Sta Fe
Sta Fe
Sta Fe
SUBJECT : ESTIMATES
B. CONSTRUCTION REQUIREMENTS
3. STRUCTURAL WORKS
3.1 Column Footings / Columns
Formworks 55.00 sq.m. 420.00 23,100.00
Rebars
16mm dia. X 6m G40 361.00 kgs. 52.00 18,772.00
10mm dia. X 6m G33 268.00 kgs. 50.00 13,400.00
Concrete
G-1, 3000 psi 28 days 2.50 cu.m. 4,892.00 12,230.00
3/4", 3000 psi 28 days 3.50 cu.m. 5,210.00 18,235.00
G.I. Tie Wires ga. 16 12.00 kgs. 75.00 900.00
3.2 Walls
Formworks 3.00 sq.m. 420.00 1,260.00
Rebars
10mm dia. X 6m G33 152.00 kgs. 50.00 7,600.00
Concrete
G-1, 3000 psi 28 days 2.00 cu.m. 4,892.00 9,784.00
G.I. Tie Wires ga. 16 3.75 kgs. 75.00 281.25
4. MASONRY WORKS
100mm thk. CHB Laying, incl. Rebars 35.00 sq.m. 585.00 20,475.00
Lintel Beams 12.00 l.m. 390.00 4,680.00
Stiffener Columns 7.00 l.m. 390.00 2,730.00
Plastering of structural surface 42.00 sq.m. 200.00 8,400.00
Plastering of CHB Wall 60.00 sq.m. 200.00 12,000.00
SUB-TOTAL 4: MASONRY WORKS 48,285.00
9. TILEWORKS
SUB-TOTAL 9 :TILE WORKS 1.00 LOT 30,000.00
Prepared by:
GENEVEVE COLASITO
ARCHITECT
December 10, 2011
B. CONSTRUCTION REQUIREMENTS
1. SITE DEVELOPMENT WORKS
Lot embankment/filling (0.40m backfill) 24.00 cu.m. 260.00 6,240.00
Grading and levelling works 59.50 sq.m. 60.00 3,570.00
Soil Poisoning 59.50 sq.m. 120.00 7,140.00
SUB-TOTAL 1: SITE DEVELOPMENT WORKS 16,950.00
2. EXCAVATION WORKS
Building Column Footings / Walls Footings 18.00 cu.m. 250.00 4,500.00
Storm Drainage Lines 5.00 cu.m. 250.00 1,250.00
Septic Vaults & Cistern 6.50 cu.m. 250.00 1,625.00
Catch Basins 1.50 cu.m. 250.00 375.00
SUB-TOTAL 2: EXCAVATION WORKS 7,750.00
3. STRUCTURAL WORKS
3.1 Column Footings / Columns
Formworks 85.00 sq.m. 420.00 35,700.00
Rebars
16mm dia. X 6m G40 455.00 kgs. 52.00 23,660.00
10mm dia. X 6m G33 338.00 kgs. 50.00 16,900.00
Concrete
G-1, 3000 psi 28 days 3.00 cu.m. 4,892.00 14,676.00
3/4", 3000 psi 28 days 5.50 cu.m. 5,210.00 28,655.00
G.I. Tie Wires ga. 16 16.00 kgs. 75.00 1,200.00
4. MASONRY WORKS
100mm thk. CHB Laying, incl. Rebars 126.00 sq.m. 585.00 73,710.00
Lintel Beams 15.50 l.m. 390.00 6,045.00
Stiffener Columns 9.00 l.m. 390.00 3,510.00
Plastering of structural surface 53.00 sq.m. 200.00 10,600.00
Plastering of CHB Wall 260.00 sq.m. 200.00 52,000.00
SUB-TOTAL 4: MASONRY WORKS 145,865.00
5. ROOF FRAMING
Assorted Angle Bars
2"x2"x3/16" 7.50 lgts. 715.00 5,362.50
1 1/2"x1 1/2"x3/16" 7.50 lgts. 637.00 4,777.50
1"x1"x3/16" 12.00 lgts. 357.50 4,290.00
C-Purlins, 50x100x1.0mm 13.00 lgts. 585.00 7,605.00
10mm dia. Sag Rod 8.00 lgts. 182.00 1,456.00
12mm dia. Cross Bracings 12.00 lgts. 338.00 4,056.00
12mm dia. Turn Buckle 6.00 pcs. 58.50 351.00
