Clean Energy Council Install and Supervise Guidelines For Accredited Installers
Clean Energy Council Install and Supervise Guidelines For Accredited Installers
Clean Energy Council Install and Supervise Guidelines For Accredited Installers
COUNCIL INSTALL
AND SUPERVISE
GUIDELINES FOR
ACCREDITED
INSTALLERS
ISSUE 11, 1 MAY 2017
TABLE OF CONTENTS
1 GENERAL 5
2 DEFINITIONS 5
4 LICENSING 6
5 DOCUMENTATION 7
6.2 Limits apply to the number of installations an accredited person shall sign-off per day 8
7 PV ARRAY INSTALLATION 9
7.1 General 9
7.7 Earthing of array frames for a PV array with maximum voltage greater than ELV (including AC modules and
micro inverter systems) 12
7.10 PV array DC isolator at array (Not applicable for micro inverter and AC modules systems) 14
8 INVERTER INSTALLATION 21
8.2 PV array DC isolator near inverter (Not applicable for micro inverter AC and modules systems) 22
9 METERING 28
10 SIGNAGE 28
11 COMMISSIONING 29
12.1 General 29
13 EXAMPLES OF SIGNAGE 34
While all care has been taken to ensure these guidelines are free from omission and error, no responsibility can be
taken for the use of this information in the installation of any grid-connected power system.
The performance of a reliable installation that fulfils customer expectations requires both careful design and correct
installation practice. Compliance with relevant state health and safety regulations is also necessary.
NOTE: These guidelines alone do not constitute a fully definitive set of rules and are to be read in conjunction with
all relevant Australian standards. Where these guidelines have additional requirements above that stated in the
Australian standards then these guidelines shall be followed.
______________________________________________________________________
2 DEFINITIONS
This document uses the same terminology as outlined in AS/NZS 5033. Two important definitions are:
2.1.1 Where the word “shall” is used, this indicates that a statement is mandatory
2.1.2 Where the word “should” is used, this indicates that a statement is a recommendation
______________________________________________________________________
3 STANDARDS FOR INSTALLATION
Accredited installers shall comply with the following standards where applicable:
______________________________________________________________________
4 LICENSING
4.1 Extra Low Voltage (ELV)
4.1.1 All extra low voltage wiring should be performed by a 'competent' person, which is defined by the
Australian Standard AS/NZS 4509.1 stand-alone power systems as: "a person who has acquired through
training, qualifications, experience or a combination of these, knowledge and skill enabling that person to
correctly perform the task required."
4.2.1 All low voltage work: >120V DC or >50V AC shall be performed by a licensed electrician.
4.2.2 A licensed electrician is required to be responsible for the safety of the system wiring prior to connection
of the system to the grid.
4.2.3 If the system contains ELV wiring installed by a non-licensed person, then a minimum level of inspection
by the electrician prior to closing the PV array isolators would include:
An open circuit voltage test on each PV string and on the total array.
A visual inspection of an open PV junction box (randomly selected) and the master array junction
box.
______________________________________________________________________
6 RESPONSIBILITIES OF ACCREDITED PERSON
6.1 An accredited person shall sign-off on systems where they have;
6.2.1 Where an accredited person is installing or supervising complete installations only, they shall not sign off
on more than three (3) installations per day.
6.2.2 Where an accredited person is installing or supervising complete installations and upgrades /repairs (the
installation or replacement of panels only) in the same day, they shall not sign off more than two (2)
complete installations and more than three (3) upgrades on the same day
6.2.3 Where an accredited person is installing or supervising complete installations and upgrades /repairs (the
installation or replacement of panels only) in the same day, they shall not sign off more than one (1)
complete installation and more than four (4) upgrades on the same day
6.2.4 Where an accredited person is installing or supervising upgrades and/or repairs to existing systems
involving the installation or replacement of panels only, the installer or supervisor shall not sign off on
more than five (5) system upgrades / repairs per day.
Note: The reasoning behind these requirements is to ensure integrity is maintained in the solar industry
and that all systems are installed in a safe manner and meet all the guidelines and standards. Data from
previous audit regimes identified that there was a direct correlation between systems deemed to require
rectification (sub-standard installation) and the number of systems signed off in one day.
If a project involves multiple systems at one location, where the systems are installed in stages, the accredited
person installing or supervising these installations may request a formal exemption from clause 6.2 to sign-off up
to 10 systems per day.
Example: multiple systems installed on an apartment block, or at a retirement village, where the cables roughed in
on one date; the inverter, mounting frame and panels installed on another date; and the final connection and
commissioning on an another date.
6.3.1 An installer shall contact the CEC and request an exemption from clause 6.2 prior to the installation
starting. Exemptions to clause 6.2 WILL NOT be granted after a project has been completed.
6.3.2 The installer must provide details of the project and the installation schedule for assessment by the CEC.
Exemptions may be granted by the CEC to installers who can demonstrate that the schedule of
installation will ensure all systems are installed in a safe manner and meet all guidelines and standards.
6.3.3 Once the assessment is complete, the CEC will respond to the installer with a letter detailing the
assessment finding, and exemption from clause 6.2.1 if granted. This letter shall be the only acceptable
evidence of an exemption from clause 6.2.1 for the purposes of STC creation.
Note: An administration fee may apply for all exemption request assessments in the future.
6.4.1 When installing a grid connect battery backup system the installation shall be performed by a person with
CEC grid connected install accreditation with battery backup endorsement or a person(s) with CEC grid
connected install accreditation and CEC stand-alone install accreditation
Note: The installation of battery storage has additional safety risks associated with their installation. These
include:
• Electric shock hazard
• Energy hazard
• Chemical hazard
7.1.1 PV arrays for installation on domestic dwellings shall not have PV array maximum voltages greater than
600 V.
7.1.2 The following types of buildings are considered “domestic dwellings”, using the building classifications in
the National Construction Code:
• Class 1 (e.g. a free-standing house, terrace house, town house, villa unit)
• Class 2 (e.g. an apartment block.)
• Class 3 (e.g. a hotel/motel, boarding house or guest house)
• Class 10a (e.g. a private garage, carport, or shed)
7.1.3 Modules that are electrically in the same string shall all be installed at the same tilt angle and orientation
(unless using DC conditioning units).
7.1.4 Unless specified by the CEC system designer, the installer shall not install two parallel strings, connected
to the same MPPT input at the inverter, installed on different orientations (e.g. east and west).
Note: Some manufacturers will not guarantee inverter performance where parallel strings are installed on
different orientations. The system designer shall confirm that this arrangement is acceptable with the
inverter manufacturer.
A minimum tilt of 10° is recommended to take advantage of self-cleaning during rain events. Where
modules are installed at a tilt angle less than 10°, the customer shall be advised about the need for more
frequent cleaning of the modules, and this should be included in the recommended maintenance
schedule.
7.2.1 All array supports, brackets, screws and other metal parts shall be of suitable low-corrosion materials
suitable for the lifetime and duty of the system, that do not increase their rates of corrosion when mounted
together in an array, and when mounted on the surface of the underlying structure.
This may include techniques to minimise corrosion rates appropriate to the local environment, including
but not restricted to methods such as: non-reactive separators between metal surfaces and under screw
and bolt heads; and selection of materials with appropriate type and thickness of anti-corrosive coating.
7.2.2 Refer to the manufacturer’s guidelines to ensure that the materials introduced are compatible with the
roofing.
7.2.3 Any roof penetrations shall be suitably sealed and waterproofed for the expected life of the system. (Refer
to roofing manufacturer’s guidelines.). See section 7.11.6 for more details.
If this is not possible then this shall be detailed in the system’s Maintenance Timetable.
7.2.4 It is important to allow sufficient clearance to facilitate self-cleaning of the roof to prevent the build-up of
leaves and other debris (Refer to roofing manufacturers guidelines.)
7.2.5 If fauna (such as birds, vermin, etc) are a problem in the vicinity of the installation then consideration
should be given to how to prevent them gaining access under the array.
