Saudi Aramco 2616-ENG (03/99)

PMT OPRNS
SAUDI ARABIAN OIL COMPANY

THIS DRAWING AND THE INFORMATION CONTAINED HEREIN ARE THE SOLE PROPERTY OF SAUDI ARAMCO. NO REPRODUCTION IN FULL OR IN PART SHALL BE OBTAINED FROM THIS DOCUMENT WITHOUT THE WRITTEN CONSENT OF ITS OW NER.
SECTION 13300
ENGG CERT

INSTRUMENTATION

SUBSECTION INDEX

Part 1 - General

1.01 Description
1.02 Related Work
DESCRIPTION

1.03 Reference Standards


1.04 Quality Assurance
1.05 Requirements of Sections 01000 and 01005
1.06 Submittals
1.07 Packing, Delivery, Storage and Handling

Part 2 - Products

2.01 Manufacturers
2.02 Design Data
JO/EWO

2.03 Local Control Panels


2.04 Instruments
DATE

2.05 Nameplates
2.06 Special Tools
2.07 Spare Parts and Test Equipment
NO.
REV

DISCIPLINE
ENGINEER Part 3 - Execution

DATE:
3.01 Installation
PROJECT
ENGINEER 3.02 Field Calibration
3.03 Performance Tests
DATE: 3.04 Acceptance Tests
CERTIFIED

DATE:
CONSTRUCTION
PART 1 - GENERAL
AGENCY

1.01 Description
DATE:
OPERATIONS
A. Work in this Section includes, but is not limited to; furnishing, installing and testing
instruments.
DATE:
CONTROL NUMBER

B. Furnish and install all instrumentation indicated on Drawings and herein after
VERIFICATION

specified. The indicated specify minimum requirements only. Furnish full technical
EDSD

details of all instrumentation offered.


DATE:
BY:

C. All indicating scales shall be in metric units as indicated on Drawings or SAES-J-003.


CERTIFCATION

APPROVAL/CERTIFICATION REQUIREMENTS,

If indicated on Drawing, provide dual units (Metric & Imperial).


THIS INDICATES THAT REV. NO.__________
ICATE
00
OF THIS DRAWING IS COVERED, FOR ALL

BY DRAWING COMPLETION CERTIFICATE


10-00167-0007-001 _
(DCC) NO. ____________________
REVISIONCERTIFI

Section 13300

Project Specification DWG.TYPE PLANT NO. INDEX DRAWING NO. SHT.NO. REV.NO.
REVISION

Construction Specifications DOC 1


Shaybah Industrial Support Facilities
B54 A CS-10-00167
of 00
Shaybah SAUDI ARABIA BI / JO: 10-00167-0007 7
EDSD/2616-0399.doc
669B: KH1134 Specs
Saudi Aramco 2616-ENG (03/99)
PMT OPRNS
SAUDI ARABIAN OIL COMPANY

THIS DRAWING AND THE INFORMATION CONTAINED HEREIN ARE THE SOLE PROPERTY OF SAUDI ARAMCO. NO REPRODUCTION IN FULL OR IN PART SHALL BE OBTAINED FROM THIS DOCUMENT WITHOUT THE WRITTEN CONSENT OF ITS OW NER.
1.02 Related Work
ENGG CERT

A. Conduit and wiring between panels and field mounted devices furnished and installed
under applicable electrical sections.

1.03 Reference Standards

A. Saudi Aramco Engineering Standard (SAES) Material System Specifications


(SAMSS):

1. SAES-A-102, Air Pollutant Emission Source Control.


DESCRIPTION

2. SAES-J-002, Technically Acceptable Instruments.

3. SAES-J-003, Instrumentation - Basic Design Criteria.

4. SAES-J-005, Instrumentation Drawings and Forms.

5. SAES-J-200, Pressure.

6. SAES-J-300, Level.
JO/EWO

7. SAES-J-400, Temperature.
DATE

8. SAES-J-600, Pressure Relief Devices.


NO.
REV

9. SAES-J-902, Electrical Systems for Instrumentation.


DISCIPLINE
ENGINEER

10. SAES-P-104, Wiring Methods and Materials.


DATE:
PROJECT
ENGINEER 11. 34-SAMSS-820, Instrument Control Cabinets-Indoor.

