Functional Testing Checklist: Equipment/System
Functional Testing Checklist: Equipment/System
com
Equipment/System:
The following activities should be checked and verified to document handover from construction to commissioning. Unsatisfactory items
that are critical to performing testing safely must be corrected prior to handover. Unsatisfactory items that are not critical to performing
testing must be documented in the handover punch list, and testing may commence.
Leak and pressure testing completed satisfactorily for all piping systems.
- Utility water
- Potable water
- Seal water
- Fire water
- Compressed air
- Natural Gas
HVAC system operable (only for facilities where HVAC is required for commissioning
activities; T&B not required).
Safety devices and equipment are installed, fully functional, adjusted, and tested.
Point to point checks have been satisfactorily completed from the equipment /device to the
PLC.
Commissioning punch list items have been documented and are attached to this form.
If any of the above are marked "NO", provide explanation or comment and details of any agreed action:
Comments:
Date: Signature:
Date: Signature: