E16355
E16355
E16355
PART 1 – GENERAL
B. The Contractor shall, as part of his responsibility, check the ratings and/or sizes
of those components whose ratings and sizes are specified in the Contract
documents. When this check indicates that the specified ratings and sizes are
not adequate, the Contractor shall make the necessary changes.
12. Special tools required for the initial installation and future maintenance.
D. The installation of switchgear and bus duct shall include the following:
3. Field testing.
E. Like parts of the circuit breaker(s) of the same rating shall be fully
interchangeable both electrically and mechanically so that where so
interchanged, the circuit breaker(s) shall perform equally well in every respect.
G. Related Work:
A. The switchgear and bus duct including all components furnished in accordance
with this Specification shall comply with the latest edition of the following
applicable Standards and Codes:
C. Contractor may, upon the approval of the Royal Commission, use other
standards and publications, the use of which will result in equipment of
comparable or better quality than that specified. The Contractor shall submit a
copy of the applicable sections of the other standards in the English language for
review by the Royal Commission.
1.3 SUBMITTALS
A. Test Reports: Submit test reports and certification of all manufacturer factory
tests. Test reports shall show compliance with applicable standards. Submit
field test plans and field test reports. All test reports shall be in English language.
B. Design and Shop Drawings: Submit for review the following as a minimum:
1. One-line diagrams.
2. Three-line diagrams.
4. Material lists.
6. Layout and installation details complete with supports for switchgear and
bus duct.
4. Bus duct induced current and voltage across insulating joints and
supporting structure.
PART 2 – PRODUCTS
2.1 GENERAL
A. The switchgear and bus duct will be installed indoors at an elevation less than
1000 meters above sea level in a seismic zone classification defined in the Royal
Commission Building Code.
B. The site conditions under which the switchgear and associated equipment is
required to operate are as follows:
C. For complete information about site conditions, see the Royal Commission
General Design Criteria and Technical Guidelines.
15kV 35kV
1. Rated system voltage kV (rms) 13.8 34.5
2. Maximum system voltage kV (rms) 15 38
3. Power frequency withstand
(1 minute) voltage kV (rms) 36 80
4. Lightning impulse withstand
(1.2x50 Microsecond) voltage (BIL) kV (peak) 95 150
5. Main buses continuous current A 1250 2000 3000 2000 2500
6. Circuit Breakers, incoming & tie A 1250 2000 3000 2000 2500
16. The switchgear shall be fully rated for the maximum expected short-circuit
current (see 1.3C2).
10. The following equipment required for handling, testing, and operating of
switchgear shall be furnished:
11. Each switchgear assembly shall have 20% spare units as shown on
contract drawings complete with medium voltage circuit breakers, relays,
switches and indicating lights.
b. One (1) current transformer per pole on the supply (line) side of the
breaker. Each current transformer shall have three (3) secondaries.
OR
h. Cubicle lighting.
b. One (1) current transformer per pole on the load side of the
breaker. Each current transformer shall have three (3) secondaries.
f. Cubicle lighting.
f. Cubicle lighting.
4. Each cubicle shall be separated into busbar, cable connection, and circuit
breaker and control compartments by steel partitions. The low voltage
control compartment shall be completely isolated from high voltage
compartments.
1. The installation shall have main and tap busbar sections. The busbars
shall be fully insulated copper. Insulation level shall be as specified in
2.2A. Bolted bus connection shall be covered with removable insulated
boots.
2. Silver-plating shall be provided for all bolted connections on the bus and
breaker cells.
3. The busbar and all other conductors shall be able to withstand the
specified ratings without dangerous temperature rise or other damage
occurring. Hottest spot temperature rise shall be limited to 50 oC above
55oC room ambient.
5. Each switchgear section shall be provided with a main copper ground bus
(not less than 51 x 6-mm) continuous throughout and connected to all
RCMYAS Guide Spec. 16355-10 Contract No.