7.2.6 Tiles shall sit flat after the installation of tile mounting brackets to ensure the tiles maintain their original
ingress protection. There may be a requirement to grind some of the underside of the tile to enable it to sit
7.2.7 Where monocrystalline or polycrystalline modules are used, at least 50mm clearance should be allowed
below the array for cooling by natural ventilation. Insufficient ventilation will result in high operating
temperatures for the modules.
7.2.8 The installer shall follow the array frame supplier/manufacturer’s recommendations when mounting the
array to the roof support structure, to ensure that the array structure still meets AS1170.2 certification.
7.2.9 Where timber is used it shall be suitable for long-term external use and fixed so that trapped moisture
cannot cause corrosion of the roof and/or rotting of the timber. The expected replacement time should be
stated in the system documentation.
NOTE: Attachment 2 provides some guidance for securing PV arrays on roof structures.
7.3.1 The array mounting frame shall be wind rated in accordance with AS 1170.2 part 2: Wind Loads.
7.3.2 Installation of footings, posts and/or in-ground fasteners shall follow the manufacturer’s instructions and
installation manual.
7.4.1 The installation of modules that are being used as building material e.g. tiles, building walls, sun-screens
should only be installed by a person qualified to install that particular type of building element.
7.5.1 Installers shall obtain from their frame supplier a copy of the engineering certificate stating that the array
frame is certified to AS1170.2 for their location.
7.5.2 Installers shall obtain information on how the frame is to be mounted on the roof to maintain this
certification.
7.5.3 The array frame shall be installed to the manufacturer’s instructions to ensure that the array structure
meets AS1170.2 certification. The installer shall consider the following:
spacing between fixings for specific wind load regions
area of roof that is applicable for panels to be installed (some manufacturers only allow the
frames to be installed in a specific internal zone of the roof)
type, length and gauge of screws to be used.
number of screws required per fixing
size of batten/purlin required for fixing.
7.5.4 The installation checklist includes a clause stating that the system has been installed in accordance with
the recommendations of the supplier/manufacturer.
Copies of both these documents shall be included in the manual provided to the customer.
(NOTE: If installers are manufacturing their own frames, then they shall provide the certificates and include in the
manual.)
7.6.1 Solar modules should be attached to the array structure either using the mounting holes provided by the
manufacturer or via clamps.
7.6.2 Where modules are installed in such way that the junction box is to the side or at the bottom, care must
be taken to ensure this is permitted by the manufacturer.
7.6.3 When using clamps solar panel manufacturer’s installation instructions shall be followed. The installer
shall consider the following:
amount of overhang allowed from clamp to end of module
size of clamp required.
7.7 Earthing of array frames for a PV array with maximum voltage greater than ELV (including
AC modules and micro inverter systems)
7.7.1 All exposed metal PV module frames and the array mounting frames shall be earthed where the PV array
has a PV array maximum voltage (Voc adjusted for lowest temperature) of greater than ELV or a.c.
modules or micro inverters with LV outputs are installed.
7.7.2 Minimum earth cable size of 4mm shall be used and may be larger. See AS/NZS 5033 clause 4.4.2.1 for
requirements.
7.7.3 Earth connection shall be:
by a purpose-made fitting providing earthing or bonding connections for dissimilar metals and
fitted to the manufacturer’s instructions, or
by purpose-made washers with serrations or teeth for the connection between the PV module
and mounting frame fitted to the manufacturer’s instructions, and
be arranged so that the removal of a single module earth connection will not affect the continuity
of the earthing or bonding connections to any other module.
7.7.4 Self-tapping screws shall not be used.
7.7.5 Ensure that rail joiners (splice) provide earth continuity.
Some rail manufacturers state that the use of the rail joiner (splice) provides earth continuity between
7.7.8 The earthing conductor from the PV array can connect to inverter’s main earth conductor in the A.C
output cable provided the following conditions are met:
7.7.9 Installation is not subject to lightning
7.7.10 Inverter A.C earth is of an appropriate size:
• Isolated inverter (transformer based) and floating array: inverter A.C earth size is appropriate
• Non Isolated inverter (transformerless): earth conductor shall be sized according to AS/NZS
3000 using the size of the PV array cabling as the active conductor.
• Functionally earthed arrays: see AS/NZS 5033 clause 4.4.2.2 for requirement.
Note: See AS/NZS 5033 clause 4.4.2.2 for more detailed information regarding this
requirement
7.7.11 AC modules / Micro Inverters additional requirements (not subject to lightning)
The earthing of the PV module and mounting frame can be achieved using the micro inverter
earth connection (see AS/NZS 5033 clause 4.4.2.2).
7.8.1 The electrical installation of the array shall be in accordance with AS/NZS 5033.
7.8.2 All LV wiring shall be undertaken by a licensed electrician.
7.8.3 Plastic cable ties are not to be used as the primary means of support.
7.8.4 The PV array wiring shall comply with the wiring requirements of AS/NZS 3000.
7.8.5 Cables shall be protected from mechanical damage.
7.8.6 The installer shall ensure that all connectors used are waterproof and connected securely to avoid the
possibility of a loose connection.
7.8.7 Only connectors which are the same type/model from the same manufacturer are allowed to be married at
a connection point.
7.8.8 Cables shall not lay on roofs or floors without an enclosure or conduit.
7.8.9 Cable size to be determined by AS/NZS 5033 Clause 4.3.6.1.
7.8.10 For LV PV arrays, the CEC recommend that under maximum load conditions, the voltage drop from the
most remote module in the array to the input of the inverter should not exceed 3% of the Vmp voltage (at
STC).
7.8.11 In particular, refer to the clause in AS/NZS 3000 that refers to fauna which states: Where the presence of
fauna is expected to constitute a hazard, either the wiring system shall be selected accordingly, or special
protective measures shall be adopted.
7.8.12 All conduits exposed to direct sunlight shall be suitably UV rated.
Faults due to short circuits in modules, junction boxes, combiner boxes, module wiring or earth faults in array
wiring can result in overcurrent within a PV array.
7.9.1 Overcurrent protection shall be provided where it is required by manufacturers of PV modules. The key
criteria for this the module’s “Maximum Series Fuse Rating”, sometimes listed as “Maximum Reverse
Current”.
7.9.2 AS/NZS 5033 Clause 3.3.4 defines the formula to calculate if string protection is required. Refer to
Attachment 3 for more details of this method.
7.9.3 AS/NZS 5033 Clause 3.3.5.1 defines the rating of the fuse protection.
7.9.4 In LV arrays, overcurrent protective devices, where required, shall be placed in all current carrying
conductors not directly connected to earth.
7.9.5 In ELV arrays, overcurrent protective devices, where required for string and sub-array cables, shall be
placed in either the positive or negative conductor (the number of current carrying conductors minus one).
7.10 PV array DC isolator at array (Not applicable for micro inverter and AC modules systems)
The positive and negative terminal of a solar array or sub-array represents a hazard with potentially high risk when
the output voltage is 120V DC or above. See Attachment 1 for more details.
Note the following requirements for the PV array isolator at array:
7.10.1 AS/NZS 5033:2014 Clause 4.4.1.5 makes it mandatory for an isolator to be installed within 3 meters of
the array and visible from both locations for LV systems. This is to enable safe disconnection of the array
and isolation of the PV array cable.
Isolators shall not be installed mid string
E.g. Where one electrical string is split over different roof faces (all faces are at the same
orientation) one isolator is required at the point where the PV panel wiring transitions from the
PV array to the fixed wiring to the inverter at the array.
The roof mounted isolator should be mounted such that the switch is in a sideways position.
(NOTE: Ensure that the switch does not shade the array.)
Note: If the conduit gland requires the conduit to be glued to maintain the IP rating the conduit shall be
glued
7.10.23 Where the entry to an isolator is a cable gland the gland shall:
Be rated at least IP 55 (CEC recommend IP 66).
Where multiple cables go through one gland a multi hole cable gland shall be used.
7.10.24 There shall be no open ends of conduit. If a cable is required to exit from conduit, a cable gland (as
specified above) shall be installed on the end of the conduit to ensure the IP rating is maintained.
