PM 4215 Havells
PM 4215 Havells
PM 4215 Havells
2/07-01-
2014
CPDCL TIN No. 28580127730 SAP P.O.No.
5100001353
From To
Chief General Manager (P&MM), M/s. Havells India Limited,
APCPDCL, 4th floor, Corporate Office, QRG Towers, 2D, Sector – 126,
Mint Compound, Hyderabad – 500 004. Expressway, Noida – 201 304
P.O.No. CGM/P&MM/E-32/STN-370/13/PM-4215/13, Dt.07-01-2014.
Dear Sirs,
Sub:- CPDC of AP Ltd., – P&MM wing - Specification No.STN-370/13 – Order for
supply of 11KV, 3Cx185 Sq.mm XLPE UG Cable – Purchase order – Issued –
Reg.
The date of delivery for the purpose of price variation shall be date on which
the Cable is notified as being ready for inspection/ despatch (in the absence of such
notification the date of manufacturer’s despatch note shall be considered as the
date of delivery) or the contracted delivery date including any agreed extension
thereto whichever shall be the earlier.
:: 2 ::
If the date of delivery as defined in the P.V. formula is beyond the contracted
delivery date, the scheduled delivery date or inspection offer date or the actual
delivery date which ever is advantageous to the purchaser will form the basis for
calculation of price variation.
As far as practicable, prices will be revised (upward or downward) abinitio, to
take care of any variation in prices of raw materials as defined above but if for any
reason it is not found to practicable shall be effected at the contracted price and
price variation claimed subsequently through a supplementary bill which will be
paid as per the documentary evidence, proof or certificate in regard to the price
variation bill is required by this office, the supplier shall have to furnish the same.
If there is downward revision in the prices of raw materials at the time of
supply, the suppliers shall invariably claim the invoices at reduced rates on account
of such downward revision.
3. SCHEDULE OF MATERIALS :
Sl. Particulars Size in Qty. FADS price per KM. Amount
No sq.mm in (Rs. Ps.) (Rs. Ps.)
. (KM
)
1. 11KV grade under ground XLPE
cable suitable for earthed 11 KV 50 6,80,070.14 3,40,03,507
system having compacted 3Cx185 0
circular stranded aluminium Sq.mm Ex-works :
conductor shielded with semi- 5,71,000.00
conducting compound E.D. & Cess
extruded layer XLPE insulated @ 12.36% : 70,575.60
dry cured core shielded with CST @ 1% : 6,415.76
semi-conducting compound F&I : 32,078.78
extruded layer followed by ------------------
metallic copper foil, screened Total :
inner sheath of extruded PVC, 6,80,070.14
galvanized single flat steel ------------------
strip armoured and PVC
sheathed overall conforming to
IS:7098 Part-II/1985, IS:5831
and IS:3975 as amended upto
date with ISI marked.
Total: 3,40,03,50
00
(Rupees Three Crores Forty Lakhs Three Thousand Five Hundred and Seven Only)
4. DELIVERY : The supply of material shall be commenced in one month from
the date of receipt of technically, commercially clear purchase order and shall be
complete the supplies as detailed below.
By 28-02-2014 15 KM
By 31-03-2014 15 KM
By 30-04-2014 20 KM
However you may advance the supplies on written request from
APCPDCL.
Delay in delivery of materials free at destination stores due to non-availability
of Railway booking, non-allotment of wagons and any such reasons will not be
considered. It is your responsibility to make alternate arrangements for the
transporting the materials by road so as to see that the materials reach the
destination stores of APCPDCL in the stipulated period.
The APCPDCL shall have the right to vary the delivery schedule mentioned in
this purchase order due to any operational exigencies at any time during the
execution of the order by the suppliers, after due notice.
The APCPDCL shall have the right to increase or decrease the ordered
quantity by 50% at any time during the execution of the order. (The order would be
treated as completely executed if the total quantity supplied is within the limits of
+/- 5% of the ordered quantity.
:: 3 ::
6. TERMS OF PAYMENT :
100% payment will be arranged within 45 days reckoned from the date of
certified receipt of material / equipment in good condition at the destination / stores
duly transferring the said amount to the bank account of the supplier by the
purchaser bank. The supplier will have to predefine the Bank details while entering
into contract.
