INSPECTION REPORT DISHEND

CLIENT : Times Automation Pvt. Ltd. M.O.C – M.S.


Draw No : As per client drawing
Fabrication Code : ASME SEC-VIII, DIV-I

S.NO DESCRIPTION REQUIRED OBSERVED REMARK


SIZE IN mm SIZE IN mm

01 DISH OD 2500 2499 OK


02 DISH CF 7854 7852 OK
03 DISH SF 50 50 TO 55 OK
04 Dish Height 534 540 Ok , observed outside

Mr. Varun Malhotra

M/S Times Automation Pvt. Ltd. M/S Malik Polychem Ltd.


DISHED END FORMATION REPORT
CLIENT : CAPACITY:
EQUIPMENT:
Draw No. : JOB CODE:
Fabrication Code: ASME SEC-VIII, DIV-I
Dish ID Req. Observed Thickness Req. Obs.
THK . Circ. Circ. SKETCH
SF KR CR Avg.
B.D.E

T.D.E

Inside Dia. Height Straight Face


( I.R ) ( S.F )
Req. Obs. Req. Obs Req. Obs.

B.D.E

T.D.E
All Dimensions are in mm.
B.D.E  Bottom Dished End
T.D.E  Top Dished End
J.D. E  Jacket Dished End

Malik Polychem Ltd.

RUN TEST REPORT


CLIENT : CAPACITY:
EQUIPMENT : INSPECTION AGENCY: M.P.L
Draw No. : JOB CODE:
AIR. NO.: TYPE: 88B2A1CG

1. SEAL MAKE

SYPHON SYSTEM:
2.SHAFT DETAIL
3. BAFFLE DETAIL

SR. NO. : TYPE :


4. GEAR BOX DETAILS
MAKE : RATIO

MOTOR CURRENT ( AMP ) : R: 15 Y: 14 B: 16

5. MOTOR DETAILS RESULT : TESTING WAS DONE WITH OUT LOAD.


REF NO. TYPE :

HP. : RPM. : MAKE :


DISTANCE BETWEEN
AGI. & BTM. D’END:
NO
7 ADDITIONAL REQI. :

SATISFACTORY
8. REMARK :

FOR (Q.C) FOR CLIENT

HYDRO TESTING REPORT


CLIENT : CAPACITY :
EQUIPMENT : INSPECTION AGENCY: M.P.L
Draw No. : JOB CODE:
A) MAIN SHEEL ( HYDRO )

Working Pressure Design Pressure Test Pressure Position Date Of Result Q.C.
Kg/cm2 Kg/cm2 (Kg/cm2) Testing Sign

Holding Time Pr. Gauge # 1 Pr. Gauge # 2


Calibration Date Calibration Date
Calibration Due Calibration Due
Date Date

B) LIMPET ( HYDRO )

Working Pressure Design Pressure Test Pressure Position Date Of Result Q.C.
Kg/cm2 Kg/cm2 (Kg/cm2) Testing Sign

Holding Time Pr. Gauge # 1 Pr. Gauge # 2


Calibration Date Calibration Date
Calibration Due Calibration Due
Date Date
REMARKS:1.MAIN SHELL HYDRO PRESSER TESTING NOT DONE DUE TO SHAFT NOT FIXED.
2. IF ANY DAMAGE DURING TRANSPORTATION BECAUSE OF PACKING THAT IS
RESPONSIBILITY OF M.P.LTD.
3. FINAL COMMISSINING WILL BE DONE BY M/s M.P.LTD AT PDLTD LALRU.
4. ALL NOZZLES AS PER DESIGNING.

Parabolic drugs Ltd Malik Polychem Ltd.