Project Id No.: Name of Project: Contractor
Project Id No.: Name of Project: Contractor
Project Id No.: Name of Project: Contractor
UNIT COST
ITEM DESCRIPTION UNIT CONTRACT IN TOTAL
QUANTITY PESO AMOUNT
(PESO)
CW1 DRAINAGE STRUCTURE
102(1) Unsuitable Excavation cu.m 490.00 360.87 176,826.30
103(1)a Structure Excavation cu.m 588.00 353.32 207,752.16
404(1)a Reinforcing Steel Bar (Grade 40)- Bridge Structures & other Major Structures) kgs 97,268.33 62.02 6,032,581.83
405(1)a2 Structural Concrete, Class "A" cu.m 917.28 5,886.13 5,399,229.33
505(2)a Grouted Riprap, Class "A" cu.m 162.50 3,748.76 609,173.50
CW2 BRIDGE STRUCTURE
103(2)a Bridge Excavation cu.m 360.00 360.68 129,844.80
400(16) Test Pile, (Furnished and Driven) m 35.00 7,409.45 259,330.75
400(4)a Precast Concrete Piles, Furnished m 1,260.00 4,629.04 5,832,590.40
400(14) Precast Concrete Piles, Driven m 1,260.00 1,754.05 2,210,103.00
404(1)a Reinforcing Steel Bar (Grade 40)- Bridge Structures & other Major Structures) kgs 57,106.61 62.02 3,541,751.95
405(1)a1 Structural Concrete, Class "A" (Major Structures)-Bridge Substructure 20.70 MPa cu.m 129.55 7,370.73 954,878.07
405(b1 Structural Concrete, Class "A" (Major Structures)-Bridge Superstructure 28.0 MPa cu.m 168.75 7,327.53 1,236,520.69
407(8) Lean Concrete cu.m 3.24 5,179.52 16,781.64
401(2)a Concrete Railing m 24.00 2,754.98 66,119.52
411(1)a Paint (Concrete Structures) sq.m 28.28 2,611.51 73,853.50
413(1)a Preformed Joint Expansion (Multi-flex Expansion) cu.m 2.73 12,961.60 35,385.17
511(2) Matresses cu.m 64.80 1,709.92 110,802.82
517(1)a Drain Pipe (Galvanized) l.m 12.00 4,581.54 54,978.48
CW3 ROAD
B.5 Project Billboard/Signboard each 2.00 5,041.90 10,083.80
B.7 Occupational Safety and Health Program mos 7.00 24,048.88 168,342.16
B.8 Traffic Management mos 6.00 30,396.80 182,380.80
B.9 Mobilization and Demobilization l.s. 1.00 218,064.00 218,064.00
101(3)a3 Removal of Existing Concrete Pavement (0.23 m thk.) sq.m 1,340.00 659.81 884,145.40
101(6) Removal of Structures and Obstruction cu.m 343.00 644.42 221,036.06
200 Aggregate Subbase Course (t=200 mm) cu.m 613.28 1,532.86 940,072.38
104(2)a Embankment (From borrow) cu.m 934.02 767.76 717,103.20
311(1)e1 PCC Pavement, Unreinforced (0.28 m thk.) sq.m 1,340.00 1,699.69 2,277,584.60
GRAND TOTAL P 32,567,316.31
F WORK ACCOMPLISHED
2018 to August 17, 2018
s/Diversion Roads: Cagayan de Oro Coastal Road, incl. Bridge and Drainage, Cagayan de Oro City