Location via proxy:   [ UP ]  
[Report a bug]   [Manage cookies]                

Right Factorz Projects PVT LTD Checklist For Cable Installation

Download as docx, pdf, or txt
Download as docx, pdf, or txt
You are on page 1of 9

RIGHT FACTORZ PROJECTS PVT LTD SECTION: FORMAT

CHECKLIST FOR CABLE INSTALLATION


SHEET:1 of 2

Project : Drawing no/ Location


Client : Loop No.
Contractor : FAP No.:

Checked
by Inspected
Sr. No. Item Description Contractor by TCE
(Tick) (Tick)

CABLE INSTALLATION

Before laying of the cable, cable drum rating and megger


value between all the cores has been checked and found
OK.
1.1 
Cable laying done as per approved method of statement
as per cable schedule
1.2 
Before glanding cable continuity is checked and found
1.3 OK. 
proper bending radius maintained
1.4 
Does the distance between each saddle within 300mm for
armored cables?
1.5 
Cabling done using conduits for armored cables while
1.6 running inside the walls? 
Plastic getties (Fischer's) are used for saddle/base
1.7 installation? 
Cable bending is done without effecting the cable
1.8 strength? 
1.9 Cable end caps provided at cable end after installation? 
1.10 proper clamping and dressing done with pvc cable tie 
1.11 Identification markings on cables 

WORK DONE BY CHECKED BY ACCEPTED BY

Name

Designation

Signature &
Date
RIGHT FACTORZ PROJECTS PVT LTD SECTION: FORMAT

CHECKLIST FOR TRAY INSTALLATION


SHEET:1 of 2

Project : Drawing no / Location


Client : Loop No.
Contractor : Make .:

Checked by Inspected
Sr. No. Item Description Contractor by TCE
(Tick) (Tick)

CABLE TRAY INSTALLATION

Cable tray layout as per G.A/ composite layout drwg


1.1 no.___________ 

Generally confirming to  
cable tray notes an details
as per
1.2 specification no. __________________________________________ 

1.3 Preparation for Erection 

Availability of materials for  


cable tray supports, cable
trays like
1.4 structural steel, Tees, Bends including all tray accessories 

Availability of necessary 
tools / tackles for
1.5 fabrication of cable trays / 
1.6 Erection 

Fabrication, erection &  


painting of cable tray
support structure as per
1.7 specifications. 

Earthing of cable trays and  


its connection to main
earthing grid. Earth
1.8 continuity connection between cable trays 


Installation of cable tray covers after completing cable


1.9 laying 

Identification markings of cable tray numbers on


1.10 trays 
1.11 Copper Earthing jumper between connecting tray 

WORK DONE BY CHECKED BY ACCEPTED BY

Name

Designation

Signature &
Date
RIGHT FACTORZ PROJECTS PVT LTD SECTION: FORMAT
TCE-HW-ELV-001
Checklist for Panel/Rack Installation
SHEET:1 of 1

Project : : Drawing no / Location


Client : : Loop No.
Contractor : : Make .:

Checked by Inspected
Sr. No. Item Description Contractor by TCE
(Tick) (Tick)

Installation Check Sheet for Panel/Rack

Name Plate details are checked with the latest IFC Drawing
1.1 and found OK. 
1.2 Factory test reports are found OK. 
Switchgear installation is carried out as per the approved
1.3 Method of Statement. 
Visual Inspection done for any transportation damages and
1.4 damages are not found. 
1.5 Foundation checks done for level and found OK. 
1.6 Base frames are fixed. 
Panel/Rack are installed in sequence as per the latest IFC
1.7 drawing. 

Alignment of Panel/Rack to be done properly and location 


found OK. 
1.8 
1.9 Glanding done properly 

WORK DONE BY CHECKED BY ACCEPTED BY

Name

Designation

Signature &
Date
RIGHT FACTORZ PROJECTS PVT LTD SECTION: FORMAT

Checklist for Devices Installation in True


ceiling
SHEET:1 of 2

Project: : Drawing no. / Location:


Client: : Loop No:
Device Name.:
Contractor: : Make :

Checked by Inspected
Sr. No. Item Description Contractor by TCE
(Tick) (Tick)

1.1
Loop checked for cables . 

1,2
Junction box installed properly . 

Proper cable entry to junction box with glands.


1.3 

1.4 Speaker fixed properly. 


Loop cables terminated to speaker with lugs and
1.5 ferules. 

Identification tag sticked on speaker.


1.6 

Hooter, Horn/strobe , control relay, Input module and


1.7 monitor module are installed properly in false ceiling . 

1.8
Speaker Installed aesthetically .


Done as per P & ID and hook up drawing.


1.9 


WORK DONE BY CHECKED BY ACCEPTED BY

Name

Designation

Signature &
Date
RIGHT FACTORZ PROJECTS PVT LTD SECTION: FORMAT

Checklist for Devices Installation in


false ceiling
SHEET:1 of 2

Project: : Drawing no. / Location:


Client: : Loop No:
Device Name.:
Contractor: : Make :

Checked by Inspected
Sr. No. Item Description Contractor by TCE
(Tick) (Tick)

1.1
Loop checked for cables . 

1,2
Junction box installed properly . 

Proper cable entry to junction box with glands.


1.3 

1.4 Detector base fixed properly. 

1.5 Detector fixed properly. 

1.6 RI fixed properly and straight to AFC . 

1.7 Loop cables terminated to base with lugs and ferules. 

Identification tag sticked on detector.


1.8 

Hooter, Horn/strobe , control relay, Input module and


1.9 monitor module are installed properly in false ceiling . 

1.10
Devices Installed aesthetically .


Done as per P & ID and hook up drawing.


1.11 

WORK DONE BY CHECKED BY ACCEPTED BY

Name

Designation

Signature &
Date

You might also like