Irussor Aor 2021 Draft
Irussor Aor 2021 Draft
Irussor Aor 2021 Draft
भारत सरकार
GOVERNMENT OF INDIA
रे ल मंत्रालय
MINISTRY OF RAILWAYS
इं जीननयररग नवभाग
Engineering Department
2021
Draft IR Unified Standard Analysis of Rates - 2021 General and Operating Instructions
1.3 Design Mix Cement Concrete of all grades from M-15 to M-40 will be paid at same rate irrespective of grade mentioned in the
item. Grade mentioned is for guidance purpose. However, grade of RCC to be used at site shall be mentioned in the BOQ.
1.4 Automatic digital weigh Batching, mixing and placing, preferably mobile RMC plant shall be used for design mix concrete.
Concrete mixer shall be used for small quantity for nominal mix only with the permission of Engineer-in charge. Placement of
concrete shall be done by concrete pump in general.
1.5 Cost of Admixture (plasticizer / super-plasticizer) is included in the item of design mix concrete.
1.6 Payment for cement shall be made extra wherever mentioned in the item for the quantity as per approved design mix subjected to
minimum and maximum limit as prescribed in IS 456. For nominal mix and other misc items, it shall be as per standard
consumption enclosed separately with this USSOR.
1.7 Cost of shuttering, wherever required, shall be paid separately and is not included in the rate of item except where specifically
mentioned otherwise. Shuttering shall be paid only for the shuttering area coming in contact with the concrete surface.
1.8 For steel fabrication work, the cost of welding/riveting has been incorporated in the item rate and no addition on nominal weight of
the sections as specified in the drawings shall be applicable on account of welding/riveting. HSFG bolts, where used, shall be
payable.
1.9 The rate of an item includes:
(i) Cost of all labor, materials, tools & plants, machinery, transportation to the site of work, all lead & lift, handling, re-
handling, erection, testing, supervision & maintenance, unless mentioned specifically otherwise in the description of an
item, required for design, fabrication, execution and testing the work conforming to all applicable codes, specifications,
manuals and guidelines.
(ii) GST & other taxes, royalties, duties, cess, levies or any other fees that may be payable under any Central Government,
State Government or other Local Bodies Acts or Rules, mandatory insurance, profit etc.
1.10 Uniform rate of GST, apllicable for works contract, @12% has been adopted for all items while arriving at the Rate.
2. Operating Instructions
Numbering System Of SOR Items –
2.1 The system of numbering SOR items has been adopted for easy identification of item and linkage between item number &
description of item. Each Item number of SOR consists of 6 numeric digits, as detailed below:
2.1.1 First 2 digits (left side) indicate Chapter no. e.g. from 01 to 21.
2.1.2 Next one digit indicates Sub-Group within the Chapter.
2.1.3 Next 2 digits are Main Item nos. within one Sub-group.
2.1.4 Next one digit, i.e. right-most digit indicates Sub-item within the main item.
Indian Railways Unified Standard Schedule Of Rates (Formation Works, Bridge Works and P.Way Works)
110 Hire charges of grout pump with agitator and accessories Hour 0110 500.00
111 Pulse Echo Test (PET) for integrity testing of piles with contractor’s men, materials and Each 0111 2,000.00
machines. The rate includes cost of Inspection of site, preparation of pile head and any other
unforeseen cost required for the test, submission of reports in triplicate as per satisfaction of
the Engineer in Charge at site.
112 Hire Charges of Hydraulic Jack of 50 t capacity for lateral load testing of piles Day 0112 2,000.00
113 Hire Charges of Hydraulic Jack of 100 t capacity for lateral load testing of piles Day 0113 5,000.00
114 Hire charges for OEW flat jack of 100 tons capacity for longitudinal slewing of girder from both Each 0114 2,500.00
sides
115 Hire Charges of CNC gas cutting Machine Day 0115 4,500.00
116 Hire Charges of CNC drilling machine - 14 to 50mm dia, 100mm thickness, set of spindle - 2 Day 0116 14,000.00
sets, accuracy +/- 0.03mm.
117 Hire Charges of MMAW machine ( Manual Metal Arc Welding Machine) - 80 to 500 Amperes. Day 0117 25.00
118 Hire Charges of SAW machine - Tornado Make, current range - 150 to 1250 Amperes. Day 0118 7,500.00
119 Hire Charges of Angle grinder - 230mm dia. Disc, 6000 rpm, CP make. Day 0119 11.00
120 Hire Charges of Impact wrench - 32mm dia.Boit, CP Make. Day 0120 25.00
121 Hire Charges of Torque wrench - 150 kgf-m, Mekaster Make. Day 0121 10.00
122 Hire Charges of Power hack saw machine (Angle) Day 0122 25.00
123 Hire Charges of CNC end milling machine - (Horizonral Spindle), (1). Longitudinal Traverse of Day 0123 17,000.00
table (X-Axis) - 1500mm (2). Vertical Axis (Y-Axis) - 1000mm, (3).RAM Column Traverses (Z-
Axis) - 500mm.
124 Hire Charges of EOT, 10 ton Capacity, Reva Make Day 0124 1,500.00
125 Hire charges of Road Cum Rail vehicle for transporting Flash Butt Welding plant Day 0125 1,000.00
126 Hire Charges for Mobile Flash Butt Welding Plant Day 0126 55,000.00
128 Hire charges of USFD testing machine(B-Scan) Day 0128 2,500.00
129 Hire charges of USFD testing machine Day 0129 800.00
130 Hire changes for sand receiver and sand blasting pipes with gun and all accessories complete Day 0130 500.00
131 Hire charges for metalising gun with all accessories Day 0131 600.00
132 Hire charges of Arc Welding Machine 500 Amp Day 0132 300.00
133 Hire charges of gas cutter Day 0133 100.00
134 Hire charges of translamatic robotic welding machine Day 0134 5,000.00
135 Hire charges of Hot Paint machine Day 0135 150.00
Draft IR Unified Standard Schedule of Rates - 2021 Basic Input Data Sheet
156 Hire charges of Furnace blower to heat the rails for bending purpose including fuel and Day 0156 300.00
operator
157 Hire charges for wood sawing machine including fuel and operator Day 0157 1,500.00
158 Hire charges of Jib crane attachable and detachable to BFR/BRH Day 0158 300.00
159 Hire charges of Portal Crane (with Fuel & Driver) Hour 0159 250.00
160 Hire charges of Insulated Rail Dolly Day 0160 20.00
161 Hire Charges of Inflatable emergency tower light 400 Watt Day 0161 50.00
162 Hire charges of boat with boatmen Day 0162 1,200.00
163 Hire charges of 3.0 m x 3.0 m waterproof Tent Day 0163 200.00
164 Hire charges of Chair Day 0164 15.00
165 Hire charges of Table Day 0165 50.00
166 Hire charges of Laptop / Computer with software & Printer Day 0166 300.00
167 Hire charges for plotter up to A0 size Day 0167 700.00
488 Hire Charges of Halogen Lamps 500 Watt Nos. 0488 40.00
168 Soil Quality Class SQ1 suitable for sub grade of embankment as per RDSO Specifications Cum 0168 75.00
RDSO/2020/GE: IRS-0004
169 Soil Quality Class SQ2 suitable for sub grade of embankment as per RDSO Specifications Cum 0169 125.00
RDSO/2020/GE: IRS-0004
170 Soil Quality Class SQ3 suitable for sub grade of embankment as per RDSO Specifications Cum 0170 150.00
RDSO/2020/GE: IRS-0004
171 Blasting Powder Kg 0171 50.00
172 Blasting Fuse (Fuse Wire) Each 0172 20.00
173 Bentonite powder MT 0173 4,025.00
174 Doob grass Sqm 0174 29.00
175 Sarkanda/ Sarpat Sqm 0175 45.00
176 Grass sods Sqm 0176 46.00
177 Non-woven Needle Punched and Mechanically or Thermally bonded type Geotextile for use as Sqm 0177 90.00
Separator/Filtration for Railway formation as per RDSO Specification No. RDSO/2018/GE:IRS-
0004 - Part Iwith minimum strengths in Grab test, Trapezoidal Tear test and Puncture test of
700N, 250 N and 1800 N respectively
178 Non-woven Needle Punched and Mechanically or Thermally bonded type Geotextile for use as Sqm 0178 170.00
Separator/Filtration for Railway formation as per RDSO Specification No. RDSO/2018/GE:IRS-
0004 - Part I with minimum strengths in Grab test, Trapezoidal Tear test and Puncture test of
1750N, 800 N and 5800 N respectively.
Draft IR Unified Standard Schedule of Rates - 2021 Basic Input Data Sheet
226 Structural steel such as T, Angles, Channels and R S Joists conforming to Grade Quintal 0226 5,730.00
Designation E250; Quality "B0" as per IS:2062,
227 tructural steel such as T, Angles, Channels and R S Joists conforming to Grade Designation Quintal 0227 5,860.00
E 250; Quality "C" as per IS 2062
228 Structural steel such as T, Angles, Channels and R S Joists conforming to Grade Quintal 0228 5,500.00
Designation E250; Quality "BR" as per IS:2062,
229 Structural Steel such as T, Angles, Channels and R S Joists Grade Designation E350; Quintal 0229 6,000.00
Quality 'B0' as per IS 2062
230 M S Flat upto 10 mm thickness Quintal 0230 6,300.00
231 HSFG bolt with DTI Wasters conforming to IRS B1-2001 with latest Correction Slips Kg 0231 100.00
232 Mild steel rivets for steel girders Quintal 0232 6,540.00
233 Rivets (different sizes) for miscellaneous works. Kg 0233 54.50
234 Nut & Bolts with washers of all sizes Kg 0234 80.00
235 Holding down HTS bolts with plates, nuts etc. Quintal 0235 7,500.00
236 Cup Grinding Stone Each 0236 900.00
237 Drill Bit Each 0237 300.00
238 Electrodes for steel fabrication work Metre 0238 24.00
239 Welding Rod for Gas Metal Arc Welding Kg 0239 116.82
240 SAW Welding Wire Kg 0240 66.00
241 Flux for SAW Weldging Kg 0241 65.00
242 Cost of Drifts Each 0242 65.00
243 Cost of Service Bolts for assembling of Girders Each 0243 35.00
244 Shielding Gas (Co2) for fabrication works Kg 0244 69.00
245 Aluminum Sheet / Strips of various sizes & thickness Kg 0245 200.00
246 GI Sheet 1.50 mm thick Quintal 0246 4,600.00
247 Mild steel chequered plate MT 0247 42,500.00
248 Polyvinyl chloride sheet 400 micron. Sqm 0248 40.25
249 Z section sheet piles AZ 18-800 (Arcellor Mittal) or equivalent & bracing Quintal 0249 4,500.00
250 G.I. wire 4mm dia Kg 0250 70.00
251 MS Bolts & Nuts below 10mm dia Kg 0251 60.00
252 MS bolts & nuts more than 10 mm dia Quintal 0252 8,500.00
253 100mm channel shoulder 2.5 m long (Shuttering material) Each 0253 1,322.50
254 MS tube 40mm dia (Shuttering material) Metre 0254 293.25
255 Wall form Panel 1250mm x 450mm (Shuttering material) Each 0255 1,150.00
256 Adjustable telescopic prop 3m (2.02m-3.75m) (Shuttering material) Each 0256 1,265.00
257 Beam Clamp 300-380mm (450mm-1070mm) (Shuttering material) Set 0257 454.25
258 Cadmium plated full threaded steel screws (30mm x 4mm dia) (Shuttering material) 100 nos. 0258 35.65
259 Aluminium washer 2mm thick & 15 mm dia (Shuttering material) 100 nos. 0259 28.75
260 uPVC Pipe- type A ISI marked 110mm dia (working pressure 4Kg/cm2) Metre 0260 160.00
261 uPVC Pipe- type A ISI marked 160mm dia Metre 0261 350.00
262 GI Pipe 50 mm dia , B Class Medium duty Metre 0262 315.35
263 GI Pipe 100 mm dia , B Class Medium duty Metre 0263 731.55
264 Clamps and MS stays including bolts and nuts for 100mm dia pipe Each 0264 90.00
265 Clamps and MS stays including bolts and nuts for 50mm dia pipe Each 0265 53.00
266 C I grating 100mm x 100mm Each 0266 75.00
267 Etch primer as per IS: 5666 Litre 0267 340.00
268 Aluminium wire for spraying Kg 0268 219.93
269 Elastomeric bearing assembly consisting of 7 layers of Elastomer bonded to 6 nos. internal Each 0269 15,360.00
reinforcing steel laminates by the process of vulcanisation, complete with all components as
per drawing and Technical Specification (Each of 19200 Cu Cm)
Draft IR Unified Standard Schedule of Rates - 2021 Basic Input Data Sheet
282 200 MT Capacity Pot type bearing (Fixed type) assembly consisting of a metal piston Each 0282 45,025.00
supported by un reinforced elastomer confined in the pot with brass ring sealing making with
cast steel assemblies/fabricated structural steel assemblies duly painted with all components
complete as per drawings and Technical Specifications.
283 200 MT Capacity Pot Cum PTFE GUIDED(L)Bearing assembly consisting of a metal piston Each 0283 57,140.00
supported by a disc of un reinforced elastomer that is confined with in the metal cylinder and
sliding assembly with guiding arrangement to bear and resist the horizontal force in the desired
direction comprising of stain less steel attached to metal backing plate sliding in horizontal
plane over PTFE confined in recess (s)on the piston with internal seal (Brass laminated
rings),hard facings ,external seal & wiper seal etc complete with cast steel
assemblies/fabricated structural steel assemblies duly painted with all components complete
as per drawings and Technical Specifications.
284 200 MT Capacity Pot Cum PTFE Guided (T) Bearing assembly consisting of a metal piston Each 0284 52,805.00
supported by a disc of un reinforced elastomer that is confined with in the metal cylinder and
sliding assembly with guiding arrangement to bear and resist the horizontal force in the desired
direction comprising of stain less steel attached to metal backing plate sliding in horizontal
plane over PTFE confined in recess (s)on the piston with internal seal (Brass laminated
rings),hard facings ,external seal & wiper seal etc complete with cast steel
assemblies/fabricated structural steel assemblies duly painted with all components complete
as per drawings and Technical Specifications.
285 150 MT Capacity Pot Cum PTFE Bearing (Free end ) assembly consisting of a metal piston Each 0285 25,320.00
supported by a disc of un reinforced elastomer that is confined with in the metal cylinder and
sliding assembly comprising of stain less steel attached to metal backing plate sliding in
horizontal plane over PTFE confined in recess (s)on the piston with internal seal (Brass
laminated rings),hard facings ,external seal & wiper seal etc complete with cast steel
assemblies/fabricated structural steel assemblies duly painted with all components complete
as per drawings and Technical Specifications.
286 150MT Capacity Pot type bearing (Fixed type) assembly consisting of a metal piston supported Each 0286 29,985.00
by un reinforced elastomer confined in the pot with brass ring sealing making with cast steel
assemblies/fabricated structural steel assemblies duly painted with all components complete
as per drawings and Technical Specifications.
287 150MT Capacity Pot Cum PTFE Guided (L) Bearing assembly consisting of a metal piston Each 0287 38,745.00
supported by a disc of un reinforced elastomer that is confined with in the metal cylinder and
sliding assembly with guiding arrangement to bear and resist the horizontal force in the desired
direction comprising of stain less steel attached to metal backing plate sliding in horizontal
plane over PTFE confined in recess (s)on the piston with internal seal (Brass laminated
rings),hard facings ,external seal & wiper seal etc complete with cast steel
assemblies/fabricated structural steel assemblies duly painted with all components complete
as per drawings and Technical Specifications.
288 150MT Capacity Pot Cum PTFE Guided (T) Bearing assembly consisting of a metal piston Each 0288 35,760.00
supported by a disc of un reinforced elastomer that is confined with in the metal cylinder and
sliding assembly with guiding arrangement to bear and resist the horizontal force in the desired
direction comprising of stain less steel attached to metal backing plate sliding in horizontal
plane over PTFE confined in recess (s)on the piston with internal seal (Brass laminated
rings),hard facings ,external seal & wiper seal etc complete with cast steel
assemblies/fabricated structural steel assemblies duly painted with all components complete
as per drawings and Technical Specifications.
289 100MT Capacity Pot Cum PTFE Bearing (Free end ) assembly consisting of a metal piston Each 0289 16,350.00
supported by a disc of un reinforced elastomer that is confined with in the metal cylinder and
sliding assembly comprising of stain less steel attached to metal backing plate sliding in
horizontal plane over PTFE confined in recess (s)on the piston with internal seal (Brass
laminated rings),hard facings ,external seal & wiper seal etc complete with cast steel
assemblies/fabricated structural steel assemblies duly painted with all components complete
as per drawings and Technical Specifications.
Draft IR Unified Standard Schedule of Rates - 2021 Basic Input Data Sheet
294 300 MT Capacity Spherical free float bearing consists of an assembly of precision machined Each 0294 55,860.00
steel components with spherical concave and convex elements in its centre designed and
sized according the specific requirements .The bottom plate with a spherically concave top
face covered with a recessed PTFE sheet .The top component is a solid stainless steel plate
with spherically machined convex bottom face mating with concave curved surface . Sliding
assembly attached consists of a polished stainless sheet welded to the under side of top steel
plate slides on PTFE disc recessed or bonded to the upper surface of convex plate as
complete unit made up of with Mild steel/cast iron steel/Stainless steel conforming to IS 2062
Grade -B & IS 1030 Grade 280-520W or 340-570W,AISI 304/316 shall be used for the backing
plates with flat or curved surfaces, Stainless sheet shall be in accordance with AISI316L OR of
IS 6911 of minimum thick 3mm
295 300 MT Capacity Spherical Slide Guide (L) bearing consists of an assembly of precision Each 0295 79,400.00
machined steel components with spherical concave and convex elements in its centre
designed and sized according the specific requirements .The bottom plate with a spherically
concave top face covered with a recessed PTFE sheet .The top component is a solid
stainless steel plate with spherically machined convex bottom face mating with concave
curved surface . Sliding assembly with guiding system bear and transmit the horizontal force in
one direction and allowing the movement perpendicular to above (Longitudinal direction)
consisting of a polished stainless sheet welded to the under side of top steel plate slides on
PTFE disc recessed or bonded to the upper surface of convex plate as complete unit made
up of with Mild steel/cast iron steel/Stainless steel conforming to IS 2062 Grade -B & IS 1030
Grade 280-520W or 340-570W,AISI 304/316 shall be used for the backing plates with flat or
curved surfaces, Stainless sheet sha all respect as directed by the Engineer - in - charge.
Note: Rail cu
Draft IR Unified Standard Schedule of Rates - 2021 Basic Input Data Sheet
297 Single coil spring washer for bridge bearing for 36 mm dia bolts Each 0297 12.00
298 Hot melt Thermo plastic road marking paint Litre 0298 160.00
299 Luminous Paint as per RDSO's Spec. no. M&C/PCN/120-2011 Litre 0299 300.00
301 Bituminous Emulsion without Mica (IP no. 56192 and RDSO Specification no.P30-1996) Litre 0301 200.00
373 Exploratory drilling of boreholes of 150mm dia. in all type of soils except hard rock / large Metre 0373 796.00
boulders (boulder core more than 30cm), for collecting the undisturbed core sample including
refilling, reinstating surface and disposing off surplus material including use of mechanical rigs
with power operated winches as well as percussion/chieselling tool for advancing through
occasional seams of hard strata, where necessary with contractor's labour, tools, plants,
machinery, equipment, consumables etc., with all lead and lift complete as per specifications
and as directed by the Engineer-in-charge in Dry area 0-10m
374 Exploratory drilling of boreholes of 150mm dia. in all type of soils except hard rock / large Metre 0374 836.00
boulders (boulder core more than 30cm), for collecting the undisturbed core sample including
refilling, reinstating surface and disposing off surplus material including use of mechanical rigs
with power operated winches as well as percussion/chieselling tool for advancing through
occasional seams of hard strata, where necessary with contractor's labour, tools, plants,
machinery, equipment, consumables etc., with all lead and lift complete as per specifications
and as directed by the Engineer-in-charge in Dry area 10m-20m
375 Exploratory drilling of boreholes of 150mm dia. in all type of soils except hard rock / large Metre 0375 880.00
boulders (boulder core more than 30cm), for collecting the undisturbed core sample including
refilling, reinstating surface and disposing off surplus material including use of mechanical rigs
with power operated winches as well as percussion/chieselling tool for advancing through
occasional seams of hard strata, where necessary with contractor's labour, tools, plants,
machinery, equipment, consumables etc., with all lead and lift complete as per specifications
and as directed by the Engineer-in-charge in Dry area 20m-30m
376 Exploratory drilling of boreholes of 150mm dia. in all type of soils except hard rock / large Metre 0376 955.00
boulders (boulder core more than 30cm), for collecting the undisturbed core sample including
refilling, reinstating surface and disposing off surplus material including use of mechanical rigs
with power operated winches as well as percussion/chieselling tool for advancing through
occasional seams of hard strata, where necessary with contractor's labour, tools, plants,
machinery, equipment, consumables etc., with all lead and lift complete as per specifications
and as directed by the Engineer-in-charge in Dry area 30m-40m
377 Exploratory drilling of boreholes of 150mm dia. in all type of soils except hard rock / large Metre 0377 1,100.00
boulders (boulder core more than 30cm), for collecting the undisturbed core sample including
refilling, reinstating surface and disposing off surplus material including use of mechanical rigs
with power operated winches as well as percussion/chieselling tool for advancing through
occasional seams of hard strata, where necessary with contractor's labour, tools, plants,
machinery, equipment, consumables etc., with all lead and lift complete as per specifications
and as directed by the Engineer-in-charge in Dry area 40m-50m
378 Exploratory drilling of boreholes of 150mm dia. in all type of soils except hard rock / large Metre 0378 1,300.00
boulders (boulder core more than 30cm), for collecting the undisturbed core sample including
refilling, reinstating surface and disposing off surplus material including use of mechanical rigs
with power operated winches as well as percussion/chieselling tool for advancing through
occasional seams of hard strata, where necessary with contractor's labour, tools, plants,
machinery, equipment, consumables etc., with all lead and lift complete as per specifications
and as directed by the Engineer-in-charge in Dry area 50m-60m
379 Exploratory drilling of boreholes of 150mm dia. in all type of soils except hard rock / large Metre 0379 1,400.00
boulders (boulder core more than 30cm), for collecting the undisturbed core sample including
refilling, reinstating surface and disposing off surplus material including use of mechanical rigs
with power operated winches as well as percussion/chieselling tool for advancing through
occasional seams of hard strata, where necessary with contractor's labour, tools, plants,
machinery, equipment, consumables etc., with all lead and lift complete as per specifications
and as directed by the Engineer-in-charge in Dry area 60m-70m
380 Extra for 150mm dia. bore in hard Rock/large Boulder at all levels Metre 0380 1,489.00
381 Drilling of NX size borehole (75mm dia.) in all types of hard rock (fresh rock) and collection of Metre 0381 2,284.00
rock core samples from boreholes and preserving in boxes 0m-10m
Draft IR Unified Standard Schedule of Rates - 2021 Basic Input Data Sheet
389 Conducting in-situ full size Plate Load Test (PLT) at selected location as per IS:10042 Each 0389 18,000.00
including making loading arrangements & casting of RCC/cast in-situ concrete footing as per
codal provisions including excavation and refilling of trial pit : Plate size- 45cm x 45cm
390 Conducting in-situ full size Plate Load Test (PLT) at selected location as per IS:10042 Each 0390 21,500.00
including making loading arrangements & casting of RCC/cast in-situ concrete footing as per
codal provisions including excavation and refilling of trial pit : Plate size- 60cm x 60cm
391 Conducting in situ Vane shear test for soil as per IS:4434 Each 0391 2,200.00
392 Conducting SCPT for soil as per IS:4968 Each 0392 35,000.00
393 Conducting DCPT for soil as per IS:4968 Each 0393 29,000.00
394 Conducting determination of California Bearing Ratio (CBR) as per IS:2720 Each 0394 1,000.00
395 Taking out 100mm dia. & 450mm long undisturbed samples of soil from bore holes, including Each 0395 103.00
provision of air tight containers for packing and, labelling incl. transporting the samples to
laboratory. Piston sampler shall be used for extracting undisturbed samples where necessary.
