Concrete Mix Design Calculation For M20, M25, M30 Concrete With Procedure & Example
Concrete Mix Design Calculation For M20, M25, M30 Concrete With Procedure & Example
Concrete Mix Design Calculation For M20, M25, M30 Concrete With Procedure & Example
Concrete mix design is the process of finding right proportions of cement, sand and
aggregates for concrete to achieve target strength in structures. So, concrete mix
design can be stated as Concrete Mix = Cement:Sand:Aggregates.
The concrete mix design involves various steps, calculations and laboratory testing to
find right mix proportions. This process is usually adopted for structures which
requires higher grades of concrete such as M25 and above and large construction
projects where quantity of concrete consumption is huge..
Benefits of concrete mix design is that it provides the right proportions of materials,
thus making the concrete construction economical in achieving required strength of
structural members. As, the quantity of concrete required for large constructions are
huge, economy in quantity of materials such as cement makes the project construction
economical.
Concrete Mix design of M20, M25, M30 and higher grade of concrete can be
calculated from example below.
Concrete Mix Design
Data Required for Concrete Mix Design
(i) Concrete Mix Design Stipulation
(a) Characteristic compressive strength required in the field at 28 days grade
designation — M 25
(f) Type of exposure the structure will be subjected to (as defined in IS: 456) — Mild
Shape of
Angular Angular Nil –
Aggregate
Total +3
Estimated water content = 186+ (3/100) x 186 = 191.6 kg /m3
Step 4 — Selection of Cement Content
Water-cement ratio = 0.5
In the present example against mild exposure and for the case of reinforced concrete
the minimum cement content is 300 kg/m3 which is less than 383.2 kg/m3. Hence
cement content adopted = 383.2 kg/m3.
As per clause 8.2.4.2 of IS: 456
pump able
Workability – – -10% See Note 2
concrete
Total -10%
Note 1: For every ±0.05 change in w/c, the coarse aggregate proportion is to be
changed by 0.01. If the w/c is less than 0.5 (standard value), volume of coarse
aggregate is required to be increased to reduce the fine aggregate content. If the w/c is
more than 0.5, volume of coarse aggregate is to be reduced to increase the fine
aggregate content. If coarse aggregate is not angular, volume of coarse aggregate may
be required to be increased suitably, based on experience.
Note 2: For pump able concrete or congested reinforcement the coarse aggregate
proportion may be reduced up to 10%.
Hence,
Volume of coarse aggregate per unit volume of total aggregate = 0.62 x 90% = 0.558
For casting trial -1, mass of ingredients required will be calculated for 4 no’s cube
assuming 25% wastage.
In this case,
Slump value = 25 mm
Mix is cohesive, workable and had a true slump of about 25 mm and it is free from
segregation and bleeding.
Slump value = 60 mm
Mix is very cohesive, workable and had a true slump of about 60 mm.
It virtually flowed during vibration but did not exhibit any segregation and bleeding.
Hence the coarse aggregate as percentage of total aggregate = 0.558 – 0.01 = 0.548
W/c = 0.55
Slump value = 75 mm
Mix is stable, cohesive, and workable and had a true slump of about 75 mm.
W/c = 0.45
A reduction of 0.05 in w/c will entail and increase of coarse aggregate fraction by
0.01.
W/c = 0.44