic geotechnical parameters;
< Excavation check dimensions;
< Details of the inspections undertaken prior to concreting;
< Concrete identity test results, including details of the concrete mix design, slump or flow
test results, cubes or cylinders taken, compressive test results, etc.;
< Backfilling, giving details of any tests undertaken of the backfill density;
< Stub or guy setting out dimensions after the foundation installation;
< Results of any foundation proof or identity tests undertaken;
< Any other pertinent information, including any changes or modifications made to the
foundation;
< Date and appropriate weather conditions over the foundation installation period.

A typical foundation record sheet is shown in Figure 4.4.

Where it is necessary to distinguish individual footings, an agreed nomenclature should be


used; a typical nomenclature based on UK practice is shown in Figure 4.7.

B C

Lower support Higher support


numbers numbers

A D

Figure 4.7 Footing nomenclature

4.6 Final records

Final as-constructed drawings form a vital part of the quality assurance requirements for a
construction contract. In addition to the as-constructed foundation drawings, the foundation
design calculations, the geotechnical report, foundation installation criteria schedule,
foundation test reports, concrete mix design, etc., should all form part of the final records.

C:\CIGRE\WG07\Foundation Installation\Section4_Final 4.12 May 2006


Care should be taken as regards the choice of the storage medium, to ensure long durability
and that any computer generated records can be retrieved and read in the future.

4.7 Conclusions

The quality assurance principles outlined in this section of the report cannot be considered in
isolation, but must be considered in the overall context of quality, safety and environmental
impact. Correspondingly, the next two sections of this report considers both of these issues
in detail.

C:\CIGRE\WG07\Foundation Installation\Section4_Final 4.13 May 2006


14

Table 4.2 Foundation Setting Tolerances

Face Diagonal Twist of Stub


Country Rake of Stub Stub Levels
Dimensions Dimensions in plan
Max. difference
Linearly from 0 to 10 mm for 0 to between highest and
Belgium 5 m face or diagonal dimensions, lowest stub 2 to 5
5 mm / m 5 mm / m
(Elia) then 10 to 15 mm for 5 to 15 m mm varying linearly
face or diagonal dimension. between 0 and 12 m
face dimensions.
Angles 100 mm Max. difference -0.01< tg < +
France 10 mm / m between each pair of 0.02
10 mm 15 mm
(EDF) Angles > 100 mm stubs 10 mm. + towards
5 mm / m centre of tower.
Max. difference in
level between all 4 Nil Bottom
Nil Bottom
stubs 3 mm; panel of tower
Ireland panel of tower
5 mm 10 mm Max. difference used as stub
(ESB) used as stub
between mean level setting
setting template.
of pairs of diagonally template.
opposite stubs 3 mm.
Difference in levels
between one stub and
Italy 12 mm or 0.2% of face or
0.3 a plane passing 0.5
(ABB) diagonal dimension.
through other 3 stubs
3 mm or 0.1%.

Norway Use of Holding Down Bolts with holes 8 to 10 mm larger than bolt diameter, horizontal tolerance 4
(Stanett) / 5mm, vertical maximum difference 3 mm.

Max. difference in
Spain level between all 4
stubs 0.01% of
(Red 0.15% of diagonal;
0.1% of face
Electrica) diagonal 5 mm /m Max. difference Not defined
dimension
dimension between mean level
of pairs of diagonally
(Iberdrola) opposite stubs
.0.15%.
Max. difference in
level between all 4
stubs 3 mm or
6 mm or 6 mm or 0.01% of diagonal;
1% of width of
0.1% of face 0.1% of diagonal 5 mm /m Max. difference
steel frame
dimension dimension between mean level
of pairs of diagonally
opposite stubs 3 mm
or .0.1%.
Max. difference in
level between all 4
stubs 10 mm or
10 mm or 15 mm or 1 about
UK 1:100 from hip 0.05% of diagonal;
0.1% of face 0.1% of diagonal longitudinal
(NGT) slope Max. difference
dimension dimension axis
between mean level
of pairs of diagonally
opposite stubs 6 mm.
Max. tolerance from
the top of each stub
0.1% of face or
0.1% of diagonal dimension;
USA 0.1% of face 1.6 mm / 300
diagonal Max. difference Not defined
(GAI) dimension mm
dimension between mean levels
of diagonally opposite
stubs 0.1% of
diagonal dimension.

C:\CIGRE\WG07\Foundation Installation\Section4_Final 4.14 May 2006


Annex 4A
Verification of Rock Suitability Based on Norwegian practice

A4.1 Introduction

To ensure that the rock will have sufficient strength to withstand the applied foundation uplift
forces it is necessary to categorize the quality of the bedrock into quality classes thereby
ensuring that the appropriate type of foundation is installed.

The rock can for convenience be divided into four categories or classes, where the fourth
class represents completely weathered rock which can be treated as equivalent to soil.

The rock quality classes and corresponding foundation types are:

Rock Quality Foundation type


1 Good (homogenous) Bolt anchor type A
2 Medium (some fractures) Bolt anchor type B
3 Poor (highly fissured) Bolt anchor type C
4 Very poor, highly weathered similar to soil Soil foundation

A4.2 Rock quality classes

The rock qualities and typical anchorage details are given below:

a) Good rock ~ Bolt anchor type A

The rock is homogeneous without fractures. The anchorage length for ribbed reinforcement
with a diameter of 25 mm is 1.3 m, while that for 32 mm diameter is1.6 m.

b) Medium rock ~ Bolt anchor type B

The rock has some fractures, but it is not faulted. The anchorage length for ribbed
reinforcement with a diameter of 25 mm is 2.0 m for 50% of the bolts and 1.3 m for the
remaining 50%; for 32 mm diameter the anchoring length is 1.6 m. Bolts with different
anchorage lengths shall be used alternately.

c) Poor rock ~ Bolt anchor type C

The rock is of poor quality, highly fissured and faulted. The anchorage length for ribbed
reinforcement with a diameter of 25 mm is between 2.0 m to 3.0 m for 50% of the bolts
(depending on the degree of weathering of the rock) and 1.3 m for the other 50%; for 32 mm
diameter the anchorage length is 1.6 m. Bolts with different anchorage lengths shall
alternate. In addition, it may be necessary to strengthen the area around the foundation
using rock bolts or equivalent; the anchorage length of the rock bolts, depending on the
degree of weathering, should be between 2.0 m to 3.0 m.

d) Very poor rock ~ Soil foundation

The rock is of very poor quality, highly fissured and strongly weathered. In these
circumstances a soil type foundation is installed.

For details of typical rock foundations, reference should be made to Figure 3A.6.

A4.3 Rock quality classification

The main parameters for a simple rock quality classification are the Block size (B) and the
C:\Cigre\WG07\Foundation Installation\Section4A.1_Final 4A.1 May 2006
fracture characteristics and the degree of weathering (S). The grading of the rock type
parameters used in the selection of the appropriate foundation types are shown in table A4.1.

Table A4.1 - Grading of rock type parameters

Parameter Description Grading


>5m 5
1m to 5 m 4
0.5 m to 1.0 m 3
Block size (B)
100 mm to 500 mm 2
100 mm 1
Very weak rock, soil 0
Rough, without filling 5
Plane, without filling 4
Fracture characteristics (S) Rough, open or with clay filling 3
Plane, open or with clay filling 2
Loose, like soil 1

Classes which are defined as number in table A4.1 are of course strongly dependent on rock
type and the geological conditions.

Examples of the application of table A4.1 to different rock and foundation types are given
below.

For classification of the rock qualities determine the sum of the rock type parameters (B+S).

Suitable rock types for the different types of foundations are given in table A4.2. The
illustrations show examples of typical rock types, together with the appropriate foundation
type. However, it must be emphasized that the classification of rock type and the choice of
foundation type will be highly influenced by the surrounding terrain.