DATE: 12. 34-SAMSS-821, Instrument Control Cabinets-Outdoor.


CERTIFIED

13. 34-SAMSS-913, Instrumentation and Thermocouple Cable.


DATE:
CONSTRUCTION
AGENCY B. Saudi Aramco Library Drawings:
DATE:
1. DB-950025, Nameplates Details for Instrument Boards.
OPERATIONS

2. DC-950043, Electrical Connections for Field Mounted Instruments.


DATE:
CONTROL NUMBER

C. National Electrical Manufacturers Association (NEMA).


VERIFICATION
EDSD

D. American National Standards Institute (ANSI).


DATE:
BY:

E. Factory Mutual System (FM).


CERTIFCATION

APPROVAL/CERTIFICATION REQUIREMENTS,
THIS INDICATES THAT REV. NO.__________
ICATE
00
OF THIS DRAWING IS COVERED, FOR ALL

BY DRAWING COMPLETION CERTIFICATE

F. Institute for Electrical and Electronic Engineers (IEEE)


10-00167-0007-001 _
(DCC) NO. ____________________
REVISIONCERTIFI

Section 13300

Project Specification DWG.TYPE PLANT NO. INDEX DRAWING NO. SHT.NO. REV.NO.
REVISION

Construction Specifications DOC 2


Shaybah Industrial Support Facilities
B54 A CS-10-00167
of 00
Shaybah SAUDI ARABIA BI / JO: 10-00167-0007 7
EDSD/2616-0399.doc
669B: KH1134 Specs
Saudi Aramco 2616-ENG (03/99)
PMT OPRNS
SAUDI ARABIAN OIL COMPANY

THIS DRAWING AND THE INFORMATION CONTAINED HEREIN ARE THE SOLE PROPERTY OF SAUDI ARAMCO. NO REPRODUCTION IN FULL OR IN PART SHALL BE OBTAINED FROM THIS DOCUMENT WITHOUT THE WRITTEN CONSENT OF ITS OW NER.
G. National Fire Protection Association (NFPA).
ENGG CERT

H. National Electrical Code (NEC).

I. Underwriters' Laboratories (UL).

1.04 Quality Assurance

A. Instrumentation is an integrated system furnished complete by one supplier who shall


be responsible for satisfactory operation of the entire system.
DESCRIPTION

B. Provide drawings and specifications indicating energy sources and supply voltage.

C. Instrumentation accuracy, in accordance with manufacturer's standard, unless


otherwise stated herein.

D. After calibration, check instrument loops in presence of Service Engineer, bench test,
document for records and submit to Saudi Aramco Representative.

E. Identify any exceptions to Specification, in proposal and in documentation submittals.


JO/EWO

1.05 Requirements of Sections 01000 and 01005


DATE

A. In regard to:
NO.
REV

1. Contractor's Shop and Working Drawings.


DISCIPLINE
ENGINEER

2. Bolts, Anchor Bolts and Nuts.


DATE:
PROJECT
ENGINEER 3. Concrete Inserts.

DATE: 4. Sleeves.
CERTIFIED

5. Foundations, Installation and Grouting.


DATE:
CONSTRUCTION
AGENCY 6. Nameplates.
DATE:
7. Operating and Maintenance Instructions and Parts Lists.
OPERATIONS

8. Special Tools.
DATE:
CONTROL NUMBER

9. Start-up Spare Parts.


VERIFICATION
EDSD

10. Delivery, Storage and Handling.


DATE:
BY:
CERTIFCATION

APPROVAL/CERTIFICATION REQUIREMENTS,
THIS INDICATES THAT REV. NO.__________
ICATE
00
OF THIS DRAWING IS COVERED, FOR ALL

BY DRAWING COMPLETION CERTIFICATE


10-00167-0007-001 _
(DCC) NO. ____________________
REVISIONCERTIFI

Section 13300

Project Specification DWG.TYPE PLANT NO. INDEX DRAWING NO. SHT.NO. REV.NO.
REVISION

Construction Specifications DOC 3


Shaybah Industrial Support Facilities
B54 A CS-10-00167
of 00
Shaybah SAUDI ARABIA BI / JO: 10-00167-0007 7
EDSD/2616-0399.doc
669B: KH1134 Specs
Saudi Aramco 2616-ENG (03/99)
PMT OPRNS
SAUDI ARABIAN OIL COMPANY

THIS DRAWING AND THE INFORMATION CONTAINED HEREIN ARE THE SOLE PROPERTY OF SAUDI ARAMCO. NO REPRODUCTION IN FULL OR IN PART SHALL BE OBTAINED FROM THIS DOCUMENT WITHOUT THE WRITTEN CONSENT OF ITS OW NER.
1.06 Submittals
ENGG CERT

A. Sales bulletins and other general publications are not acceptable as submittals except
where necessary to provide supplemental technical data.