7.10.25 A secondary shield is required to shelter the DC isolator from direct exposure to rain and sun.
Where the panels are installed parallel to the roof, a shroud shall be installed over the
isolator. PV DC Isolator(s) shall not be installed under a solar module when the panels are
parallel to the roof.
Where the panels are on a tilt frame the isolator shall be installed in a location where it is
sheltered by the panels.
Note: Installation of a PV DC Isolator under a solar module, of a tilt array, may be considered
as a “secondary shield.” However, this method must also comply with relevant local
requirements (such as regulatory bodies, etc)
7.11.1 PV array cables within a domestic building that are installed in ceiling spaces, wall cavities, under floors
shall be enclosed in metal or heavy-duty (HD) insulating conduit. When installed in a building, other than
those listed previously, the PV array cable shall be in medium duty conduit as a minimum.
Note: the intention of this is to provide additional protection for cables in locations where they may not be
visible, e.g. a person drilling a hole into a wall cavity will hit the conduit first before making contact with the
cables. Where cables are installed inside buildings but clearly visible (e.g. surface mounted conduit on
the inside a of garage wall), medium-duty (MD) conduit is acceptable as an alternative.
Note: For non-domestic installations, see AS/NZS 5033 clause 4.3.6.3.2 for requirements.
7.11.3 AS/NZS5033:2014 does not allow for any medium duty (MD) conduit to be installed in the ceiling space.
Ensure that the transition from MD to HD occurs at the point of penetration of the roof.
Alternatively, UV rated HD corrugated conduit could be used where the cable enters the ceiling space.
7.11.4 Double insulation of each conductor shall be maintained within wiring enclosures (e.g. conduit).
7.11.5 The wiring enclosure shall be labelled ‘SOLAR’ at not more than 2m intervals.
7.11.6 Where the PV array cable and conduit passes through a tile or steel roof an appropriate collar flashing
shall be installed (e.g. dectite).
Note: Grinding a tile and passing the conduit between tiles is not an acceptable method as it is in breach of
AS/NZS 3000 (clause 3.9.4.3.1)
Conduit passing through a hole in a steel roof and then sealed with silicon is in breach of Standards Australia
Handbook 39-1997 (clause 8.6)
8.1.2 The inverter heat sink shall be clear of any obstacles to facilitate cooling of the inverter.
8.1.3 Cables connected to the inverter shall be mechanically secured in such a manner that they cannot be
inadvertently unplugged from the inverter. This can be achieved by:
installing the inverter in an external enclosure (with cables suitably supported)
the use of an inverter which has the cable connection area of inverter covered by a removable
enclosure/cover which protects the supported cables so that there are no exposed,
unsupported cable loops
the use of conduit and secure wall fixings.
Note: Where the inverter requires DC connectors to be used, a maximum allowable distance of
no more than 300mm of unprotected DC cable shall be permitted between connectors and
conduit, provided the location is not subject to mechanical damage.
Where the inverter is exposed to the weather there shall be no open ends of conduit. If a cable
is required to exit from a conduit, an appropriate cable gland shall be installed on the end of the
conduit to ensure the IP rating is maintained (see section 7.10.24.
8.1.4 The installer shall ensure that the inverter is configured for Australia, and that the AS/NZS4777.2
parameters are loaded.
Note: one method to ensure the 4777.2 parameters are installed is by monitoring the inverter power out
when the inverter is turned on. The inverter should not go straight to full power. It is required to ramp up
from 0%-100% over a 6 minute period.
8.1.5 The installer shall ensure that the grid parameters of the inverter are set to the local distributor’s
requirements.
8.2.1 Where the inverter in LV systems is not in sight of the array or more than 3m from the array, PV array
switch-disconnector/s shall also be installed adjacent to the inverter.
Note: Generally the PV array DC isolator at the inverter will always be required for roof top mounted
systems.
8.2.2 All PV array switch-disconnectors shall be readily available (see section 7.10.10 for details on readily
available).