Welding Rod 1.00 box 2,340.00 2,340.00
Cut-off Blade 5.00 pcs. 585.00 2,925.00
Grinding Disk 2.00 pcs. 364.00 728.00
Oxygen 1.00 tanks 455.00 455.00
Acetylene 0.50 tanks 1,040.00 520.00
Sand Paper 100 8.00 shts. 58.50 468.00
Red Oxide Metal Primer 4.00 gals. 845.00 3,380.00
Paint Thinner 2.00 gals. 546.00 1,092.00
SUB-TOTAL 5 :ROOF FRAMING 39,806.00
6. ROOFING WORKS
ga. 26Prepainted Rib-type Roofing 50.00 sq.m. 416.00 20,800.00
Wall end flushing 12.00 l.m. 182.00 2,184.00
Wall Capping 33.00 l.m. 208.00 6,864.00
Roof Gutter 12.00 l.m. 208.00 2,496.00
Teck Screw, 2 1/2" 580.00 pcs. 2.60 1,508.00
Blind Rivets, 1/8" x 1/2" 380.00 pcs. 0.85 323.00
Ga. 16 G.I. Tie Wires 7.00 kgs. 75.00 525.00
10mm PE Foam with one side Alum. 50.00 l.m. 104.00 5,200.00
Touch-up Paint 3.00 cans 364.00 1,092.00
Silicone Sealant 4.00 bottles 234.00 936.00
SUB-TOTAL 6 :ROOFING WORKS 41,928.00
WINDOWS
W1, 2400x1000 Sliding Glass Window, Brown 1.00 set 12,420.00 12,420.00
frame and glass
W2, 2400x2400 Sliding Glass Window, Brown 1.00 set 29,808.00 29,808.00
frame and glass
W3,1200x2400 Sliding Glass Window, Brown 2.00 set 13,248.00 26,496.00
frame and glass
W-8&11, 600x600 Awning Glass Window, Brown 2.00 sets 1,863.00 3,726.00
frame and glass
W5,1200x600 Sliding Glass Window, Brown 1.00 set 3,726.00 3,726.00
frame and glass
W6, 600x2400 Awning Window, Brown 3.00 sets 7,452.00 22,356.00
frame and glass
SUB-TOTAL 7 :DOORS AND WINDOWS 122,712.00
8. CARPENTRY WORKS
CEILING
Exterior Ceiling (Above Carport)
4.5mm thk Cement board on 1"x2" 12.00 sq.m. 630.00 7,560.00
Light Metal Framing
Interior Ceiling
4.5mm thk Cement board 1"x2" 68.00 sq.m. 630.00 42,840.00
Light Metal Framing
KITCHEN CABINETS
3/4" thk plyboard varnish finish with 1.00 lot 21,600.00 21,600.00
concealed hinges and handles
BEDROOM CLOSET
3/4" thk plyboard varnish finish with 3.00 sets 5,670.00 17,010.00
concealed hinges and handles
9. TILEWORKS
Prefab pathway blocks 4.00 sq.m. 520.00 2,080.00
Porch, 40x40cm ceramic floor tiles 1.60 sq.m. 830.00 1,328.00
Living, Dining and Kitchen, 40x40cm semi polished floor 27.50 sq.m. 830.00 22,825.00
Second Floor Bed Rooms, 40x40cm semi polished floor t 29.50 sq.m. 830.00 24,485.00
Stairs , 30x30 steeped floor tiles 22.00 sq.m. 830.00 18,260.00
Service Area, 40x40cm ceramic floor tiles 7.60 sq.m. 780.00 5,928.00
Toilet Floor, 20x20cm non-skid floor tiles 8.50 sq.m. 780.00 6,630.00
Toilet Wall, 20x30cm glazed wall tiles 34.00 sq.m. 780.00 26,520.00
Tile Trims 35.00 l.m. 40.00 1,400.00
Stair Nosing 14.00 l.m. 530.00 7,420.00
SUB-TOTAL 9 :TILE WORKS 116,876.00
PLUMBING STRUCTURES
Grease Trap 1.00 set 1,323.00 1,323.00
