Piping Built in Clean Flowchart
Piping Built in Clean Flowchart
Piping Built in Clean Flowchart
0
PIPING Clean Built Procedure Flow Chart 3-Aug-19
H.Kobayashi
Scope of Work
Piping Construction Work Flow Action by Form Sheet Construction COMM (Under Coordination of
Warehouse QC
(Subconractor) Cleanliness Coordinator)
Shipping -
Delivery at site
Receiving Inspection Warehouse
Prefabricated Spool / Loose Pipe
Warehouse shall perform random check of internal cleanliness during receiving inspection
Other piping Component
Warehouse shall perform 100% internal cleanliness during receiving inspection. Result of
Inspection, and Corrective action shall be controlled with OSD Report.
OSD Report /
Disposition Report issue For Info. For Info.
Plan
Site Storage
Storage at Laydown
Warehouse Warehouse shall control spool/component preservation during installation
yard
Preservation and Cleanliness Patrol shall be performed periodically by SUSU and Preservation
team (Commissioning)
Issue to Subcontractor Const. Const.(Subcon) shall confirm cleanliness of internal piping before receiving materials
Installation Const. Const.(Subcon) shall control piping preservation and cleanliness during installation Preservation
and Cleanliness Patrol shall be performed periodically by SUSU and Preservation team
Flushing/Blowing
Flushing/Blowing if debris observed
Pressure Test Borescope Const.(Subcon) shall control dewatering condition of each piping system. i.e) test package wise.
Review of Cleanliness
Const.
Check Sheet
Commissioning Cleanliness Coordinator shall review and evaluate the summary of Cleanliness
Draining/Drying TEP-ITR-PIP-114 Check Sheet.
Commissioning Cleanliness Coordinator shall refect the result of above mentioned evaluation to
Critical
TEP-ITR-PIP-126
Borescope Inspection Const. Please refer to : TEP-930-SPE-QA-BP4-0021 QCP PIPING PREFABRICATION AND ERECTION
Reinstatement Const. Air Blow / Water flushing can be ommitted, if result of borescope check is satisfactory.
As per TEP-900-PRC-OP-BP4-0007 General Cleaning Procedure that have been approved by CPY
Commissioning NON-CRITICAL --> Pressure Test - Borescope - Reinstatement
CRITICAL --> Pressure Test - Blowing/Flushing - Borescope - Reinstatement
L/O Flushing Comm. CRITICAL line/system need to complete ITR-126 while NON CRITICAL shall complete ITR-112