Samples shall be collected as per IS:2720.
396 Taking out 100mm dia. & 450mm long disturbed samples of soil from bore holes, including Each 0396 110.00
provision of air tight containers for packing, labelling and transporting the samples to
laboratory. Samples shall be collected as per IS:2720.
397 Conducting standard penetration test as per IS:2131 at approximate1.5m intervals in bore Each 0397 600.00
holes, as directed by the Engineer in charge
398 Collection of water samples at required intervals Each 0398 170.00
399 Moisture Contents/Dry Density Each 0399 200.00
400 Atterberg Limit Each 0400 400.00
401 Specific Gravity Each 0401 400.00
402 Grain size analysis including Hydrometer analysis Each 0402 550.00
403 Direct Shear Test Each 0403 1,500.00
404 Natural Density Test Each 0404 450.00
405 Consolidation Test Each 0405 5,000.00
406 Unconfined Compression Test Each 0406 1,500.00
407 Tri-axial Test Each 0407 1,500.00
408 Density Test Each 0408 200.00
409 Water Absorption & Porosity Each 0409 200.00
410 Hardness Test Each 0410 100.00
411 Unconfined Compression Test for rock Each 0411 1,500.00
412 Point Load Test Each 0412 800.00
413 Modulus of Elasticity Each 0413 4,000.00
414 Abrasion Testing Each 0414 450.00
415 Conducting chemical analysis of ground water samples to determine suitability for concreting Each 0415 1,000.00
and aggressiveness in relation to attack on concrete / reinforcement including determination
of pH value
416 Conducting chemical analysis of soil samples to determine aggressiveness in relation to Each 0416 1,000.00
attack on concrete / reinforcement including determination of pH value
Draft IR Unified Standard Schedule of Rates - 2021 Basic Input Data Sheet
423 TERRA C I-94 - Electrodes of make L & T, AdvaniOerlicon, Diffusion, SHARP - 650, or Each 0423 175.00
equivalent for reconditioning of MCI insert of points & crossings sleeper
424 H3 C Electrodes as per RDSO's Spec. no. IRS M:28-2011 Nos. 0424 78.13
425 H3 B Electrodes as per RDSO's Spec. no. IRS M:28-2011 Nos. 0425 76.50
426 H3 A Electrodes as per RDSO's Spec. no. IRS M:28-2011 Nos. 0426 38.75
427 H3 Electrodes as per RDSO's Spec. no. IRS M:28-2011 Nos. 0427 20.00
428 1.6mm dia core flux wire of cast manganese steel Kg 0428 916.00
429 10 mm thick Grooved Rubber Pads as per drg. No. RDSO/T-5199 & RDSO's Spec. no. IRS-T- Each 0429 132.00
47-2006 (Prov.)-1989
430 Galvanised steel fittings for non insulated galvanized channel sleepers (52/60 kg rail) as per set 0430 1,534.00
RDSO drawing no. RDSO/T-5197 to 5200
431 Galvanised steel fittings for insulated galvanized channel sleepers (52/60 kg rail) as per RDSO set 0431 2,000.00
drawing no. RDSO/T-5155 to 5164
432 Supply of 25/30 mm thick Elastomeric Pad as per RDSO drawing No. B/1636/I/R2 Each 0432 152.00
433 Supply of 2 nos. Elastomeric Pad 25mm/30mm and 4 nos. Grooved Rubber Pad as per RDSO Set 0433 1,650.00
drawing No. B/1636/5/Alt 2
434 Galvanised MS liner and Outer Clip for steel channel sleeper (RDSO Drg. No. T-6150 & T- Set 0434 434.00
6151)
435 Single Coil spring washers T-10773 Each 0435 4.35
436 Dip Galvanisation @ 705gm / sqm ( 100 Microns thick ) MT 0436 17,000.00
437 Hook Bolts 28mm dia & 320mm long as per RDSO's drg. No. BA-1636/I/R2 Each 0437 35.00
438 Zero toe load galvanised fixtures for H Beam sleepers of 52/60kg Rails as per RDSO Set 0438 3,000.00
approved drawing
439 Lifting Barrier assembly for 6m long Lifting Barrier, having fragmented boom, boom light boxes set 0439 96,858.59
with suitable gate lamps, bell, Boom supports (stay wires) with adjusters, counter weight,
pedestal and lock posts with foundation of ‘A’ type as required, turn union wheel with
brackets, balance and auxiliary weights clamps etc to approved standard drawings to nos SA
7973 to 7980 with all fittings and fastenings complete (excluding fringes)
440 Lifting Barrier assembly for 8m long Lifting Barrier, having fragmented boom, boom light boxes set 0440 129,144.47
with suitable gate lamps, bell, Boom supports (stay wires) with adjusters, counter weight,
pedestal and lock posts with foundation of ‘A’ type as required, turn union wheel with
brackets, balance and auxiliary weights clamps etc to approved standard drawings to nos SA
7973 to 7980 with all fittings and fastenings complete (excluding fringes)
441 Lifting Barrier assembly for 10m long Lifting Barrier, having fragmented boom, boom light set 0441 161,431.29
boxes with suitable gate lamps, bell, Boom supports (stay wires) with adjusters, counter
weight, pedestal and lock posts with foundation of ‘A’ type as required, turn union wheel with
brackets, balance and auxiliary weights clamps etc to approved standard drawings to nos SA
7973 to 7980 with all fittings and fastenings complete (excluding fringes)
442 Winch arrangement for operation of level crossing lifting barriers, as per RDSO’s approved Each 0442 35,289.90
layout having standard covering arrangement, foundation of ‘A’ type as required and pulleys,
pulley guides and stakes, horizontal rope wheel, vertical rope wheel, wire adjusting screws
wire ropes 6x6x19 with all fittings, fixtures and accessories to RDSO’s approved drawings
with all parts including painting of steel work as per specification(excluding excavation and
concrete work)
Draft IR Unified Standard Schedule of Rates - 2021 Basic Input Data Sheet
444 Auto boom locking arrangement (Double lever) for existing lifting barriers, consisting of Each 0444 85,105.91
interlocking ground frame near gate lodge, foundation of ‘A’ type as required and connecting
ground frame to lock posts of gate booms with stipulated rodding on guide rollers, supported
on trestles as per RDSO’s drawings complete (Excluding excavation, concrete work)
445 Railway's lifting barrier assembly of one side at level crossing Each 0445 80,715.65
446 Railway's lifting barrier assembly and boom supports, gate lamps, of one side at level crossing Each 0446 84,751.43
447 GI wire rope of 6mm dia. 6 ply to suit lifting barrier gates Kg 0447 350.00
448 Boom Supports (stay wires) for lifting barrier (approx. 8mm dia) Each 0448 1,000.00
449 4" dia round ceramic Light Reflector as per specification Each 0449 350.00
450 Pulley with Pulley stakes complete, wire rope 6x6x19 ply with accessories as per Railway’s Each 0450 347.00
approved drawings for operation of lifting barriers
451 Vertical / Horizontal Turnout Wheels and Shafts mounted over the base plate weighing not Each 0451 1,320.00
less than 6 Kg with supporting vertical base made of MS angles 75mm x 75mm x 10mm as
per Railway's approved drawing and specifications
452 Turnout wheel- HORIZONTAL ROPE WHEEL double wire (2 way) including guides Each 0452 2,024.00
453 Galvanized STEEL WIRE ROPE for DW signalling 6 x 19 ply as per IRS No. S.11 amended Kg 0453 250.00
upto date for lifting barrier at level crossing gates
454 Precast CC Paver block -80mm thick M35 grade Sqm 0454 495.00
455 Precast CC Paver block -120mm thick M40 grade Sqm 0455 774.00
456 HDPE Dowels Each 0456 100.00
457 High Speed Hacksaw Blade of size 300mm x 12.5mm x 0.63mm (18TPI) as per as per Nos. 0457 160.00
RDSO's Spec. no. TM/SM/26 (latest Rev.)