Catch Basin 4.00 sets 810.00 3,240.00
B. CONSTRUCTION REQUIREMENTS
1. SITE DEVELOPMENT WORKS
Lot embankment/filling (0.40m backfill) 104.00 cu.m. 260.00 27,040.00
Grading and levelling works 120.00 sq.m. 60.00 7,200.00
Soil Poisoning 120.00 sq.m. 120.00 14,400.00
SUB-TOTAL 1: SITE DEVELOPMENT WORKS 48,640.00
2. EXCAVATION WORKS
Building Column Footings / Walls Footings 60.00 cu.m. 250.00 15,000.00
Storm Drainage Lines 2.88 cu.m. 250.00 720.00
Septic Vaults & Cistern 8.00 cu.m. 250.00 2,000.00
Catch Basins 3.50 cu.m. 250.00 875.00
SUB-TOTAL 2: EXCAVATION WORKS 18,595.00
3. STRUCTURAL WORKS
A. Column Footings / Columns
Formworks 96.00 sq.m. 420.00 40,320.00
Rebars
16mm dia. X 6m G40 805.00 kgs. 52.00 41,860.00
10mm dia. X 6m G33 678.00 kgs. 50.00 33,900.00
Concrete
G-1, 3000 psi 28 days 5.00 cu.m. 4,892.00 24,460.00
3/4", 3000 psi 28 days 10.00 cu.m. 5,210.00 52,100.00
G.I. Tie Wires ga. 16 50.00 kgs. 75.00 3,750.00
B. Walls Footings
Formworks 180.00 sq.m. 420.00 75,600.00
Rebars
10mm dia. X 6m G33 600.00 kgs. 50.00 30,000.00
Concrete
G-1, 3000 psi 28 days 3.00 cu.m. 4,892.00 14,676.00
G.I. Tie Wires ga. 16 5.00 kgs. 75.00 375.00
D. Suspended Slabs
Formworks 98.00 sq.m. 420.00 41,160.00
Rebars
10mm dia. X 6m G33 ### kgs. 50.00 60,000.00
Concrete
3/4", 3000 psi 28 days 2.88 cu.m. 5,210.00 15,004.80
G.I. Tie Wires ga. 16 30.00 kgs. 75.00 2,250.00
E. On-Grade Slabs
Formworks 1.00 lot 5,000.00 5,000.00
Rebars
10mm dia. X 6m G33 898.00 kgs. 50.00 44,900.00
Concrete
G-1, 3000 psi 28 days 24.00 cu.m. 4,892.00 117,408.00
G.I. Tie Wires ga. 16 35.00 kgs. 75.00 2,625.00
4. MASONRY WORKS
100mm thk. CHB Laying, incl. Rebars 120.00 sq.m. 585.00 70,200.00
Lintel Beams 18.00 l.m. 390.00 7,020.00
Stiffener Columns 12.00 l.m. 390.00 4,680.00
Plastering of structural surface 110.00 sq.m. 200.00 22,000.00
Plastering of CHB Wall 336.00 sq.m. 200.00 67,200.00
SUB-TOTAL 4: MASONRY WORKS 171,100.00
5. ROOF FRAMING
Assorted Angle Bars
2.5x2.5x1/4 9.00 lgts. 715.00 6,435.00
2x2x1/4 9.00 lgts. 637.00 5,733.00
C-Purlins, 50x100x1.0mm 18.00 lgts. 585.00 10,530.00
10mm dia. Sag Rod 9.00 lgts. 182.00 1,638.00
12mm dia. Cross Bracings 13.00 lgts. 338.00 4,394.00
12mm dia. Turn Buckle 8.00 pcs. 58.50 468.00
Welding Rod 10.00 box 2,340.00 23,400.00
Cut-off Blade 30.00 pcs. 585.00 17,550.00
Grinding Disk 25.00 pcs. 364.00 9,100.00
Oxygen 1.00 tanks 455.00 455.00
Acetylene 1.00 tanks 1,040.00 1,040.00
Sand Paper 100 9.00 shts. 58.50 526.50
Red Oxide Metal Primer 5.00 gals. 845.00 4,225.00
Paint Thinner 2.00 gals. 546.00 1,092.00
LABOR COST 1.00 LOT 35,000.00 35,000.00
SUB-TOTAL 5 :ROOF FRAMING 121,586.50
