Erection Methodoly Electrical 50 MWP
Erection Methodoly Electrical 50 MWP
Erection Methodoly Electrical 50 MWP
a. GENERAL
The Contractor shall complete the erection, testing and commissioning of the substation and shall
hand over in proper working order in accordance with the specifications. All work of assembly,
construction and erection shall be done in a neat, first class workmanship manner according to
the best practice applicable and as approved by the Consultant/Client.
The Contractor shall submit a detailed description of the field tests he intends to carry out on his
equipment, comprising test protocols, testing and commissioning procedures etc. for Employer’s
Representative’s review well before starting of the field tests.
The Contractor shall be responsible for satisfactory field testing and commissioning of equipment
to the satisfaction of the Consultant/Client prior to the energization. Consultant/Client may also
ask the Contractor to perform additional tests, which may not be listed, to prove that a particular
equipment is fit for commissioning and energization.
A record of all performance tests shall be embodied in a report to be submitted by the Contractor
upon completion, to the satisfaction of the Consultant/Client, of the tests described herein
together with such other tests as may be agreed between the Contractor and the
Consultant/Client, which collectively shall constitute the Commissioning Tests.
The Consultant/Client e may, at his option, require that, tests be made after the equipment has
gone into service in order to demonstrate that all performance guarantees have been met. The
Contractor will be permitted, to have his representative present at his own expense and make all
necessary corrections. Additional tests shall then be made under the directions of the
Consultant/Client to demonstrate to his own satisfaction the effectiveness of these corrections.
These additional tests shall be at the Contractor's expense. Until the necessary corrections have
been satisfactorily made, the conditions of the Contract shall not be considered fulfilled.
Upon completion to the satisfaction of the Consultant/Client, of the tests specified hereafter
together with such other tests as may be agreed between the Contractor and Consultant/Client
shall collectively constitute the commissioning tests. The Contractor shall certify in writing to the
Consultant/Client that the equipment or part of the equipment has been installed and tested to the
satisfaction of the Employer’s Representative and is ready for energization.
1. Outdoor Installations
The Contractor shall install the conductor, insulators and the hardware for the outdoor
elements of 132kV sections of the substation and overhead shield wire in accordance
with, approved drawings. All connections shall be thoroughly cleaned to remove oxide
film. An oxide retarding compound of approved type shall be used at all connections and
precautions shall be taken to seal moisture out of the joint to avoid galvanic corrosion.
2. Transformers
(1) Installation:
The bushing holding bolts shall be properly tightened to avoid unequal clamping strains
and subsequent damage to the bushing porcelain or support.
(2) Wiring:
Connection to oil and winding temperature gauges and oil level indications shall be with
control cables running through conduit from cable trench to the cabinet or terminal boxes.
The oil shall be passed through filter press shall be cleaned and dried before filling under
vacuum. It shall be ascertained that no contamination takes place during oil filling.
In case the inert gas filled in the transformers leaks then drying out under vacuum shall be
done by a suitable drying process.
(4) Painting:
The transformer paint finish shall be examined and if necessary, proper retouching after
cleaning and applying coats shall be done as per approved practice to give correct match
of paint on the transformers.
3. Surge Arresters
Surge arresters shall be mounted as close as possible to the apparatus being protected.
Control desk and relay board shall be erected on channel iron bases. The channel iron
shall be levelled and grouted in place and the control board and relay board panels
mounted thereon. The Contractor shall mount all equipment and shall make all necessary
connections and interconnections to the panels in accordance with the approved standard
practices.
All instruments and relays shall be properly installed, connected and tested to meet the
technical specifications in the presence of the Employer’s Representative.
Cables shall be installed on cable supports, in cable trenches or in conduits. Cables shall
be installed with sufficient slack to allow for expansion and contraction and tied at each
support point. If laid in trenches, the cables shall rest on cable supports suitably spaced,,
and shall be fastened at appropriate points, using bolted galvanized straps; which should
not press tightly against the insulation.
