Watercourse Design
Watercourse Design
Watercourse Design
What is designing
Objectives of watercourse designing
Causes of water loss in watercourse
Benefits of watercourse improvement
Quality of designing
Introduction
Pakistan is blessed with various natural resources including land and water. Water is a
scarce resource which is the life blood of our agriculture. The water resources of Pakistan have
been estimated up to 142 MAF. Only 42 MAF is available for agricultural production. A huge
amount of water is lost in our deteriorated irrigation system, causing water-logging and salinity
problems in our agricultural land.
Irrigation system of Pakistan consists of barrages, headworks, main canals, branch canals,
distributaries, minors and watercourses. Approximately 37 MAF water is lost in watercourses
only. Keeping in view the huge water losses, the government launched a On farm water
management project in 1977. Later on various OFWM projects were implemented with the help
of different donor agencies. The targets set forth for these projects were successfully achieved
and about 23,000 watercourses out of 58,000 watercourses have been renovated in Punjab so far.
Various studies have been conducted for impacted evaluation of OFWM activities including
watercourse improvement. The result of these studies was so encouraging that it paved the way
for improvement of all watercourses throughout the country.
Now the Government of Pakistan has approved nationwide project captioned as “National
Program for Improvement of Watercourses in Pakistan”. It is anticipated that 28,000
watercourses will be improved under said program during a period of four years.
Watercourse Design Objectives
Purpose of watercourse is to convey water from the canal outlet to the farm. The watercourse
design objectives include:-
- To achieve maximum conveyance efficiency.
- To prevent siltation.
- To prevent erosion.
- To attain the full supply level in watercourse high enough to provide a proper working
head to the command area.
- To avoid submergence of mogha or canal outlet.
TERMINOLOGIES
Non modular outlet An outlet in which discharge depends upon the hydraulic head
difference between FSL canal and FSL watercourse. E.g.
scratchly outlet, pipe outlet, in submerged condition
Semi modular outlet An outlet in which the discharge depends upon water level in
canal only, and is independent of water level in watercourse.
E.g. open flume, adjustable orifice outlets.
LRTB The elevation of lower side of roof block fixed in AOSM outlet
Discharge Volume of water flow per unit of time. Also known as flow rate
Watercourse Channel which conveys water from canal to the field for
irrigation purpose
FSL FSL (Full Supply Level) represents water surface elevation
Slope The difference in elevation per unit length (drop per unit length)
Flow depth Difference between water surface level and bed level of a
channel
Freeboard The height of berm above the maximum designed water surface
Check Structure Structure that heads up the FSL up to elevation needed for the
turnout
Drop Structure used to drop water at lower level and dissipate its
excess energy.
Syphon Structure that carries the discharge of one channel beneath the
bed of another channel
Hydraulic radius R Ratio of flow area (A) to wetted perimeter (P) R=A/P It
expresses the shape of the channel.
Roughness coefficient The resistance or friction between water and channel. Also
known as Manning’s ‘n’
Conveyance / Ratio of the water delivered from the canal to water delivered to
delivery efficiency the farm
Right of Way The space fixed by the Government for a community
watercourse along its sanctioned route.
Basic Hydraulics
Data required for watercourse design
Basic Hydraulics.
Watercourse or channel cross-section Nomenclature.
Before starting with designs, it is necessary to define the nomenclature of watercourse elements
and dimensions.
A. Trapezoidal Channel
b = Bottom width
d = Flow depth
B = Width at water surface = b + (2 x z x d)
D = Total depth of watercourse = d + FB
FB = Free board
BW = Bank width
Z = Side slope, the slope of the sides as the ratio of horizontal to vertical,
shown as Z:l. (such as 1:1. 1.5:1, 2:1,etc.)
FSL = Full supply level (design water surface)
TW = Top width of the ditch = b + (2 x Z x D)
B. Rectangular Channel
Hydraulic formulas:
The basic hydraulic formula for channel capacity is: Q = A x V.
Manning's Formula for velocity is: V = [R2/3 x S1/2 ] / n
By combining these two formulae, channel capacity or quantity of flow can be determined by:
Q=[A x R2/3 x S1/2 ]/n
Where:
Q = Quantity of flow in cubic meters per second
V = Mean velocity in meters per second
A = Flow area in square meters
P = Wetted perimeter in meters
R = Hydraulic radius in meters = A/P
S = Slope or energy gradient in meters drop per meter length
n = Roughness coefficient
Trapezoidal watercourse: A=bxd+Zxd2 & P = b + 2d [Z2 + l]0.5
Rectangular watercourse: A=bxd & P=b+2d
Channel conditions which have the greatest influence on the "n" value are:
2. vegetation,
4. channel alignment,
6. obstructions.
- For earthen channels an "n" value of 0.035 is used to determine capacity (cross-section)
and 0.025 to check for non-erosive velocity.