Rev. A, 24 Dec ‘06
units near the bottom in accordance with IEEE Std C37.20. The ground
bus shall be furnished with clamp-type terminals at each end for
connection of 240 mm2 copper ground cable. All framework, metal
enclosures, and barriers shall be securely grounded and grounding
connections shall be brought to the ground bus.
1. 15kV and 35kV circuit breakers shall be draw-out, vacuum or SF6 type, 3-
pole, single throw, mechanically and electrically trip-free and with electric
motor wound spring-charged operating mechanism.
2. Each circuit breaker truck shall have fully connected, test and draw-out
positions. In test position the breaker main contacts shall be isolated from
the bus by positive-action insulated shutters and the truck shall remain
inside cubicle. Guides and racking mechanisms shall be adequate to
perform this function without the application of undue force and with
complete safety.
4. Breaker auxiliary contacts and the draw out truck-operated auxiliary switch
shall be furnished and completely wired. A minimum of five (5) each
normally open (“a”) and five (5) each normally closed (“b”) spare auxiliary
contacts shall be provided in addition to the auxiliary contacts required for
circuit breaker operation. Normally closed auxiliary spare contacts shall
break before the normally open spare contacts are made. All auxiliary
contacts shall be operated by the breaker mechanism in both the
operating and test positions. All spare auxiliary contacts shall be wired to
terminal blocks for external connections.
5. Each circuit breaker shall be furnished with a manual trip push button
which mechanically trips the breaker. The manual trip push button and its
associated breaker trip linkage shall have no common components with
the electrical trip mechanism, except the final breaker release device. The
pushbutton shall be operable from the outside without having to open the
door.
9. In the event the circuit breaker has been tripped by a protective relay,
means shall be provided to prevent reclosing (antipumping).
11. Operation counter for recording the number of switching operations shall
be incorporated.
13. Facilities hall be provided for lifting/lowering circuit breakers when located
above the floor level.
Grounding Switch when used, shall comply with the following requirements:
Grounding truck when used, shall comply with the following requirements:
2. Minimum accuracy class and rated output on full winding taps shall be
provided as follows:
6. The BIL of the voltage transformers shall be the same as that of the
switchgear.
J. Circuit Breaker control and monitoring systems and equipment shall be provided
and mounted on or within the switchgear compartments designated for this
purpose. Control and monitoring systems shall follow philosophies
established by existing "like" systems. In addition, these systems and
equipment shall comply with contract drawings and the following requirements as
a minimum:
1. Control voltage shall be 125 Vdc. Closing coil shall operate in the range of
100 to 140 V. Tripping coil shall operate in the range of 70-140 V. A two-
pole circuit breaker shall be furnished for each bus of switchgear
assembly for incoming 125 Vdc control power supplies. The two-pole
breaker shall be installed preferably in the incoming breaker cubicle or
auxiliary cubicle of the switchgear assembly.
3. Circuit breakers shall be provided with a door mounted control switch, two-
position “CLOSE-TRIP” spring-return to center. This control shall be active
when circuit breaker is in operating position and in LOCAL control only.
This function can be combined with the appropriate interlocks, with the
function specified above.
5. Door mounted red "CLOSED" and green "OPEN" lights or Light Emitting
Diodes (LED’s) shall be provided to indicate the breaker state in both the
test and operating positions.
K. Bus transfer for 15kV and 35kV switchgear with two redundant incomers and a
tie: Bus transfer system shall follow philosophies established by existing
"like" systems. All auxiliary transfer relays, inter-compartment wiring, and
interlocks shall be furnished as required. These systems and equipment shall
comply with contract drawings and with the following requirements as a
minimum:
1. Normal condition: Incoming breakers are closed (NC) and tie breaker is
open (NO).
2. Manual transfer:
4. Automatic transfer:
L. Metering systems and equipment shall be provided and mounted on or within the
switchgear compartments designated for this purpose. Metering systems shall
follow philosophies established by existing "like" systems. In addition, these
systems and equipment shall comply with contract drawings and the following
requirements:
g. Test switches for current and voltage circuits such that each
metering device can be isolated or removed without de-energizing
the metering circuit.
