02 - Part A - Earth Work
02 - Part A - Earth Work
02 - Part A - Earth Work
1.1 This section deals with the Design of Railway Formation, Selection of
Materials for Construction, Execution of Earthwork in formation, Quality
Control of the Earth work, Maintenance of Records and Quality
Assurance. The earth work should be carried out as per the provisions
of “Guidelines for Earthwork in Railway Projects-2003” issued by
RDSO/ Lucknow.
(a) Setting out the alignment of proposed line and establishing working,
bench marks and alignment references, taking the details from
bench marks and alignment references established by the
Employer earlier. This work has to be done once before starting
the earth work in formation and once after the earth work in
formation has been completed, but before starting the works
connected with installation of Permanent Way.
(c) Carrying out the work of Earth work in formation in banks and
cuttings with Contractor’s earth, cut spoils, if suitable, including
laying blanket layer where found necessary with Contractor’s
material. The earth work and blanket layer have to be
compacted with suitable machinery at OMC.
1.4.1 The Engineer when necessary will provide the contractor with the data
necessary for setting out of the centerline. All dimensions and levels
shown on the drawing or mentioned in the documents forming part of
or issued under the contract shall be verified by the contractor on the
1.4.2 The contractor will be entirely responsible for accurate setting out of
the works and safe guarding all survey monuments, bench marks,
beacons, etc. The work of setting out shall be deemed to be a part of
the general works preparatory to the execution of work and no
separate payment shall be made for the same.
1.4.3 These design drawings like plans and ‘L’ section and sheets indicating
the typical cross sections proposed to be used for formation of earth
work for the proposed double line are tentative for giving guidance to
the tenderers and also for enabling them to calculate the rates to be
quoted. These details should be studied by the Contractor and
Engineer in the first instance after their detailed field inspection. In
case any changes are required to these details to suit the available site
condition, the same should be proposed by the contractor and got
approved from the Engineer. Both the Contractor and the Engineer
should keep a clear record of such approvals. This work should be
done before start of any work related to earth work in formation for that
particular section.
1.4.4 As stated above taking guidance from the design drawings showing
plan and ‘L’ section, typical cross section, blanket details etc., which
form part of the tender, and detailed field inspection, the contractor
shall, within 56 days of the issue of Letter of Acceptance prepare
working drawings. The working drawings that will be prepared by the
contractor, should clearly indicate the details of alignment, formation
levels, formation width at ground level, cross sections of catch water
drains & side drains, cross sections indicating levels of sub grade,
blanket etc., to facilitate smooth execution of work at site. Such
working drawings should be submitted to the Engineer for his approval.
Any suggestions and modifications by the Engineer and or the
Employer shall be duly incorporated by the Contractor in these
drawings. The work of execution of embankment shall be commenced
only after the approval of these working drawings including drawings
showing the cross sections, by the Engineer.
1.4.5 For the work of proposed line on the present contract, doing the work
of Design of formation, Design of sub grade & sub soil, Design of
thickness of blanket layer, Stability Analysis of side slopes of
embankment etc., are not contemplated. However, some of the
salient details on these points have been given in Annexure A to
Section B - SPECIFICATIONS FOR EARTHWORK IN FORMATION
mainly for
The Engineer should take a decision on getting these works carried out
by the contractor, in case such doubts arise. Necessary help from the
available experts in the field, including RDSO may be obtained by the
contractor at the specific instructions of the Engineer. Such cases of
getting the uncontemplated works done should be very few and for in
between. It should not become a routine matter.
No extra payment will be made to the Contractor for carrying out these
incidental works, including cost of testing, if any, mainly for clarification
of doubts.
2.2.2 Adequate drainage must be ensured for the worst service conditions.
The top of formation should have cross slope of 1 in 40 from centre of
track towards both sides for single line and from one end towards
cess/drain side (single slope) in multiple lines. Further elaboration on
drainage has been given subsequently.
2.2.3 Suitable and cost-effective erosion control system considering soil matrix,
topography and hydrological conditions to protect the side slopes of
bank should be provided. Further elaborations on this measure have
been given subsequently.