B. Submit for Saudi Aramco approval before fabrication or installation:

1. Component manufacturing data sheets together with a technical product


brochure or bulletin indicating pertinent data and identifying each component
by tag number and nomenclature as indicated on Drawings and in
Specifications, or required.
DESCRIPTION

2. System wiring diagrams with full description of operation utilizing same


identifications, numbers and symbols as shown on Drawings.

3. Component drawing showing dimensions, mounting, and external connection


details.

4. Data sheet for each instrument and equipment, diagrams, and schematics
using Saudi Aramco Standard sheets and format as applicable, all in
accordance with SAES-J-005.
JO/EWO

5. Detailed shop drawings of the Instrument Control Panels indicating the


DATE

location, method of mounting and nameplate engraving of each device, and


complete fabrication detail including doors, latching, foundation bolt holes,
equipment mounting channels, terminal blocks, stiffeners, sills and bulkhead
NO.
REV

fittings.
DISCIPLINE
ENGINEER

C. Submit operating and maintenance instructions and spare parts lists separately from
DATE:
instrumentation submittal. Operating instructions incorporates functional description
PROJECT
ENGINEER of the entire system.

DATE: D. Submit as-built of drawings for review within 30 days after completion of system
CERTIFIED
installation as part of operating and maintenance instructions. Clearly define special
maintenance requirements particular to system along with special calibration and test
DATE:
CONSTRUCTION
procedures.
AGENCY

1.07 Packing, Delivery, Storage, and Handling


DATE:
OPERATIONS
A. Packing and Labeling:

DATE: 1. Prior to shipment, each component shall be tagged to identify its' location, tag
CONTROL NUMBER

number, and system function. Identification shall be prominently displayed on


VERIFICATION

the outside of the package.


EDSD

DATE:

2. Firmly attach permanent stainless-steel, tag to the equipment. Mark tags with
BY:

the instrument tag number shown in the Instrumentation Data Sheets.


CERTIFCATION

APPROVAL/CERTIFICATION REQUIREMENTS,
THIS INDICATES THAT REV. NO.__________
ICATE
00
OF THIS DRAWING IS COVERED, FOR ALL

BY DRAWING COMPLETION CERTIFICATE


10-00167-0007-001 _
(DCC) NO. ____________________
REVISIONCERTIFI

Section 13300

Project Specification DWG.TYPE PLANT NO. INDEX DRAWING NO. SHT.NO. REV.NO.
REVISION

Construction Specifications DOC 4


Shaybah Industrial Support Facilities
B54 A CS-10-00167
of 00
Shaybah SAUDI ARABIA BI / JO: 10-00167-0007 7
EDSD/2616-0399.doc
669B: KH1134 Specs
Saudi Aramco 2616-ENG (03/99)
PMT OPRNS
SAUDI ARABIAN OIL COMPANY

THIS DRAWING AND THE INFORMATION CONTAINED HEREIN ARE THE SOLE PROPERTY OF SAUDI ARAMCO. NO REPRODUCTION IN FULL OR IN PART SHALL BE OBTAINED FROM THIS DOCUMENT WITHOUT THE WRITTEN CONSENT OF ITS OW NER.
B. Delivery:
ENGG CERT

1. Following completion of shop assembly, factory test, and approval of all


equipment by Saudi Aramco, the panels, and cabinets shall be prepared for
shipping by being wrapped in heavy-duty polyethylene covers, and packed in
protective crates to protect the equipment from damage, dust, and moisture.

2. Dehumidifying agents shall be placed inside the covers, and the equipment
shall then be skid-mounted for transport to it's final location. The packed
weights shall be conspicuously shown, and the crate shall have instructions
for unloading, transporting, storing, and handling at the job-site.
DESCRIPTION

3. Deliver spare parts at same time as pertaining equipment. Deliver to Saudi


Aramco after completion of work.

