Computer Applications in Power Systems
Computer Applications in Power Systems
JIGJIGA UNIVERSITY
COLLEGE OF ENGINEERING & TECHNOLOGY
Course Outline
DEPARTMENT OF ELECTRICAL AND COMPUTER
ENGINEERING
Course Title:
Computer Applications in Power Systems (ECEg5252 )
By
Shimekit Kifle
Contents
Load flow Analysis:
Introduction
Load flow Analysis: Fault Studies:
Fault Studies:
SCADA system SCADA system
Optimization and
security:
shimekit 1
Computer Applications in Power Systems 6/7/2022
Introduction
Electricity is the most preferred used form of energy used
in industry, homes, businesses and transportation.
It can be easily and efficiently transported from the
CHAPTER ONE production centers to the point of use.
It is highly flexible in use as it can be converted to any
Introduction to desired form like mechanical, thermal, light, chemical etc.
An electrical power system is made up of many
Computers in Power Systems components connected together to form a large, complex
system that is capable of generating, transmitting and
distributing electrical energy over large areas.
Generation
The main sources of thermal energy sources are coal, natural gas, nuclear
fuel and oil. The use of non-fossil fuels such as wind, solar, tidal, and
geothermal and biogas in electricity generation is also increasing.
shimekit 2
Computer Applications in Power Systems 6/7/2022
• Typically the sub-transmission voltage levels are from 66 kV to 132 kV. Economy:
Some large industrial consumers may be served directly from the sub- In interconnected systems, it is possible to reduce the total set of
transmission system.
generating plants required to maintain the desired level of generation
reserve.
• The transmission lines connect the neighbour power systems at
transmission levels, thus forming a grid. This results in reduction of operational and investment costs.
Also, operational (including plant start-ups and shut down) and
• The grid is the network of multiple generating resources and several generation scheduling of units can be more economically
layers of transmission network. coordinated.
shimekit 3
Computer Applications in Power Systems 6/7/2022
2 System frequency control and tie-line power Few seconds to few minutes
control
shimekit 4
Computer Applications in Power Systems 6/7/2022
Generating unit controls • As the time constant of excitation system is much smaller than that of
• The controls provided in generating units consist of prime mover control prime mover system, the coupling between LFC and AVC loop is
and excitation controls as shown in Fig. 1.3. negligible and hence they are considered independently.
• The controls are also called as load frequency control (LFC) and automatic
voltage control (AVC).
• These controllers are set for a particular operating condition and maintain
the frequency and voltage magnitude within the specified limits following
small changes in load demand.
In LFC, two feedback loops namely, primary and secondary loops are In AVC, the bus voltage is measured and compared to a reference. The
provided. Both the loops help in maintaining the real power balance by resulting error voltage is then amplified and applied to the excitation control
system.The output of the exciter controls the generator field current.
adjusting the turbine input power.
An increase in the reactive power load of the generator causes the terminal
voltage to decrease and this results in generation of voltage error signal. The
The primary LFC loop senses the generator speed and accordingly amplified error signal then increases the exciter field current which in turn
controls the turbine input. This is a faster loop and operates in the increases the exciter terminal voltage. This increases the generator field
order of seconds. But this loop provides only a coarse frequency current, which results in an increase in the generated emf.
control. The reactive power generation of the generator is thus increased and the
terminal voltage is brought back to its nominal value.
The secondary LFC loop which senses the system frequency and tie- The generation control maintains the active power balance in the system. It
line power, fine tunes the frequency back to the nominal value. This is also controls the division of load active power between the generators in the
system to ensure economic operation.
a slower loop and may take minutes to eliminate frequency error.
shimekit 5
Computer Applications in Power Systems 6/7/2022
Economic dispatch
Economic operation and planning of electric energy generating system has
been accorded due importance by the power system operators to make The economic dispatch and minimum loss problems can be solved by means of
electrical energy cost-effective to the consumer and profitable for the optimal power flow (OPF) method.
operator. The OPF calculations involve a sequence of load flow solutions in which certain
The operational economics that deals with power generation and delivery can controllable parameters are automatically adjusted to satisfy the network
be divided into two sub-problems. constraints while minimizing a specified objective function.
One dealing with minimum cost of power generation and other dealing with The power system control objectives are dependent on the operating state of the
delivery of power with minimum power loss. system.
The problem of minimum production cost is solved using economic dispatch. Under normal operating conditions, the controller tries to operate the system as
economically as possible with voltages and frequency maintained close to
The main aim of economic dispatch problem is to minimize the total cost of
nominal values.
generating real power at different plants in the system while maintaining the
real power balance in the system. But abnormal conditions like outage of a larger generator, of a major
transmission line or sudden increase or reduction of system load can cause havoc
For system having hydro-plants, a coordinated dispatch of hydro-thermal
in the system, if not properly controlled.
units is carried out.
Different operating objectives have to be met in order to restore the system to
normal operation after the occurrence of such contingencies.
shimekit 6
Computer Applications in Power Systems 6/7/2022
Occurrence of a contingency with the system already in alert state, may cause
overloading of equipments and the system may enter emergency state. If the It is most urgent that the system be restored to normal or alert state by
disturbance is very severe, the system may enter into extremis state directly from means of these actions.
alert state. In-extremis state:
Emergency state: If the emergency control actions fail when the system is in emergency state,
If the preventive controls fail or if a severe disturbance occurs, the system enters then the system enters into in-extremis state. The system starts to disintegrate
emergency state. The transition to this state can occur either from normal state or into sections or islands.
alert state. Some of these islands may still have sufficient generation to meet the load.