2.2.4 It will be necessary to keep borrow pits sufficiently away from the toe of
the embankments to prevent base failures due to lateral escapement of
The site slopes to be adopted for the banks and cutting in the length of
the proposed double line under this contract should generally confirm
to the following:
The contractor shall, at its own cost, identify the soil, suitable for
Railway formation, which he proposes to use in construction of the
embankment and obtain the approval of Engineer for use of such said
soil.
3.6.1.1 Turfing shall not be commenced without the prior written permission of the
Engineer. The stretch of embankment where turfing is to be done should be
completed in all respects and should be so recorded in the level books.
Contractor should be given permission in writing to this effect before starting
the Turfing.
3.6.1.2 Before turfing is commenced, the side slopes are to be dressed to the
designated profile after cutting the extra width of 500 mm beyond the
designated profile. This dressing is included in the initial rate for earthwork,
and should a contractor stop work before dressing the bank, he shall be debited
with the estimated cost of the dressing to be done by another contractor or
departmental labour, as decided by the Engineer. Where the slope is already
consolidated, it should be loosened for a depth of about 4 cms before the sods
are laid.
3.6.1.3 The sod shall consist of dense, well-rooted growth of permanent and desirable
grasses and shall be practically free from weeds or other undesirable matter.
At the time the sod is cut, the grass on the sod shall have a length of
approximately 50 mm and the sod shall have been freed of debris.
Thickness of the sod shall be as uniform as possible, with some 50-80 mm or
so of soil covering the grass roots depending on the nature of the sod, so that
practically all the dense root system of the grasses is retained in the sod strip.
Each sod strip shall be laid edge to edge and such that the joints caused by
abutting ends are staggered. Every strip, after it is snugly placed against the
strips already in position, shall be lightly tamped with suitable wooden or
metal tampers so as to eliminate air pockets and to press it into the underlying
soil.
On side slopes steeper than 2 (horizontal) to 1 (vertical), the laying of sods
shall be started from bottom upwards.
The contractor shall be responsible for watering to ensure that the turf grows
properly; and in the event of it not doing so, he will returf such parts as have
Doob grass
Chloris gyne
The contractor shall be responsible for watering to ensure that the grass grows
properly; and in the event of it not doing so, he will replant such parts as have
not grown, at his own cost. The plantation/turfing shall be measured and taken
over only after the grass has formed a sufficiently dense growth over the earth
slopes.
3.6.3 Sarkanda or similar type of planting on bank slopes: Where Sarkanda is
planted on bank slopes, the approximate distance centre to centre in rows shall
be 40 cm in either direction. The plantation in adjacent rows will be staggered
for proper coverage of the area. For other types of plantation, the local practice
shall be followed as directed by the Engineer.
The contractor shall be responsible for watering to ensure that the plantation
grows properly; and in the event of it not doing so, he will replant such parts
as have not grown, at his own cost. The plantation/turfing shall be measured
and taken over only after the grass has formed a sufficiently dense growth
over the earth slopes.
3.7 Execution of Earthwork
(d) The rolling for compaction of fill material should commence from
edges towards center with minimum overlap of 200 mm between
each run of the roller. In final pass, roller should simply move over
the surface without vibration so that top surface is properly
finished.
(f) At the end of the working day, fill material should not be left
uncompacted. Care should be taken during rolling to provide
suitable slope on top of the bank to facilitate quick shedding of
water and avoid ponding on formation.
(i) Once the top surface of the formation has been finished to proper
slope and level, movement of either empty or loaded Road vehicle
for transportation of ballast, sleepers etc. should be avoided, as
these movements will cause development of unevenness, ruts on
the surface which will accumulate water and weaken the
formation. The methodology of transportation of P.Way materials
needs to be planned properly avoiding movement on finished
formation.