6. ROOFING WORKS
ga. 26Prepainted Rib-type Roofing 74.00 sq.m. 416.00 30,784.00
Wall end flushing 24.00 l.m. 182.00 4,368.00
Wall Capping 68.00 l.m. 208.00 14,144.00
Concrete gutter 18.00 l.m. 401.00 7,218.00
Teck Screw, 2 1/2" ### pcs. 2.60 2,600.00
Blind Rivets, 1/8" x 1/2" 450.00 pcs. 0.85 382.50
Ga. 16 G.I. Tie Wires 8.00 kgs. 75.00 600.00
10mm PE Foam with one side Alum. 1.00 rolls 3,500.00 3,500.00
Touch-up Paint 3.00 cans 364.00 1,092.00
Silicone Sealant 5.00 bottles 234.00 1,170.00
LABOR COST 1.00 lot 18,000.00 18,000.00
SUB-TOTAL 6 :ROOFING WORKS 83,858.50
8. DOORS
DOOR JAMBS ( Good lumber 2"x6")
D1- 1.6 x 2.1 Main entrance door 1.00 set 6,500.00 6,500.00
D3- 0.9 x 2.1 1.00 set 3,500.00 3,500.00
D4- 0.8x2.1 8.00 sets 3,500.00 28,000.00
D5- .7 x 2.1 3.00 sets 3,000.00 9,000.00
SUB-TOTAL : DOOR JAMBS 47,000.00
9. PAINTING WORKS
Exterior Walls, primeir white/with water proofing 60.00 sq.m. 230.00 13,800.00
Interior Walls, primier white 110.00 sq.m. 180.00 19,800.00
Door Jambs 35.00 sq.m. 270.00 9,450.00
LABOR COST 1.00 LOT 25,000.00 25,000.00
SUB-TOTAL 10 :PAINTING WORKS 68,050.00
10. MOULDINGS AND CANOPY
Formworks 36.00 sq.m. 420.00 15,120.00
Rebars
10mm dia. X 6m G33 ### kgs. 50.00 60,000.00
Concrete
3/4", 3000 psi 28 days 6.00 cu.m. 5,210.00 31,260.00
G.I. Tie Wires ga. 16 15.00 kgs. 75.00 1,125.00
SUB-TOTAL : MOULDINGS AND CANOPY 107,505.00
PLUMBING STRUCTURES
Grease Trap(stainless) 1.00 sets 4,500.00 4,500.00
4" pvc pipe 12.00 sets 450.00
Catch Basin 4.00 sets 2,350.00 9,400.00
Septic vault 1.00 lot 35,000.00 35,000.00
84.00
841,848.80
Prepared by:
GENEVEVE L. COLASITO
Architect
December 10, 2011
A. GENERAL REQUIREMENTS
Mobilization / demobilization 1.00 lot 20,000.00 20,000.00
Temporary Facilities
Power 4.00 mos.
Water 4.00 mos.
Communication 4.00 mos. 1,000.00 4,000.00
Materials Testing 1.00 lot 3,000.00 3,000.00
SUB-TOTAL A: GENERAL REQUIREMENTS 27,000.00
B. ROADWAYS
Road Lot Clearing and Grubbing 120.00 sq.m. 65.00 7,800.00
Road Lot Embankment (Backfilling) 295.00 cu.m. 320.00 94,400.00
Sub-base Preparation, 95% compaction 230.00 sq.m. 120.00 27,600.00
Basecourse Preparation, 100mm thk. Graded 26.00 cu.m. 1,400.00 36,400.00
gravel
Concrete Pavement, 150mm thk, 3000 psi 35.00 cu.m. 4,892.00 171,220.00
12mm. Dia.x30cm Deformed dowel bars 140.00 pcs. 40.00 5,600.00
Concrete Curb and Gutter 76.00 l.m. 400.00 30,400.00
Sidewalk, 75mm thk 4.00 mos. 305.00 1,220.00
Concrete cutting and asphalt sealant at weaken 1.00 lot 6,300.00 6,300.00
plane
SUB-TOTAL B: ROADWAYS 380,940.00
C. PERIMETER FENCE
C.1 1.20M CHB FENCE WITH STEEL GRILLS ABOV 24.87 l.m.
Excavation 8.00 sq.m. 420.00 3,360.00
Formworks 7.50 sq.m. 420.00 3,150.00
Rebars
12mm dia. X 6m G33 155.00 kgs. 50.00 7,750.00
10mm dia. X 6m G33 195.00 kgs. 50.00 9,750.00
Concrete
G-1, 3000 psi 28 days 2.50 cu.m. 4,892.00 12,230.00
3/4", 3000 psi 28 days 3.00 cu.m. 5,210.00 15,630.00
G.I. Tie Wires ga. 16 15.00 kgs. 75.00 1,125.00
100mm thk. CHB Laying, incl. Rebars 40.00 sq.m. 585.00 23,400.00
Plastering of CHB Wall 85.00 sq.m. 200.00 17,000.00
Steel Grill using 12mm square bars at .15m 25.00 l.m. 1,890.00 47,250.00
(1.0m high steel grills)
SUB-TOTAL C.1: 1.2M CHB FENCE 140,645.00
C.2 3.0M CHB FENCE WITH BROKEN GLASS AT T 76.04 l.m.
Excavation 16.00 cu.m. 250.00 4,000.00
Formworks 23.00 sq.m. 420.00 9,660.00
Rebars
12mm dia. X 6m G33 1,360.00 kgs. 50.00 68,000.00
10mm dia. X 6m G33 985.00 kgs. 50.00 49,250.00
Concrete
G-1, 3000 psi 28 days 3.00 cu.m. 4,892.00 14,676.00
3/4", 3000 psi 28 days 4.50 cu.m. 5,210.00 23,445.00
G.I. Tie Wires ga. 16 13.00 kgs. 75.00 975.00
100mm thk. CHB Laying, incl. Rebars 270.00 sq.m. 585.00 157,950.00
Plastering of CHB Wall 540.00 sq.m. 200.00 108,000.00
Broken Glass 76.00 l.m. 120.00 9,120.00
SUB-TOTAL C.2: 3.0M CHB FENCE 445,076.00
D. GUARDHOUSE
Excavation 2.50 sq.m. 250.00 625.00
Formworks 12.00 sq.m. 420.00 5,040.00
Rebars
12mm dia. X 6m G33 165.00 kgs. 50.00 8,250.00
10mm dia. X 6m G33 125.00 kgs. 50.00 6,250.00
Concrete
G-1, 3000 psi 28 days 0.80 cu.m. 4,892.00 3,913.60
3/4", 3000 psi 28 days 1.30 cu.m. 5,210.00 6,773.00
G.I. Tie Wires ga. 16 25.00 kgs. 75.00 1,875.00
100mm thk. CHB Laying, incl. Rebars 19.00 sq.m. 585.00 11,115.00
Lintel Beams 4.00 l.m. 390.00 1,560.00
Stiffener Columns 4.00 l.m. 390.00 1,560.00
Plastering of CHB Wall 38.00 sq.m. 200.00 7,600.00
Roof Slab 9.50 sq.m. 877.50 8,336.25
Tileworks 16.00 sq.m. 840.00 13,440.00
Painting Works 1.00 lot 6,000.00 6,000.00
Ceiling Works 4.00 sq.m. 630.00 2,520.00
Electrical 1.00 lot 5,000.00 5,000.00
Plumbing
Water supply 1.00 lot 3,000.00 3,000.00
Sewer Lines 1.00 lot 3,900.00 3,900.00
Water Closet 1.00 set 3,780.00 3,780.00
Lavatory 1.00 set 2,160.00 2,160.00
Doors and Windows 1.00 lot 4,725.00 4,725.00
SUB-TOTAL D. GUARDHOUSE 107,422.85
F. UNDERGROUND UTILITIES
Excavation 28.00 cu.m. 250.00 7,000.00
300mm dia. RCP Storm Drainage 70.00 l.m. 890.00 62,300.00
450x450mm Catch Basin 18.00 pcs. 1,890.00 34,020.00
150mm dia. PVC Sewer Pipe 64.00 l.m. 890.00 56,960.00
150x100mm dia. PVC Wye 12.00 pcs. 607.50 7,290.00
