1. Insulation Resistance Test: (Not Possible, since transformer LV Side cable is connected and neutral
point is earthed).
Note:
1. During testing, ACB settings made into minimum setting current at 0.4 In and time at 3 Sec. After
testing done, settings was normalized.
2. Tripping time mentioned above, the values are approximately equal to.