- For lined channels, “n” value of 0.018 is used for concrete and plastered brick masonry.
The discharge at a given section in the channel depends not only on the roughness coefficient
(n). the longitudinal slope (S) and the cross-section area (A), but also on shape of channel, as
expressed by its hydraulic radius (R).
A deep-narrow channel and a wide-shallow channel may both have the same cross-sectional
area. but the hydraulic radius and consequently the discharge will be different. The cross-section
with the larger hydraulic radius (less wetted perimeter) is the hydraulically optimum cross-
section. Therefore rectangular and trapezoidal shapes are usually used. The following width and
flow depth ratios give hydraulically optimum cross-sections.
A structure such as a nucca or culvert in a watercourse results in headloss. This causes water to
back up, upstream, of the structure. Usually the headless is not great enough to affect the overall
hydraulics of the watercourse. When the structures are so close, that the backwater curve reaches
the next structure upstream the headloss becomes significant and additive.
As a rule of thumb if the structure headloss is 50% (or less) of the headloss due to slope between
the structures, the back water curve should not reach the upstream structure.
Assume a slope of 0.0003 meters per meter and an average check spacing of 330 meters, then
headloss due to slope is 10 cm. (330 x 0.0003). Using a headloss of 3 cm. (30% of the 10 cm.
headloss) the capacity of round check structures would be as follows:
Dia. M aximum capacity with
A 3 cm headloss
in. cm lps
12 31 45
15 38 70
18 46 105
20 51 130
24 61 180
To introduce the parameters to be considered while finalizing the design of a watercourse so that
the design may be:-
- Technically feasible
- Economically viable
- Socially acceptable
Capacity Requirements.
The design capacity of the channel should be determined by considering the measured discharge,
sanctioned discharge by the Irrigation Department including any special quota and additional
water from tubewells if any. Earthen channels should be designed with sufficient capacity to
carry the required flows at slower velocities that develop under greater retardance conditions due
to grass weeds etc.
Velocities.
Flow velocities in earthen channels should be non-erosive for the soil material in which it is
constructed. Erosion will occur if the velocity is too high. For checking velocities, the lower “n”
value of the newly constructed or cleaned channel should be used. Drop structures may be
required to reduce the channel slope and velocity. The maximum permissible non-erosive
velocities for various soils are given following Table. The maximum design velocity of concrete
or brick lined channels is 2.5 meters per second. Fast velocities may cause cavitation that causes
pitting or wearing away of the lining.
More freeboard may be provided if required for berm settlement, siltation or expected
poor maintenance.
The design water surface elevations should be high enough at turnouts to provide required flow
onto the fields. A minimum working head of 10 to 15 cms should be provided at each turnout for
the highest field elevation it commands.
Seepage loss per 1000m (%) Seepage loss per 1000m (lps)
A) Fine textures soil – (clays-clay loams)
B) Medium textured soils – (loams-silts)
C) Coarse textured soils – (sandy loams)
DESIGN PROCEDURE
Q = K Bt G3/2
Where Q = Discharge of outlet (in LPS)
K = Constant
Bt = Width of throat (in m)
G = Depth of water in canal above crest of mogha (in m)
K Bt
1600 0.06 to 0.09 m
1630 0.09 to 0.12 m
1650 > 0.12 m
AOSM Outlet
Q = 4030 Bt Y (Hs)1/2
Where Q = Discharge of outlet (in LPS)
Bt = Width of throat (in m)
Y = LTRB – Crest of mogha (in m)
Hs = FSL Canal – LTRB (in m)
Pipe & Scratchly Outlets
Q = Cd A (2gH)1/2
Where Q = Discharge of outlet (in m3 /sec)
Cd = Coefficient of Discharge
A = Cross sectional area of outlet pipe (in sq.m)
= 3.14 D2 /4 D = diameter of pipe (in m)
g = Acceleration due to gravity = 9.81 m/sec2
H = Difference in FSL canal & FSL watercourse (in m)
(e) Using suitable measuring devices, take discharge measurement at head, middle
and tail of watercourse to determine the extent of water losses.
(f) Determine the total discharge for design purpose by adding the mogha discharge,
any special quota and tubewell discharge if any.
(g) Prepare discharge calculation sheet and record the relevant data in this sheet.
DESIGN STEPS
1. To Determine Maxi FSL below Mogha
Maximum FSL below mogha can be computed for different types of mogha as follow:
Plot the maxi. FSL below mogha and required FSL for each turnout on the profile map.
The tentative design surface profile can be fitted to these elevations. Water surface profile
must maintain downward slope.
Place a long straight edge on the profile map and draw best fitted line, starting at or
below the maximum FSL below mogha keeping the line on or above the required FSL at
each turnout. This will result a design water surface profile. It is desirable to keep the
slope as uniform as possible.
In some cases it may not be possible to maintain a downward slope from the maximum
FSL below mogha to meet the required FSL at each turnout. In these cases the water may
have to checked up with temporary submergence of the mogha or the high field may have
to be lowered.
If either of these two alternatives are not feasible the field may have to be left un-
commanded.
V = R2/3 . S1/2
n
For Rectangular Section
A = bd P = b+2d
A = bd + zd2 P = b + 2d z2 +1
Q = AV
= A (A/P)2/3 . S1/2
n
In equation (1) Q, S and n are known but only b & d are two variables for rectangular
section; whereas b, d and z are three variables for trapezoidal sections and are required to be
determined.
Assume the value of b and calculate d accordingly. Velocity should be computed . Check
whether it falls in the permissible range or not
The bed level is determined by subtracting d from designed FSL.
Use of Nomographs.
The nomographs are direct solutions to Mannings equation and can be used to find channel
velocity and cross section requirements against the given value of discharge, slope. Flow depth
and velocity can be found at certain value of bottom width.
Example.
Given parameters for earthen channel with Side slopes 1:1 and b = 0.40.
S = 0.0005 and Q = 90 lps
Find flow depth and velocity
Refer to figure A8 for solution.
Find 90 on the left scale for discharge
Read across to the vertical line for a slope of 0.0005 on the bottom
The intersection is at a flow depth of 0.45m and a velocity of about 0.30 m/sec
Location of turnouts is shown on the map. But the location of check structure is to be
determined. By utilizing the freeboard a check can raise FSL high enough to save upstream
turnouts without over toping.
L = F .B / 2 S
Where L Distance (m) upstream a check structure can save
F.B = Freeboard (m )
S = Slope of watercourse (m/m)
Example:
FB = 0.15 m
S = 0.0004 m/m
L = 0.15 x 2 ( 0.0004) = 187.5 m
Therefore the check structures can serve turnouts as far as 188 upstream
Material Estimate
An estimate of material quantities needed for construction should be made. Estimate of the lined
watercourse will be based on the quantity of masonry in volume unit (m3 ) Then an estimate for
bricks, cement, sand etc can be determined on following basis:
One cubic meter of bricks masonry contains 450 bricks and 0.23 m3 mortar
Plaster 1 cm thick = 0.01 m3 per square meter of planned area
These estimates do not include allowances for losses. Losses can vary considerably from place to
place for a given situation. Therefore, the decision is left to the executing agency. OFWM
standards used to estimate watercourse construction material i.e. bricks, cement and sand
Cement sand ratio both for masonry and plaster work 1:4
Maximum material requirements per m3 masonry volume including losses are
A deep narrow channel may both have the same cross-sectional area but their hydraulic
radius and consequently discharge will be different.
The cross-section with huge hydraulic radius is more efficient and thus hydraulic optimum
cross-section. The following width flow depth ratio gives most hydraulically optimum cross-
section.
Rectangular
b=2d
Trapezoidal
Side Slop
1 : 1 b = 0.08 d
1.5 : 1 b = 0.69 d
2 : 1 b = 0.5 d
- Preparation of Cost Estimates & Record keeping
o Preparing Inventory
o Civil Work Dimensions
o Description of Works
o Calculation of cost per unit volume
o Government / farmer cost sharing mechanism
o Material Procurement Procedure
o Record of Water Users Association
Preparation of Materials & Cost Estimates
After completion of social mobilization, watercourse surveying and designing, the material &
cost estimates are required as a financial component. Following steps are taken in this regard.
1- Preparing Inventory
For preparing cost estimates, the following information is required; watercourse no., village,
tehsil, total length, percentage of lining, length to be improved. It is the first part of cost estimate.
The dimensions of the channel are dependent upon the design. Design is prepared for lined
section and katcha section. The dimensions for culvert and other structures are as given in the
drawing in manual. The following dimension for lined are required.
3- Description of works
The detail of civil works which have to be executed is required. In this section the following
details are required;
2- Total nakkas and size to be installed, unit volume and total volume
3- Total culverts to be constructed and their size, unit volume, and total volume
5- Other structures, sluice drops, siphons, their unit volume or data volume
9- Cement, total volumes multiplied by 1.87 will give the quantity of cement
required in number of bags.
10- Sand, total volume multiplied by 0.26 gives the total sand required in cubic
meters.
12- To calculate the rate/m3 , the total cost is divided by the total volume.
In the PC-I of National Program for Watercourse Improvement, the Government and Farmers
share is 64:36. 64% cost will be equal to the total material cost. This share has to be borne by the
Government. The 36% cost will be borne by the farmers in shape of katcha improvement and
skilled and unskilled labor. The katcha improvement work will be 18%. It is presumed that the
katcha work will be equal to 18% of the total cost estimate. The remaining 18% will be the labor
charges for lined section of skilled and unskilled labor. The narrated form can be translated by
the givien example;