Table A4.2 - Example of rock types and foundation types

Sum B+S Description Type of Example of rock types


foundation
Good rock Bolt anchor A Compact rock types with some fractures, e.g.
8 -10
(class I) Gneiss, Granite, Gabbro, Amphibolite,
crystalline Shale.
Medium rock Bolt anchor B Medium fractured rock types, e.g. Gneiss, Granite,
6-7 (class II) Gabbro, Amphibolite, crystalline Shale.
Good, homogeneous and unweathered
Sandstone, Limestone and Phyllites.
Poor rock Bolt anchor C Highly fissured, but little weathered rock types, e.g.
4-5 (class III) Gneiss, Granite, Gabbro, Amphibolite.
Little fractured and little weathered Sandstones,
Limestone, Phyllites and clay Shale.
1-3 Very poor rock, Soil foundation Highly fissured and strongly weathered rock types,
similar to soil Phyllit, black Shale, clay Shale.
(class IV) Alum Shale (caution - aggressive to concrete!).

The classification shown in table A4.2 is applied to all the following figures (B+S = class I, II,
III or IV).

C:\Cigre\WG07\Foundation Installation\Section4A.1_Final 4A.2 May 2006


Figure 4A.1 - Bedrock Gneiss

Bedrock Gneiss B+S = 5 + (3 or 5) Class I


= 8 -10 (good rock)

Figure 4A.2 - Compact non-weathered Phyllite (Hallingskarvet)

Compact non-weathered Phyllite B+S = (3 or 4) + (4 or 5) Class I II


(Hallingskarvet) =7-9 (good medium rock)

C:\Cigre\WG07\Foundation Installation\Section4A.1_Final 4A.3 May 2006


Figure 4A.3 - Typical thick-bedded and fissured Gneiss

Typical thick-bedded and fissured B+S = 2 or (3 + 3) Class II III


Gneiss =5-6 (medium poor rock)

Figure 4A.4 - Typical thick-bedded Quartzite

Typical thick-bedded Quartzite B+S = 3 + 3 Class II


=6 (medium rock)

C:\Cigre\WG07\Foundation Installation\Section4A2_Final 4A.4 May 2006


Figure 4A.5 - Layered and weathered Gneiss

Layered and weathered Gneiss B+S = (2 or 3) + (2 or 4) Class II III


(dagfjell) = 4 -7 (medium poor rock quality)

Figure 4A.6 - Alum Shale

Alum Shale (Hallingskarvet) B+S = (1 or 2) + (1 or 2) Class III - IV


highly fissured and weathered =2-4 (poor rock soil foundation)

C:\Cigre\WG07\Foundation Installation\Section4A2_Final 4A.5 May 2006


5 Health and Safety

5.1 General

Foundation installation can be a hazardous operation both to the site operatives and
members of the general public, if due care and attention is not paid to the health and safety
(H&S) aspects of the work. The information contained in this section of the report is indicative
only and is based on current UK practice. However, it should not be considered as being
complete, nor fully satisfying the requirements of the relevant statutory or approved codes of
practice of the readers own country.

One of the guiding principals of the UKs H&S legislation, is the principle of so far as
reasonably practicable. In other words, an employer (or designer) does not have to take
measures to avoid or reduce the risk if they are technically impossible or if the time, trouble
or cost of the measure would be grossly disproportionate to the risk [HSE 2003]. However, in
strict Health and Safety terms so far as reasonable practical are not measured against cost
and benefit but refer to any means, which are technically possible irrespective of cost.

A diagrammatic representation of the development of health and safety procedures in shown


in Figure 5.1

Design
Assessment

Pre-Tender
H&S plan

Construction
H&S plan

Method Risk Supporting


Statements Assessment Calculations

Site
Inspections

Figure 5.1 - Diagrammatic representation of development of H&S procedures

Within this section of the report consideration is given both to the initial design assessments
and on-site risk assessments, whereby the foundation design or the installation process are
reviewed for their inherent hazards and by a process of hierarchical risk control the risks are
eliminated or at least reduced to an acceptable level. Preparation of health and safety plans
both at the pre-tender and construction phases are also considered, together with the
associated method statements.

C:\CIGRE\WG07\Foundation Installation\Section5_Final 5.1 May 2006


The health and safety aspects of securing the site from the general public and the need for
an excavation checklist are also outlined in this section.

5.2 Design assessments

Under the UKs Construction (Design and Management) Regulations [HMSO 1994], there is
a requirement for all designers to ensure that when they design for construction work they
consider foreseeable H&S risks during the construction, maintenance and eventual removal
of the structure and, that they are in balance with other design considerations, e.g. aesthetics
and costs.

The designers should apply a hierarchy of risk control, i.e. the designers need to identify the
hazards inherent in undertaking the construction work and where possible alter the design to
eliminate them. If the hazards cannot be removed by design changes, the designers should
minimise the risks and provide information about the risks that remain. Information regarding
these residual risks is then contained in the pre-tender health and safety plan. This point is of
particular importance when overhead line support foundations are being refurbished or
upgrading with the support in place, or during any preliminary investigations to ascertain the
condition of existing foundations.

For foundation installation, the following factors may need to be considered:

< Previous use of the site;


< Location of adjacent properties and services;
< The types of soil and/or rock present and their characteristics;
< The level of the ground water and the permeability of the soils;
< Ground or ground water contamination;
< A suitable scheme for temporary support of the excavation and the prevention of falls into
the excavation.

Mitigation measures that could be considered are the use of alternative foundation types,
which require smaller and shallower excavations, e.g. replacing reinforced concrete spread
foundations by driven steel tube piles or micropiles with a small reinforced concrete cap. The
use of driven piles on brownfield (contaminated) sites instead of bored piles eliminates the
need for the removal of contaminated spoil.

For further details regarding risk assessments, please refer to section 5.4 of this report.

5.3 Health and safety plan

5.3.1 General

The H&S plan develops with the project and has two distinct phases; the first is associated
with the design and planning of the project before tendering, the second is associated with
the construction phase. The purpose of the plan is to ensure information relevant to health
and safety is passed on to those who need it. For further details, reference should be made
to Health and Safety in Construction [HSE1996].

5.3.2 Pre-tender health and safety plan

The pre-tender H&S plan may include:

< A general description of the works and details of the project timescale;
C:\CIGRE\WG07\Foundation Installation\Section5_Final 5.2 May 2006
< Details of the H&S risks as they are known, including information provided by designers
about specific project risks they were unable to eliminate and assumptions in broad terms
they have made about precautions which will be taken by the installation contractor to
combat these risks;
< Information required by the potential principal contractor, to allow them to identify the H&S
competences and resources they will need for the project;
< Information on which to base a construction phase H&S plan.

Often the necessary information will already be contained within existing documents, e.g. the
tender documents and design drawings. In these cases the plan can be simply an index to
where the necessary information can be found.

The plan only needs to contain information which is specific to the project and is necessary
to assist in the development of a safe system of working; it does not need to repeat
information which a competent contractor would already know.

5.3.3 Construction phase health and safety plan

For the construction phase the principal contractor (i.e. the contractor appointed by the client
to plan, manage and control H&S during the construction phase of the project), develops the
H&S plan so that it addresses issues which are relevant to health, safety and welfare matters
of the project. Issues which may need to be considered in the plan are:

< How the H&S will be managed during the construction phase, including how information
will be passed to other contractors and how their activities will be coordinated;
< Information about welfare arrangements;
< How the views of site operatives and their representatives on H&S issues will be
coordinated;
< Information on the necessary levels of H&S training required;
< Arrangements for monitoring compliance with H&S law;
< Site H&S rules, e.g. permits to work, and relevant H&S standards where appropriate;

The extent to which a particular item needs to be addressed within the plan will depend on
the degree of risk associated with the project and how much coverage has been given to the
issues in other documentation. Where the risk is low and the issues are covered in the
principal contractors health and safety policy, a simple reference to the safety policy
arrangements may be sufficient.

5.4 Method statements and risk assessments

5.4.1 Risk assessments

a) General
Risk assessments are required during the design phase of the project and prior to
undertaking any hazardous operations on-site. A risk assessment is a systematic
determination of what the hazards are, the probability of harm occurring and the possible
consequences of the harm and its severity. A hazard is the potential for harm, whereas a
risk is the chance or probability that somebody will be harmed by the hazard.