8.2.3 For inverters with an integrated switch-disconnector: a separate switch-disconnector is not required at the
inverter if the switch-disconnector is mechanically interlocked with a replaceable module of the inverter
and allows the module to be removed from the section containing the switch-disconnector without risk of
electrical hazards.
8.2.4 Where multiple disconnection devices are required to isolate power conversion equipment, they shall be
grouped so that they all operate simultaneously, or they shall all be grouped in a common location and
have warning signs indicating the need to isolate multiple supplies to isolate the equipment (see section
12 for examples of signs).
Where there are more than one isolator, they shall be individually labelled e.g. “PV Array DC
isolator inverter 1 MPPT A”
The shutdown procedure shall align with the labelling of multiple isolators – see the example
below.
Note: This will enable the cable to either string to be safely de-energised, without the need to turn off both
rooftop isolators.
8.2.6 Where the inverter and isolator are exposed to the weather the isolator shall have an IP rating of at least
IP 55, (Note: the CEC recommend using isolators rated to IP66).
8.2.7 Where an isolator is exposed to the weather, the CEC recommend that there be no top entries into the
isolator, and drip loops are utilised at the bottom of the isolator to minimise water ingress.
The purpose of the AC isolator is to de-energise the inverter for maintenance or fault rectification.
8.4.1 A labelled, lockable, isolating switch (inverter a.c. isolator) shall be installed at the point of transition from
micro inverter interconnect cable to fixed wiring. The purpose of the a.c. isolator is to de-energise the a.c.
from the micro inverter for maintenance or fault rectification
8.4.2 The isolator shall be installed adjacent to the inverter or inverter group. This isolator may be a single
isolator and can be used to isolate multiple adjacent inverters.
8.4.3 Where micro inverters are not installed adjacent to each other, additional isolators shall be installed.
8.4.4 Isolator enclosures shall be IP55 rated (CEC recommend IP66)
8.4.5 All entry points (conduit and cable glands) to the isolator should be on the lower end of the enclosure -
either underneath or facing down the roof.
8.4.6 A secondary shield is recommended to shelter the Inverter AC isolator from direct exposure to rain and
sun.
TABLE 1
MAXIMUM CABLE LENGTHS FOR 1% VOLTAGE RISE
Inverter Configuration Single Three Phase Three Phase
Phase
Inverter Rating (kVA) 5 5 10
Conductor Current (A) 21.7 7.2 14.5
Cable Conductor Size (mm2) Conductor Maximum Maximum Maximum
Material Route length Route length Route length
(m) (m) (m)
6 Cu 14 85 42
10 Cu 24 143 71
16 Cu 38 227 113
25 Cu 59 357 179
8.5.2 The inverter shall be connected by fixed wiring to a dedicated circuit on a switchboard.
8.5.3 AC cables between the inverter and any switchboard and all the cables between any distribution boards
and a main switchboard which carry current from the inverter shall be rated for at least the full output
current of the inverter energy system.
8.5.4 All cabling shall be sized in accordance with AS/NZS 3000 and AS/NZS 3008.
WARNING: PV array DC isolators do not de-energise the PV array and array cabling. (see below
for example)
8.7.3 Micro inverter and AC module systems (shall be installed at the switchboard to which the inverter is
connected)
An example shutdown procedure would be:
• Turn off the main switch solar supply at the AC switchboard
As of 11 July 2015 AS/NZS 5033 requires the installation of an earth fault alarm indication
______________________________________________________________________
12 INSTALLATION AND COMMISSIONING
12.1 General
WARNING: Where short circuit current measurements are required, follow AS/NZS 5033 Appendix D for the steps
that shall be undertaken to measure the short circuit current safely.
NOTE: Some projects require that short circuit currents are recorded as part of the contractual commissioning;
otherwise a record of the actual operating current of each string is sufficient. This could be done by using the
meter on the inverter or by using a clamp meter when the system is operational.
WARNING: PV array dc circuits are live during daylight and, unlike a conventional ac circuit, cannot be isolated
before performing this test.
Follow AS/NZS 5033 Appendix D4 for the steps that shall be undertaken to measure the insulation resistance
safely.