150mm dia. PVC Cleanout with Plug 4.00 pcs. 435.00 1,740.00
100x100mm dia. X 45 deg PVC Elbow 16.00 pcs. 108.00 1,728.00
50mm dia. G.I. Pipe Water Lines 14.00 l.m. 338.00 4,732.00
12mm dia. G.I. Pipe Water Lines 85.00 l.m. 162.00 13,770.00
50mm dia. Gate Valve 2.00 pcs. 1,323.00 2,646.00
50x50mm G.I. Tee 103.00 pcs. 472.50 48,667.50
50x12mm G.I. Tee 16.00 pcs. 337.50 5,400.00
12mm dia. Elbow Valve 14.00 pcs. 432.00 6,048.00
Waterflowmeter 12mm dia. (labor only, material 14.00 pcs. 400.00 5,600.00
by owner)
SUB-TOTAL F: UNDERGROUND UTILITIES 257,901.50
GRAND TOTAL : SITE DEVELOPMENT WORKS Php1,685,620.27
I. BUILDING
Unit A 362,622.25 7 units 2,538,355.75
Unit B 1,287,471.25 6 units 7,724,827.50
Unit C 2,405,282.30 2 units 4,810,564.60
SUB-TOTAL (BUILDING) Php15,073,747.85
EXCLUDED ITEMS:
1 Value Added Tax
2 Permits (Building, Occupancy & etc.)
3 Door threshold & Door Closer
4 Bathroom Accessories
5 Bathroom Partitions
6 Main Entrance Gate
7 Plant boxes & Landscapping
8 Electrical connection from VECO supply to Building
9 Main Distribution Panel
10 All Water Tank System & Water Heater
11 Waste Water Treatment
12 Water connection from Stud-out to Building Meter
13 Mechanical Works
14 Garbage Bin
SUMMARY
I. GROUND FLOOR AREA TOTAL(12,0000/SQM
1. Terrace 0.00 sqm 0.00
2. Dirty Kitchen 0.00 sqm 0.00
3. Office 7.03 sqm 84,360.00
4.Dining 16.00 sqm 192,000.00
5. Kitchen 9.00 sqm 108,000.00
6.Living Area 12.00 sqm 144,000.00
7. Mini Bar/Stairs 6.00 sqm 72,000.00
8. Playroom 6.00 sqm 72,000.00
9. Laundry Area 0.00 sqm 0.00
10. Porch 9.00 sqm 108,000.00
11.Toilet and Bath 2.40 sqm 28,800.00
12.Garrage 27.60 sqm 331,200.00
13. Maid's Quarter 5.50 sqm 0.00
100.53 sqm 1,140,360.00
SUBMITTED BY:
GENEVEVE L. COLASITO
Architect:
Approved by:
JEFFREY IBANEZ
Owner
Note: Rough estimate 12,000/sqm based but still have to submit PERT-CPM and Final Estimates
PROJECT : PROPOSED TWO STOREY RESIDENTIAL BUILDING
LOCATION : BRGY. San jose Dulag Leyte
:
B. CONSTRUCTION REQUIREMENTS
1. SITE DEVELOPMENT WORKS
Lot embankment/filling (0.40m backfill) 104.00 cu.m. 260.00 27,040.00
Grading and levelling works 120.00 sq.m. 60.00 7,200.00
Soil Poisoning 120.00 sq.m. 120.00 14,400.00
SUB-TOTAL 1: SITE DEVELOPMENT WORKS 48,640.00
2. EXCAVATION WORKS
Building Column Footings / Walls Footings 60.00 cu.m. 250.00 15,000.00
Storm Drainage Lines 2.88 cu.m. 250.00 720.00
Septic Vaults & Cistern 8.00 cu.m. 250.00 2,000.00
