Traction Simulation Example Using ETrax Analysis.
Traction Simulation Example Using ETrax Analysis.
Analysis will be carried out for a 2.3km long 4 station 25kV AC 50Hz single phase traction
power supply system as shown in the details following.
ETRAX module can be utilized to evaluate the performance of rolling stock over a rail
traction network and monitor the adequacy of catenary & traction transformers, voltage
profile over the catenary, overall reactive power consumption requirements of the network,
etc. Results of the ETRAX study is given at the end of the notes which includes simulation
plots of the following parameters with respect to time: -
• Tractive Effort
• Net Acceleration
• Speed
• Distance travelled
• kW and Amp
This document is confidential and proprietary to ETAP / ETAP Automation and may not be reproduced, published or disclosed to others without
written authorization of ETAP / ETAP Automation. All Rights Reserved.
Page 1
ETAP Workshop Notes
Inputs Required
This document is confidential and proprietary to ETAP / ETAP Automation and may not be reproduced, published or disclosed to others without
written authorization of ETAP / ETAP Automation. All Rights Reserved.
Page 2
ETAP Workshop Notes
This document is confidential and proprietary to ETAP / ETAP Automation and may not be reproduced, published or disclosed to others without written authorization of ETAP / ETAP Automation. All
Rights Reserved.
Page 3
ETAP Rolling Stock library
Number of Cars 3 (2M+T)
Auxilary
Voltage 415 V
Power 180 kVA
Boogie
Number of Axles 12
General
Line voltage AC25 kV
Total mass 191361 T
Tare weight 128051 T
Passenger mass(AW3) 63310 T
Max Axle load 16 T
Min Axle Load 15.9 T
Length 68032 mm
Width 2840 mm
Hieght 4200 mm
Continuous Rating
Power 5887.581699 kW
Shaft power kW
Tractive effort 225.2 kN
Speed 80 kmph
Max Tractive effort 225.2 kN
Max Speed 80 kmph
Efficiency 85
Power factor 90
Resistance Coefficients
Cross sectional Area m²
A 14.01 kN/tonne
B 0.264 (kN/tonne)* hr/km
C 0.00191 (kN/tonne)* (hr/km²)
Wheel Diameter
New 860 mm
Half worn 820 mm
Full worn 780 mm
Cross sectional Area m²
Inverter
Rated voltage 1.4 kV
Rated kVA 320 kVA
Current Limit 950 Apeak
Number of Pulses Asynchronous - 3P-1P
Quantity 2
Efficiency 0.99
Pantograph
Quantity 2
Make Faiveley
Type LX1800
Rectifier
Rated kV 0.951 kV
Rated kVA 601.032 kVA
Rated pf 0.98
Current Limit 2000 Apeak
Number of Pulses 25 Pulse
Rated DCV 1800 V
Quantity 2
Current 133 A
Speed 2005 rpm
Gear Ratio 6.478
SF
Transformer
Make MELCO
Type ATM29A
Quantity 1
Cooling Forced Oil, Forced Air cooling
Primary Rating 2737 kVA
Secondary rating 2405 kVA
Tertiary Rating 332 kVA
Number of taps
Location of Taps
Primary Voltage 22.5 kV
Secondary Voltage 0.856 kV
Tertiary Voltage 0.342 kV
Primary Current 122 A
Secondary Current 702 A
Tertiary Current 485 A
Impedance Please refer 3.6 Impedance ohms
Voltages (22.5kV, 50Hz,
85°C)
X/R
ETAP Workshop Notes
This document is confidential and proprietary to ETAP / ETAP Automation and may not be reproduced, published or disclosed to others without written authorization of ETAP / ETAP Automation. All
Rights Reserved.
Page 4
ETAP Workshop Notes
This document is confidential and proprietary to ETAP / ETAP Automation and may not be reproduced, published or disclosed to others without written authorization of ETAP / ETAP Automation. All
Rights Reserved.