Risk = Hazard Likelihood


effect X of
(Severity) occurrence

C:\CIGRE\WG07\Foundation Installation\Section5_Final 5.3 May 2006


b) Design risk assessments
During the design phase of the project the designer should undertake a risk assessment, to
ascertain whether their design can be constructed, maintained and eventually dismantled
without causing harm to the site operatives or members of the general public.

A precise estimate of risk is not required, under most conditions a qualitative method could
be selected, provided its limitations are recognized. For example three categories of severity
could be assumed, e.g. High (fatality, major illness, etc.), Medium (injury causing short-term
disability) and Low (minor injury). Similarly, the designers need to consider whether the
hazard and the worker will coincide and again only a crude, qualitative judgement need be
made, e.g. High (certain or near certain to occur), Medium (reasonably likely to occur) or Low
(very seldom or never occurs).

The product of the severity and the occurrence will then give some measure of the assessed
risk, which can in turn provide an indication of the action required, i.e. does the designer
need to change his design or can it be accepted without modifications.

As an alternative to a design risk assessment, the designer could produce a Hazard


Elimination and Management list, this list could than be passed to installation contractor on
completion of the design phase of the work. A typical example is shown in Figure 5.2.

Hazardous Residual Hazard Information provided for hazard control


Activity
Foundation Electric shock Note: 11 kV overhead power line crosses the access
Installation overhead power track approximately 50 m from site. (See Drg. No xxx)
line

Figure 5.2 Hazard Elimination and Management List

c) Hazardous on-site operations


Under the UKs Management of Health and Safety at Work Regulations [HMSO 1992], an
employer must identify the hazards involved with their work, assess the likelihood of any
harm arising and deciding on adequate precautions.

The associated risk assessment is usually undertaken in five steps:

< Consider how the job or process will be undertaken, where it is done and what equipment,
materials and chemicals will be used;
< Decide who might be harmed, e.g. employees, or other workers on the site, members of
the general public;
< Evaluate the risks and decide on the action, i.e. is somebody likely to be harmed?
< Record the results;
< Review the findings.

Where there is a risk, the hierarchy of safety controls described in sub-section (d) should be
invoked.

d) Basic hierarchy of safety controls and precautions


The basic hierarchy of safety controls and precautions are:

< Eliminate - Remove the hazard;


< Isolate or contain - Create a barrier between the hazard and people;
< Safe system of work - Use a defined system of working, following safety procedures
designed to reduce risk;
< Training, instruction and information - This should be combined, where appropriate, with
C:\CIGRE\WG07\Foundation Installation\Section5_Final 5.4 May 2006
supervision. Information may include warning signs or notices;
< Personal protective equipment and/or clothing.

e) Typical risk assessment for foundation installation


A typical risk assessment for foundation installation for a concrete pyramid and chimney
foundation is shown in Table 5.1. For convenience, it has been assumed that risk
assessments for material delivery to site, storage of material on site, safe use of lifting gear
and the effect of handling cement / concrete or other substances hazardous to health have
already been undertaken.

Table 5.1 - Foundation installation typical risk assessment

Risk Method of controlling risk


Complete collapse of excavated hole with All excavations over 1.2 m deep are close
persons working in excavation. sheeted and framed.
Persons falling into excavation when not All excavations are fenced or side sheeting
working above open excavation. extended above ground level.
Spoil stacked by hole falls into excavation Material to be stacked a minimum of 1.5 m
onto persons working below. from edge of excavation.
Mechanical excavator too close to
Stop boards positioned 1m from edge of
excavation edge causing partial collapse and
excavation.
or excavator falling into excavation.
Objects falling on persons working in
Safety helmets to be worn at all times.
excavation.
Persons falling during access / egress to Ladders to be used for access and to be
excavation. adequately secured.
Instability of excavation arising from high
Use of pumps or de-watering plant installed.
ground water table and or accumulation of
water in excavation.
Risk of foot medical problems Use of personal protective equipment.
Back strain due to handling stub setting
Use of mechanical lifting plant.
template, etc.
Risk of falling when working on chimney
Ladders and use of safety harness.
section of formwork.
Formers are prevented from upward
Poured concrete forces bottom foundation
movement by use of timber sprags to sides
formers upwards and dislodges whalings
of excavation. Wedges driven into upper side
resulting in collapse of sheeting.
of whalings prevent upward movement.

5.4.2 Method statements

The H&S method statement sets out how a hazardous job or process will be carried out,
including all the control measures which will be applied; this will assist in planning the work
and identifying the health and safety resources required. In addition, it is an effective and
practical way of providing information to the site operatives about how the work is expected
to be done and the precautions to be taken.

Method statements should include details of safe means of access and egress from the site,
arrangements for a safe place of work on site, plant and equipment to be used, training and
competence, specific hazards to be expected, measures to control the hazards, routine
inspections to be undertaken, precautions or limitations on the activities of others in the
vicinity and a cross-reference to the associated risk assessment. For further information,
reference should be made to Health and Safety for Engineers [Thomas Telford 1996].

C:\CIGRE\WG07\Foundation Installation\Section5_Final 5.5 May 2006


5.4.3 Supporting calculations

As part of the risk assessment or the preparation of the method statement, supporting
calculations may be necessary. Typical examples would be if a foundation is subject to a
reversal of loadings, e.g. a spread footing designed for compression is required to take uplift
under a temporary loading condition, or an existing foundation is being partially uncovered as
part of a preliminary investigation or during refurbishment/upgrading activities with the
support and conductors still in place.

5.5 Site access

One of the major safety issues connected with site access and/or work on-site, is that
associated with working adjacent to, or underneath live overhead lines. For site access
normal procedure is to use a height barrier as shown in Figure 5.3.

Figure 5.3 - Typical overhead line height barrier

5.6 Foundation installation

5.6.1 General

All construction sites should be fenced-off from the general public and/or from other site
activities. The types of fencing will reflect the degree of risk involved and whether the site is
enclosed in an overall protected area. Typical fencing would be timber paling with a suitable
lockable gate, ensuring that in agriculture areas the site is fully stock proof at all times. In
areas adjacent to public areas or highways, it may be necessary to use 2.0 m high steel link
fencing. In addition, warning notices and lighting may need to be provided.

Sites should be kept clean and tidy, with materials safely stored and all working areas should
be free from obstructions. In addition, there should be proper arrangements for collecting and
disposal of waste and, if appropriate, additional lightning should be provided if it is envisaged
that work will be undertaken in poor natural lighting or in the dark.

5.6.2 Excavation health and safety checklist

The following checklist identifies some of the hazards most commonly found on a foundation
installation site:

C:\CIGRE\WG07\Foundation Installation\Section5_Final 5.6 May 2006


< Has the site been checked for utility services, e.g. gas, water, electricity,
telecommunications, etc;
< If appropriate, has the site been checked for unexploded ordinance;
< Is there an adequate supply of timber, trench sheets, props or other supporting material
available before excavation works start;
< Is the material strong enough to support the sides of the excavation, see Figures 5.4 and
5.5;
< Is a safe method used for putting in the excavation supports, i.e. one that does not rely on
people working within an unsupported excavation;
< Is there a suitable method statement covering the use of explosives for excavation
purposes;
< If the sides of the excavation are sloped back or battered, is the angle of batter sufficient
to prevent collapse;
< Is there an adequate method available to deal with any ground water entering the
excavation, including ensuring that existing field or temporary drains are in working order,
see Figure 5.6.
< Is there safe access to the excavation, e.g. by a sufficiently long, secured ladder;
< Are there guard rails or is there other equivalent protection to stop people falling in;
< Are properly secured stop blocks provided to prevent vehicles falling in;
< Does the excavation effect the stability of neighbouring structures, this in particularly
important if groundwater control processes are used;
< Are stacked materials, backfill, spoil or plant stored near the edge of the excavation likely
to cause a collapse of the sides;
< Is the excavation inspected by a competent person at the start of each shift: and after any
accidental collapse or an event likely to have affected its stability.