Catch Basins 3.50 cu.m. 250.00 875.00
SUB-TOTAL 2: EXCAVATION WORKS 18,595.00
3. STRUCTURAL WORKS
A. Column Footings / Columns
Formworks 96.00 sq.m. 420.00 40,320.00
Rebars
16mm dia. X 6m G40 805.00 kgs. 52.00 41,860.00
10mm dia. X 6m G33 678.00 kgs. 50.00 33,900.00
Concrete
G-1, 3000 psi 28 days 5.00 cu.m. 4,892.00 24,460.00
3/4", 3000 psi 28 days 10.00 cu.m. 5,210.00 52,100.00
G.I. Tie Wires ga. 16 50.00 kgs. 75.00 3,750.00
B. Walls Footings
Formworks 180.00 sq.m. 420.00 75,600.00
Rebars
10mm dia. X 6m G33 600.00 kgs. 50.00 30,000.00
Concrete
G-1, 3000 psi 28 days 3.00 cu.m. 4,892.00 14,676.00
G.I. Tie Wires ga. 16 5.00 kgs. 75.00 375.00
D. Suspended Slabs
Formworks 98.00 sq.m. 420.00 41,160.00
Rebars
10mm dia. X 6m G33 1,200.00 kgs. 50.00 60,000.00
Concrete
3/4", 3000 psi 28 days 2.88 cu.m. 5,210.00 15,004.80
G.I. Tie Wires ga. 16 30.00 kgs. 75.00 2,250.00
E. On-Grade Slabs
Formworks 1.00 lot 5,000.00 5,000.00
Rebars
10mm dia. X 6m G33 898.00 kgs. 50.00 44,900.00
Concrete
G-1, 3000 psi 28 days 24.00 cu.m. 4,892.00 117,408.00
G.I. Tie Wires ga. 16 35.00 kgs. 75.00 2,625.00
4. MASONRY WORKS
100mm thk. CHB Laying, incl. Rebars 120.00 sq.m. 585.00 70,200.00
Lintel Beams 18.00 l.m. 390.00 7,020.00
Stiffener Columns 12.00 l.m. 390.00 4,680.00
Plastering of structural surface 110.00 sq.m. 200.00 22,000.00
Plastering of CHB Wall 336.00 sq.m. 200.00 67,200.00
SUB-TOTAL 4: MASONRY WORKS 171,100.00
5. ROOF FRAMING
Assorted Angle Bars
2.5x2.5x1/4 9.00 lgts. 715.00 6,435.00
2x2x1/4 9.00 lgts. 637.00 5,733.00
C-Purlins, 50x100x1.0mm 18.00 lgts. 585.00 10,530.00
10mm dia. Sag Rod 9.00 lgts. 182.00 1,638.00
12mm dia. Cross Bracings 13.00 lgts. 338.00 4,394.00
12mm dia. Turn Buckle 8.00 pcs. 58.50 468.00
Welding Rod 10.00 box 2,340.00 23,400.00
Cut-off Blade 30.00 pcs. 585.00 17,550.00
Grinding Disk 25.00 pcs. 364.00 9,100.00
Oxygen 1.00 tanks 455.00 455.00
Acetylene 1.00 tanks 1,040.00 1,040.00
Sand Paper 100 9.00 shts. 58.50 526.50
Red Oxide Metal Primer 5.00 gals. 845.00 4,225.00
Paint Thinner 2.00 gals. 546.00 1,092.00
LABOR COST 1.00 LOT 35,000.00 35,000.00
SUB-TOTAL 5 :ROOF FRAMING 121,586.50
6. ROOFING WORKS
ga. 26Prepainted Rib-type Roofing 74.00 sq.m. 416.00 30,784.00
Wall end flushing 24.00 l.m. 182.00 4,368.00
Wall Capping 68.00 l.m. 208.00 14,144.00
Concrete gutter 18.00 l.m. 401.00 7,218.00
Teck Screw, 2 1/2" 1,000.00 pcs. 2.60 2,600.00
Blind Rivets, 1/8" x 1/2" 450.00 pcs. 0.85 382.50