Page 5
TRACK LAYOUT
PT 1A PT 2A PT 3A UP TRACK
PT 1B PT 2B PT 3B DN TRACK
PT
1005 M
4A
200 Mtrs 1041.7 Mtrs trs
PT
ST
4B
AT
IO
N
4
LEGENDS :-
FROM TO LENGTH (m)
132kV, 20kA
X/R = 14
R
Y
B
21 MVA 21 MVA
132 / 27.5kV 132 / 27.5kV
Ph Ph
N N
SECTION SWITCH
TO RAIL TO RAIL
TRACK TRACK
25kV CATENARY UP TRACK
ISOLATOR
SECTION SWITCH
ISOLATOR PANTOGRAPH
PANTOGRAPH
PT 1A UP TRACK PT 2A PT 3A PT 4A
PT 1B DN TRACK PT 2B PT 3B PT 4B
Catenary Data
Catenary Impedance
Raa 0.14 ohm/km
Rab 0.084 ohm/km
Xaa 0.4 ohm/km
Xab 0.24 ohm/km
The values of self and mutual impedances should be evaluated based on overhead catenary conductor
size, configuration, its distance from the ground and soil resistivity. In this case, the traction supply
comprises of single-phase double track 25kV AC network; above table indicates typical data for 150
sq.mm. CuAg contact wire.
Track Data
The above data indicates typical AC resistance per unit length @ 90deg for UIC60 track.
This document is confidential and proprietary to ETAP / ETAP Automation and may not be reproduced, published or disclosed to others without
written authorization of ETAP / ETAP Automation. All Rights Reserved.
6
ETAP Workshop Notes
PROCEDURE
2. Select library TEST.lib and warehouse Traction1.wh from the project folder.
Warehouse is a database utilized by ETRAX for entering catenary and track details.
This document is confidential and proprietary to ETAP / ETAP Automation and may not be reproduced, published or disclosed to others without
written authorization of ETAP / ETAP Automation. All Rights Reserved.
7
ETAP Workshop Notes
Library file can be selected as below -
This document is confidential and proprietary to ETAP / ETAP Automation and may not be reproduced, published or disclosed to others without
written authorization of ETAP / ETAP Automation. All Rights Reserved.
8
ETAP Workshop Notes
3. To build the rail traction network, go to Geospatial View
This document is confidential and proprietary to ETAP / ETAP Automation and may not be reproduced, published or disclosed to others without
written authorization of ETAP / ETAP Automation. All Rights Reserved.
9
ETAP Workshop Notes
4. Go through the traction elements available in the ‘Traction Editor Toolbar’ on the
right-hand side and select track segment.
5. Develop a track 1841m long as shown below. Once the track segment is placed on the
page, user can drag the cursor and accordingly adjust the length.
6. Tilt the track to achieve some bend and further increase the track length up to 400m.
Total length of track route is 2.23km.
7. Select Train station from the traction element toolbar and create train station on ends of
the track and name it as Station 1.
This document is confidential and proprietary to ETAP / ETAP Automation and may not be reproduced, published or disclosed to others without
written authorization of ETAP / ETAP Automation. All Rights Reserved.
10
ETAP Workshop Notes
9. Place the platform on each Train station. For this select the track segment and from the
traction toolbar select ‘platform’ element and place it where track ends in station 1
area.
Note: The platform element will be visible on the toolbar only after selecting the track
segment.
This document is confidential and proprietary to ETAP / ETAP Automation and may not be reproduced, published or disclosed to others without
written authorization of ETAP / ETAP Automation. All Rights Reserved.
11
ETAP Workshop Notes
10. Follow the same procedure and place the second platform on track in station 2 area.
11. Select the track segment between platform1 and platform2 and select the ‘Measure
selection’ tool from the top toolbar
This document is confidential and proprietary to ETAP / ETAP Automation and may not be reproduced, published or disclosed to others without
written authorization of ETAP / ETAP Automation. All Rights Reserved.
12
ETAP Workshop Notes
12. As per the data mentioned in Track layout diagram on Pg. 9, the length between
station1 and station is 200m. To achieve this length adjust the location of platform 2.
Select platform 2 alone and drag it to the right-hand side; this will stretch the track.
Repeat step10 and check whether the length of track segment has increased to 200m.
13. Repeat step 9 –step 11 for station 3 and station 4 and model the tracks as per track
segment lengths mentioned in Track Layout diagram on Pg. 9.
After preparation of tracks, platforms and station layout, assign following limit as per the
layout drawings
Speed Limit,
Curve radius,
Elevation
Also assign acceleration/deceleration limit in ETRAX editor.
14. Model a speed limiter of 80kmph on track segment length between every 2 stations. From
the toolbar select speed limit and place it on the track. The speed limit represents the
maximum operating speed of the train on the track. This data could be obtained from vendor
or as project specification.
This document is confidential and proprietary to ETAP / ETAP Automation and may not be reproduced, published or disclosed to others without
written authorization of ETAP / ETAP Automation. All Rights Reserved.
