Method Statement For LV Cable Replacement Works

Download as pdf or txt
Download as pdf or txt
You are on page 1of 6

PROJECT: BLANKET AGREEMENT

CLIENT: Al AIN ZOO

CONTRACTOR: HYDROPOWER ENERGY & GENERAL CONSTRUCTION LLC.

METHOD STATEMENT FOR


REPLACEMENT OF DAMAGE LV
CABLE NEAR OPERATION
BUILDING FROM SMDB TO
ELECTRICAL ROOM

REV.-00 METHOD STATEMENT DOC. No.

DATE: 13.04.2023
INSTALLATION OF LV CABLES

Prepared By: Reviewed By: Checked By: Approved By:


Mohd Khurram

Method Statement for Replacement of Damage LV Cable with new Cable. 1


INDEX
1. PURPOSE & SCOPE
2. REFERNCE.
3. DEFINITIONS
4. RESOURCES

4.1 Materials & Approval.


4.2 Equipment & Tools.
4.3 Human Resource.
5. SAFETY PRECAUTIONS

5.1 Emergency Procedures.


5.2 Accident & Incident Reporting
5.3 Action In The Event of an Accident
5.4 First Aid.

6. PROCEDURE FOR INSTALLATION OF LV CABLES

6.1 Survey
6.2 Cable Pulling & Installation
6.3 Termination
6.4 Testing & Commissioning

7. RESPONSIBILITIES

Method Statement for Replacement of Damage LV Cable with new Cable. 2


1. PURPOSE & SCOPE

This method statement is for the Replacement of existing damage LV cable and
Installation of new LV Cable as per Order from client and shall be treated as a guide line
for the detailed planning, safety and execution of the work.

This is also to ensure that all information, material, tools, equipment, manpower and
adequate supervision are available during execution of this work and that work steps are
analyzed and all safety measures as per AADC HSE Regulations are taken so that work can
be done in a safe and appropriate manner.

2. REFERENCE
1. Contract Specifications
2. Cable route drawings.
3. As built drawings of existing underground installations.(If any).
4. Any other instructions issued by local authorities.

3. DEFINITIONS

3.1 MS –Method Statement


3.2 GS- General Specification
3.3 PPE –Personal Protective Equipment
3.4 ITL - Inspection Testing Laboratory
3.5 ITP - Inspection Testing Plan
3.6 QA- Quality Assurance.
3.7 HSE - Health, Safety and Environment

4. RESOURCES

4.1 Materials& their Approval

Following materials will be used after getting approval from client..

 LV Cables.
 Earth Cables
 Heat Shrinkable Cable Terminations.

Method Statement for Replacement of Damage LV Cable with new Cable. 3


4.2 Equipment & Tools

 Heavy Crane
 3 Ton Pickup
 Hydraulic Cable Cutter
 Hydraulic Crimping Tool
 Torque Wrench
 Cable Detector
 Spanner set
 Drilling & Grinding Machines
 Hand Showel and Pick axe
 Multimeters, Earth Megger etc.
 Screw Drivers & Connectors.
 Hand Crimping Tools & Cutting Pliers.
.
4.3 Human Resource
 Project Engineer
 Site Engineer-Electrical
 HSE Officer
 Supervisors
 Technicians
 AADC Approved Cable Jointers
 Labours

5. SAFETY PRECAUTIONS:

5.1 Emergency Procedures

In case of an emergency on site the following procedures will be used at site:

1. Method of communication will be provided at site for calling the emergency


services.

Method Statement for Replacement of Damage LV Cable with new Cable. 4


Emergency contact person:

(HEGE Safety Officer) -0529815188

Fire - 997
Police - 999
Ambulance - 998

5.2 Accident and Incident Reporting


All accidents and incidents will be reported to site supervisor and to the project
manager.
5.3 Action In The Event of An Accident
 Stay calm
 Inform the supervisor.
 For minor injuries use First Aid Box.
 Assist the injured person only if there are no further dangers to yourself and do
not move the injured person.
 If you witnessed the accident, provide information to the investigation team.

5.4 First Aid


First Aid facilities will be provided at site. These shall be utilized by personnel
working in the field in the event of minor injury whilst on the project. All injuries
sustained on the project shall be reported to the Supervisor who will report to the
Project Manager.

6. PROCEDURE FOR INSTALLATION OF LV CABLES

The scope of works comprises manual site survey and installation of cable in existing
duct.
6.1 Survey

 Survey of the cable routes.


 Obtaining route approval for cables from the concerned authorities..

Method Statement for Replacement of Damage LV Cable with new Cable. 5


6.2 Cable Pulling & Laying

 As cable pulling is inside the duct so cable pulling will be done manually.
 When pulling through areas with corners, through road crossings and through
existing ducts, special care shall be taken.
 Provide end caps for both end of cut cable and identification also to be done

6.3 Jointing & Termination

 To allow easy jointing & Termination works, sufficient cable lengths have
to be provided. Joint/Termination shall be done as per manufacturer’s
instructions by AADC approved cable jointer.

6.4 Testing & Commissioning

 Testing and commissioning of the cables shall be done as per the Test Procedures.
 7. RESPONSIBILITIES

Project Engineer shall ensure that all tools & plants are made available sufficiently
in advance for the commencement of work. He shall make necessary store facilities
to keep all these materials in a safe & clean environment.
Site Engineer (Electrical) who shall ensure that this procedure is fully implemented
including documentation till completion. He shall raise Inspection Request at each
step, where ever applicable.

HSE officer should ensure that all safety precautions are taken as per AADC HSE
Policy and are implemented accordingly.
Project Engineer shall employ Supervisor‘s professionals with good experience for
all installation activities, ensuring best workmanship while taking into account all
required safety precautions.
It is every site workers duty to properly wear the protective equipment provided and
obey all safety rules. He must also perform the work as described in the method
statement procedure.

Method Statement for Replacement of Damage LV Cable with new Cable. 6