C. Storage:

1. The equipment shall not be stored outdoors. Equipment, including in-line


equipment, shall be stored in dry permanent shelters, and shall be adequately
protected against mechanical damage. Any damaged equipment shall be
repaired by the Contractor at his own expense. Equipment that may have
JO/EWO

been subjected to possible water damage shall be thoroughly dried out and
tested as required by Saudi Aramco. This additional work shall be at the
DATE

expense of the Contractor. Failure of the equipment to meet the original


specifications shall require the equipment to be replaced at the expense of the
Contractor.
NO.
REV

DISCIPLINE
ENGINEER D. Handling:

DATE:
1. Install in accordance with manufacturer's instructions, locate as shown on the
PROJECT
ENGINEER Drawings, and as approved by Saudi Aramco.

DATE:
CERTIFIED
PART 2 - PRODUCTS
DATE:
CONSTRUCTION
2.01 Manufacturers
AGENCY

A. Instrumentation manufacturer shall be Saudi Aramco approved as per SAES-J-002.


DATE:
Control panel manufacturers shall have minimum 8 years experience in fabricating
OPERATIONS
similar control panel.

DATE: 2.02 Design Data


CONTROL NUMBER
VERIFICATION

A. Electrical components: To operate on 120 v, single-phase, 60 Hz current, except as


EDSD

otherwise noted in Specifications or Drawings.


DATE:
BY:

B. Provide auxiliary relays and other items necessary for proper operation and
CERTIFCATION

APPROVAL/CERTIFICATION REQUIREMENTS,

integration into the designed system.


THIS INDICATES THAT REV. NO.__________
ICATE
00
OF THIS DRAWING IS COVERED, FOR ALL

BY DRAWING COMPLETION CERTIFICATE


10-00167-0007-001 _
(DCC) NO. ____________________
REVISIONCERTIFI

Section 13300

Project Specification DWG.TYPE PLANT NO. INDEX DRAWING NO. SHT.NO. REV.NO.
REVISION

Construction Specifications DOC 5


Shaybah Industrial Support Facilities
B54 A CS-10-00167
of 00
Shaybah SAUDI ARABIA BI / JO: 10-00167-0007 7
EDSD/2616-0399.doc
669B: KH1134 Specs
Saudi Aramco 2616-ENG (03/99)
PMT OPRNS
SAUDI ARABIAN OIL COMPANY

THIS DRAWING AND THE INFORMATION CONTAINED HEREIN ARE THE SOLE PROPERTY OF SAUDI ARAMCO. NO REPRODUCTION IN FULL OR IN PART SHALL BE OBTAINED FROM THIS DOCUMENT WITHOUT THE WRITTEN CONSENT OF ITS OW NER.
C. Provide fuses or switches, required by instrumentation manufacturer, for equipment.
ENGG CERT

D. Instrument identifying nameplates of engraved lamicoid, mounted below panel-


mounted units and attached to field-installed units.

2.03 Local Control Panel

A. Conforming to 34-SAMSS-821 for outdoor locations, the local control panels


enclosure shall be NEMA-4X. Constructed of 316L stainless steel to dimension as
required for properly accommodating all devices shown on drawings.
DESCRIPTION

B. Instruments and Accessories: Mounted, wired or piped to terminal strips and properly
identified to provide ease of field connection. Cover mounted devices shall be wired
with blinded harnesses to permit full door opening.

C. Provide a stand-off removable panel at the back for mounting of devices. All internal
relays, terminal blocks, circuit devices and items shall be installed on mounting rails
where available from manufacturer.

D. Refer to general arrangement, wiring and P&ID Drawings and instruments


specification sheets for items and devices to be mounted on the panel.
JO/EWO

2.04 Instruments
DATE

A. Instruments shall be supplied as specified on instruments specification sheets and in


compliance with Saudi Aramco standards listed under section 1.03 above.
NO.
REV

DISCIPLINE
ENGINEER 2.05 Nameplates

DATE:
A. 1/8 in. thick bakelite laminated black core with white finish per Library Drawing DD-
PROJECT
ENGINEER 950025.