13
ETAP Workshop Notes
For this example, consider a speed limit of 80kmph for both Passenger Train and freight
trains
15. For modelling a bend on track between station3 and station4, take bend radius marker from
the traction toolbar and insert it on either side of the bend.
This document is confidential and proprietary to ETAP / ETAP Automation and may not be reproduced, published or disclosed to others without
written authorization of ETAP / ETAP Automation. All Rights Reserved.
14
ETAP Workshop Notes
Click on the marker and open the “Bend Radius” tab, to check the bend radius evaluated by
ETRAX.
16. To make track curve smooth right click on the bend radius marker and select ‘Re-shape
Edge along the Curve’.
17. Similarly take elevation marker from the traction toolbar and insert it at some distance away
from the station 2.
This document is confidential and proprietary to ETAP / ETAP Automation and may not be reproduced, published or disclosed to others without
written authorization of ETAP / ETAP Automation. All Rights Reserved.
15
ETAP Workshop Notes
18. Now in the distribution view and insert an element ‘insulator with isolator’ on track
segment between Station 2 and station 3.
This document is confidential and proprietary to ETAP / ETAP Automation and may not be reproduced, published or disclosed to others without
written authorization of ETAP / ETAP Automation. All Rights Reserved.
16
ETAP Workshop Notes
19. The above procedure needs to be repeated for the second track (Down Track)
This document is confidential and proprietary to ETAP / ETAP Automation and may not be reproduced, published or disclosed to others without
written authorization of ETAP / ETAP Automation. All Rights Reserved.
17
ETAP Workshop Notes
Part: 2 ETRAX editor
20. Go to ETRAX analysis module and open ETRAX editor and go to the first page ‘Track
Group’. Click on new to form a new track group. Then select the track and observe the track
group has been updated with the two platforms, track and speed limit lying on the track.
This document is confidential and proprietary to ETAP / ETAP Automation and may not be reproduced, published or disclosed to others without
written authorization of ETAP / ETAP Automation. All Rights Reserved.
18
ETAP Workshop Notes
21. Now click on ‘Add elements’ and select the platform from where you wish to start the train.
Similarly form Track groups for other tracks between Station 2 to Station 3, Station 3 to
Station 4.
22. Go to next Page ‘Track Route’ and click on new to form a track Route. Update the track
Route by selecting the Platform1 and observe Track group1 to Track group5 has been update
under Track Route.
This document is confidential and proprietary to ETAP / ETAP Automation and may not be reproduced, published or disclosed to others without
written authorization of ETAP / ETAP Automation. All Rights Reserved.
19
ETAP Workshop Notes
23. Go to next page ‘time schedule’ and Create a new timetable for the Track Route1. Create
new Timetable and put Headway time as 3 min and Dwell Time as 0.5 min (30sec). Enable
the timetable for Monday.
This document is confidential and proprietary to ETAP / ETAP Automation and may not be reproduced, published or disclosed to others without
written authorization of ETAP / ETAP Automation. All Rights Reserved.
20
ETAP Workshop Notes
Based on the above details entered ETAP will generate a schedule automatically as shown below.
24. Go to Next page and create a new Train Configuration and from Rolling stock Library
select the following Rolling Stock.
This document is confidential and proprietary to ETAP / ETAP Automation and may not be reproduced, published or disclosed to others without
written authorization of ETAP / ETAP Automation. All Rights Reserved.
21
ETAP Workshop Notes
This document is confidential and proprietary to ETAP / ETAP Automation and may not be reproduced, published or disclosed to others without
written authorization of ETAP / ETAP Automation. All Rights Reserved.
22
ETAP Workshop Notes
Put acceleration and deceleration limit as 1m/s² each and set the quantity as 1. Although the selected
train has a 2M+1T configuration, the quantity entered here is one.
The rolling stock library data considered for this exercise represents complete train set i.e. rolling
stock parameters such as power consumption, tractive effort, weight, length are representative of
complete train set comprising of 2 Motor Coaches and 1 Trailer Coach (2M+1T). Hence the
quantity in the above page shall be entered as 1.
It should be noted that e-TraX also facilitates modelling of individual Motor Coaches/
Engines/Locomotives and Trailer Coaches in the Rolling Stock library (based on actual vendor
data) and can form combinations of motor and trailer coaches in this Train Configuration page by
adding more than 1 elements and entering quantity as desired.
