FRONT Release of
SL.NO. Description UOM Actual Quantity Completion of
RELEASE Percentage (%) WORK Front Till Previous
work Percentage Today Cumm Balance Next Day PLAN REMARKS
COMPLETED Available Day
(%)
1 EQUIPMENT (LAGGING) M2 2,183.12 1,244.00 56.98 % 1,319.00 60.42 % 45.00 1,319.00 - 1,319.00 864.12### -
2 EQUIPMENT (CLADDING) M2 2,183.12 1244.00 56.98 % 1,180.00 54.05 % 64.00 1,130.00 50.00 1,180.00 1003.12
### 50.00
3 PIPING (LAGGING) M2 15,840.00 275.00 1.74 % 275.00 1.74 % - 275.00 - 275.00 15,565.00
4 PIPING (CLADDING) M2 15,840.00 275.00 1.74 % 275.00 1.74 % - 275.00 - 275.00 15,565.00 0.00
5 REFORMER PACKAGE (LAGGING) M2 2,856.00 250.00 8.75 % 450.00 30.00 30.00 2,826.00 40.00 scaffolding is progress