DATE: 2.06 Special Tools


CERTIFIED

A. A complete set of tools shall be provided with the equipment packed within durable
DATE:
CONSTRUCTION
high-density polyethylene cases.
AGENCY

2.07 Spare Parts and Test Equipment


DATE:
OPERATIONS
A. Test Equipment:

DATE: 1. Test equipment, including Technical Manuals, carrying/storage cases, battery


CONTROL NUMBER

charger, (where applicable), shall be provided. Special tools, calibration


VERIFICATION

fixtures, card/cord extenders, patch-cords, and test leads which are not
EDSD

specified but which are necessary for checking the field operation of the
DATE:

equipment, shall also be provided in this section.


BY:
CERTIFCATION

APPROVAL/CERTIFICATION REQUIREMENTS,
THIS INDICATES THAT REV. NO.__________
ICATE
00
OF THIS DRAWING IS COVERED, FOR ALL

BY DRAWING COMPLETION CERTIFICATE


10-00167-0007-001 _
(DCC) NO. ____________________
REVISIONCERTIFI

Section 13300

Project Specification DWG.TYPE PLANT NO. INDEX DRAWING NO. SHT.NO. REV.NO.
REVISION

Construction Specifications DOC 6


Shaybah Industrial Support Facilities
B54 A CS-10-00167
of 00
Shaybah SAUDI ARABIA BI / JO: 10-00167-0007 7
EDSD/2616-0399.doc
669B: KH1134 Specs
Saudi Aramco 2616-ENG (03/99)
PMT OPRNS
SAUDI ARABIAN OIL COMPANY

THIS DRAWING AND THE INFORMATION CONTAINED HEREIN ARE THE SOLE PROPERTY OF SAUDI ARAMCO. NO REPRODUCTION IN FULL OR IN PART SHALL BE OBTAINED FROM THIS DOCUMENT WITHOUT THE WRITTEN CONSENT OF ITS OW NER.
PART 3 - EXECUTION
ENGG CERT

3.01 Installation

A. Use Saudi Aramco Standard Drawings as per SAES-J-006 in the installation details in
addition to the manufacturer's recommendation.

3.02 Field Calibration

A. Calibrate instrumentation in presence of Saudi Aramco Representative.


DESCRIPTION

B. Adjust secondary functions such as alarm actuation and pacing during initial
calibration, and demonstrated after system is placed in service.

3.03 Performance Test

A. Calibrate all process sensing instruments using test equipment.

B. Adjust functions such as alarm actuations and control during initial calibration, and
demonstrate correct operation after system is placed in service. Document for records
and submit to Saudi Aramco.
JO/EWO

C. System energizing not allowed, except when Manufacturer tests system, until
DATE

approval of certified statement of installation by Saudi Aramco.

3.04 Acceptance Testing


NO.
REV

DISCIPLINE
ENGINEER A. After complete construction of project, Contractor shall provide test for all integrated
system operating automatically without shut down or failure. Interlocks, alarms,
DATE:
automatic speed change etc. in presence of manufacturer's service engineer and
PROJECT
ENGINEER Saudi Aramco Representative. All instruments and systems must work properly at
that time without any heating, overloading as specified and must perform required
DATE: service satisfactorily otherwise Contractor shall remove and replace the equipments
CERTIFIED
at his own cost.
DATE:
CONSTRUCTION
AGENCY - END OF SECTION -
DATE:
OPERATIONS

DATE:
CONTROL NUMBER
VERIFICATION
EDSD

DATE:
BY:
CERTIFCATION

APPROVAL/CERTIFICATION REQUIREMENTS,
THIS INDICATES THAT REV. NO.__________
ICATE
00
OF THIS DRAWING IS COVERED, FOR ALL

BY DRAWING COMPLETION CERTIFICATE


10-00167-0007-001 _
(DCC) NO. ____________________
REVISIONCERTIFI

Section 13300

Project Specification DWG.TYPE PLANT NO. INDEX DRAWING NO. SHT.NO. REV.NO.
REVISION

Construction Specifications DOC 7


Shaybah Industrial Support Facilities
B54 A CS-10-00167
of 00
Shaybah SAUDI ARABIA BI / JO: 10-00167-0007 7
EDSD/2616-0399.doc
669B: KH1134 Specs