This document is confidential and proprietary to ETAP / ETAP Automation and may not be reproduced, published or disclosed to others without
written authorization of ETAP / ETAP Automation. All Rights Reserved.
23
ETAP Workshop Notes
Close the eTraX editor and in the distribution view select the complete track and Right Click to
assign track and catenary warehouse
This document is confidential and proprietary to ETAP / ETAP Automation and may not be reproduced, published or disclosed to others without
written authorization of ETAP / ETAP Automation. All Rights Reserved.
24
ETAP Workshop Notes
This document is confidential and proprietary to ETAP / ETAP Automation and may not be reproduced, published or disclosed to others without
written authorization of ETAP / ETAP Automation. All Rights Reserved.
25
ETAP Workshop Notes
25. Select the complete traction model in geospatial view and click on create OLV button in the
Traction elements toolbar. This step will create equivalent one-line diagram of the traction
model in the ‘One Line View’ OLV page.
26. Go to One Line Diagrams and click on ‘Zoom to Fit Page’ button and observe the traction
model developed in geospatial view has been transferred to OLV.
This document is confidential and proprietary to ETAP / ETAP Automation and may not be reproduced, published or disclosed to others without
written authorization of ETAP / ETAP Automation. All Rights Reserved.
26
ETAP Workshop Notes
Part: 3 TSS modelling
30. Connect an HVCB on the secondary of the Transformer and develop the 25kV traction supply
bus. From this bus, take the supply connection to one node of the insulator+isolator block as
This document is confidential and proprietary to ETAP / ETAP Automation and may not be reproduced, published or disclosed to others without
written authorization of ETAP / ETAP Automation. All Rights Reserved.
27
ETAP Workshop Notes
shown. Note that the isolator position can be set to ‘Open’ or ‘Close’ based on the desired
operating mode.
31. Similarly, develop the SLD for the second feeder & second bus as shown above.
32. Once the second feeder is modelled, the user can switch between dual-transformer (with bus-
breaker open) or single-transformer operation using the configuration manager.
34. In the schedules page, for Track Route1 select schedule ‘TEST-Mrng” from the dropdown
list. Also check Update Check box for the selected Time schedule.
This document is confidential and proprietary to ETAP / ETAP Automation and may not be reproduced, published or disclosed to others without
written authorization of ETAP / ETAP Automation. All Rights Reserved.
28
ETAP Workshop Notes
Note that a simulation time step of 1 second has been selected which ensures that calculation
is performed for every second over the schedule. The plot time step has been set to 10 sec,
which means the response plots will be displayed for values evaluated every 10 seconds. For
observing values at every second, the user can choose 1 second as the plot step.
Simulate the case by clicking on ETRAX Analysis button
35. Once the case is simulated a Time Slider appears. Move the the slider and observe the
movement of Trains along the track
Observe the speed, distance travelled and Tractive effort being display while the train is
moving along the track
36. Go to Display Options and check ‘Show Units’ and ‘Branch Losses’. Data of each train can
be displayed on screen by toggling desired parameters in the display options.
This document is confidential and proprietary to ETAP / ETAP Automation and may not be reproduced, published or disclosed to others without
written authorization of ETAP / ETAP Automation. All Rights Reserved.
29
ETAP Workshop Notes
37. Go to Plot manager and plot the following for any one trip
(i) Speed
(ii) Distance travelled
(iii) Net Acceleration
(iv) Rolling Resistance
(v) Tractive Effort
(vi) KW
(vii) Amp
This document is confidential and proprietary to ETAP / ETAP Automation and may not be reproduced, published or disclosed to others without
written authorization of ETAP / ETAP Automation. All Rights Reserved.
30
ETAP Workshop Notes
ANNEX 1
E-TRAX Theory Methodology and Formulas
This document is confidential and proprietary to ETAP / ETAP Automation and may not be reproduced, published or disclosed to others without
written authorization of ETAP / ETAP Automation. All Rights Reserved.
31
ETAP Workshop Notes
Schematic Diagram of Electric Locomotive
A
electric locomotive takes power supply from a overhead catenary line through a pantograph. The supply voltage is
brought down with the help of step down transformer located in the locomotive itself. The low ac voltage so
obtained is converted dc using rectifier/converter. This voltage is then fed to traction motors and auxiliary supply
Typical Speed Time Curve
Initially during a constant acceleration is maintained. As the speed increases and approaches max operational value the
acceleration gradually decreases. Once the train achieves its max operating speed it made to run at this speed constantly
for some time and ten power to the motor is cut off so that train runs under its momentum the speed gradually falls due
to friction and windage. During coasting kinetic energy of the train is utilized which would otherwise be wasted during
retardation. To bring the train to rest brakes are applied.