458 Hack Saw Blades Each 0458 593.22
459 Abrasive rail cutting disc as per RDSO's Spec. no. TM/SM/2 Each 0459 574.00
460 Driving belt (abrasive rail cutter) Each 0460 600.00
461 Grinding Stone wheel GQ6 of 150mm dia Nos. 0461 490.00
462 Shearing Blade for weld trimming machine Each 0462 150.00
463 Rechargeable Battery for ETLMD as per RDSO's Spec. no. TM/SM/ETLMD/218 Each 0463 1,000.00
464 Drill twist made of high speed of size 16 mm dia of Addison / I.T. make Each 0464 1,631.50
465 Drill twist made of high speed of size 7.2 mm dia of Addison / I.T. make Each 0465 271.00
466 Drill twist made of high speed steel for size 26.5mm dia of Addison / I T make Each 0466 2,852.30
467 Drill twist made of high speed steel for size 18mm dia of Addison / I T make Each 0467 1,866.40
468 Drill twist made of high speed steel for size 28.75 mm dia of Addison / I T make Each 0468 3,242.40
469 Drill twist made of high speed steel for size 31.75 mm dia of Addison / I T make Each 0469 4,335.90
470 Drill Bit (32 mm & 26.5 mm dia) Each 0470 300.00
471 Auger Carpenter Each 0471 90.00
472 Hand lever box full set BG Each 0472 11,000.00
473 Point lock pin full set BG Each 0473 720.00
474 Fosroc conbextra-GP2 grout or similar make in 25 Kg bag Each 0474 494.00
475 Black Oil (used lubricating oil) Litre 0475 15.00
476 High intensity retro-reflective sheet Sqm 0476 1,625.00
477 Retro Reflective tape 50mm wide Metre 0477 71.30
478 Steel wires released from U/S PSC Sleeper Kg 0478 15.00
479 Bamboo 50 mm dia 2.5 metre long (1 Score = 20 nos.) score 0479 1,500.00
480 Hollock Ballies 80mm diameter Metre 0480 85.00
481 Hollock Ballies 150mm diameter Metre 0481 150.00
482 150 mm dia Eucalyptus Ballies Metre 0482 143.75
483 125 mm dia ballies of locally available wood Metre 0483 90.00
484 100 mm dia ballies of locally available wood Metre 0484 65.00
Draft IR Unified Standard Schedule of Rates - 2021 Basic Input Data Sheet
493 U pin of 6mm dia mild steel of 0.3m length for stone cladding work Each 0493 14.00
494 Cotton Jute Kg 0494 40.00
495 Empty cement bag polythene 50 Kgs capacity Each 0495 5.00
496 Sand Paper Nos. 0496 5.00
497 Poly propylene tarred rope gabion fabricated from 9mm dia rope 100m x 100m mesh with Cum 0497 1,380.00
partition at every 1m interval
498 Precast Concrete bridge No plaque/ stone Each 0498 287.50
499 Precast Concrete bridge foundation details plaque including engraving complete Each 0499 525.00
500 PVC pipe 25 mm dia confirming to IS standard for Electric Wiring Metre 0500 75.00
501 PVC junction boxes 4 way for Electric Work Each 0501 18.99
502 Tracing paper in roll with specification- weight 95gm/m2 width 914mm and length 45.7m Each 0502 250.00
503 Ammonia Print Sheet of 55 to 60 GSM, 914mm wide and 10m long Each 0503 250.00
504 Hire Charges of Total Station instrument Day 0504 200.00
505 Electricity Charges ( 1 Unit ) KWH 0505 7.50
Fixed rate elements
507 Sundries Lumpsum 9901 1.00
508 Add for Water Charges @ 1% Lumpsum 9902 0.01
509 Add for GST @ 12% (multiplying factor 0.1405) Lumpsum 9903 0.14
510 Add for Contractor’s Overheads and Profit @ 15% Lumpsum 9904 0.15
511 Add for Cess @ 1% Lumpsum 9905 0.01
512 Add for working under traffic block @ 5% Lumpsum 9991 0.05
513 Add for working under traffic block @ 10% Lumpsum 9992 0.10
514 Add for working under traffic block @ 15% Lumpsum 9993 0.15
515 Add for working under traffic block @ 20% Lumpsum 9994 0.20
516 Add for working under traffic block @ 25% Lumpsum 9995 0.25
Draft IR Unified Standard Analysis of Rates - 2021 Chapter - 1: Earthwork
Machinery:
Hire charges of dozer 215 HP capacity Hour 0057 1500.00 40.00 60,000.00
Hire charges of tractor with Ripper arrangement Day 0082 1200.00 2.00 2,400.00
Hire charges of Water tanker 5 to 6 KL capacity Hour 0051 150.00 24.00 3,600.00
Hire Charges of Vibratory roller 8 to 10 tonne Hour 0052 600.00 56.00 33,600.00
Labour:
Bhisti (Semi skilled) Day 0023 505.00 3.00 1,515.00
Coolie (Un skilled) Day 0026 431.00 50.00 21,550.00
122,665.00
Add for Water Charges @ 1% Lumpsum 9902 0.01 1,226.65
123,891.65
Add for GST @ 12% (multiplying factor 0.1405) Lumpsum 9903 0.14 17,406.78
141,298.43
Add for Contractor’s Overheads and Profit @ 15% Lumpsum 9904 0.15 21,194.76
162,493.19
Add for Cess @ 1% Lumpsum 9905 0.01 1,624.93
Cost for 30,000 Sqm 164,118.12
Cost of 100 Sqm 100 Sqm 547.06
Cost of Earthwork for Benching = Average rate of items of Earthwork for SQ1, SQ2,
SQ3 classifications of Soil
Rate of SQ1 Cum 011031 174.14
Rate of SQ2 Cum 011032 259.16
Rate of SQ3 Cum 011033 294.64
Average rate of above 3 items 242.65 900.00 218,382.33 A
Labour:
Labour Unskilled Day 0020 431.00 300.00 129,300.00
Misc:
T&P Lumpsum 9901 1.00 100.00 100.00
Total excluding A 129,400.00
Add for Water Charges @ 1% Lumpsum 9902 0.01 1,294.00
130,694.00
Draft IR Unified Standard Analysis of Rates - 2021 Chapter - 1: Earthwork
011030 Earthwork in filling in embankment, guide bunds, around buried type abutments,
bridge gaps, trolley refuges, platforms etc. with contractor's own earth conforming to
Soil Quality Class SQ1/SQ2/SQ3, after preparation of foundations as applicable,
benching in existing banks wherever required, spreading in layers with motor grader,
bringing the moisture content to OMC, mechanical compaction to specified density
and dressing of bank to final profile as per RDSO Specifications: RDSO/2020/GE:
IRS-0004 with latest correction slips.
Note:
1) Foundation preparation, Benching including additional earthwork on account of
this, wherever required, shall be paid extra under relevant schedule item for
benching.
2) Payment for Earthwork under this item shall be made based on the cross section
measurements calculated (i) with original ground profile of existing bank based on
initial ground levels before doing benching and (ii) final profile of the bank worked out
with final levels as per prevailing guidelines.
Material:
Soil Quality Class SQ1 suitable for sub grade of embankment as per RDSO Cum 0168 75.00 106.08 7,956.00
Specifications RDSO/2020/GE: IRS-0004
Hire and running charges of Tipper 12 Cum Capacity Day 0048 7000.00 0.15 1,050.00
Hire charges of Hydraulic Excavator (0.9 Cum Bucket Capacity) Day 0044 6400.00 0.17 1,088.00
Hire charges of Motor grader (3.35 metre blade) Hour 0050 2450.00 0.25 612.50
Labour:
Beldar (Un skilled) Day 0025 431.00 2.20 948.20
Coolie (Un skilled) Day 0026 431.00 0.20 86.20
Hire Charges of Vibratory roller 8 to 10 tonne Hour 0052 600.00 1.50 900.00
Hire charges of Water tanker 5 to 6 KL capacity Hour 0051 150.00 1.50 225.00
Sundries Lumpsum 9901 1.00 150.00 150.00
13,015.90
Add for Water Charges @ 1% Lumpsum 9902 0.01 130.16
13,146.06
Add for GST @ 12% (multiplying factor 0.1405) Lumpsum 9903 0.14 1,847.02
14,993.08
Add for Contractor’s Overheads and Profit @ 15% Lumpsum 9904 0.15 2,248.96
17,242.04
Add for Cess @ 1% Lumpsum 9905 0.01 172.42
Cost for 100 cum 17,414.46
Rate per Cum Cum 174.14
Machinery:
Hire charges of Hydraulic Excavator (0.9 Cum Bucket Capacity) Day 0044 6400.00 1.00 6,400.00
Hire and running charges of Tipper 12 Cum Capacity Day 0048 7000.00 4.00 28,000.00
Labour:
Helper (Semi-skilled) Day 0021 505.00 4.00 2,020.00
Beldar (Un skilled) Day 0025 431.00 8.00 3,448.00
39,868.00
Add for Water Charges @ 1% Lumpsum 9902 0.01 398.68
40,266.68
Add for GST @ 12% (multiplying factor 0.1405) Lumpsum 9903 0.14 5,657.47
45,924.15
Add for Contractor’s Overheads and Profit @ 15% Lumpsum 9904 0.15 6,888.62
52,812.77
Add for Cess @ 1% Lumpsum 9905 0.01 528.13
Draft IR Unified Standard Analysis of Rates - 2021 Chapter - 1: Earthwork
Machinery:
Hire charges of Hydraulic Excavator (0.9 Cum Bucket Capacity) Day 0044 6400.00 1.14 7,296.00
Hire and running charges of Tipper 12 Cum Capacity Day 0048 7000.00 1.00 7,000.00
Labour:
Rock Excavator (Semi skilled) Day 0014 505.00 3.00 1,515.00
Rock Breaker (Semi skilled) Day 0015 505.00 3.00 1,515.00
Rock Hole Driller (Semi skilled) Day 0016 505.00 1.00 505.00
Beldar (Un skilled) Day 0025 431.00 7.00 3,017.00
Coolie (Un skilled) Day 0026 431.00 4.00 1,724.00
Sundries Lumpsum 9901 1.00 100.00 100.00
22,672.00
Add for Water Charges @ 1% Lumpsum 9902 0.01 226.72
22,898.72
Add for GST @ 12% (multiplying factor 0.1405) Lumpsum 9903 0.14 3,217.27
26,115.99
Add for Contractor’s Overheads and Profit @ 15% Lumpsum 9904 0.15 3,917.40
30,033.39
Add for Cess @ 1% Lumpsum 9905 0.01 300.33
Cost for 150 Cum 30,333.72
Rate per Cum Cum 202.22
Machinery:
Hire charges of Hydraulic Excavator (0.9 Cum Bucket Capacity) Day 0044 6400.00 0.50 3,200.00
Hire and running charges of Tipper 12 Cum Capacity Day 0048 7000.00 2.00 14,000.00
Labour:
Rock Excavator (Semi skilled) Day 0014 505.00 3.00 1,515.00
Rock Breaker (Semi skilled) Day 0015 505.00 3.00 1,515.00
Rock Hole Driller (Semi skilled) Day 0016 505.00 7.00 3,535.00
Beldar (Semi Skilled) Day 0024 505.00 7.00 3,535.00
Coolie (Un skilled) Day 0026 431.00 15.00 6,465.00
Material
Blasting Powder Kg 0171 50.00 52.00 2,600.00
Blasting Fuse (Fuse Wire) Each 0172 20.00 75.00 1,500.00
Sundries Lumpsum 9901 1.00 100.00 100.00
37,965.00
Add for Water Charges @ 1% Lumpsum 9902 0.01 379.65
38,344.65
Add for GST @ 12% (multiplying factor 0.1405) Lumpsum 9903 0.14 5,387.42
43,732.07
Add for Contractor’s Overheads and Profit @ 15% Lumpsum 9904 0.15 6,559.81
50,291.88
Add for Cess @ 1% Lumpsum 9905 0.01 502.92
Cost for 150 Cum 50,794.80
Rate per Cum Cum 338.63
012014 In hard rock with hammer / chisel / pavement breaker etc. where blasting is not
permitted due to special circumstances and if specifically ordered in writing including
drilling and all incidental works thereto.
Detail of Cost for 10 cum
Draft IR Unified Standard Analysis of Rates - 2021 Chapter - 1: Earthwork
012015 Extra for leading of Cut spoil every one km beyond original lead of 2 km over item no.
011010
Cost for 12 cum for additional leading of 1 km
Hire and running charges of Tipper 12 Cum Capacity Day 0048 7000.00 0.01 56.00
56.00
Add for Water Charges @ 1% Lumpsum 9902 0.01 0.56
56.56
Add for GST @ 12% (multiplying factor 0.1405) Lumpsum 9903 0.14 7.95
64.51
Add for Contractor’s Overheads and Profit @ 15% Lumpsum 9904 0.15 9.68
74.18
Add for Cess @ 1% Lumpsum 9905 0.01 0.74
Cost for 12 cum 74.92
Rate per Cum Cum 6.24
012020 Foundation preparation in cutting - ploughing and pulverizing 15 cm of top of soil with
tractor trolley, mixing water to achieve OMC with water sprinkler or allowing for
natural drying, as required, and compaction with vibratory roller of suitable capacity to
achieve 98% MDD for laying blanketing layer
012030 Mechanical manufacturing of blanketing material by using only hard and durable
stone crushed in mechanical crusher to different gradations, wet mixing of the same
in designed proportion in Pug mill or wet mix plant to have uniform gradation including
all incidental transportation, laying over finished formation in uniform layer(s) with
motor grader, compaction with suitable vibratory roller to specified density and
finishing to correct profile, complete as per RDSO Specification No. RDSO/2020/GE:
IRS-0004 with latest correction slips.
Note: This item shall be used only when entire constituent of blanketing material is
mechanically manufactured.
Draft IR Unified Standard Analysis of Rates - 2021 Chapter - 1: Earthwork
012040 Manufacturing of blanketing material by wet mixing of naturally available suitable soil
including additional blending with naturally available or manufactured material as
required to achieve specified gradation, in designed proportion in Pug mill or wet mix
plant to have uniform gradation including all incidental transportation, laying over
finished formation in uniform layer(s) with motor grader, compaction with suitable
vibratory roller to specified density and finishing to correct profile, complete as per
RDSO Specification No. RDSO/2020/GE: IRS-0004 with latest correction slips.
Wastage due to additional 50 cm width is about 9.76% . For 225 cum finished work,
total volume of blanketing material required = 246.96 cum.
Material:
Considering 80% of the Blanketing Quantity as naturally available material and 20%
qnty for Blending material.
Natural soil = 0.8*246.96 = 197.57 cum
Blending material = 0.20x246.96 = 49.39 cum
Since this is naturally available, the cost shall be the same cost of Soil as SQ3.
However, in all probability it may be available at a reasonable distance away from
worksite in most of the cases. Distance of availability of material is considered as
additional 30 km for analysis purpose.
Soil Quality Class SQ3 suitable for sub grade of embankment as per RDSO Cum 0170 150.00 197.57 29,635.50
Specifications RDSO/2020/GE: IRS-0004
Considering availability of natural material meeting the specification may not be in
close vicinity, a distance of 30 km is considered for calculation of additional cost for
transportation.
Cost of 30 km of transportation for 197.56 cum as per working sheet
012050 Mechanical manufacturing and supply of blanketing material by using only hard and
durable stone crushed in mechanical crusher to different gradations, wet mixing of the
same in designed proportion in Pug mill or wet mix plant to have uniform gradation as
per RDSO Specification No. RDSO/2020/GE: IRS-0004 with latest correction slips
including transportation to nominated place and stacking.
Note:
1.This item shall be used only when entire constituent of blanketing material is
mechanically manufactured.
2. Measurement shall be done as per Stack measurement.
For 246.96 cum (493.92 MT) of compacted blanketing, the volume in loose state
shall be 246.96 x 1.20 = 296.352 cum.
Material:
Detail of cost for 296.352 cum in stacks
Stone Aggregate (Single size) : 20 mm nominal size Cum 0207 825.00 45.69 37,696.80
Stone Aggregate (Single size) : 10 mm nominal size Cum 0208 775.00 68.53 53,113.96
Stone Aggregate (Single size) : 06 mm nominal size Cum 0209 775.00 91.38 70,815.78
Crusher Screening(Quarry Dust) Conforming to Grading Zone - I to Zone- II Cum 0211 600.00 114.22 68,529.75
Machinery:
Hire Charges of Wet Mix Plant 60 TPH Capacity Hour 0055 950.00 8.25 7,837.50
Hire Charges of Generator 100 KVA/125 KVA Day 0076 2500.00 1.03 2,575.00
Hire charges of Water tanker 5 to 6 KL capacity Hour 0051 150.00 4.50 675.00
Hire and running charges of front end loader (1.0 Cum bucket capacity) Day 0047 6000.00 0.75 4,500.00
Hire and running charges of Tipper 12 Cum Capacity Day 0048 7000.00 2.80 19,600.00
Transportation of material within a distance of 5 kms on either side of the Wet Mix
plant requires 2.8 tippers.
Add 10% of cost of carriage to cover cost of loading and unloading 0.10 1,960.00
Labour:
Beldar (Semi Skilled) Day 0024 505.00 2.00 1,010.00
Beldar (Un skilled) Day 0025 431.00 4.00 1,724.00
Total 270,037.79
Add for Water Charges @ 1% Lumpsum 9902 0.01 2,700.38
272,738.17
Add for GST @ 12% (multiplying factor 0.1405) Lumpsum 9903 0.14 38,319.71
311,057.88
Add for Contractor’s Overheads and Profit @ 15% Lumpsum 9904 0.15 46,658.68
357,716.57
Add for Cess @ 1% Lumpsum 9905 0.01 3,577.17
Cost for 296.352 cum 361,293.73
Rate per Cum Cum 1,219.14
For 246.96 cum (493.92 MT) of compacted blanketing, the volume in loose state
shall be 246.96 x 1.20 = 296.352 cum.
Material:
Draft IR Unified Standard Analysis of Rates - 2021 Chapter - 1: Earthwork
Since this is naturally available, the cost shall be the same cost of Soil as SQ3.
However, in all probability it may be available at a reasonable distance away from
worksite in most of the cases. Distance of availability of material is considered as
additional 30 km for analysis purpose.
Soil Quality Class SQ3 suitable for sub grade of embankment as per RDSO
Cum 0170 150.00 197.57 29,635.50
Specifications RDSO/2020/GE: IRS-0004
Considering availability of natural material meeting the specification may not be in
close vicinity, a distance of 30 km is considered for calculation of additional cost for
transportation.
Cost of 30 km of transportation for 197.56 cum as per working sheet
013000 Miscellaneous:
013010 Felling trees of girth (measured at a height of 1m above ground level) including lead
and stacking of material within 100m.
Note : 1. When stumps are grubbed up in addition, the rates shall be doubled for
trees cut and grubbed 2. Payment for grubbing shall only be made where specially
ordered. 3. Grubbing shall be ordered only where it is essential to remove the
stumps, including the roots, as per specification. 4. Grubbing shall include removal of
roots of trees and saplings to a depth of 60cm below ground level or 30 cm below
formation level or 15 cm below sub grade level, whichever is lower.
013020 Turfing / planting, including all lead & lift and watering as required until properly
rooted with.
Note: Initially payment of only 40% will be made. Balance 60% will be paid only after
3 months of maintenance period, if the turfing is properly rooted.
013021 Turfing with sods, 10cm thick and 20cm square closely laid.
Details of cost for 100 Sqm.
Material:
Grass sods Sqm 0176 46.00 70.00 3,220.00
{Considering coverage of 70% area of turfing with sods}
Labour:
Beldar (Un skilled) Day 0025 431.00 1.00 431.00
Coolie (Un skilled) Day 0026 431.00 1.00 431.00
Bhisti (Semi skilled) Day 0023 505.00 0.50 252.50
Sundries Lumpsum 9901 1.00 20.00 20.00
4,354.50
Add for Water Charges @ 1% Lumpsum 9902 0.01 43.55
4,398.05
Add for GST @ 12% (multiplying factor 0.1405) Lumpsum 9903 0.14 617.93
5,015.97
Add for Contractor’s Overheads and Profit @ 15% Lumpsum 9904 0.15 752.40
5,768.37
Add for Cess @ 1% Lumpsum 9905 0.01 57.68
Rate per 100 Sqm 100 Sqm 5,826.05
013023 Planting Sarkanda / sarpat or any other suitable species approved by the engineer
Details of cost for 100sqm
Material:
Sarkanda/ Sarpat Sqm 0175 45.00 70.00 3,150.00
{Considering coverage of 70% area of turfing
Labour:
Beldar (Un skilled) Day 0025 431.00 2.00 862.00
Coolie (Un skilled) Day 0026 431.00 2.00 862.00
Sundries Lumpsum 9901 1.00 20.00 20.00
4,894.00
Add for Water Charges @ 1% Lumpsum 9902 0.01 48.94
4,942.94
Add for GST @ 12% (multiplying factor 0.1405) Lumpsum 9903 0.14 694.48
5,637.42
Add for Contractor’s Overheads and Profit @ 15% Lumpsum 9904 0.15 845.61
6,483.04
Add for Cess @ 1% Lumpsum 9905 0.01 64.83
Rate per 100 Sqm 100 Sqm 6,547.87
013030 Cleaning out silt from bed of reservoir/canals including 50m lead and lift upto 1.5m.
Taking output 10 cum
Labour:
Beldar (Un skilled) Day 0025 431.00 1.50 646.50
Coolie (Un skilled) Day 0026 431.00 1.50 646.50
Sundries Lumpsum 9901 1.00 10.00 10.00
1,303.00
Add for Water Charges @ 1% Lumpsum 9902 0.01 13.03
1,316.03
Add for GST @ 12% (multiplying factor 0.1405) Lumpsum 9903 0.14 184.90
1,500.93
Add for Contractor’s Overheads and Profit @ 15% Lumpsum 9904 0.15 225.14
1,726.07
Add for Cess @ 1% Lumpsum 9905 0.01 17.26
Cost for 10 Cum 1,743.33
Rate per Cum Cum 174.33
013040 Providing and removing barricading with the help of portable fencing along running
track where work is to be done in close vicinity of track. Fencing shall consist of self
supporting steel angles of size 50mm x 50mm x 6mm, 1.5m long provided with hooks
etc. and embedded in CC 1:2:4 block of size 0.23m x 0.23m x 0.23m placed at c/c
distance of 2m along track. 12mm dia rods in three horizontal layers shall be tack
welded with angle posts.
Note : Released material will be property of the contractor after completion of work.
Cost of cement to be paid separately.
013041 With provision of one 50mm wide retro-reflective tape in horizontal direction, duly
secured/tight with vertical posts.
Details of cost for 30m
Material:
Steel angle supports 50mm x 50mm x 6mm (steel angles to be used 8 times). Quintal 0224 4950.00 0.14 688.05
Therefore, quantity taken = 1.1 / 8 = 0.14 qtl.)
Weight of Angle of size 50mm x 50mm x 6mm is 4.5 kg/m
15 no. x 1.5m = 22.5m @ 4.5kg/m = 101.25 kg (Add 5% extra for wastage) = 111.375
kg say 1.1 qtl.
MS round bar for reinforcement- average rate for various dia Quintal 0220 3600.00 0.11 400.50
M.S. bars 12mm dia = 30m x 3no. x 0.89 = 0.80 quintal (Steel to be used 8 times).
Therefore, quantity taken = 0.8 / 8 = 0.11 qtl.)
Less salvage value after full use of material @ 25% on (A + B) -272.14
Draft IR Unified Standard Analysis of Rates - 2021 Chapter - 1: Earthwork
013042 With provision of painting verticals & horizontals with red luminous paints / strips of
30cm each with a gap of 30 cm.
Taking out put 30m
Material:
Structural steel such as T, Angles, Channels and R S Joists conforming to Grade Quintal 0224 4950.00 0.14 688.05
Designation E 250; Quality "A" as per IS 2062
Weight of Angle of size 50mm x 50mm x 6mm is 4.5 kg/m
15no's x 1.5m = 22.5m @ 4.5kg/m = 101.25 kg (Add 5% extra for wastage) =
111.375 kg say 1.1 qtl.
Considering angles to be used 8 times, quantity taken for one time use = 1.1 / 8 =
0.14 qtl.)
MS round bar for reinforcement- average rate for various dia Quintal 0220 3600.00 0.11 399.60
M.S. bars 12mm dia = 30m x 3no. x 0.89 = 0.80 quintal (Steel to be used 8 times).
Therefore, quantity taken = 0.8 / 8 = 0.111 qtl.)
Less salvage value after full use of material @ 25% on (A + B) -271.91
Luminous Paint as per RDSO's Spec. no. M&C/PCN/120-2011 Litre 0299 300.00 0.40 120.00
Surface area of angle 50mm + 50mm + 6mm + 6mm = 112mm, for 22.5 metre long
angle, Area = 22.5m x .112m = 2.52 Sqm, Surface area of 12mm dia rods for 90m
long = 3.42 Sqm, i.e. Total coverage Area = 2.52sqm + 3.42sqm = 5.94 Sqm, Paint
required @ 15sqm/litre = 5.94 / 15 = 0.396 litre
013050 Provision of barricading with contractor's bamboos / balli vertical post of 100mm dia.
planted at every 2m interval, projecting at least 1.5m above ground level and driven
firmly (minimum 0.5m) inside ground and including painting verticals & horizontals
with red luminous paints / strips at alternative bay on barricade. Barricades shall be
maintained through out the execution of the work and shall be removed in workman
like manner on completion of the work only after instruction of Engineer in-Charge.
Note:
(1) 60% payment shall be made on provision of barricading at work-site and balance
40% payment after removal of barricades.
(2) The released ballies shall be the property of the Contractor.
Draft IR Unified Standard Analysis of Rates - 2021 Chapter - 1: Earthwork
Bamboo 50 mm dia 2.5 metre long (1 Score = 20 nos.) score 0479 1500.00 2.50 3,750.00
100 mm dia ballies of locally available wood Metre 0484 65.00 34.00 2,210.00
Luminous Paint as per RDSO's Spec. no. M&C/PCN/120-2011 Litre 0299 300.00 3.00 900.00
Iron spike (different sizes) Kg 0485 60.00 2.00 120.00
Labour:
Mate (Skilled) Day 0002 609.00 0.25 152.25
Carpenter (Skilled) Day 0006 609.00 1.00 609.00
Helper (Semi-skilled) Day 0021 505.00 1.00 505.00
Labour Unskilled Day 0020 431.00 4.00 1,724.00
Misc :
T&P Lumpsum 9901 1.00 16.00 16.00
9,986.25
Add for Water Charges @ 1% Lumpsum 9902 0.01 99.86
10,086.11
Add for GST @ 12% (multiplying factor 0.1405) Lumpsum 9903 0.14 1,417.10
11,503.21
Add for Contractor’s Overheads and Profit @ 15% Lumpsum 9904 0.15 1,725.48
13,228.69
Add for Cess @ 1% Lumpsum 9905 0.01 132.29
Cost for 100 RM 13,360.98
Rate per RM RM 133.61
013052 Joining with strong nylon rope in one cross and one horizontal pattern of minimum
5mm dia.
Details of cost for 100 RM
Material:
100 mm dia ballies of locally available wood Metre 0484 65.00 34.00 2,210.00
Iron spike (different sizes) Kg 0485 60.00 2.00 120.00
Nylon rope 5 mm dia Kg 0486 90.00 12.00 1,080.00
Labour:
Mate (Skilled) Day 0002 609.00 0.25 152.25
Carpenter (Skilled) Day 0006 609.00 0.50 304.50
Helper (Semi-skilled) Day 0021 505.00 0.50 252.50
Labour Unskilled Day 0020 431.00 4.00 1,724.00
Misc:
T&P Lumpsum 9901 1.00 15.00 15.00
5,858.25
Add for Water Charges @ 1% Lumpsum 9902 0.01 58.58
5,916.83
Add for GST @ 12% (multiplying factor 0.1405) Lumpsum 9903 0.14 831.31
6,748.15
Add for Contractor’s Overheads and Profit @ 15% Lumpsum 9904 0.15 1,012.22
7,760.37
Add for Cess @ 1% Lumpsum 9905 0.01 77.60
Cost for 100 RM 7,837.97
Rate per RM RM 78.38
013060 Supplying, driving and erecting in all types of soils, hard wood pile 5m to 7m long
without joint, 125mm average dia. for protection of bank slope including two coats of
coal tar paint complete, as directed
Note: Payment will be made as per actual driven length of pile.
013070 Driving rails 90R/52 Kg section below average ground level within the slope/toe of
embankment including making of nose with contractor’s own arrangement complete
in all respect
Note: Payment will be made as per actual driven length of rail which will be supplied
free by Railways at site of work.
013080 Shoring with 'Z' section MS sheet piles side by side in all kinds of soil mechanically or
manually as per approved drawing with contractor’s own arrangement complete in all
respects and removal of sheet piles after completion of the work as directed by
engineer in-charge
Note: Payment will be made as per actual driven length of pile.
Details of cost for 100 m of Z section Pile having wall area of 100x0.80 = 80.00 Sqm.
Material:
AZ 18-800 Sheet piles 100m @ 80.70 kg/m=8070 kg=80.70 Quintals. Add 10% for
bracing.
Total weight = 80.70 x 1.10 = 88.077quintals
This can be used 12 times with a salvage value of 25% , the weight to be taken for
using once = 0.75 x 88.77/12 = 5.5048 Say 5.505 quintal
Z section sheet piles AZ 18-800 (Arcellor Mittal) or equivalent & bracing Quintal 0249 4500.00 5.51 24,772.50
Hire charges of Hydraulic Excavator (0.9 Cum Bucket Capacity) Day 0044 6400.00 0.75 4,800.00
Hire charges of Vibratory Hammer attachment of Hydraulic Excavator for driving Day 0046 700.00 0.75 525.00
Sheet pile driving
Hire charges of Diesel Truck - 9 tonne Day 0060 3940.00 2.00 7,880.00
( 1 day for transportation of material to work site and 1 day for return)
Extra 20% of Hire Charges of Truck for loading unloading 0.20 1,576.00
Labour:
Mistry (Semi skilled) Day 0027 505.00 2.00 1,010.00
Beldar (Un skilled) Day 0025 431.00 4.00 1,724.00
Coolie (Un skilled) Day 0026 431.00 12.00 5,172.00
Sundries Lumpsum 9901 1.00 100.00 100.00
47,559.50
Add for Water Charges @ 1% Lumpsum 9902 0.01 475.60
48,035.10
Add for GST @ 12% (multiplying factor 0.1405) Lumpsum 9903 0.14 6,748.93
54,784.03
Add for Contractor’s Overheads and Profit @ 15% Lumpsum 9904 0.15 8,217.60
63,001.63
Add for Cess @ 1% Lumpsum 9905 0.01 630.02
Cost per 80 Sqm 63,631.65
Rate per Sqm Sqm 795.40
Draft IR Unified Standard Analysis of Rates - 2021 Chapter - 1: Earthwork
013091 On top of subgrade or prepared subgrade before laying blanketing layer with
minimum strengths in Grab test, Trapezoidal Tear test and Puncture test of 700N,
250 N and 1800 N respectively.
Cost for 100 Sqm
Material:
Non-woven Needle Punched and Mechanically or Thermally bonded type Geotextile Sqm 0177 90.00 100.00 9,000.00 P
for use as Separator/Filtration for Railway formation as per RDSO Specification No.
RDSO/2018/GE:IRS-0004 - Part Iwith minimum strengths in Grab test, Trapezoidal
Tear test and Puncture test of 700N, 250 N and 1800 N respectively
Add 10 % of P for wastage and accessories for joining elements, overlap, 0.10 900.00
transportation etc.
Labour:
Mate (Semi skilled) Day 0003 505.00 0.12 60.60
Beldar (Un skilled) Day 0025 431.00 2.00 862.00
Coolie (Un skilled) Day 0026 431.00 1.00 431.00
11,253.60
Add for Water Charges @ 1% Lumpsum 9902 0.01 112.54
11,366.14
Add for GST @ 12% (multiplying factor 0.1405) Lumpsum 9903 0.14 1,596.94
12,963.08
Add for Contractor’s Overheads and Profit @ 15% Lumpsum 9904 0.15 1,944.46
14,907.54
Add for Cess @ 1% Lumpsum 9905 0.01 149.08
Cost for 100 Sqm 15,056.62
Rate per Sqm Sqm 150.57
013092 Below the ballast and above blanket layer with minimum strengths in Grab test,
Trapezoidal Tear test and Puncture test of 1750N, 800 N and 5800 N respectively.
Add 10 % of P for wastage and accessories for joining elements, overlap, 0.10 1,700.00
transportation etc.
Labour:
Mate (Semi skilled) Day 0003 505.00 0.12 60.60
Beldar (Un skilled) Day 0025 431.00 2.00 862.00
Coolie (Un skilled) Day 0026 431.00 1.00 431.00
20,053.60
Add for Water Charges @ 1% Lumpsum 9902 0.01 200.54
20,254.14
Add for GST @ 12% (multiplying factor 0.1405) Lumpsum 9903 0.14 2,845.71
23,099.84
Add for Contractor’s Overheads and Profit @ 15% Lumpsum 9904 0.15 3,464.98
26,564.82
Add for Cess @ 1% Lumpsum 9905 0.01 265.65
Cost for 100 Sqm 26,830.47
Rate per Sqm Sqm 268.30
013093 Supplying & laying of drainage composite for use behind abutments, wing walls,
return walls and Retaining walls Geocomposite drain (Vertical) as per RDSO
Specification No. RDSO/2018/GE:IRS-0006 latest version with all material, labour,
equipment, tools and plants, lead, lift etc. complete in all respects as per the direction
of Engineer-in-Charge.
Add 10 % of P for wastage and accessories for joining elements, overlap, 0.10 4,500.00
transportation, perforated pipes etc.
Labour:
Mate (Semi skilled) Day 0003 505.00 0.12 60.60
Beldar (Un skilled) Day 0025 431.00 2.00 862.00
Coolie (Un skilled) Day 0026 431.00 1.00 431.00
50,853.60
Add for Water Charges @ 1% Lumpsum 9902 0.01 508.54
51,362.14
Add for GST @ 12% (multiplying factor 0.1405) Lumpsum 9903 0.14 7,216.38
58,578.52
Add for Contractor’s Overheads and Profit @ 15% Lumpsum 9904 0.15 8,786.78
67,365.29
Add for Cess @ 1% Lumpsum 9905 0.01 673.65
Cost for 100 Sqm 68,038.95
Rate per Sqm Sqm 680.39
Draft IR Unified Standard Analysis of Rates - 2021 Chapter - 2: Bridge Works (Sub-structure)
021011 0m to 10m
Exploratory drilling of boreholes of 150mm dia. in all type of soils except hard rock / Metre 0373 796.00 1.00 796.00
large boulders (boulder core more than 30cm), for collecting the undisturbed core
sample including refilling, reinstating surface and disposing off surplus material
including use of mechanical rigs with power operated winches as well as
percussion/chieselling tool for advancing through occasional seams of hard strata,
where necessary with contractor's labour, tools, plants, machinery, equipment,
consumables etc., with all lead and lift complete as per specifications and as directed
by the Engineer-in-charge in Dry area 0-10m
796.00
Add for Water Charges @ 1% Lumpsum 9902 0.01 7.96
Total 803.96
Add for GST @ 12% (multiplying factor 0.1405) Lumpsum 9903 0.14 112.96
916.92
Add for Contractor’s Overheads and Profit @ 15% Lumpsum 9904 0.15 137.54
1,054.45
Add for Cess @ 1% Lumpsum 9905 0.01 10.54
Cost per meter Metre 1,065.00
836.00
Add for Water Charges @ 1% Lumpsum 9902 0.01 8.36
Total 844.36
Add for GST @ 12% (multiplying factor 0.1405) Lumpsum 9903 0.14 118.63
962.99
Add for Contractor’s Overheads and Profit @ 15% Lumpsum 9904 0.15 144.45
1,107.44
Add for Cess @ 1% Lumpsum 9905 0.01 11.07
Cost per meter Metre 1,118.52
880.00
Add for Water Charges @ 1% Lumpsum 9902 0.01 8.80
888.80
Draft IR Unified Standard Analysis of Rates - 2021 Chapter - 2: Bridge Works (Sub-structure)
955.00
Add for Water Charges @ 1% Lumpsum 9902 0.01 9.55
964.55
Add for GST @ 12% (multiplying factor 0.1405) Lumpsum 9903 0.14 135.52
1,100.07
Add for Contractor’s Overheads and Profit @ 15% Lumpsum 9904 0.15 165.01
1,265.08
Add for Cess @ 1% Lumpsum 9905 0.01 12.65
Cost per meter Metre 1,277.73
1,100.00
Add for Water Charges @ 1% Lumpsum 9902 0.01 11.00
1,111.00
Add for GST @ 12% (multiplying factor 0.1405) Lumpsum 9903 0.14 156.10
1,267.10
Add for Contractor’s Overheads and Profit @ 15% Lumpsum 9904 0.15 190.06
1,457.16
Add for Cess @ 1% Lumpsum 9905 0.01 14.57
Cost per meter Metre 1,471.73
1,300.00
Add for Water Charges @ 1% Lumpsum 9902 0.01 13.00
1,313.00
Add for GST @ 12% (multiplying factor 0.1405) Lumpsum 9903 0.14 184.48
1,497.48
Draft IR Unified Standard Analysis of Rates - 2021 Chapter - 2: Bridge Works (Sub-structure)
021017 60 m to 70 m
Exploratory drilling of boreholes of 150mm dia. in all type of soils except hard rock / Metre 0379 1400.00 1.00 1,400.00
large boulders (boulder core more than 30cm), for collecting the undisturbed core
sample including refilling, reinstating surface and disposing off surplus material
including use of mechanical rigs with power operated winches as well as
percussion/chieselling tool for advancing through occasional seams of hard strata,
where necessary with contractor's labour, tools, plants, machinery, equipment,
consumables etc., with all lead and lift complete as per specifications and as directed
by the Engineer-in-charge in Dry area 60m-70m
1,400.00
Add for Water Charges @ 1% Lumpsum 9902 0.01 14.00
1,414.00
Add for GST @ 12% (multiplying factor 0.1405) Lumpsum 9903 0.14 198.67
1,612.67
Add for Contractor’s Overheads and Profit @ 15% Lumpsum 9904 0.15 241.90
1,854.57
Add for Cess @ 1% Lumpsum 9905 0.01 18.55
Cost per meter Metre 1,873.11
021020 Exploratory drilling of Boreholes down to required depth, drilling of 150mm diameter
boreholes in all type of soils except hard rock and large boulders (boulder core more
than 30cm), including refilling, reinstating surface and disposing off surplus material
including use of mechanical rigs with power operated winches as well as percussion /
chiselling tool for advancing through occasional seams of hard strata to be employed
where necessary in River bed area including standing/flowing water with all
necessary arrangements except making of platform under water which shall be paid
under relevant item of SOR.
021021 0m to 10m
Rate as per item no 021011 for drilling in dry area Metre 021011 1,065.00
Add extra for doing drilling in water 20% over item no 021011 0.20 213.00
Cost per meter Metre 1,278.00
021030 Extra for 150mm dia. bore in hard Rock/large Boulder at all levels
Extra for 150mm dia. bore in hard Rock/large Boulder at all levels Metre 0380 1489.00 1.00 1,489.00
1,489.00
Add for Water Charges @ 1% Lumpsum 9902 0.01 14.89
1,503.89
Add for GST @ 12% (multiplying factor 0.1405) Lumpsum 9903 0.14 211.30
1,715.19
Add for Contractor’s Overheads and Profit @ 15% Lumpsum 9904 0.15 257.28
1,972.46
Add for Cess @ 1% Lumpsum 9905 0.01 19.72
Cost per meter Metre 1,992.19
021040 Erection of temporary working platform to drill bore hole through flowing/standing
water through river bed upto water depth of 1.5m, and dismantling after completing
work and removing from the site to clear the water way.
021050 Drilling of NX size borehole (75mm dia.) in all types of hard rock and collection of
rock core samples from boreholes and preserving in boxes
021051 0m to 10m
Drilling of NX size borehole (75mm dia.) in all types of hard rock (fresh rock) and Metre 0381 2284.00 1.00 2,284.00
collection of rock core samples from boreholes and preserving in boxes 0m-10m
2,284.00
Add for Water Charges @ 1% Lumpsum 9902 0.01 22.84
2,306.84
Add for GST @ 12% (multiplying factor 0.1405) Lumpsum 9903 0.14 324.11
2,630.95
Add for Contractor’s Overheads and Profit @ 15% Lumpsum 9904 0.15 394.64
3,025.59
Add for Cess @ 1% Lumpsum 9905 0.01 30.26
Draft IR Unified Standard Analysis of Rates - 2021 Chapter - 2: Bridge Works (Sub-structure)
2,558.00
Add for Water Charges @ 1% Lumpsum 9902 0.01 25.58
2,583.58
Add for GST @ 12% (multiplying factor 0.1405) Lumpsum 9903 0.14 362.99
2,946.57
Add for Contractor’s Overheads and Profit @ 15% Lumpsum 9904 0.15 441.99
3,388.56
Add for Cess @ 1% Lumpsum 9905 0.01 33.89
Cost per meter Metre 3,422.44
2,835.00
Add for Water Charges @ 1% Lumpsum 9902 0.01 28.35
2,863.35
Add for GST @ 12% (multiplying factor 0.1405) Lumpsum 9903 0.14 402.30
3,265.65
Add for Contractor’s Overheads and Profit @ 15% Lumpsum 9904 0.15 489.85
3,755.50
Add for Cess @ 1% Lumpsum 9905 0.01 37.55
Cost per meter Metre 3,793.05
021060 Conducting in-situ full size Plate Load Test (PLT) at selected location as per IS:1888
including making loading arrangements & casting of RCC/cast in-situ concrete
footing as per codal provisions including excavation and refilling of trial pit.
15,000.00
Add for Water Charges @ 1% Lumpsum 9902 0.01 150.00
15,150.00
Add for GST @ 12% (multiplying factor 0.1405) Lumpsum 9903 0.14 2,128.58
17,278.58
Add for Contractor’s Overheads and Profit @ 15% Lumpsum 9904 0.15 2,591.79
19,870.36
Add for Cess @ 1% Lumpsum 9905 0.01 198.70
Cost of Each Each 20,069.06
18,000.00
Add for Water Charges @ 1% Lumpsum 9902 0.01 180.00
18,180.00
Add for GST @ 12% (multiplying factor 0.1405) Lumpsum 9903 0.14 2,554.29
20,734.29
Add for Contractor’s Overheads and Profit @ 15% Lumpsum 9904 0.15 3,110.14
23,844.43
Add for Cess @ 1% Lumpsum 9905 0.01 238.44
Cost of Each Each 24,082.88
21,500.00
Add for Water Charges @ 1% Lumpsum 9902 0.01 215.00
21,715.00
Add for GST @ 12% (multiplying factor 0.1405) Lumpsum 9903 0.14 3,050.96
24,765.96
Add for Contractor’s Overheads and Profit @ 15% Lumpsum 9904 0.15 3,714.89
28,480.85
Add for Cess @ 1% Lumpsum 9905 0.01 284.81
Cost of Each Each 28,765.66
021070 Conducting in situ Vane shear test for soil as per IS:4434
Conducting in situ Vane shear test for soil as per IS:4434 Each 0391 2200.00 1.00 2,200.00
2,200.00
Add for Water Charges @ 1% Lumpsum 9902 0.01 22.00
2,222.00
Add for GST @ 12% (multiplying factor 0.1405) Lumpsum 9903 0.14 312.19
2,534.19
Add for Contractor’s Overheads and Profit @ 15% Lumpsum 9904 0.15 380.13
2,914.32
Add for Cess @ 1% Lumpsum 9905 0.01 29.14
Cost of Each Each 2,943.46
021110 Taking out 100mm dia. & 450mm long undisturbed samples of soil from bore holes,
including provision of air tight containers for packing and, labeling incl. transporting
the samples to laboratory. Piston sampler shall be used for extracting undisturbed
samples where necessary. Samples shall be collected as per IS:2720.
Taking out 100mm dia. & 450mm long undisturbed samples of soil from bore holes, Each 0395 103.00 1.00 103.00
including provision of air tight containers for packing and, labelling incl. transporting
the samples to laboratory. Piston sampler shall be used for extracting undisturbed
samples where necessary. Samples shall be collected as per IS:2720.
103.00
Add for Water Charges @ 1% Lumpsum 9902 0.01 1.03
104.03
Add for GST @ 12% (multiplying factor 0.1405) Lumpsum 9903 0.14 14.62
118.65
Add for Contractor’s Overheads and Profit @ 15% Lumpsum 9904 0.15 17.80
136.44
Add for Cess @ 1% Lumpsum 9905 0.01 1.36
Cost of Each Each 137.81
021120 Taking out 100mm dia. & 450mm long disturbed samples of soil from bore holes,
including provision of air tight containers for packing, labeling and transporting the
samples to laboratory. Samples shall be collected as per IS:2720.
Taking out 100mm dia. & 450mm long disturbed samples of soil from bore holes, Each 0396 110.00 1.00 110.00
including provision of air tight containers for packing, labelling and transporting the
samples to laboratory. Samples shall be collected as per IS:2720.
110.00
Add for Water Charges @ 1% Lumpsum 9902 0.01 1.10
111.10
Add for GST @ 12% (multiplying factor 0.1405) Lumpsum 9903 0.14 15.61
126.71
Add for Contractor’s Overheads and Profit @ 15% Lumpsum 9904 0.15 19.01
145.72
Add for Cess @ 1% Lumpsum 9905 0.01 1.46
Cost of Each Each 147.17
021150 Conducting laboratory Tests on collected soil samples as per relevant IS code
021160 Conducting Laboratory tests on collected ROCK SAMPLES as per relevant IS code
021163 Hardness
Hardness Test Each 0410 100.00 1.00 100.00
100.00
Add for Water Charges @ 1% Lumpsum 9902 0.01 1.00
101.00
Add for GST @ 12% (multiplying factor 0.1405) Lumpsum 9903 0.14 14.19
115.19
Add for Contractor’s Overheads and Profit @ 15% Lumpsum 9904 0.15 17.28
132.47
Add for Cess @ 1% Lumpsum 9905 0.01 1.32
Cost of Each Each 133.79
021170 Conducting chemical analysis of ground water samples to determine suitability for
concreting and aggressiveness in relation to attack on concrete / reinforcement
including determination of pH value
Conducting chemical analysis of ground water samples to determine suitability for Each 0415 1000.00 1.00 1,000.00
concreting and aggressiveness in relation to attack on concrete / reinforcement
including determination of pH value
1,000.00
Add for Water Charges @ 1% Lumpsum 9902 0.01 10.00
1,010.00
Add for GST @ 12% (multiplying factor 0.1405) Lumpsum 9903 0.14 141.91
1,151.91
Add for Contractor’s Overheads and Profit @ 15% Lumpsum 9904 0.15 172.79
1,324.69
Add for Cess @ 1% Lumpsum 9905 0.01 13.25
Cost of Each Each 1,337.94
Conducting chemical analysis of soil samples to determine aggressiveness in Each 0416 1000.00 1.00 1,000.00
relation to attack on concrete / reinforcement including determination of pH value
1,000.00
Add for Water Charges @ 1% Lumpsum 9902 0.01 10.00
1,010.00
Add for GST @ 12% (multiplying factor 0.1405) Lumpsum 9903 0.14 141.91
1,151.91
Add for Contractor’s Overheads and Profit @ 15% Lumpsum 9904 0.15 172.79
1,324.69
Add for Cess @ 1% Lumpsum 9905 0.01 13.25
Cost of Each Each 1,337.94
022020 Extra over item nos. 022011 to 022014 for executing the work under water and/or
liquid mud to compensate all additional arrangements including pumping out water as
required.