Where group of cables enter or leave the trench, each shall be identified with stencilled
metal tags. Each tag shall indicate the major equipment to which it is attached. At each
cable termination, the cables shall be clamped below the terminal block. Cable glands of
appropriate sizes shall be used at cable entrances into control panels, relay panels and
marshalling boxes. The cable glands shall have provision for grounding the earth shielded
cables. The jacket shall be stripped back and individual conductors trimmed to fit.
Insulation shall be cut square and terminals installed without damage to insulation by
over heating or abrasion.
Cable runs shall be continuous from terminal to terminal to the extent permitted by
available commercial lengths. Splicing shall not be permitted.
Insulated wire and cable shall be handled with care so as to avoid kinking and damage to
insulation and outer jackets. Cables shall not be bent around a radius less than that
recommended by the manufacturer:
Each wire terminating in a terminal block shall carry a permanent identification tag
(ferrule) bearing the same identification number as given in the drawings. Slip-in type
ferrules should not be used for this purpose.
The Contractor shall install all lugs, terminal blocks and terminals required and shall
make all connections required to provide a complete installation ready to operate. Cable
identification tags of a permanent type shall be provided and installed on both ends of
each power and control cable.
Connections in lighting wires and cables shall be insulated with layers of plastic
insulating tape or with high grade rubber tape over which friction tape shall be applied.
Sufficient slack shall be allowed in each run where a number of cables or wire comprising
a circuit are trained through a pull box, terminal box, trench or tray and shall be neatly
placed and tied together. Lacing shall also apply from the point of leaving a cable-tray or
raceway to the point of attachment on the terminals of the Switchgear, switchboard or
other devices unless the run is in conduit.
The Contractor shall install all required lighting, power and auxiliary apparatus, cables
and make all connections. Illumination level of the installed lighting fixtures shall be
measured according to the specified levels.
7. AC & DC Auxiliary Supplies
The Contractor shall install and connect the equipment under these specifications as
specified in Section-19.
Outdoor Installations
i) Transformers
The operating mechanism and control circuits of the on-load tap changer and forced air
cooling equipment shall be tested for proper operation and for tap changer position
indications.
All tests shall be made from the remote control points as well as the local control points.
Tests, performed to the satisfaction of the Employer’s Representative, shall include, but
not limited to the following:
(a) Drying shall be performed. The method and tests shall be subjected to the
approval of the Employer’s Representative.
(b) Final sample testing of the insulation oil, after the completion of the
dehumidifying and degassing process to ascertain specified chemical and physical
characteristics.
(f) Low voltage ratio test on each position of the tap changer.
(g) Zero sequence impedance test.
(h) Functional test for auxiliary equipment, buchholz relay, thermal relay, oil level
indicator etc.
(i) Adjustment of the protective devices such as gas and oil temperature relays and
system to show compliance with operating requirements, correct operation
verification of oil-preservation, and oil-protection system.
(c) Verification of pick-up and drop-off of each of the SF6 pressure switches at rising
and dropping pressures.
(d) Inspection and operational test on the completely assembled and installed three
pole circuit breakers to verify that they are accurately aligned and levelled and
shimmed in place as necessary for proper operation.
(e) Inspection and operation test to verify that electrical wiring within the equipment
and operating mechanism is correctly connected.
(f) Verification for each hydraulic/pneumatic pressure switch in respect of pick-up &
drop-off
(h) Verification of pressure thresholds for pump start/stop, breaker automatic tripping/
blocking/lockout of close, trip and auto-reclose operations.
(i) Measurement of starting and running currents, and direction of rotation of
hydraulic/pneumatic pump/compressor motors.
While performing the timing tests, in addition to the numerical printout, traces of
contact travel and close/open positions i.e. graphical recording of times should be
appended to the test reports.
(o) Verification of time variation between opening of series contacts on any one
phase.
(p) Verification of time variation between openings of contacts of any two phases.
(s) Verification of setting of the hydraulic/ pneumatic motor thermal protection relay
by secondary injection.
(w) Functional tests of heating and lighting for the panels and cubicles.
f) Verification of ratios.
