Schedule of Loads Motor Layout: C1 C2 C3 C4 C5 C6
Schedule of Loads Motor Layout: C1 C2 C3 C4 C5 C6
Schedule of Loads Motor Layout: C1 C2 C3 C4 C5 C6
C1 C2 C3 C4 C5 C6
C7 C8
C11
C13
C10
C14 FOR MAIN BREAKER : TOTAL LOAD CURRENT + (HIGHEST MOTOR LOAD CURRENT X 1.5)
544.143 + ( 236.263 X 1.5 ) = 898.538 AMPS
C12
THEREFORE USE 1,000 AT, 3P, and 2 SETS OF 3 - 400 mm² THW IN 90 mm ø RSC PIPE
P.T.
3 - 333 KVA
POTENTIAL TRANSFORMER
DIST. TRANSFORMER
L.A. 7620 / 13200 V TRANSFER SWITCH
220 / 440 V
LIGHTNING ARRESTER
M
GENSET
G M KILOWATT-HR METER
MCCB
MTS / ATS
1000 AT
3P
1000 AT
3P G GENERATOR SET
DISTRIBUTION TRANSFORMER
CONTROL SYSTEM
FROM THE OFFICE OF: PROFESSIONAL ELECTRICAL ENGINEER: SEAL: PROJECT TITLE: OWNER: SHEET CONTENTS: PREPARED BY : SHEET NUMBER: