Tripartite Report
Tripartite Report
Tripartite Report
1. Introduction
I. Contract Data
Region: SNNP
Project Length: 70 Km (25km Main Road, 23km Compound Road, Airfield 3.12km
Project Start & End Points: Dimtu Town (330 Km from Addis Ababa) and Bilate
PLC
Time Elapsed (As of July 14, 2023): 456 Calendar Days (41.64%)
Page 1 of 15
2. MOBILIZATION
I. Personnel Mobilization
a) Consultant’s Mobilization
S. S.
Name of Staff Position Name of Staff Position
No No
FULL-TIME STAFFS
INTERMITTENT STAFFS
Page 2 of 15
b) Contractor’s Key Manpower Mobilization
S. No. Position Descriptions Total Available Number
Project Manager 1
1
Office Engineer Head 1
2
Construction Engineer 1
3
Project Administration 1
4
Material Engineer 1
5
Office Engineer 1
6
7 Junior Office Engineer 1
Page 4 of 15
d) Material Mobilization and Production
Produced
S. Material Total Consumed Available on
Unit or
No Description Required Up to date Stock
Supplied
1 Subbase M3 257,660.00
4 Chipping M3 740.99
Bitumen (AC
6 Ton 8,587.98
60/70)
Bitumen (AC
7 Ton 108,810.01
80/100)
8 MC 30 Lit. 27,100.01
Page 5 of 15
3. Facilities and Administration
Page 6 of 15
4. Health and safety
i) Health and Safety Report from Contractor Including STD/HIV/AIDS
5. Public Coordination
i) Site Handover, land acquisition
ii) Traffic Management, Diversions
iii) Coordination with local authorities, key stakeholders
Physical Accomplishment
Previous Total of
Previous This Cumulative Total To-
Months of Previous
2014 FFY Month of 2015 EFY date
2015 EFY Months
% Km % Km % Km % Km % Km % Km
Plan 1.87 1.31 23.32 16.32 25.19 17.63 4.12 2.88 27.44 19.21 29.31 20.52
Actual 0.16 0.11 13.06 9.14 13.22 9.25 1.85 1.29 14.91 10.44 15.07 10.55
Page 7 of 15
ii) Financial Accomplishment (June 2023)
Previous Total of
Previous This Cumulative Total To-
Months of Previous
2014 FFY Month of 2015 EFY date
2015 EFY Months
Plan 1.87 31.95 23.32 472.29 25.19 472.29 4.12 70.24 27.44 467.99 29.31 549.49
Actual 0.16 2.73 13.06 225.46 13.22 225.46 1.85 31.54 14.91 254.27 15.07 257.00
A/P
8.54 56.00 52.47 44.90 54.33 51.41
(%)
From Plan
From Time
Master WP Revised WP
Page 8 of 15
iv) Progress by Activity
a) Earthworks
Page 9 of 15
Airfield - Earthworks
Station
S. No. Work Description Side Remark
From To
1 Clearing and grabbing
2 Road bed preparation
3 Excavation Works
0+500 0+660 RHS On Progress
3.1 Removal of unsuitable material 1+400 1+600 RHS Completed Partially
1+600 1+800 FW On Progress
0+680 1+400 FW On Progress
3.2 Common Excavation 1+400 1+600 LHS Completed Partially
1+800 2+000 FW On Progress
3.3 Hard Rock/Boulder Excavation
4 Undercut Replacement Fill
0+500 0+600 15m Completed
4.1 1st layer embankment fill (Replacement)
0+500 0+640 45m Completed
0+300 0+500 15m Completed
4.2 2nd layer embankment fill (Replacement)
0+500 0+540 15m Completed
0+000 0+300 30m Completed
4.3 3rd layer embankment fill (Replacement)
0+300 0+500 30m Completed
0+000 0+100 15m Completed
0+000 0+140 15m Completed
4.4 4th layer embankment fill (Replacement)
0+300 0+500 15m Completed
0+300 0+500 15m Completed
4.5 5th layer embankment fill (Replacement) 0+100 0+300 15m Completed
4.6 6th layer embankment fill (Replacement) 0+100 0+300 15m Completed
Page 10 of 15
b) Minor and Major Structures Construction
Secondary
Grouted stone 0+000 3+300 Not yet Started LHS
pitching ditch
(Runway)
Masonry ditch Not yet Started
0+000 1+300 RHS & LHS
(Runway)
Masonry ditch Not yet Started
0+000 0+465 RHS, LHS & Rear
(Apron)
Town Section Not yet Started
0+000 2+400 Dimtu Town Section
U-Ditch
Page 11 of 15
c) Precast Production
7. Outstanding Issues
i) Potential Delays, Early Warnings, Causes and Mitigation Measures
Station
Current Status Remarks
From To
Page 12 of 15
8. Appointment of Sub contractors
▪ Not done yet
Page 13 of 15
9. Employment Opportunities:
Page 14 of 15
10. Information Required
▪ Final design review has been on progress.
11. Quality Management, Procedures and Reporting
▪ Consultant’s progress and comments on performance appraisal systems.
12. Quality Control
▪ Monthly laboratory report summarizing test result from on site, site laboratory or
external laboratories.
▪ Test result failures, causes, rectifications and avoidance measure.
13. Environmental Management
▪ Environmental Management Plan, Preparation, management inspection and
audits.
14. Financial Management
a) Up to June 2023, the project has been generated 09 IPCs.
15. Claim Status
▪ There are no recorded claim statuses so far.
16. Other Matters
▪ RoW Matters (Public utilities in military compound)
Page 15 of 15