If it is proposed to use explosives for excavation purposes, their use and storage must be
undertaken strictly in accordance with all appropriate civil and, if appropriate, military
requirements.

Figure 5.4 Inadequate support of sides of Figure 5.5 Failure of surrounding soil
excavation
C:\CIGRE\WG07\Foundation Installation\Section5_Final 5.7 May 2006
Steel trench sheeting supporting
sides of excavation

Steel support I-sections


(Whalings)

Failure of lower section of trench


sheeting and excavation support
system

Figure 5.6 - Failure of an excavation support system

The cause of the failure was due to water from broken field drains being allowed to soften the
ground behind the excavation, thereby causing a complete rotational slip of the supported
material and failure of the excavation support system. The steel trench sheeting had been
driven to a minimum of 1 m below the depth of the excavation.

5.7 Summary

Good health and safety practices can be summarised as follows:

< The adoption of good working practices, ensuring that unofficial and unsafe systems of
working are eliminated by site inspections and H&S audits;
< Provision of adequately trained and motivated site operatives;
< Ensure that design assessments and pre-tender health and safety plans concentrate on
the hazardous operations that a competent contractor could not foresee;
< Ensure that, where applicable, site specific risk assessments and method statements are
prepared for hazardous operations;
< Ensure the site is kept tidy, simple checklists are used and adequate inspections are
undertaken;
< Ensure that there is effective communication between all parties to the work, i.e. the
designers, site engineers and site operatives is in place;
< Ensure that timely action is taken if the assumptions made in the design regarding the
ground conditions, e.g. ground water level, soil and/or rock strength etc., are not found on-
site.

While this section of the report has concentrated on specific health and safety aspects in
relation to foundation installation, the general H&S requirements in respect of the control of
substances hazardous to health, noise, manual handling, provision of personal protective
equipment, etc., should not be overlooked.

C:\CIGRE\WG07\Foundation Installation\Section5_Final 5.8 May 2006


6 Environmental Impact and Mitigation

6.1 General

This section of the report deals specifically with the environmental impacts and the
associated mitigation measures related to overhead transmission line support foundations.
For details regarding the overall issue of environmental impacts of overhead transmission
lines, reference should be made to Cigre Technical Brochure 147 [Cigre 1999b].

Since the installation of the foundations is the first major activity associated with the
construction of an overhead transmission line, the affect of the access route construction on
the environment is also considered in this section of the report.

Potential environmental impacts caused by the foundation installation process including the
provision of site access are reviewed in this section of the report. Possible mitigation
measures, e.g. the use of temporary access systems or alternatively the use of helicopters
are considered, together with means to reduce the impact caused by the actual foundation
installation process.

6.2 Environmental impact

Both the local environment and the communities adjacent to the route of the overhead
transmission line are affected by the construction activities, with access construction and
foundation installation having a major impact. Consequentially, the adoption of the
appropriate mitigation measures can significantly reduce the environmental impact of an
overhead transmission line during the construction phase.

Potential environmental impacts, which may occur, during access construction and
foundation installation activities include:

< Increase in traffic on local roads, especially as regards the delivery of plant, equipment
and materials, e.g. excavation or piling equipment, supply of ready-mix concrete;
< Impact of access tracks on the environment;
< Disturbance of land and vegetation management;
< Vegetation and tree removal;
< Noise, dust and vibrational pollution;
< Soil erosion and pollution of water courses;
< Disturbance to birds and other fauna;
< Foundation installation, including the dispersion of contaminated soil or ground water.

Other impacts that may occur are:

< Disturbance to farming, agriculture and other business or leisure activities;


< The clients relationships with landowners, grantors, local authorities and other statutory or
public agencies;
< Disturbance of archaeological remains.

While it is not possible to completely remove all of the potential impacts, described above, it
is possible to at least reduce their impact and therefore to a degree, the publics and/or
landowners/grantors perception of the affect of overhead transmission line construction on
the environment.

C:\CIGRE\WG07\Foundation Installation\Section 6_Final 6.1 May 2006


6.3 Environmental mitigation

6.3.1 Design phase

As an integral part of the planning and consent process, the majority of new overhead
transmission lines are subject to an environmental assessment, e.g. The Electricity Works
(Environmental Impact Assessment) (England and Wales) Regulation 2000' [HMSO 2000].
This requirement has also been extended to cover the constructional activities associated
with the refurbishment and/or upgrading of existing overhead transmission lines. Both an
initial desk-top study and site assessments would be undertaken to establish which of the
existing support sites are likely to be affected by environmental and/or archaeological
constraints. The area to be considered would possibly extend to include a buffer zone 500 m
wide either side of the route centre line and including the access roads/tracks.

Overhead transmission line support sites, which are located in designated areas of
importance under international conventions or by national regulations, will require specific
studies to be undertaken in consultation with the appropriate statutory bodies, within the UK
these would be:

< Wetlands of International Importance under the Convention of Wetlands of International


Importance Especially as Waterfowl Habitat (Ramsar Convention 1976);
< Classified under European Community Directive 79/409 on the Conservation of Wild
Birds;
< Classified under European Directive 92/43/EEC on the Conservation of Natural Habitats
of Wild Fauna and Flora;
< UK Sites of Special Scientific Interest or National Nature Reserve.

In conjunction with the environmental studies, a separate study is usually undertaken in


respect of determining whether any support site, or the area adjacent to any site, may have
an archaeological interest.

Once the studies outlined above have been completed and depending on their outcome in
terms of the environmental and archaeological impacts, it may be necessary to prepare a site
environmental plan, detailing the mitigation measures required.

Mitigation measures that can or may, need to be taken are:

< Commencement of early consultations with the appropriate statutory or voluntary bodies,
to ensure that necessary notifications, agreements, consents etc., are made and/or
received prior to proposed commencement of site activities;
< Removal of any bird nests in the proposed or existing support location during the non bird
nesting period prior to commencing site work;
< Vegetation management, e.g. tree lopping and/or hedge trimming and/or removal, before
the commencement of any site work;
< Translocation of any protected species of fauna from the working area;
< Working outside the bird nesting period, over-wintering period of migratory birds or fauna
breeding period;
< Adoption of special access procedures, or installation techniques;
< Use of low emission equipment, use of silent or equipment with a low noise profile;
< Minimizing the number of trips to the site or reduced working periods.

Archaeological mitigation measures might include the necessity for a watching brief during
the foundation installation.

With regards to the actual design of the foundation, mention has been previously made of the
C:\CIGRE\WG07\Foundation Installation\Section 6_Final 6.2 May 2006
use of alternative foundation types, which may lessen the overall environmental impact, e.g.
the use of micropiles, driven steel tube piles, helical screw anchors, etc., as an alternative to
conventional reinforced concrete spread foundations. However, this may have to be
counterbalanced against the possible temporary increase in environmental impact during the
installation phase from the use of larger plant and equipment.

Where foundations are located in contaminated sites, there is a need to control the migration
of pollutants to the surrounding area and particularly aquifers, especially when piled
foundations are being considered. For further information, regarding piling and other ground
improvement methods on contaminated land, reference should be made to the National
Ground Water and Contaminated Land Centre Report NC/99/73 [EA 2001]. An example of
a solution to overcome the problems associated with installing support foundations in
contaminated ground is detailed below:

The ground conditions at the support sites under consideration had a 2 m clay cap, 6 m
depth of landfill, and 2 to 3 m of virgin clay above layers of sand and peat, above the Keuper
Marl. The sand and peat layers acting as a minor aquifer. The particular problem was that
Tritium from a university physics laboratory experiments had dissolved into the
leachate. The other waste included incinerator ash, some food waste and low level
radioactive waste from the local hospital X-ray facility. The latter had decayed to background
radioactive levels and was simply re-buried.

The landfill was excavated down to the virgin clay over an area which was at least 1.5 m in
length and width greater than the footprint of the piles. Clay of low permeability was used to
fill the excavations up to ground level, was compacted in layers with a swing machine, and
the steel tubular piles were then driven through the new clay - in effect each tower is
standing on a clay island. The environmental agency responsible subsequently monitored
the local groundwater, and no rise in contamination was found. No problems were
encountered due to settlement of the clay, but the method adopted is not considered to be
applicable with raked concrete piles. The additional cost (circa 1998) was approximately
15,000 for each tower site, compared to 6,000,000 to underground the 6 circuits around
the landfill.

Leachate flooding the excavations was a problem; however, this could be overcome by
spraying it over the site and allowing it to evaporate, once consent had been obtained from
the owner and the weather was suitable. When the work commenced, the weather was cold
and wet, and the installation contractor had to transport the leachate away to a licensed
disposal site at considerable expense. Subsequentially, the installation contractor kept two
excavations open all the time, and pumped from the one which was to be backfill into the
other. For the final excavation the installation contractor was able to spray the remaining
leachate over the site.

Other environmental mitigation measures, which could be considered at the design stage (in
the widest environmental context), are the use instead of Portland cement of alternative
cementious materials, which in themselves are waste by-products from other industrial
processes, e.g. use of pulverised fly ash or blast furnace slag. In the same context,
consideration should also to given to the use reclaimed aggregates, EN 206 [BSI 2000a],
permits the use of both recycled aggregates or recycled crushed concrete in the production
of concrete.

6.3.2 Site access

The successful planning and construction of site access roads or tracks, modifications to field
fences and/or hedges, gateways, etc. (accommodation works), will obviously make a
significant contribution to the overall impact of the project, both in terms of the environmental
C:\CIGRE\WG07\Foundation Installation\Section 6_Final 6.3 May 2006
impact and the relationship with landowners, grantors and the general public, and where
appropriate the environmental protection agencies. The need to commence early
negotiations with landowners, grantors, civic authorities, environmental protection agencies,
etc., is highly recommended.

Consideration will also be required in respect of the use of public roads by site traffic, with
particular reference to road width, weight limits on bridges, clearance to structures or
overhead lines, location of schools or other areas where there is a concentration of children,
etc. Any traffic management scheme will need to be agreed with the responsible authorities.

Wherever possible use should be made of existing tracks as access roads/tracks, although
they may need to be upgraded, depending on the existing wearing surface, drainage
conditions, general ground conditions and the anticipated volume and size/weight of site
traffic using the proposed access. Consideration may also need to be made in the respect of
provision of temporary bridging of water courses or drainage systems. The removal of
hedges, fences, widening of gateways and possible insertion of new entrances from the
public highway, will all need control and agreement with the appropriate parties. In addition,
the landowner/grantor should not be put to any inconvenience in gaining access to his
land/property by the installation contractors use of the access route.

Where new access tracks are required, these should wherever possible, follow the natural
contours of the terrain to minimise cut and fill quantities. Care should also be taken to
minimise the effect of erosion caused by water runoff and siltation of water courses. For
further details regarding the control of water pollution reference should be made CIRIA report
C648 [CIRIA 2006].

Consideration should also be given to the use of special temporary access systems, i.e.
aluminium track way panels or temporary stone roads (i.e. crushed imported stone laid on a
geotechnical membrane), see Figure 6.1. The effect of failing to install a temporary access
system is shown in Figure 6.2.

Aluminium track way panels Temporary stone roads

Figure 6.1 - Temporary access system

As an alternative to the use of special temporary access systems, consideration should be


given to the use of low ground pressure vehicles, thereby preventing excessive soil
compaction or damage.
C:\CIGRE\WG07\Foundation Installation\Section 6_Final 6.4 May 2006
Figure 6.2 The consequences of failing to provide a temporary access system

The cost and temporary environmental impacts (increase in local traffic and noise level etc.),
must be weighed against the benefits, i.e. protection of environmental sensitive areas,
reduction in soil compaction and reduction in avoidable land damage. In addition,
consideration should also be given to extending the temporary access system to provide a
working-platform at the tower site for plant and equipment; although the benefits in reduction
in land damage, etc., may have to be weighed against the detrimental effects of extended
seasonal working periods and hence temporary environmental impacts. Other benefits that
will accrue from the use of special temporary access systems will be a reduction of soil
deposited on the public highway and may lessen the possibility of the spread of soil borne
diseases in agricultural crops, e.g. Rhizomania in Sugar Beet.

6.3.3 Helicopters

As an alternative to the use of access tracks, it may be necessary to consider the


transportation of materials, equipment and site operatives by helicopter, see Figure 6.3. The
use of helicopters may be a condition of the planning consent of the overhead transmission
line route, because the route passes through sensitive ecological areas or as an economic
alternative to the construction of long and expensive access tracks from the nearest public
highway.

One of the key features of the use of helicopters is the need for careful planning prior to
commencing the work, taking into consideration payload limitations, duration and altitude
limit of the helicopter, downtime for helicopter maintenance, weather conditions, possible
need to breakdown installation equipment into manageable units, the establishment of
strategically placed depots for the transfer of materials, equipment and personnel from road
to air and possibly changes in the concrete mix design to allow for longer periods of
workability.

C:\CIGRE\WG07\Foundation Installation\Section 6_Final 6.5 May 2006


Figure 6.3 - Transportation of foundation concrete by helicopter

6.3.4 Foundation installation

Potential mitigation measures that the foundation installation contractor can undertake are:

< Removal of the topsoil and vegetation for subsequent reinstatement;


< Where it is necessary to bench the site, because of excessively steep hillsides or cross-
falls, ensuring that this does not become a cause of future soil erosion;
< Keeping the top soil separate from the subsoil during on-site storage prior to backfilling.
Note top soil should not be stock piled to a height greater than 2 m to prevent damage to
the soil structure;
< Fencing off the site working area to prevent injury to farm livestock or wild animals;
< Preventing the contamination and/or siltation of water courses arising from removal of
water from the excavation or surround area, e.g. well point dewatering;
< Ensuring that the removal of any ground water, does not affect adjacent land or
properties;
< Controlled disposal of contaminated soil or materials used in the installation process, e.g.
excavation stabilizing fluids (bentonite), or the use of polymer based drilling aids which
can be broken down with an oxidizing agent for safe disposal;
< Prevention of fuel, oil, concrete or grout spillages;
< Use of synthetic (biodegradable) oil for hydraulic lubrication as opposed to mineral oil;
< Ensuring all material wrappings, general site litter, etc., are removed off-site on a daily
basis;
< Possible restriction in the hours of working and control of noise, dust and vibration
pollution;
< Use of wheel washing facilities or regular sweeping of public roads;
< Ensuring that site is secured against vandalism, all plant and equipment are immobilised
when not in use and that all chemicals are correctly stored, etc.;
< Having a contingency/emergency plan ready, in the case of an environmental accident on-
C:\CIGRE\WG07\Foundation Installation\Section 6_Final 6.6 May 2006
site.

Although, not strictly an environmental mitigation measure, it may be necessary for an


archaeologist to be present on-site, if the preconstruction archaeological survey has
indicated the site to be of potential historical interest.

For further information regarding environmental good practice on-site in the UK, reference
should be made to CIRIA Report C 502 [CIRIA 1999].

6.3.5 Site reinstatement

Site reinstatement should include, as appropriate, the following actions:

< Reinstatement of site drainage and/or provision of new site drainage;


< Controlled spreading of excessive spoil from the foundation;
< Reinstatement of hedges, etc.;
< Replanting of removed flora;
< Removal of access roads/tracks.

The sequence of the reinstatement will obviously depend on the construction activities and to
a degree will not be completed until all site work has been finished.

6.4 Conclusions

This section of the report has considered the potential environmental impacts arising from
both the site access accommodation works and the actual foundation installation. The actual
environmental impact will obviously depend on the environment of the transmission line route
and the type and size of the support foundations being installed.