E-TRAX will evaluate this from station to station based on the input entered (See the result in the last section)
This document is confidential and proprietary to ETAP / ETAP Automation and may not be reproduced, published or disclosed to others without
written authorization of ETAP / ETAP Automation. All Rights Reserved.
32
ETAP Workshop Notes
Tractive Effort
Tractive effort is the force developed by the traction unit at the rim of the driving wheel for moving the unit and it’s
tailing loads
Ft = Fa + Frr ± Fgr+ Fcr kN
Where,
Ft = Tractive effort in kN
Fa = Acceleration resistance =force required for linear acceleration in kN
Frr = Rolling Resistance = Force required to overcome resistance to train motion in kN
Fgr = Grade Resistance = Force required to overcome gravitational force required to overcome ascending /
descending gradient in kN. +Fg for ascending gradient and –Fg for descending gradient.
Fcr = Curve Resistance = Force required to overcome a bend or curve on track in kN
W= Weight in tons
AF = Cross Sectional Area in m²
V = Speed in Km/hr
n = Number of Axles
A = bearing resistance coefficient
A1 = mass per axle rolling resistance coefficient to represent the journal or bearing resistance
A2 = mass per axle coefficient to represent resistance between wheel flange and rail
B = rolling resistance coefficient
C = air resistance coefficient
B1 = rolling resistance coefficient for EMU motor coach
From the data provided by the vendor following co-efficient have been considered.
A 1.4010E-02 kN/tonne
B 2.6400E-04 kn/tonne * hr/km
C 1.6000E-07 kn/tonne * (hr/km)^2
A1 0 kN
A2 0 kN/Tonne
B1 0 (kN/Tonne^2)* hr/km
Fa(adjusted) = Me * alimit kN
Fa(Adjusted) = Ft(adjusted) - (Frr + Fgr + Fcr)
This document is confidential and proprietary to ETAP / ETAP Automation and may not be reproduced, published or disclosed to others without
written authorization of ETAP / ETAP Automation. All Rights Reserved.
33
ETAP Workshop Notes
3. Gradient Resistance Fg
Gradient resistance is amount of force on a train due to change in level grade. This force can be +ve or –ve
depending on up or down grade respectively.
Fg = 9.8 X M X sinθ kN
Where,
M = Net mass in Tonne
G = Gradient of a slope in % (which is worked out in e-TRAX editor)
Θ = ATAN (G/100) rad
4. Curve Resistance
Curve resistance is additional rolling resistance a train must overcome when travelling on a curved section of
a track. It is calculated from bend radius.
Where:-
S = Wheel diameter in m
A = Set constant at 2.896. Mean value of all fixed wheel bases with a< 3.3S in m
R = Curve radius in m
Fcr = Curve resistance in kN
This document is confidential and proprietary to ETAP / ETAP Automation and may not be reproduced, published or disclosed to others without
written authorization of ETAP / ETAP Automation. All Rights Reserved.
34
ETAP Workshop Notes
ANNEX 2
E-TRAX Simulation Results
This document is confidential and proprietary to ETAP / ETAP Automation and may not be reproduced, published or disclosed to others without
written authorization of ETAP / ETAP Automation. All Rights Reserved.
35
ETAP Workshop Notes
Train Speed
Distance Travelled
This document is confidential and proprietary to ETAP / ETAP Automation and may not be reproduced, published or disclosed to others without
written authorization of ETAP / ETAP Automation. All Rights Reserved.
36
ETAP Workshop Notes
Net Acceleration
Rolling Resistance
This document is confidential and proprietary to ETAP / ETAP Automation and may not be reproduced, published or disclosed to others without
written authorization of ETAP / ETAP Automation. All Rights Reserved.
37
ETAP Workshop Notes
Tractive Effort
kW
This document is confidential and proprietary to ETAP / ETAP Automation and may not be reproduced, published or disclosed to others without
written authorization of ETAP / ETAP Automation. All Rights Reserved.
38
ETAP Workshop Notes
Amps
This document is confidential and proprietary to ETAP / ETAP Automation and may not be reproduced, published or disclosed to others without
written authorization of ETAP / ETAP Automation. All Rights Reserved.
39