The supplier should invariably submit test certificates and other documents
before despatch of the material to the destination stores so that they can be
checked and approved well in advance.
If the supplier has received any over payments by mistake or if any amounts
are due to the APCPDCL due to any other reason, when it is not possible to recover
such amounts under the contract resulting out of this specification, the APCPDCL
reserves the right to collect the same from any other amount and / or Bank
Guarantees given by the company due to or with the APCPDCL.
When the supplier does not at any time, fulfill his obligations in replacing /
rectifying etc. of the damaged/defective materials in part or whole promptly to the
satisfaction of the APCPDCL Officers, the APCPDCL reserves the right not to accept
the bills against subsequent dispatches made by the supplier and only the supplier
will be responsible for any demurrages, wharfages or damage occurring to the
consignments so dispatched.
7. DESPATCH :
(A) Please arrange to supply the cable specified herein on freight prepaid
basis to the consignees.
8. ACKNOWLEDGEMENT :
The Lorry receipt should be sent to the persons noted against each circle and
should be accompanied by two copies of the invoice/challan, one of which will be
returned to you direct in token of acknowledgement of receipt of the goods. A copy
of the invoice shall be sent to this office as soon as despatch is made.
9. LOSS OR DAMAGE :
External damages or shortages that are prima facie the result or rough
handling in transit or due to defective packing will be intimated within a fortnight of
receipt of materials. Internal defects damages or shortages or any internal parts
which cannot ordinarily be detected on superficial examination though due to bad
handling in transit or defective packing would be intimated within 2 months from
the date of receipt of the materials. In either case the damaged or defective
materials should be replaced by you free of cost.
:: 4 ::
Where any materials supplied by you are found defective in whole or in part
WITHIN THE GUARANTEE PERIOD, you will be intimated of the same. You should
take immediate steps to rectify the defects or to replace the defective materials free
of cost. If no steps are taken within 15 days of receipt of intimation of defects or
such other reasonable time as the APCPDCL may deem to afford the APCPDCL may
without prejudice to its rights and remedies, cause to replace the same and recover
the expenditure incurred therefore from the deposits such as EARNEST MONEY
SECURITY DEPOSIT AND PERFORMANCE or other monies available with APCPDCL or
by resorting to legal action and also decline to accept further deliveries of materials.
For the purpose of any legal construction, the materials should be deemed to
pass into APCPDCL’s ownership only at the destination stores where they are
delivered and accepted.
The APCPDCL reserves the right apart from the above said provisions, not to
accept further despatches of materials and the connected bills etc., under
conditions of your continued negligence to replace any materials supplied earlier
and received in damaged condition or failed within the guarantee period, or not
conforming to the purchase order specification.
10. GUARANTEE :
If, during the guaranteed period, the cables are found to be defective in
materials or workmanship it shall be replaced by you free of cost.
For supplies made beyond the agreed delivery schedule, penalty shall be
levied for an amount of equivalent to ½ % of the value of the material not delivered
within the prescribed time limit for every week of delay or part thereof subject to a
maximum of 5% of cost of the undelivered portion within the scheduled time.
In case you do not adhere to the delivery schedule the APCPDCL reserves the
right to purchase the balance quantity from the open market and recover
expenditure incurred from you. This is in addition to the right of the APCPDCL
mentioned in first para of this clause and under law.
13. INSPECTION :
The despatches shall be made only after the inspection by the APCPDCL’s
satisfaction or such inspection is waived by this office.
APCPDCL reserves the right to insist for witnessing the acceptance/ routine
tests of the bought out items.
a) The drum along with the UG Cable shall be weighed 4 or 5 empty reels
normally used for winding the UG Cable shall also be weighed. Net
weight of the UG Cable shall be calculated by subtracting average
weight of the empty reel from the gross weight of the drum containing
UG Cable. Having known the weight of the UG Cable and other
parameters of the conductor its length can be computed.
b) ALTERNATIVELY : Transfer the UG Cable from one reel to the other while
at the same time measuring the length of the UG Cable so transferred
by means of meter.