(k) At locations where the water table is high and the fill soil is fine-
grained, it may be desirable to provide a granular layer of about
30 cm thickness at the base, above subsoil across the full width of
formation. The contractor shall take this factor into account while
designing the formation.
d) Acceptance Criteria :
i) Coarse grained soils which contains fines passing 75 micron IS Sieve,
upto 5 percent should have the Density Index (Relative Density) a
minimum of 70% as obtained in accordance with IS: 2720 ( Part 14)
-1983.
ii) For other soils, field dry density should not be less than maximum
attainable dry density obtained in field compaction trial. However, in
field compaction trial, the maximum attainable dry density should not
be less than 98% of MDD values as obtained by Heavy Compaction
Test (IS: 2720 (part 8) -1983) in the laboratory. In case, there are
difficulties in achieving 98% of the MDD values as obtained by
Laboratory test, in the field trials, the same may be relaxed upto 95% of
At work site, details of works along with materials being used are to be
properly recorded so that work of satisfactory quality can be achieved
which can also be verified at later stage. Records are also required to
be maintained to develop completion drawings and other details, which
would become permanent records of the section and could be helpful
in future to plan developmental activities and remedial measures if
need be. Some of important records to be maintained by the Contractor
are as follows:
7.1 Earthwork
i) Soil excluding rock: This shall include all type of soils such as
vegetable or organic soil, turf, sand, gravel, loam, clay, mud, black
cotton, moorum, kankar soil, shingle and boulder studded soil and soft
conglomerate, river or nallah bed boulders, hard core, macadam surface
of any description (water bound, grouted tarmac etc.), lime concrete,
mud concrete and their mixtures which for excavation yields to
application of picks, showels, jumper, sacrifiers, ripper and other
manual digging implements.
ii) Rock Not Requiring Blasting: This shall include any rock which can
be. This shall also include laterite and hard conglomerate.
iii) Hard Rock Requiring Blasting: This shall include any rock or
boulder which cannot be excavated or split with crow bars or similar
means and requires blasting for the excavation.
(B) Computation of Quantities for various classifications of soil for Earthwork
in Cutting: For purpose of payment, cuttings shall be assumed to be
composed of such soil / soils only, as stand exposed on both or one side of the
finished cuttings, depending upon whether the cutting is box type or one sided
on a transversely sloping ground. The content of each type of soil thus
assigned to any cross section shall be determined as indicated below. It is to be
noted that no portion of cutting will be payable for any such type of soil as is
not exhibited on the finished side slope, where the side slope exists.
(a) For box type cutting: The centre line of the alignment will be marked
vertically on the cross section and the content of each type of soil will
be determined by computing the area of the strip, formed by joining the
points, which form the extremity of occurrence of the particular soil on
the finished side slope of cutting, by straight horizontal lines
terminating on the centre line. Figure No.1.1 (given below)is
illustrative of the manner in which payment is to be made.
(b) For one sided cutting on a transversely sloping ground: Content of each type
of soil will be determined by computing the area of the strip, formed by joining
the points, which form the extremity of occurrence of the particular soil on the
finished side slope of the cutting, by straight lines to the zero point. Zero point is
(c) For widening of existing cuttings for one or more lines where the existing
cutting slope disappears and a fresh slope stands: Before undertaking
widening of the cutting, pre-classification of the existing cutting slope (which
will disappear) should be done after clearing and cleaning the surface and the
strata met marked on the cross-section sheets. After completion of the work
various strata as stand exposed on the new finished slope of the cutting shall
again be marked on the cross-sections. Then the demarcation points of adjacent
strata as determined by classification of the existing slope and the final slope
should be joined as shown in Figure No. 1.3(given below). The cross-sectional
areas for different strata may be worked out and quantities payable classification-
wise assessed accordingly.
(d) For extension to the existing cutting where no fresh cutting slope is available
after work: Before execution of the work pre-classification of the existing
cutting slope which will not be finally available, should be done and recorded in
the initial cross-section. Figure No. 1.4 is illustrative of the manner in which the
payment for the cutting is to be made for soil of different classifications.
7.1.1 Measurement
7.1.1.1 Taking of initial levels and plotting cross sections
(e) The contractor should then prepare the drawing showing the
Longitudinal levels and the cross sections taking the ground
levels from his copy of level book. In the cross sections, the
blanket layer should clearly be shown.
(h) All the above mentioned works for each Reach should be done
before the commencement of further work connected with
construction of embankment.
7.1.1.2 Similarly when the earth work in formation has been completed up to
the bottom of the blanket layer, levels and measurements should be
taken by the Engineer in presence of the Contractor. The level books
containing these levels should be signed by both the Engineer and
Contractor. Two photo copies of these level books should be taken –
one for the record of contractor and one for the record of the Engineer.
These original level books should be handed over to the Employer
before start of the work of blanketing.