Following checks and tests shall be made for the current circuits fed from the bay
CTs, transformer bushing CTs:
– Each CT circuit shall be verified for grounding at one point.
– Phase-N loop resistance values shall be measured and recorded.
– Loop resistance measurements shall also provide lead resistance values.
– Resistance measurements shall be with wheatstone bridge.
– Verification of all current circuits associated with bay CTs and, bushing
CTs with primary injection.
– Primary injection shall be carried out for at least the following
combinations:
– Each CT:
R-G
Y-G
B-G
R-Y
R-B
– Busbar Protection of Double Bus double breaker Scheme for 132kV
applicable to the CT’s in each branch.
R-G
Y-G
B-G
* Changeover of current circuits in the bank selector kiosk and with selector
switches in the pole selector kiosk shall be verified during these tests.
c) Verification of polarities:
– In case polarity of CVT windings cannot be verified with the flick test,
phase angle meter shall be used to check the phase angle between the
primary injected voltage and secondary output.
3) Events Recorders
a) Measurement of insulation resistance (Megger tests)
b) Verification of ac & dc auxiliary supply magnitude and polarity/phasing.
c) Verification of grounding connections.
d) Verification of MCBs' operation at settings of thermal/magnetic relays.
e) Verification of calibration of adjustable devices such as timers
f) Tests to verify point programming and functioning of each input.
g) Verification of functioning of each peripheral device.
h) Verification of battery back-up and power-down and power-up function of
real time clock.
i) Verification of time synchronization with local event recorder.
j) Verification of time synchronization with remote time source i.e. radio time
signals or GPS signals.
k) Functional tests to verify alarms, indications, annunciations.
1) Functional tests of panels'/cubicles` humidity control, ventilation, internal
illumination.
4) Metering Boards
g) On-load tests:
– Current circuits: Measurement of current magnitude, relative phase
angle, burden volts
– Voltage circuits: Measurement of voltage magnitude, phase angle,
phase rotation and burden amperes
– Directional checks of power recorders and energy meters.
4) Control Cubicles
m) On-load tests:
– Verification of current circuits
– Verification of voltage circuits
– Directional tests
– Tests of differential protections by de-stabilising the current circuits.
1) HT/ LT Cables
2) LT Cables
3) HT Cables
1) Grounding System
d) Check of voltage magnitude and phase rotation for each three phase power
socket.
1) HT Switchgear
o) On-load tests.
2) LT Switchgear
o) On-load tests.
xv) Miscellaneous
c) Humidity and vibration recording devices are fitted to the equipment and
systems for monitoring during transportation. Recordings of these devices
shall be inspected upon arrival/installation at the site. Copies of the recordings
shall be made part of the site test books.
d) High voltage tests shall be performed on the equipment in accordance with the
standards.
e) Applicable tests and verifications mentioned in the above sections and sub-
sections shall be applicable to all the equipment and systems not specifically
mentioned herein above but may be installed at the substation.
1. PV Field Area
PV field area has two major division that’s are given below
a. Installation of tracker system and PV plates
b. DC/AC cable laying directly buried in trench and PV area earthing.
A. Installation of tracker system and PV plates
We have experienced and will aware technical and skilled for this work. They worked
according to drawings. First we will prepare the tracker material as per drawing the
workshop after we do it installed on the foundation steel channel. Installed the major
beam of tracker system. Then we installed moving part of tracking system on the beams.
After moving part we installed tie beams on it.
Open the box of PV plates in the presentation of client or EPC contractor and check any
kind of damaged material. If damaged material is available inform the client on the time.
After open the box and get installed the plates on the tie beam as per drawing instruction
under supervision of engineers and supervisors.
i. Erection of steel structure beam for moving tracking system
ii. Erection of moving part
iii. Erection of tie beam for PV plates
iv. Erection of PV plates
v. Connection of PV strings to combiner box
vi. Connection of combiner box to inverter through DC cable
vii. Inverter connected to LV panel through LV cables
viii. LV panel connected to transformer
Earthing system.
For earthing flat strip we dig the trench as per approved level and directly buried
and backfill it.