In this state the balance between generation and load is still maintained (equality The components are overloaded and the active power balance is also
constraints still satisfied) and the system remains in synchronism. Some disrupted.
components are however overloaded (some inequality constraints violated). Failure Overloaded generators start tripping leading to cascade outages and possible
of these components results in system disintegration. ‘blackout’.
Emergency control actions like disconnection of faulted section, re-routing of Control actions, such as load shedding and controlled system operation are
power excitation control, fast valving, and load curtailment have to be taken. taken to save as much of the system as possible from a widespread blackout.
Unit Commitment
Restorative state: The total load in the power system varies throughout a day and its
The restorative state represents a condition in which control action is being
value also changes with the day of the week and season. Hence, it is
taken to restart the tripped generators and restore the interconnections. The not economical to run all the units available all the time.
system transition can be either to normal or alert state depending on system
conditions. Thus, the problem of unit commitment is to determine in advance, the
The sequence of events that result in system transition from normal to in- start and the shut down sequence of the available generators such that
extremis state may take from few seconds to several minutes. the load demand is met and the cost of generation is minimum.
Bringing the system back to normal through the restorative state is an
extremely time consuming process and may last for hours or may be days. A
large generator may require many hours from restart to synchronization.
The switched off loads can be picked up gradually and resynchronization of
operating islands to the grids is also a time consuming process.
The control actions may be initiated from the central energy control centre
either through operators or automatically.
shimekit 7
Computer Applications in Power Systems 6/7/2022
shimekit 8
Computer Applications in Power Systems 6/7/2022
Stability studies Transient stability study deals with the response of a power system
The stability studies ascertain the impact of disturbances on the subjected to a large disturbance such a short circuit, line tripping or
electrochemical dynamic behavior of the power system. loss of large generation.
These studies are of two types; small signal stability study and
transient stability study. In this study the equations describing system dynamics are solved using
The small signal stability studies deal with the behavior of a system numerical techniques.
following any small disturbances like small change in load, small
change in AVR gain etc. The power system transient stability problem is then defined as that of
As the disturbance is small, the equations that describe the dynamics of assessing whether or not the system will reach an acceptable steady
the power system are linearized for the purpose of analysis. state operating point following a large disturbance.
The system is small signal stable for a particular operating point, if
following a small disturbance it returns to essentially the same steady
state operating condition.
Power system planning, design and operations require Impact of computers in Power system
careful studies in order to evaluate the system More efficient and economic means of performing routine
performance, safety, efficiency, reliability and engineering
economics. calculations required in the planning, design , and operation of a
power system
The modern interconnected power systems are A better utilization of engineering talent by relieving the
complex, with several thousand buses and components. engineer
from tedious hand calculations and permitting him to spend more
The manual calculation of the performance indices is time on technical work
time consuming. The ability to perform more effective engineering studies by
applying calculating procedures to obtain a number of alternate
The computational efforts are very much simplified solutions for a particular problem to provide a broad base for
due to the availability of efficient programs and engineering decisions
powerful microcomputers. The capability of performing studies which heretofore were not
possible because of the volume of calculations involved.
35 Computer Applications in Power Systems 36 Computer Applications in Power Systems
shimekit 9
Computer Applications in Power Systems 6/7/2022
shimekit 10
Computer Applications in Power Systems 6/7/2022
shimekit 11
Computer Applications in Power Systems 6/7/2022
Automatic Generation Control (AGC): a collection of equipment Network Configuration/Topology Processor: analyzes the status of
and computer programs implementing closed-loop feedback circuit breakers as well as measurements to automatically determine the
control of frequency and net interchange current model of the power system
Economic Dispatch Calculation (EDC): the scheduling of power State Estimation: provides a means of processing a set of redundant
from all available sources in such a way to minimize cost within information to obtain an estimate of the state variables of the system
some security limit
Contingency Analysis: simulates outages of generating units and
Interchange Transaction Scheduling (ITS): ensures that transmission facilities to study their effect on bus voltages, power flows,
sufficient energy and capacity are available to satisfy load energy and the transient stability of the power system as a whole.
and capacity requirements.
Unit Commitment (UC): produces the hourly start-up and loading Three-Phase Balanced Power Flow: obtains complete voltage angle and
schedule which minimizes the production cost for up to one week magnitude information for each bus in a power system for specified load
in the future. and generator real power and voltage conditions
Short-Term Load Forecasting (STLF): produces the hourly Optimal Power Flow: optimize some system objective function, such as
system load for up to one week into the future and is used as input production cost, losses, and so on, subject to physical constraints on
to the unit commitment program facilities and the observation of the network laws
Hydrothermal coordination: the scheduling of power from all
available hydro generation in such a way to minimize cost within
constraints (e.g., reservoir levels) Computer Applications in Power Systems Computer Applications in Power Systems
47 48
shimekit 12
Computer Applications in Power Systems 6/7/2022
END
shimekit 13