Procedure - GCC - Building Permit
Procedure - GCC - Building Permit
Procedure - GCC - Building Permit
For obtaining planning permission of all other buildings other than those
mentioned above, the applicant has to submit the application in CMDA.
For area above 5,000 sq.ft and up to 10,000 sq.ft the application to be
submitted in online and will be processed in Headquarters, Works
Department.
5. Zoning of Land
Assistant
Verifies the payment done by the applicant and
6 Executive
forwards the application to the Executive Engineer.
Engineer
Executive
7 Approves the fees verified by AEE.
Engineer
12. NOC from Civil Aviation department (if required as per special rules
for the vicinity of Civil Aerodromes), NOC from the competent
authority of Air Force (if required as per the notification / order of
the concerned Air Force Authority in respect of the area in the
vicinity of Air Force Stations).
……………………………………………………………………………………………………………………………
our supervision and we certify that all the materials (type and grade) and the
workmanship of the work shall be generally in accordance with the general and detailed
specifications, as per NBC standards and to meet out the structural design of the
proposed building.
We undertake not to continue construction without any supervision by the Site Engineer
and submit the respect to the local body.
1. Signature of Architect
Name of the Architect with Reg.No.
Address of the Architect
Date:
Place:
I certify to engage the above mentioned Engineers for the active period of
building execution and I hereby assure to give revised certificate, in case of any change
of Engineer, I would ensure no work is taken up in this period till required Engineers
are engaged by me.
……………………………………………………………………………………………………………………………
……………………………………………………………………………………………………………………………
………………………………… we certify that the structural plan of the building meet the
applicable, as stipulated under part 6 structural design of the national building code of
the India and other relevant codes, the design as been done after detailed soil test and
we are satisfied as to be adequacy of soil test carried out and the information given
The land is fit for the proposed construction, it has been tested vide soil test report no.
………………………………
………………...…………………………………………………………………………………………………………
…………………………………………………………………………………………………………………….. is
designed to resist earthquake, check has been made and found safe and I hereby
certify that:
2. The design and analysis using the code of practice for loading standards as
per IS-875 Part – I to V and seismic force as per code IS-1893, is carried out.
The building will be sound and stable when used for the purpose for which it is
designed.
As Below:
Zonal Executive
Planning permission / Building
Engineers (stilt
Permit for Residential & Respective
1 + 2 floors)
Commercial buildings up to Zonal Office
Regional S.E.
5,000 sq.ft FSI area
(stilt + 3 floors)
Planning permission for
Respective Zonal Executive
2 Demolition Application
Zonal Office Engineers
(unlimited area).
Headquarters,
Planning permission for Chief Engineer
3 Works
subdivision or layout of land (SWM & TP)
Department
Moreover SMS alerts / e-mails are sent to the applicants / land owner
at each stages. The applicant can act immediately if a letter is sent
requesting to furnish additional documents / particulars by seeing the
SMS alerts / e-mails. Further if it is sanctioned, the necessary fees to
be paid are made known, so that the applicant can make the
payment immediately and obtain the permits.
The plans are submitted online for checking for provisions in Tamil
Nadu Combined Development & Building Rules, 2019 and any
correction required are informed through online. The applicants shall
make the necessary corrections and submit the plan for scrutiny. The
Auto-DCR software is used for scrutiny of the plan submitted online.
On receipt of the payment for the demand advice the planning permit
/ building permit are issued. The SMS alerts / email are sent to the
applicant once the permit are ready.
----------