Possible mitigation measures include the initial environmental assessment, the preparation
of a site environmental plan, the use of temporary access systems or alternatively the use of
helicopters for the transportation of plant, material and site operatives. Since any mitigation
measure will, to a degree, have an impact on the foundation installation and possibly the
actual design of the foundation; it can not be considered in isolation, but must be considered
as part of the overall interaction between the foundation installation, foundation design, the
associated quality management, and health and safety requirements for the scheme.

C:\CIGRE\WG07\Foundation Installation\Section 6_Final 6.7 May 2006


7 Foundation Costs

7.1 General

The support foundations represents between 14 and 23 percent of the total cost of an
overhead line, with an average value of 19 percent [Cigr 1991]. This average value remains
reasonably constant and is not affected by changes in the transmission line voltage, circuit
configuration (single or double circuit) and support type. Similarly, the percentage breakdown
between material supply and installation also remains reasonably constant at 65 percent to
35 percent.

The factors which have the greatest influence on the foundation cost are:

< The foundation type which is to a degree dependant upon the support type;
< The magnitude of the applied loadings;
< The geotechnical conditions of the in-situ soil and/or rock.

The Cigre foundation cost study [Cigre 1996], indicated that:

< Foundation costs were a linear function of the load capacity for a given foundation type
per soil condition and location;
< That for compact foundations for a 10 percent change in load, there was a 2 to 8 percent
change in cost;
< For spread footings with an initial high uplift resistance, for a 10 percent change in load,
there was a 9 to 10 percent change in the cost.

From the above, it can be seen that there are no universal rules that can be developed for
support foundation costs and this to a degree is a reflection of the difference in costs in
relation to different foundation types which in itself is a reflection of the variability of the
ground conditions.

Other factors which may influence the selection of foundation type and hence its cost are:

< Environmental, e.g. topography, climate, contamination and access requirements, e.g. the
predominate use of steel grillage foundations in Canada;
< Resource limitations;
< Health and safety requirements.

The price or rate for the foundation, in other words what the foundation installation contractor
gets paid by the client, will in addition to the factors described above, depend on the method
of measurement and payment plus the allocation of risk between the client and the
installation contractor. Details of typical methods of measurement and payment are given in
the following sections of this report.

7.2 Allocation of risk

With regards to the allocation of risk between the client and the installation contractor, for the
foundation installation this specifically relates to the question of the in-situ geotechnical
conditions. Either, the foundation installation contractor carries the majority of the risk, based
on a fixed all-inclusive rate with limited geotechnical information at the time of tendering or
whether the risk is shared, based on a re-measured fixed rate with extras payments for
changes in the assumed ground conditions. Obviously, there are intermediate levels of risk
allocation, whereby the client undertakes the geotechnical investigation prior to the tender
stage or undertakes the actual foundation design. Other factors which need to be considered
C:\CIGREWG07\Foundation Installation\Section 7_Final 7.1 May 2006
are the question of foundation testing and the risk of a test failure, whether environmental
assessments (impacts) have been undertaken and the associated mitigation measures
agreed with the relevant authorities before the tender stage.

In respect of the geotechnical risks, it is interesting to note that the final warning in the paper
by Littlejohn, Cole and Mellors entitled Without site investigation ground is a hazard [ICE
1994], states That you pay for site investigations whether you have one or not, and you are
likely to pay considerably more if you do not, or if it is inadequately designed, executed or
interpreted. Consequentially, it is preferable if the client undertakes a reasonable extensive
geotechnical investigation prior to going out to tender.

7.3 Methods of measurement and payment

During the past twenty to thirty years, there has been a noticeable change in the method of
measurement and payment for OHL support foundations, from a re-measured fixed rate with
extras payments for changes in the assumed ground conditions, to one of inclusive prices
based on a fixed rate with no re-measure apart from piled foundations, and this only in
respect of pile length.

Typically in the UK until the early 1980's, foundation contract prices were based on:

< A fixed unit rate for a standard foundation per tower type (inclusive of all tower
extension); based on normal ground conditions, irrespective of access conditions, ground
slope, subsoil conditions or the presence of water, unless the Engineer certified the
conditions as abnormal. The rate of a standard foundation to include the supply of all
materials and all site work in respect of the foundation installation, e.g. setting-out,
excavation, excavation support, stub setting, concreting, backfilling, site reinstatement,
etc.

If the Engineer certified the conditions as abnormal, additional payments, based on fixed
rates, would be made in respect of the following items, all subject to re-measured quantities:

< Additional excavation, related to the difference in ground level between any two stub
positions exceeding 1.5 m, after taking into consideration the use of differential leg
extensions. Note that an allowance was made with regards to the excavation plan area
being 0.45 m wider than the foundation base area.
< Close timbering (support) of the foundation excavation due to poor soil conditions was
required, based on the assumption that for normal ground conditions only 50% of the
excavation sides would be timbered. Additional payment, based on the difference in cost
between close timbering and the cost of 50% timbering.
< Additional pumping was necessary in excess of that required to remove overnight
accumulation of water in the excavation: payment based on the pump size and the hours
of pumping.
< Rock was encountered in the excavation, which could not be removed by pick and shovel
and was unsuitable for a rock foundation.
< Piling was required. Payment based on piling sub-contractors cost plus a percentage to
cover main contractors on-costs.

Standard foundations suitable for normal ground conditions, were spread footings either
reinforced concrete pyramid and chimney foundations or drilled shaft (augered) foundations.
Normal ground conditions were defined in terms of the maximum allowable bearing pressure
of the foundation in conjunction with an assumed frustum angle for, use in uplift resistance
calculations.

C:\CIGREWG07\Foundation Installation\Section 7_Final 7.2 May 2006


Taking into consideration the need to have a stricter control of the final contract price,
especially when the overhead transmission line is being financed by an international aid
agency or a private bank loan and the reduction in clients site supervisor staff, there has
been a change from a fixed rate re-measured method of pricing to an all-inclusive approach.

A typical method of measurement and payment for support foundations based on an


inclusive cost approach would be:

< The rates for foundation supports shall include for site clearing, geotechnical investigation
(assuming that this has not already been undertaken by the client), excavating in any
material and by any means, manual or mechanical, and for ensuring stability and natural
drainage inside the working area including pumping and well-point dewatering, excavation
support, concrete work, formwork, concrete reinforcement, stub steelwork, stub cutting,
routine testing, for all backfilling, compacting and disposal of surplus material, site
restoration and all other work required to complete the foundation in accordance with the
technical specification.
< In addition, the rate shall include for the use of any type of cement or density of concrete
required to ensure the durability of the foundation, the supply of weak-mix concrete or the
importation of any backfill material necessary due to the excavated material being
unsuitable as backfill.
< The rate for foundations shall include all stub steelwork installation and setting out,
including the use of templates, setting to any level and any excavation necessary for
setting out. The protective treatment to defined concrete faces or support steelwork,
provision of site protective barriers and foundation earthing as necessary.
< Design tests to prove the foundation design shall be paid for at the rates quoted and shall
include for the removal of the foundation to a defined depth below ground level.

Support foundations would be defined in terms of permitted types of foundations, e.g. spread
footings, anchor or piled for a range of soil categories. Soil categories are usually described
in terms of soil and backfill density, the internal angle of friction of the soil, allowable bearing
and lateral earth pressures, etc., and the correlation with geotechnical investigation, e.g.
standard or cone penetration tests.

Even if this approach is adopted, additional work in respect of the provision of access
development or the use of helicopters for the transportation of materials and plant would be
paid for as an extra.

7.4 Conclusions

Irrespective of the method of measurement and payment adopted for the foundation design
and installation, the actual total cost of the foundation, i.e. the design, supply of material and
installation and hence the total cost of the project, can be reduced if sufficient time is spent in
the preparation of the work prior to the actual commencement of the installation. This
effectively means reducing the risk due to geotechnical uncertainties, environmental impacts,
access development, quality, health and safety, and especially effective communications
between the client, foundation design and foundation installation contractor.

C:\CIGREWG07\Foundation Installation\Section 7_Final 7.3 May 2006


8 Summary

8.1 General

Although the support foundations typically only represents nineteen percent of the total cost
of an overhead transmission line [Cigre 1991]: the actual installation process differs from that
of all the other transmission line components, in that it is undertaken in a variable medium
which can rapidly change not only between support locations but also between adjacent
footings on the same support site. This variability of the in-situ soil or rock and the ground
water level, can have a marked influence not only on the long term performance of the
foundation, but also on the short term success of the scheme, unless the interaction between
the foundation design and installation is carefully controlled. The failure to control this
interaction has been demonstrated in Figures 1.3 and 2.6, and is further illustrated in Figure
8.1.

Figure 8.1 ~ Failure of the Tully Falls Townsville 132 kV OHL, Queensland, Australia

< Foundation installed in dry season with no consideration


Failure due to a combination given to potential change in ground water level, i.e.
of circumstances: standard non-buoyant foundation ;
< General reduction in ground level (0.5 m to 0.75 m) due to
adjacent agriculture activities and subsequent soil erosion;
< High ground water table after heavy rain (at or near
ground level) in conjunction with cyclonic winds

This report has attempted to demonstrate that to achieve both the intended performance and
service life of the support foundations, the installation process cannot be viewed in isolation,
but must be considered as an evolving process that has a continuous interaction with the
foundation design. Furthermore, the interaction with respect to the environmental impact of
the actual foundation installation and associated access, the health and safety of the site
operatives and general public must also be taken into consideration.
C:\CIGREWG07\Foundation Installation\Section 8_Final 8.1 May 2006
8.2 Foundation design

To provide initial guidance to the readers of this report, the relationship between the support
types, i.e. broad based lattice towers, externally guyed supports, monopoles or narrow based
lattice towers and H-framed supports, the primary applied foundation loading, e.g. vertical
uplift and compression forces for broad base lattice towers or overturning moments for
monopoles and the principal foundation types, e.g. separate, anchor and compact, has been
provided in section 1 of this report and is shown diagrammatically in Figure 1.4.

To assist the readers further, a description of individual foundation types within each of the
three principal categories of foundations considered has also been given in that section, i.e.:

< Separate Spread footings, e.g. pad or pyramid and chimney, grillage;
Drilled shafts;
Piled, i.e. driven (displacement) and bored (no-displacement).
< Anchor Ground, Block, Helical screw, Deadman.
< Compact Monoblock, Direct embedment and Raft

8.3 Interaction with the design process

The interaction between the foundation installation activities and the foundation design
process has been considered in section 2, for each of the individual types of foundation
described above. This interaction has been portrayed by the use of interaction diagrams and
descriptive tables, which for each foundation type highlights the key design parameter, the
associated installation activity and the effect on the foundation design.

The effect on the foundation design can, as has already been stated, be summarised as a
potential reduction in the foundations geotechnical design strength and a reduction in the
long term durability of the foundation and hence its service life. The major causes of these
potential effects can be ascribed to the following foundation installation activities:

< Changes in the assumed geotechnical conditions during the foundation installation;
< Incorrect foundation excavation or installation techniques;
< Poor dimensional control of the foundation overall size or in the stub and/or holding bolt
setting;
< Inappropriate concreting techniques, e.g. placing, compacting or curing;
< Inappropriate techniques or controls during the backfilling of the foundation.

8.4 Foundation installation activities

To ensure that the foundations are correctly installed and the effects described in section 2
do not occur, section 3 of this report provides an overview of the accepted good practice with
respect to the foundation installation activities.

Foundation installation can be considered as a series of discreet interrelated activities, which


for convenience can be divided between the pre-site activities i.e. the activities that are
undertaken prior to the commencement of the contract foundation installation and those
undertaken as part of the main works. The pre-site activities including the preparation of
foundation installation drawings, the concrete mix design, the preliminary foundation design
tests and the preparation of the foundation installation criteria schedule detailing for each
support location the type of foundation to be installed. The main works activities encompass:
setting out of the foundations, excavation including the control of ground water, the
C:\CIGREWG07\Foundation Installation\Section 8_Final 8.2 May 2006
installation of drilled shafts and piles, concrete production, delivery and placing, backfilling of
the excavation, and site reinstatement.

To provide further guidance to the reader, a selection of photographs illustrating different


sequences in the installation process has been provided in section 3A.

8.5 Quality management

The need to ensure the that the project works comply with project requirements has been
considered in section 4 of this report, with respect to the quality assurance and quality control
requirements associated with foundation installation activities.

The pre-project activities relate to the foundation design process, the vetting of proposed
suppliers or sub-contractors, the concrete mix design, the foundation design tests and the
foundation installation criteria and associated method statements. The project foundation
installation activities encompassing: setting out, verification of the foundation design soil
/rock parameters, concrete placing and identity tests, backfilling, foundation proof and
integrity tests.

While it is not restricted to foundation installation the question of the final as-installed
records, is also considered in this section of the report.

8.6 Health and safety

The health and safety of the foundation installation contractors site operatives and members
of the general public in respect of foundation installation activities, has been outlined in
section 5. This has been based on current UK practice and may not be completely applicable
to the readers own local statutory requirements or accepted local practice.

One of the guiding principals of UKs H&S legislation is the principle of so far as reasonable
practical; in others words an employer does not have to avoid or reduce the risks if they are
technically impossible or if the time, trouble or cost of the measure would be grossly
disproportionate to the risk. However, in strict Health and Safety terms so far as reasonable
practical are not measured against cost and benefit but refer to any means, which are
technically possible irrespective of cost.

Health and safety stems from the designer ensuring that this proposed design can be safely
built, maintained and eventually removed. Where the designer identifies a hazard, he should
if possible eliminate, or minimise the risk or where this is not possible identify the residual
risks.

The need for employers to undertake risk assessments of hazardous on-site operations,
preparation of method statements and excavation health and safety checklists are also
considered in this section of the report.

8.7 Environmental impact and mitigation

The environmental impacts associated with the foundation installation and the associated
accesses considered in section 6, can be summarised as: increase in traffic on local roads,
impact of access tracks, disturbance of land and vegetation management, noise, dust and
vibrational pollution, soil erosion and pollution of water courses, disturbance to birds and
other fauna, and the effect on the flora surrounding the support site.

C:\CIGREWG07\Foundation Installation\Section 8_Final 8.3 May 2006


Mitigation measures described include undertaking an environmental (ecological) impact
assessment, use of temporary access systems or helicopters (see Figure 8.3) and controls
during the foundation actual installation, e.g. removal of top soil and vegetation for
subsequent reinstatement, prevention of spillages on sites, restrictions in working hours etc.

Figure 8.3 Transportation of foundation concrete by helicopter

8.8 Foundation cost

The support foundations represents between 14 and 23 percent of the total cost of an
overhead line, with an average value of 19 percent [Cigr 1991]. This average value remains
reasonably constant and is not affected by changes in the transmission line voltage, circuit
configuration and support type. Similarly, the relative percentage breakdown between
material supply and installation also remains reasonably constant at 65 percent to 35
percent.

The factors which have the greatest influence on the foundation cost are: the support type,
the magnitude of the applied loadings, the foundation type and the geotechnical conditions.

With respect to support foundation costs there are no universal rules that can be developed
and this to a degree is a reflection of the difference in costs in relation to different foundation
types which in itself is a reflection of the variability of the ground conditions. Other factors
which may influence the selection of foundation type and hence its cost are: environmental,
resource limitations and health and safety requirements.

The price or rate for the foundation will in addition to the factors described above, depend on
the method of measurement and payment plus the allocation of risk between the client and
C:\CIGREWG07\Foundation Installation\Section 8_Final 8.4 May 2006
the installation contractor. Details of typical methods of measurement and payment are given
in the section 7 of the Brochure.

8.9 Conclusions

The installation of overhead line support foundations can not be viewed in isolation but must
be considered as on going process, with a seamless transition between design and
construction, if the adverse effects outlined in section 2 of this Brochure are to be avoided.
Similarly, to ensure that the intended service life is achieved, quality management
requirements must also be integrated within the installation process. Since foundation
installation is also hazardous both to site operatives and the environment, mitigation
measures must also be considered from the outset of the project.

C:\CIGREWG07\Foundation Installation\Section 8_Final 8.5 May 2006


9 Bibliography

ACI [1974] 543-74 >Recommendations for Design, Manufacture and Installation of Concrete
Piles=, American Concrete Institute, Detroit, MI, USA.

ACI [1993], 336.3R-93 >Design and Construction of Drilled Piers=, American Concrete Institute.

ASTM [1984], D2488 Description and Identification of Soils (Visual Manual Procedures).
American Society for Testing and Materials, 100 Barr Harbour Drive, West Conshohocken, PA
19428, USA.

ASTM [1996], D5882 >Standard Test Method for low Strain Integrity Testing of Piles.
BCA [2000], >Early age strength assessment on site=, British Cement Association, Century
House, Telford Avenue, Crowthorne, Berkshire, RG45 6YS. www.bca.org.uk

BRE [1971], >Problems of Concrete Production in Arid Climates=, Overseas Building Note 139,
Building Research Establishment, August 1971. BRE publications are available from CRC, 151
Rosebery Avenue, London EC1R 4GB, UK.

BRE [2002], Special Digest 1, >Concrete in aggressive ground conditions=. Note revised in 2005.

BSI [1984], BS 8004 >Code of practice for foundations=. BSI, 389 Chiswick High Road, London
W4 4AL, UK. www.bsi-global.com/bsonline

BSI [1989], BS 8081 'Ground anchorages=.

BSI [1990a], BS 5328:Part 3 >Specification for procedures to be used in producing and


transporting concrete=.

BSI [1990b], BS 5328 >Concrete=.

BSI [1990c] ,BS 1377-9 >Methods of tests for soils for civil engineering purposes, In-situ tests=.
BSI [1997], BS 8110-1 >Structural use of concrete - Part 1 : Code of practice for design and
construction=.

BSI [1999], ISO 14654 >Epoxy-coated steel for reinforcement of concrete=.

BSI [2000a], EN 206-1 >Concrete - Part 1: Specification, performance, production and


conformity=.

BSI [2000b], EN 1536 >Execution of special geotechnical work - Bored piles=.

BSI [2000c], BS 8666 >Specification for scheduling, dimensioning, bending and cutting of steel
reinforcement for concrete=.

BSI [2000d], EN 1537 >Execution of special geotechnical work - Ground anchors=.

BSI [2000e], ISO 9001 >Quality management systems. Requirements=.

BSI [2000f], EN12350-2 >Testing fresh concrete - Part2: Slump tests=.

BSI [2000g], EN12350-5 >Testing fresh concrete - Part5: Flow table tests=.

BSI [2000h], EN 12350-7 >Testing of fresh concrete - Part7: Air content - Pressure methods=.

BSI [2000j], EN 12390-2 >Testing hardened concrete - Part2: Making and curing specimens for
C:\Cigre\Foundation Installation\Section 9_Final 9.1 May 2006
strength tests=.

BSI [2000k], EN 12390-3 >Testing hardened concrete - Part3: Compressive strength of test
specimens=.

BSI [2000m], EN 12390-7 >Testing hardened concrete - Part7: Density of hardened concrete=.

BSI [2001a], EN 934 >Admixtures for concrete, mortar and grout=.

BSI [2001b], BS 7973-2 >Spacers and chairs for steel reinforcement and their specifications.
Fixing and application of spacers and chairs and tying of reinforcement=.

BSI [2001c], EN 12699 >Execution of special geotechnical work - Displacement piles=.

BSI [2001d] EN 50341-1 >Overhead electrical lines exceeding AC 45kV - Part1: General
requirements - Common specification=.

BSI [2002], BS 8500 >Concrete - Complementary British Standard to BS EN 206-1'.

BSI [2005], EN 14199 Execution of special geotechnical works Micropiles.

C&CA [1975], >Concrete Practice=, Cement and Concrete Association, Wrexham Springs,
Slough, SL3 6PL, UK, 1975.

Cigre [1991], >An International Survey of Component Costs of Overhead Transmission Lines=,
Cigre, Electra No.137, August 1991. Cigr, 21, rue d =Artois - F -75008 Paris, France.

Cigre [1994], Special Publication No.81 >Foundation Testing=, Cigre WG 22-07,

Cigre [1996], Foundation Cost Study, Cigre, Electra No. 165, April 1996.

Cigre [1999a], Technical Brochure No. 141, Refurbishment and Upgrading of Foundations=,
Cigre WG 22.07.

Cigre [1999b], Technical Brochure No. 147, High Voltage Overhead Lines Environmental
Concerns, Procedures, Impacts and Mitigations, Cigre WG22.14.

Cigre [2002], Technical Brochure No.206 >The Design of Transmission Line Support Foundations
- An Overview=, Cigre WG 22-07.

Cigre [2004], Technical Brochure No.265 Life Cycle Assessment (LCA) for Overhead Lines,
Cigre WG B2-15.

CIRIA [1977a], Report R165 >Concrete mixes - planning and design for transporting, placing and
finishing. Construction Industry Research & Information Association, Classic House, 174-180
Old Street, London, EC1V 9BP, UK. www.ciriabooks.com

CIRIA [1977b], DOE/CIRIA Report PG2 >Review of problems associated with construction of
cast-in-place concrete piles=,

CIRIA [1977c], Report PG3, >The use and influence of bentonite in bored pile construction=.

CIRIA [1979], Report SP12, >Piling in Chalk=.

CIRIA [1980], DOE/CIRIA Report PG8, >Survey of problems associated with the installation of
displacement piles=.
C:\Cigre\Foundation Installation\Section 9_Final 9.2 May 2006
CIRIA [1984], DOE/CIRIA Special Publication 32, >Construction over abandoned mine workings=.

CIRIA [1995], Report 147, >Care and treatment of steel reinforcement and the protection of
starter bars=.

CIRIA [1997], Report R144, >Integrity testing in piling practice=.

CIRIA [1999], Report C502, >Environmental good practice on site=.

CIRIA [2002a], Report C577, >Guide to the construction of reinforced concrete in the Arabian
Peninsular=.

CIRIA [2000b], Report C569, >Concrete technology for cast in-situ foundations=.

CIRIA [2006], Report C648, Control of water pollution from Linear construction projects. See
also associated guide C649.

ICE [1994], Without site investigation ground is a hazard, Littlejohn G, Cole K, Mellors T, Civil
Engineering Proceedings 102, Paper 10373. The Institution of Civil Engineers, 1 Great George
Street, Westminster, London, SW1P 3AA UK.

ICE [1996], >Specification for Piling and Embedded Retaining Walls=, The Institution of Civil
Engineers, Thomas Telford Ltd. Thomas Telford House, 1 Heron Quay, London E14 4JD, UK.
www.thomastelford.com

IEC [1996], IEC 61773, >Overhead lines - Testing of foundations for structures=

IEEE [1991], Std 977-1991 >Guide to Installation of Foundations for Transmission Line
Structures, IEEE, 345 East 47th Street, New York, NY 10017, USA.

HMSO [1992], >Management of Health and Safety at Work Regulations 1992=.

HMSO [1996], >The Construction [Design and Management] Regulations 1994'.

HMSO [2000], >The Electricity Works (Environmental Impact Assessment) (England and Wales)
Regulation 2000'.

HSE [1996], >Health and Safety in Construction=, Health & Safety Executive, HSE Books, PO Box
1999, Suffolk, CO10 6FS, UK.

HSE [1999] , >Health and safety in excavations=, Health & Safety Executive, HSE Books.

HSE [2003], >Health and Safety regulations - a short guide=, HSC13(rev1), 08/03.

Jones A, Deal J A and Paisley D F [1988], >The design and construction of a 132 kV double
circuit line over a route containing extensive uncharted mineworkings=, IEE Conference
Publication No.297.

Thomas Telford [1996], >Health and Safety for Engineers, Edited by M J Barnard, Thomas
Telford Ltd.

C:\Cigre\Foundation Installation\Section 9_Final 9.3 May 2006

You might also like