L. Relay and metering systems and equipment shall be provided and mounted on
or within the switchgear compartments designated for this purpose. Provide
complete protection and metering schemes. Relay and metering systems shall
follow philosophies, function, configuration, features and quality of components of
similar “like” schemes used in utility and industrial application and established
by existing “like” systems. In addition, these systems and equipment shall
comply with contract drawings and the following requirements as a minimum:
i. All multifunction relays shall have circuit breaker close and trip coil
circuit supervision with output contact.
(5) Peak current demand for each phase and ground since last
reset
d. All protective relays shall have built-in LEDs for trip and status
indication.
3. Other requirements for relays and protection circuits include the following:
b. The use of auxiliary relays for tripping, interlock, local control and
for remote control and alarm interfaces shall be minimized
d. Each breaker trip coil, lockout relay coil and auxiliary tripping relay
coil shall be monitored.
e. Test switch assemblies shall be provided and each trip circuit from
each lockout relay shall run through a test switch.
4. It shall be possible for protective relays to trip the circuit breaker when it is
in either the TEST or in the OPERATING position.
5. When test equipment other than typical (such as a Multi Amp relay test
set) is required to test protection relays, provide one set of the special test
equipment as “special tools for switchgear”.
a. All panel, cabinet and rack mounted devices such as relays, control
switches, instruments, meters, circuit breakers and fuses shall be
suitably identified with nameplates showing device name and
device number. Nameplates for fuses shall also identify the current
rating. Each panel, cabinet and rack shall also be identified with a
nameplate. Flush mounted devices shall have identical nameplates
on both the interior and exterior surfaces. Control components
mounted within the assembly, such as fuse blocks, relays, push
buttons, switches, etc., shall be suitably marked for identification
corresponding to appropriate designations on manufacturers wiring
diagram. Engravings and markings shall be in English. All warning,
safety and instruction for operation nameplates shall be both in
Arabic and English.
N. INTERFACES
2. Interfaces shall be provided for all outgoing power and control cable
circuits.
A. Ratings: The most significant ratings of bus duct in accordance with IEEE Std
C37.23 shall be as follows:
2 The temperature rise at rated load at any point on the bus shall not
exceed 500C in an ambient temperature of 550C.
3. The temperature rise at rated load at any point on the bus duct enclosure
shall not exceed 250C when accessible and 550C when not accessible in
an ambient temperature of 550C.
1. The bus duct shall be designed and manufactured in accordance with the
applicable IEEE Std C37.23 and IEC standards for all components and
related auxiliary equipment.
2. The bus duct shall match the switchgear and transformer without requiring
field modifications or custom interfaces. To ensure this match, the bus
duct shall preferably be the product of the switchgear manufacturer.
3. Bus duct installed outdoor shall be totally enclosed and gasketed, dust-
tight,
4. Outdoor sections of bus duct under direct sun rays shall be provided with
sunshades.
5. Bus duct and its supports installed outdoor in the open shall withstand a
140km/hour wind blowing in the most unfavorable direction.
1. Contractor shall determine the need for space heaters. Heaters shall be
low temperature (surface temperature not to exceed 200 0C)
thermostatically controlled. The required wattage shall be determined
based on bus duct volume and surface area. The voltage rating of heating
elements shall be approximately twice the supply voltage. Heaters and
associated circuits shall be rated for continuous duty. A maximum load of
15 A at 127 V shall be placed on a single heater circuit.
2. A ground bus shall run along the phase buses, inside, throughout the
length of the bus duct. The ground bus shall be capable of carrying the
rated short-circuit current of the bus.
3. Provision shall be made for ground bus connection to station ground grid
preferably at one end. More connection points are acceptable when
induced current loops have been avoided.
4. Fire stop/smoke barriers shall be provided at all floor and fire wall
penetrations.
1. Bus duct housing shall be galvanized carbon steel or aluminum alloy with
removable bolted joint covers. Enclosure shall be corrosion resistant with
stainless steel hardware. Gasket material shall be suitable for an ambient
temperature of 550C plus bus losses at continuous rating.