To ensure that the equipment are in accordance with the specifications, the
supplier shall adopt suitable quality assurance programme to control such activities
at all points, as necessary. The QA programme shall be generally in line with the
ISO-9000/IS-14000.
:: 6 ::
The supplier shall be required to submit two sets of the following Quality
Assurance documents within three weeks of receipt of order (preferably through
compact discs).
(ii) Factory tests results for testing required as per applicable codes
and standard referred in the specification.
The technical particulars as per the ISI shall be guaranteed by you for the
supplies against this order. Also refer to the Annexure-I.
You shall not be liable for any liquidated damages for delay or for failure to
perform the contract, for reasons for force majeure such as Acts of God, Acts of
Public Enemy, Acts of Government, Fires, Epidemics, Quarantine restrictions, strikes,
Riots, Freight Embargoes and provided that you shall within ten days from the
beginning of such delay, notify the APCPDCL in writing the cause of delay, the
APCPDCL shall verify the facts and grant such extension as facts justify.
The latest certificates containing the results of the tests as per ISS (of latest
issue) must be submitted to Chief General Manager/P&MM, 4 th floor, Corporate
Office, Mint Compound Hyderabad and got approved by him before sending
bills for payment.
Note : Detailed despatch instructions will be issued as and when the material is
offered for inspection and cleared for despatch.
:: 7 ::
20. PACKING :
The cable shall be wound on a drum of suitable size and duly packed. You
should ensure that the packing is such that the cable reaches the departmental
stores without damage after transport by Rail and Road.
PACKING SLIP
f) You shall invariably send to the purchasing office a copy of the delivery
challan whenever materials are despatched.
c) The ownership of the materials would rest with the supplier till it is
received in good condition at destination stores and accepted by the
consignee.
:: 8 ::
vi) Unless otherwise specified, you shall abide by all the terms and
conditions specified in the specification No.STN-370/13.
vii) This is in regularization of preliminary acceptance letter No.CGM/P&MM/E-
32/ STN-370/13/LOI/D.No.6846/13, Dt. 30-12-2013.
Encl: Annexure-I
Yours faithfully,
(M. VENKATESULU)
CHIEF GENERAL MANAGER (P&MM)
Acting for and on behalf of APCPDCL
Copy to :
The Chief General Manager (Finance)/APCPDCL/Hyderabad.
The Accountant General/Andhra Pradesh/Hyderabad.
The Pay Officer/APCPDCL/Hyderabad
The General Manager/SP & P&A/CPDCL/Hyderabad.
The Superintending Engineer/Operation/Anantapur Kurnool, Mahaboobnagar,
Nalgonda, Medak, Ranga Reddy-South, Ranga Reddy-North, Ranga Reddy-East,
Hyd-North, Hyd-South, Hyd-Central.
The Accounts Officer/Expr. O/o.SE/Opn./Anantapur Kurnool, Mahaboobnagar,
Nalgonda, Medak, Ranga Reddy-South, Ranga Reddy-North, Ranga Reddy-East,
Hyd-North, Hyd-South, Hyd-Central.
The Asst. Divisional Engineer/Stores/Anantapur, Kurnool, Mahaboobnagar,
Nalgonda, Sangareddy, Ranga Reddy, City-Hyd.
The Chief General Manager/P&MM/APEPDCL/APNPDCL/APSPDCL
The General Manager/IT/CPDCL/Hyd : Place the scanned purchase order copy in the
APCPDCL website.
/conversion/tmp/scratch/390273706.doc
:: 9 ::
GUARANTEED TECHNICAL PARTICULARS
1.0 General 3C x 185 Sq.mm – 11KV
1.1 Name and country of the manufacturer Havells India Ltd., (Cable Division)
- Alwar
2.0 Cables
2.1 Cable Description HT XLPE Power Cable Armoured
2.2 Trade name / Brand name Havells Cable
2.3 Applicable standards / Specification IS : 7098 (Part-2) 1985
2.4 Cable code A2XFY
2.5 Voltage Grade (KV) 6.35/11KV
2.6 Whether suitable for effectively earthed Yes
system
2.7 Whether conductor screen, insulation and Yes
insulation screen are simultaneously extruded
by way of triple extrusion process.
