Check List Analyzer and Analyzer System
Check List Analyzer and Analyzer System
1.9 Whether latest revision of approved template / format has been used G-INST-004.102-F X
Aker Powergas Pvt Ltd Operating System Procedure Number G-INST-004.301-A-00 Control Object Check List for Analyzers Sheet 1 of 6
Group Head-Instruments
Control Object Check List Checklist approved for use by:
Aker Powergas Pvt Ltd
for Analyzer & Analyzer System Issued date: 15.03.2011
1.17 Whether all revision marks on revised document and index are in place. X X
- General Standards X
- Norms X
- Contractual Requirements X
- Licensor documents X
1.20 Whether Site conditions are enclosed. X
Aker Powergas Pvt Ltd Operating System Procedure Number G-INST-004.301-A-00 Control Object Check List for Analyzers Sheet 2 of 6
Group Head-Instruments
Control Object Check List Checklist approved for use by:
Aker Powergas Pvt Ltd
for Analyzer & Analyzer System Issued date: 15.03.2011
Aker Powergas Pvt Ltd Operating System Procedure Number G-INST-004.301-A-00 Control Object Check List for Analyzers Sheet 3 of 6
Group Head-Instruments
Control Object Check List Checklist approved for use by:
Aker Powergas Pvt Ltd
for Analyzer & Analyzer System Issued date: 15.03.2011
Aker Powergas Pvt Ltd Operating System Procedure Number G-INST-004.301-A-00 Control Object Check List for Analyzers Sheet 4 of 6
Group Head-Instruments
Control Object Check List Checklist approved for use by:
Aker Powergas Pvt Ltd
for Analyzer & Analyzer System Issued date: 15.03.2011
3.2 Piping
Whether Piping interface for Sample in, Sample out, Utilities like
3.2.1 Cooling water / Air / N2 have been identified and interface requirements X X
given to Piping
Whether Analyzer panel / House / Shelter has been shown in the 3 D
3.2.2 X X
model along with interface tie in points for Piping.
Whether Steam tracing requirements for Sample line (if applicable) have
3.2.3 X X
been specified.
Whether Sample return line , Vent and Drain lines have been routed to
3.2.4 X X
safe location in the plant.
3.3 Instruments
N.A.
3.4 Electrical
Whether Power supply requirements of UPS and non-UPS Power for
3.4.1 X X
Analyzer & Analyzer house/ shelter is specified.
Aker Powergas Pvt Ltd Operating System Procedure Number G-INST-004.301-A-00 Control Object Check List for Analyzers Sheet 5 of 6
Group Head-Instruments
Control Object Check List Checklist approved for use by:
Aker Powergas Pvt Ltd
for Analyzer & Analyzer System Issued date: 15.03.2011
3.7.1 Whether HVAC requirements for Analyzer house/ shelter are specified. X X
3.8 Construction
N.A.
Aker Powergas Pvt Ltd Operating System Procedure Number G-INST-004.301-A-00 Control Object Check List for Analyzers Sheet 6 of 6