INSTALLATION DETAILS
Address of installation:
PV module manufacturer
and model number:
Number of modules in Number of strings in parallel
series in a string: in PV array:
Inverter manufacturer and
model number:
Number of inverters: Number of MPPTs:
PV ARRAY
PV array tilt ……………………° PV array orientation ……………………°
Array frame is certified to AS1170.2 for Array frame is installed to manufacturer’s
installation location instructions
No galvanically dissimilar metals are in contact Roof penetrations are suitably sealed and
with the array frames or supports weatherproofed
PV wiring losses are less than 3%at the Where PV array comprises multiple strings- string
maximum current output of the array protection has been provided
Wiring is protected from mechanical damage Weatherproof PV array isolator mounted adjacent to
and is appropriately supported the array
(Brand /
Model:…………………………..Rating:……………….
………………….Vdc,…………….Adc)
LV DC and AC INSTALLATION
All low voltage wiring has been installed by a All wiring has been tested and approved by qualified
licensed electrical tradesperson electrical tradesperson
SYSTEM CHECK
WARNING:
• IF A STRING IS REVERSED AND CONNECTED TO OTHERS, FIRE MAY RESULT.
• IF POLARITY IS REVERSED AT THE INVERTER DAMAGE MAY OCCUR TO THE INVERTER.
String 1 V A A
String 2 V A A
String 3 V A A
String 4 V A A
Sub-arrays where required V A A
PV array at PV array switch-disconnector V A A
Irradiance at time of recording the current W/m2 W/m2
INSULATION RESISTANCE MEASUREMENTS (see table 12.3.1 for minimum values of insulation resistance)
Array positive to earth MΩ
INSTALLER INFORMATION
CEC Accredited installer’s
name:
CEC Accreditation number:
I verify that the above system has been installed to all relevant standards
Signed: Date:
Signed: Date:
INSTALLATION DETAILS
Address of installation:
Number of inverters:
PV ARRAY
PV array 1 tilt……………………° PV array 1 orientation..…° Number of panels……
PV array 2 tilt……………………° PV array 2 orientation..…° Number of panels……
PV array 3 tilt……………………° PV array 3 orientation..…° Number of panels……
PV array 4 tilt……………………° PV array 4 orientation..…° Number of panels……
Array frame is certified to AS1170.2 for installation Array frame is installed to manufacturer’s
location instructions
Wiring is protected from mechanical damage and is No galvanically dissimilar metals are in contact with
appropriately supported the array frames or supports
Roof penetrations are suitably sealed and
weatherproofed
LV DC and AC INSTALLATION
All low voltage wiring has been installed by a licensed All wiring has been tested and approved by
electrical tradesperson qualified electrical tradesperson
SYSTEM CHECK (may need to be verified through the system communications portal)
WARNING:
• IF POLARITY IS REVERSED AT THE INVERTER DAMAGE MAY OCCUR TO THE INVERTER.
String Inverters:
SIGNAGE (AS 4777)
On switchboard to which inverter is directly connected
Micro Inverters
On switchboard to which inverter is directly connected
Shutdown procedure is permanently fixed Any other signage as required by the local electricity distributor
at inverter and/or on main switchboard
A dangerous situation can occur if the person installing the system comes into contact with the positive and
negative outputs of the solar array or sub-array when the output voltage is 120V DC or above.
Most grid-connected systems use approved solar modules which are connected using double insulated leads with
polarised shrouded plug and socket connections.
A dangerous situation is only likely to occur at:
the PV array isolator before the inverter
the roof-top isolator
the sub-array and array junction boxes (if used).
DISCONNECT
To prevent the possibility of an installer coming in contact with live wires, it is recommended practice that one of
the interconnect cables in each string (as shown above) is left disconnected until all the wiring is completed
between the array and the inverter.
Only after all isolators and other hard wired connections are completed, should the interconnection in the middle of
the array be connected.
______________________________________________________________________
15 ATTACHMENT 2: PV ARRAY ROOF MOUNTING
Image: Sunlock