7.1.1.3 Similarly when the work of embankment including blanket layer, if any,
has been completed the levels and measurements should be taken by
the Engineer in presence of the Contractor. The level books containing
these levels should be signed by both the Engineer and Contractor.
Two photo copies of these level books should be taken – one for the
record of contractor and one for the record of the Engineer. These
original level books should be handed over to the Employer before
handing over the completed the work.
7.1.1.4 The final profiles of the completed work should be plotted on the cross
section sheets containing the initial levels by the Contractor. The
Contractor and the Engineer should sign these sheets which forms the
record of as constructed work.
7.1.1.5 The gross volume of earth work shall be calculated from the original
and finished profile of the bank/cutting.For the purpose of payment ,
the gross quantity thus calculated shall be reduced by 5% towards
shrinkage allowance for earth work in embankment only if the
embankment has been compacted by heavy machinery as per RVNL
Standard Specifications and the BOQ of the contract (no such
deductions shall be made for earth work in cuttings). However, if with
approval the Engineer, the embankment has not been compacted as
above, shrinkage allowance shall be deducted at the rate of 10%of
the gross quantity of earth work.
The payment, however, will be restricted only to the approved
design profiles furnished by the Engineer; or the actual quantity
executed whichever is less.
7.1.2 Rate :
7.1.3.1 The rate quoted by the bidder/s shall be deemed to include work
necessary for setting out the execution of works in the different phases
as ordered by the Engineer’s Representative. No extra payment shall be
made for such works or for phase works carried out which are necessary
for satisfactory execution of works.
7.1.3.2 The rates quoted by the bidder/s shall be deemed to include clearing the
site of all bushes, roots, grass etc. demarcating by furrows the toes/
edges of the slopes of banks/ cutting and cost of setting out by stakes,
bamboos, strings, pegs etc. and benching of slopes. After site clearance
all pockets and depressions in the soil, shall be made good and
compacted.
7.1.3.3 The rate quoted by the bidders shall be deemed to include excavation in
all types of soil whether dry or wet, loading into and unloading from
contractor’s own transport, all leads and lifts, filling in bank in layers,
dressing all slopes and surface to final dimensions.
7.1.3.4 Rate quoted by the bidder shall be deemed to include the cost of
maintenance of the bank/cutting by the contractor to the correct profile
including repairs of all rain cuts and removal of slips making good the
profile etc. until final measurement have been taken by the Engineer-in-
charge. Completed bank/ cutting shall be taken over after the final
measurements are recorded.
7.1.3.6 The quoted rates by the bidder shall be deemed to include cutting of
trees up to ground level and branches (infringing moving dimension and
coming in the way of earthwork) up to 30cm away from the toe of the
proposed bank after obtaining necessary permission from the Forest
7.1.3.7 The affected trees and branches which are coming in the way of work,
will be marked by the Engineer’s representative and only these trees and
branches which have been thus marked and listed will be removed by
the contractor and handed over to Engineer.
7.1.3.8 The rates quoted by the bidder shall be deemed to include execution of
earth in water logged and swampy area wherever they come across and
no claim for any extra payment on this account shall be entertained.
7.1.3.9 The work shall be carried out as per the longitudinal section plan and
cross section profile to be furnished by the Engineer.
7.1.3.10 The rates quoted by the bidder shall be deemed to include mechanical
compaction of the earthwork in bank shall cover full cost of the finished
bank.
7.1.3.11 The rates quoted by the bidder shall be deemed to include the work of
clearing the site after completion of work.
7.1.3.12 Extra earthwork above the required level will have to be scrapped by the
contractor before recording the final levels. No payments will be made for
such extra earthwork or for removing it to the required levels.
(b) Rate
7.3.1 Contractor will ensure correct levels for doing earthwork in bank.
Levels will be checked at different stages of the work to form the basis
for running bill payments.
7.3.2 On account payment for unfinished work for earthwork, may at the
discretion of the Engineer, be made up to 90% of the accepted rate for
the quantity of work calculated up to the layer accepted, by taking
representative measurements, at intervals of 100 meter, which may be
increased/reduced with the permission of the employer.
Levels at the centre line and both the edges of the bank along
with width of the bank at that level shall be taken and shall be
either marked with pencil on the existing cross section sheets or
plotted on the computerized cross section to check if the bank
width executed on either side of the centre line is equal to or
more than the required width as per designed profile plus 50cm,
only then the bank will be acceptable for payment.
1.4.1 Slope stability analysis should be carried out to design stable slopes for
the embankment. Usually, slopes of 2:1 of embankment upto height of
6.0 m would be safe for most of the soils. However, this analysis has to
be carried out in detail for any height of embankment in following
situations:
a) When subsoil is soft, compressible & marshy type for any depth.
b) When subgrade soil (fill material) has very low value of cohesion C'
such that C’/OH (where H is height of embankment and O is bulk
density of soil) is negligible, i.e in range of 0.01 or so.
c) When highest water table is within 1.5xH (H is the height of
embankment), below ground level, then submerged unit weight of
soil below water level should be taken.
1.4.2 In cutting slope, softening of soil occurs with the passage of time, and
therefore, long term stability is the most critical, and should be taken
into consideration while designing the cuttings.
1.4.3 Detailed slope stability analysis may be carried out according to the
procedure detailed in Annexure-III of ‘RDSO, Guidelines for Earthwork
in Railway Projects’ wherein a typical worked out example of slope
stability analysis is also given for guidance. This procedure would be
applicable for most of the cases. However, in certain rare situations
where, further detailed analysis may be required due to the site
conditions, the same may be got done by the contractor through an
expert consultant including RDSO nominated by the Engineer
1.4.4 Slope stability analysis may also be carried out using standard
computer programme /software especially made for this purpose.
However, the efficacy of the software used should have approval the
Engineer.
1.4.5 As already indicated in the foregoing paras, for the present Patch
doubling works, as the banks or of very low height , carrying out the
work of either design of side slope of the embankment or slope stability
analysis is not contemplated.
1.0 Compaction
1.1 Each layer should be compacted to the desired density over its entire width
commencing from the sides, before the next layer is commenced. There
should be minimum overlap of 150mm between each run of the rollers. Care
should be taken during rolling to suitably slope the surface of the bank to
facilitate the shedding; and to minimise absorption of rainwater; special
attention being given to the prevention of ponding.
1.2 The suitability of various rolling equipment for different types of soils should
be as per the sound Engineering practices. Guidelines given in RDSO
instructions for earthwork may be referred as given in Annexure-V (of the
guidelines).
1.3 Extra wide bank by 50 cm on either side shall be rolled and then dressed to
size for avoiding any loose earth at the shoulders.
1.4. Five samples shall be collected for testing of each compacted layer of
1000m2.
2.1 With the moderate cohesion, the compaction in layers by rollers is most
effective. Vibratory roller have been found more effective than the static roller
and greater thickness of layers can be allowed.
2.2.1 The water content at which a soil is compacted has an effect on all the
physical properties of compacted soil, however, physio-chemical properties
remain unchanged. Embankment soil shall attain moisture density equilibrium
during weather cycles and the bank/ cutting should be safe during service
conditions. Therefore, design parameters should be carefully selected to cater
for the most unfavourable conditions.
i. The quarry shall be approved after testing the soil samples in the
laboratory for determination of soil parameters.
2.4 For compaction controls, IS:2720 (Pt. XXXVIII)-1976 should be used for field
trials.
3.2. Sheep-foot rollers are most effective in breaking the clods and filling large
spaces. The layer thickness should be equal to the depth of the feet of roller
plus 50mm. For specifications o sheep-foot rollers IS:4616-1968 may be
referred.
4.1 After site clearance, all pockets and depressions left in the soil, if any, should
be made good and compacted suitably.
5.2 The performance of rollers is dependent mainly on the type of soil. The
different type of rollers and the types of soil for which they are more suitable
are given in Annexure-V of RDSO guideline.
5.3 Before the work is commenced, field compaction trials should be conducted
as per IS Code: 10379-1982 for deciding upon the most desirable moisture
content and economical thickness of layer and the number of passes required
to achieve the specified density. Heavy compaction tests should be first
carried out on the soil from the borrow pit areas to ascertain the optimum
moisture content and the maximum dry density
6.1 The objective should be to compact near OMC or above to achieve the
density as specified in most efficient manner