Ga. 16 G.I. Tie Wires 8.00 kgs. 75.00 600.00
10mm PE Foam with one side Alum. 1.00 rolls 3,500.00 3,500.00
Touch-up Paint 3.00 cans 364.00 1,092.00
Silicone Sealant 5.00 bottles 234.00 1,170.00
LABOR COST 1.00 lot 18,000.00 18,000.00
SUB-TOTAL 6 :ROOFING WORKS 83,858.50
8. DOORS
DOOR JAMBS ( Good lumber 2"x6")
D1- 1.6 x 2.1 Main entrance door 1.00 set 6,500.00 6,500.00
D3- 0.9 x 2.1 1.00 set 3,500.00 3,500.00
D4- 0.8x2.1 8.00 sets 3,500.00 28,000.00
D5- .7 x 2.1 3.00 sets 3,000.00 9,000.00
SUB-TOTAL : DOOR JAMBS 47,000.00
WINDOWS
W1, 2400x1000 Sliding Glass Window, Brown 1.00 set 12,420.00 12,420.00
Frame and Glass
W2, 2400x2400 Sliding Glass Window, Brown 1.00 set 29,808.00 29,808.00
Frame and Glass
W3,1200x2400 Sliding Glass Window, Brown 5.00 set 13,248.00 66,240.00
Frame and Glass
W-8&11, 600x600 Awning Glass Window, Br 2.00 sets 1,863.00 3,726.00
Frame and Glass
W5,1200x600 Sliding Glass Window, Brown 1.00 set 3,726.00 3,726.00
Frame and Glass
W6, 600x2400 Awning Window, Brown 2.00 sets 7,452.00 14,904.00
Frame and Glass
W, 1200x2000 Fixed Window on Analok Fram 1.00 sets 9,600.00 9,600.00
SUB-TOTAL 7 :DOORS AND WINDOWS 234,424.00
9. PAINTING WORKS
Exterior Walls, primeir white/with water proof 60.00 sq.m. 230.00 13,800.00
Interior Walls, primier white 110.00 sq.m. 180.00 19,800.00
Door Jambs 35.00 sq.m. 270.00 9,450.00
LABOR COST 1.00 LOT 25,000.00 25,000.00
SUB-TOTAL 10 :PAINTING WORKS 68,050.00
PLUMBING STRUCTURES
Grease Trap(stainless) 1.00 sets 4,500.00 4,500.00
4" pvc pipe 12.00 sets 450.00
Catch Basin 4.00 sets 2,350.00 9,400.00
Septic vault 1.00 lot 35,000.00 35,000.00
PLUMBING FIXTURES AND ACCESSORIES
Kitchen Sink 2.00 sets 3,200.00 6,400.00
Water Closet 3.00 sets 5,500.00 16,500.00
Lavatory 3.00 sets 2,300.00 6,900.00
Shower Head and Valve 3.00 sets 3,500.00 10,500.00
Soap Holder 3.00 sets 700.00 2,100.00
Paper Holder 3.00 sets 700.00 2,100.00
Floor Strainer 3.00 sets 700.00 2,100.00
LABOR COST 1.00 LOT 31,800.00 31,800.00
SUB-TOTAL 12 : PLUMBING WORKS 195,340.70
SUBJECT : SUMMARY
PHASE I
A. GENERAL REQUIREMENTS
B. CONSTRUCTION REQUIREMENTS
PHASE I:
4: MASONRY WORKS 171,100.00 1,338,264.60
PHASE II
5 :ROOF FRAMING 121,586.50
PHASE II:
8 : DOOR JAMBS 47,000.00 568,875.00
PHASE III
9 :PAINTING WORKS 68,505.00
PHASE III:
11 :STAIRS RAILINGS AND TERRACE RAILINGS 140,000.00 316,010.00
PHASE IV
12 : PLUMBING WORKS 195,340.70
PRESENTED BY:
GENEVEVE L. COLASITO
ARCHITECT
APPROVED:
JEFFREY IBANEZ
OWNER