2.8 Permissible frequency variation and voltage Frequency + 3%
variation for satisfactory operation. Voltage + 10%
2.9 Design ambient temperature (Degree C) 40
2.1 Recommended minimum bending radius 15 x D where D is overall
0 (mm) diameter of cable
2.1 Safe pulling force with pulling eye (kg) 30 x T (where T is cross sectional
1 area of conductor in sq. mm)
3.0 Conductor
3.1 Material and grade Aluminium H2/H4 Grade
3.2 Flexibility class Class-2 of IS:8130/1984
3.3 Number of conductors Three
3.4 Nominal area of cross-section of each 185
conductor-phase (Sq.mm)
3.5 Minimum number of wire/strand per 30 (Min.)
conductor-phase
3.6 Diameter of wire/strand (mm) Dia of wires shall be suitable
selected to meet DC resistance as
per Class-2 requirements of
IS:8130/84
3.7 Diameter of conductor-phase (mm) 15.8 (Approx.)
3.8 Shape of conductor Stranded circular - Compacted
3.9 Whether compacted Yes
4.0 CONDUCTOR SCREEN
4.1 Material Semi conducting compound
4.2 Type Extruded
4.3 Thickness of screen (mm) 0.30
4.4 Continuous working temperature (Degree C) 90
4.5 Maximum allowable temperature at the 250
termination of the short circuit (Degree C)
5.0 INSULATION
5.1 Material XLPE confirming to IS : 7098 (PT-
2) 1985
5.2 (a) Thickness of insulation between Cores 3.6 (Nominal)
(mm)
(b) Nom. Thickness of Insulation --
5.3 Thickness of insulation between Cores and -
inner sheath (mm)
5.4 Tolerance of thickness of insulation Thickness minimum at point =
1 – (0.1 + 0.1 t) where t is
nominal thickness
5.5 Diameter of core over insulation 23.8
5.6 Specific insulation resistance at 90 Degrees C 1 x 1012
(Ohm-cm)
5.7 Whether XLPE insulation dry cured or not Dry
5.8 Whether XLPE insulation filled or unfilled Unfilled
5.9 Whether XLPE comply in all respects to the IS Yes
specified.
:: 10 ::
iii) max continuous & short time (1 sec.) Not applicable since 3 core cables
volt, withstand capability of inner PVC
Sheath of the cable (volts)
iv) max continuous & short time (1 sec.) Not applicable since 3 core cables
volt, withstand capacity of outermost PVC
sheath over the armour (volts).
v) Max. continuous & short time (1 sec.) Not applicable since 3 core cables
current carrying capability of copper tape
screen (amps).
12. Can the insulation screen & the armour be Yes
5 connected together at both ends &
grounded at both ends permanently.
If not, can the grounding be done at one ---
end and the insulation screen only grounded
at the other end and the cable inner and
outermost sheath withstand voltage under
short circuit condition at the open end.
13. TYPE TESTS
0
13. Whether the particular type and size of the
Yes, CPRI/ERDA
1 cable got type tested.
13. If so, address and approval reference of the
---
2 testing agency
13. Details of type tests got done, enumerate All type tests as per IS : 7098(Part-
3 2)1985
14. FACTORY TESTS
0
14. Enumerate in detail for each type of cable
All tests as per IS : 7098 (PT-2) 85
1
15. PHYSICAL DETAILS
0
15. Cable weight (Kg/Km) (Approx)
5000
1
15. Standard Packing length of cable per drum 500 / 250
2 (Mtrs)
- % tolerance thereof + 5%
15. Cable drum
3 Cable net weight (Kgs) (Approx.) 2500 / 1250
Empty reel/drum weight (Kgs) (Approx.) 750 / 450
Gross / Shipping weight (Kgs) (Approx.) 3250 / 1700
15. Core identification phase Provide Red, Yellow and Blue colour
4 strips below copper tape.
15. Cable identification on outer sheath Havells 6.35 / 11KV 185 Sq.mm XLPE
5 Electric Cable – 2013 - ACEPDCL
16. Any other details the supplier may desire to
---
0 furnish
17. Non-Standard length Max. 5% of the ordered qty, no length
0 less than 100 m
18. Order Quantity Tolerance
+ 5%
0
/conversion/tmp/scratch/390273706.doc