2. Openings shall be provided for inspecting the busbar joints and support
insulators throughout the length of the bus duct.
4. Filtered breathers shall be provided for air circulation while preventing dust
entry. Filters shall be removable for cleaning and reusable.
2. The bus shall be full size and continuous throughout. Tapered bus is not
acceptable.
3. All bus bar connection surfaces shall be silver plated or tin plated.
3. Warning and caution signs in English and Arabic shall be provided on the
body of the bus duct conspicuously placed at several locations.
G. INTERFACES
2. Interfaces shall be provided for all power and control cable circuits.
1. All steel external surfaces of switchgear and bus duct and also internal
surfaces when not galvanized shall be painted. At least one coat of
corrosion resisting paint shall be applied. The coating shall have corrosion
resistance to salt spray in accordance with IEEE Std C37.20.2 and IEEE
Std C37.23.
2. The finish color on internal surfaces when painted shall preferably be white.
The exterior finish color shall be light gray Munsell notation 8.3G6.10/0.54
thermosetting, polyester powder paint applied electrostatically to pre-
cleaned and phosphatized steel parts.
4. Aluminum and stainless steel alloy sheet metal and parts when inherently
resistant to corrosion in marine environment, need not be painted.
A. General:
3. In the event of failure of any equipment to meet the test requirements, the
Contractor shall replace the defective items at his expense.
4. The Royal Commission reserves the right to witness all tests. Contractor
shall provide written notification to the Royal Commission at least eight (8)
weeks in advance of test date. The notice shall include an outline of the
procedures to be used in performance of tests. This outline shall include a
5. The Contractor shall maintain a file of all test reports which shall be fully
auditable and accessible to the Royal Commission.
B. Type Tests:
2. The Royal Commission may at its own discretion waive the type tests,
provided the Contractor has performed these tests on identical equipment
which are substantiated by available certificates. These certified test data
may be submitted in lieu of performing the type tests.
C. Routine Tests:
C. Test Reports:
1. The Contractor shall submit six (6) copies of certified reports of all type,
routine and special tests performed, including those specified herein. The
report for each test shall include the date of performance, the name of the
company and the signature of person in charge of the test. Approval is
required prior to shipment of switchgear and bus duct.
PART 3 – EXECUTION
A. The switchgear and its relaying, metering and control systems and equipment
shall be installed per the approved design and shop drawings. All work shall be
performed by qualified field personnel.
B. The installation of new switchgear with protection and control systems shall
include work on related systems whether existing or new to provide satisfactory
interfaces and overall, integrated systems.
F. Contractor shall be responsible for installation of all AC and DC supplies and for
grounding the equipment to the substation ground grid. Existing spare branch
circuit breakers, where available, may be used for AC and DC station
supply sources.
B. At least eight (8) weeks prior to testing, test plans and procedures shall be
prepared by the Contractor and submitted to Royal Commission for approval.
Test procedures shall contain descriptions of test equipment, descriptions of the
tests, connection diagrams, test sheets, calculations, reference drawings and
minimum/maximum test and performance values conforming to applicable
standards. Tests shall be witnessed by the Royal Commission representative.
C. Verification and tests shall include but not be limited to the following:
9. Functional tests ensuring correct trip and close operation of relays, circuit
breakers and local and remote alarm indication.
11. Setting and testing all protective devices (relays) for minimum pickup,
timing and special requirements per relay coordination study data sheets.
Test results shall be submitted as contract documents.
13. After energization and with load currents, perform phase angle checks at
each relay using the voltage and current phase or quantities at the relays
to verify correct connections. For directional over current relays only, use
metering potential for reference.
D. Upon completion of all testing the Contractor shall submit to the Royal
Commission six (6) copies of a certified report attesting that each test was
performed in accordance with the approved test procedures. The report for each
test shall include the date of performance and the name of the person in charge
of the test.
E. All factory and field test reports shall be included into the Operation and
Maintenance manuals.