Note:
The extra percentage rate is applicable only for the quantity of work executed under
water.
Draft IR Unified Standard Analysis of Rates - 2021 Chapter - 2: Bridge Works (Sub-structure)
022030 Providing and laying in position Plain cement concrete of specified Nominal Mix for
miscellaneous works like side drains, foundation for OHE masts and other
miscellaneous structures excluding the cost of Cement, centering and shuttering -
All work up to plinth level :
022036 1:4:8 (1 Cement : 4coarse sand (zone-III): 8 graded stone aggregate 40 mm nominal
size).
Details of cost for 15 cum.
Material:
Stone Aggregate (Single size) : 40 mm nominal size Cum 0206 754.00 9.52 7,178.08
(0.70 cum - 7.5% for voids i.e. 0.05 = 0.65 cum)
Stone Aggregate (Single size) : 20 mm nominal size Cum 0207 825.00 4.76 3,927.00
Coarse Sand (Zone III) Cum 0202 1200.00 6.75 8,100.00
Portland Cement (0.1175 cum) tonne
Labour:
Mate (Semi skilled) Day 0003 505.00 0.64 323.20
Mason 2nd class (Semi-skilled) Day 0005 505.00 1.00 505.00
Coolie (Un skilled) Day 0026 431.00 15.00 6,465.00
Machinery:
Hire charges of Concrete Mixer 0.25 to 0.40 cubic metre capacity Day 0070 800.00 0.75 600.00
Hire charges of 25 KVA Generator Day 0074 1500.00 0.75 1,125.00
Hire charges of Pin Vibrator Day 0079 350.00 0.75 262.50
Sundries Lumpsum 9901 1.00 100.00 100.00
28,585.78
Add for Water Charges @ 1% Lumpsum 9902 0.01 285.86
28,871.64
Add for GST @ 12% (multiplying factor 0.1405) Lumpsum 9903 0.14 4,056.47
32,928.10
Add for Contractor’s Overheads and Profit @ 15% Lumpsum 9904 0.15 4,939.22
37,867.32
Add for Cess @ 1% Lumpsum 9905 0.01 378.67
Cost for 15 Cum. 38,245.99
Rate per Cum Cum 2,549.73
Draft IR Unified Standard Analysis of Rates - 2021 Chapter - 2: Bridge Works (Sub-structure)
022050 Providing and laying in position machine batched, machine mixed and machine
vibrated Cement Concrete of specified grade as per approved Design Mix (mixed in
Mobile Concrete Batching/Mixing Plant at site or RMC from approved plants) using
20mm graded crushed stone aggregate and coarse sand of approved quality for the
following Reinforced cement concrete structural elements up to height of 9.0 m from
foundation top level, including finishing, using Admixtures in approved proportions
(as per IS:9103), to modify workability & other properties without impairing strength
and durability complete as per specifications and direction of the Engineer in
charge. Payment for cement, reinforcement, shuttering shall be paid extra.
022053 Abutment cap, Pier Cap, Inspection Platform & Pedestal over Pier cap, Fender wall,
Diaphragm wall etc.
Rate same as item 022040 Cum 022040 2602.39 1.00 2,602.39
Add extra for height @15% on the Cost of labour and machinery as per analysis of Cum 022040 723.43 0.15 108.51
item no. 022040 for 1 cum i.e 15% on Cost of labour and machinery for 120 Cum
before adding CPOH, GST etc multiplied by (1.01*1.1405*1.15*1.01) /120.
Cost per cum Cum 2,710.90
022054 Approach slab at formation level, Dirt wall/ ballast wall at formation level
Rate same as item 022040 Cum 022040 2602.39 1.00 2,602.39
Additional cost for thin section and slanting height @5% on the cost of labour and Cum 022040 723.43 0.05 36.17
machinery as per analysis of item no. 022040 for 1 cum i.e 5% on Cost of labour
and machinery for 120 Cum before adding CPOH, GST etc multiplied by
(1.01*1.1405*1.15*1.01) /120.
022055 Extra for every increase of 1m or part thereof in the height above 9.0 m
Taking output = 120 Cum considering increase in cost of labour and machinery in
proportion of height i.e. 10% per meter.
Additional cost of labour per meter height @10% on Cost of labour and machinery 120 Cum 022040 64884.20 0.10 6,488.42
for 120 Cum as per analysis of item no. 022040 before adding overheads and other
percentages like GST, CPOH etc.
Add for Water Charges @ 1% Lumpsum 9902 0.01 64.88
6,553.30
Add for GST @ 12% (multiplying factor 0.1405) Lumpsum 9903 0.14 920.74
7,474.04
Add for Contractor’s Overheads and Profit @ 15% Lumpsum 9904 0.15 1,121.11
8,595.15
Add for Cess @ 1% Lumpsum 9905 0.01 85.95
Cost for 120 Cum 8,681.10
Cost/Cum/mt. height or part thereof Cum 72.34
022060 Providing and laying Plain Cement Concrete 1:3:6 with graded stone aggregate of
40mm nominal size, in foundation and floors, retaining walls of bridges including
mechanical mixing, vibrating, pumping and bailing out water where ever required
with all materials and labour complete but excluding the cost of cement and
shuttering as per drawings and technical specifications as directed by Engineer
CC 1:3:6
Taking output = 15 cum
Material:
Stone Aggregate (Single size) : 40 mm nominal size Cum 0206 754.00 9.75 7,351.50
Stone Aggregate (Single size) : 20 mm nominal size Cum 0207 825.00 3.60 2,970.00
Coarse Sand (Zone III) Cum 0202 1200.00 6.75 8,100.00
Labour:
Mate (Semi skilled) Day 0003 505.00 0.64 323.20
Mason 2nd class (Semi-skilled) Day 0005 505.00 1.00 505.00
Coolie (Un skilled) Day 0026 431.00 15.00 6,465.00
Machinery:
Hire charges of Concrete Mixer 0.25 to 0.40 cubic metre capacity Day 0070 800.00 0.75 600.00
Hire charges of 25 KVA Generator Day 0074 1500.00 0.75 1,125.00
Hire charges of Pin Vibrator Day 0079 350.00 1.00 350.00
Hire charges of surface vibrator Day 0080 300.00 1.00 300.00
Sundries Lumpsum 9901 1.00 500.00 500.00
28,589.70
Add for Water Charges @ 1% Lumpsum 9902 0.01 285.90
Draft IR Unified Standard Analysis of Rates - 2021 Chapter - 2: Bridge Works (Sub-structure)
022070 Providing and fixing Weep Holes in Abutments, Wing walls and Return walls etc., of
new bridges with 110mm dia UPVC pipe Type A ISI marked with all contractor's men,
material, transportation, all taxes as per specifications and as directed by Engineer-in-
Charge.
022080 Boring, providing and installation of bored cast in-situ Reinforced Cement Concrete
piles of specified diameter and length below pile cap of specified grade with Design
Mix Cement Concrete, using 20mm graded crushed stone aggregate and coarse
sand of approved quality, to carry a safe working load not less than specified,
concreting by machine batching, machine mixing, scaffolding, using Admixture in
approved proportion (as per IS:9103), placing with tremie pipe, chipping off of pile
top to remove laitance concrete above cut off level etc., pumping and bailing out
water, by percussion drilling using Direct Mud Circulation (DMC) or Bailor and Chisel
technique by tripod and mechanical Winch machine, complete in all respect as per
approved drawing, specification and direction of the Engineer in charge.
Note:
1. Payment for only cement, reinforcement and permanent casing pipe (if any )
shall be made extra.
2. Length of the pile for payment shall be measured upto the bottom of RCC pile cap.
022090 Boring, providing and installation of bored cast in-situ Reinforced Cement Concrete
piles using Hydraulic piling Rig of specified diameter and length below pile cap of
specified grade with Design Mix Cement Concrete, using 20mm graded crushed
stone aggregate and coarse sand of approved quality, to carry a safe working load
not less than specified, concreting by machine batching, machine mixing, scaffolding,
using Admixture in approved proportion (as per IS:9103), placing with tremie pipe,
chipping off of pile top to remove laitance concrete above cut off level etc., pumping
and bailing out water complete in all respect as per approved drawing, specification
and direction of the Engineer in charge.
Note:
1. Payment for only cement, reinforcement shall be made extra.
2. Length of the pile for payment shall be measured upto the bottom of RCC pile
Cap.
022100 Providing, fabricating and installing permanent casing pipe for bored piles for all
diameters with specified thickness of steel plate including all labour, materials, tools
& complete as per approved drawing & specifications complete in all respect as per
the direction of Engineer in charge.
Note: Payment shall be made as per the weight of circular plate of casing pipe only.
Unit = 1 MT
Taking output = 5 MT = 50 qtl
Considering wastage of 5%, quantity required = 50 x 1.05 = 52.50 quintal.
Material:
Structural Steel Plates conforming to Grade Designation E 250; Quality "A" as per IS Quintal 0223 6300.00 52.50 330,750.00
2062
Considering consumables, machinery, tools & plants required for fabrication, placing 0.15 49,612.50
in position etc. @15% of the cost of plate
Labour:
Welder (Skilled) Day 0029 609.00 1.00 609.00
Fitter Grade - 1 (Skilled) Day 0010 609.00 5.00 3,045.00
Blacksmith - 1st Class (Skilled) Day 0008 609.00 5.00 3,045.00
Fitter Grade - 2 (Semi-skilled) Day 0011 505.00 5.00 2,525.00
Beldar (Un skilled) Day 0025 431.00 30.00 12,930.00
Sundries Lumpsum 9901 1.00 230.00 230.00
402,746.50
Add for Water Charges @ 1% Lumpsum 9902 0.01 4,027.47
406,773.97
Add for GST @ 12% (multiplying factor 0.1405) Lumpsum 9903 0.14 57,151.74
463,925.71
Add for Contractor’s Overheads and Profit @ 15% Lumpsum 9904 0.15 69,588.86
533,514.56
Add for Cess @ 1% Lumpsum 9905 0.01 5,335.15
Rate for 5 MT 538,849.71
Rate per MT MT 107,769.94
022120 Conducting load test of a single pile upto specified capacity in accordance with
IS:2911 (Part-IV) including installation of loading platform and preparation of pile
head or construction of test cap and dismantling of test cap after test etc. with all
labour, material, tool & plants, equipment, machinery, etc. complete as per drawing
and specification, as directed by the Engineer.
022122 Initial load test above 50 ton and upto 100 T capacity pile
Detail of cost of each
Considring requirement of load on loading platform as 150% of pile capacity and
further 25% more for stability of the load, total load required on the platform on the
average of the range i.e. 75 T = 75*1.5*1.25 - 140.63 say 140 mt
Material:
Cost of filled bags including material as sand or earth for kentledge purpose. 1000 nos. 0200 5000.00 2.80 14,000.00
Labour:
(i) For making preparatory arrangement like erecting platform, kentledge etc. for
conducting load test
Mate (Semi skilled) Day 0003 505.00 1.00 505.00
Coolie (Un skilled) Day 0026 431.00 33.00 14,223.00
Fitter Grade - 2 (Semi-skilled) Day 0011 505.00 1.00 505.00
(ii) labour for clearing the site after completion of the test and removing an disposing
the materials.
Mate (Semi skilled) Day 0003 505.00 1.00 505.00
Coolie (Un skilled) Day 0026 431.00 22.00 9,482.00
Mate (Semi skilled) Day 0003 505.00 1.00 505.00
39,725.00
Cost of use of platform materials, instrumentation and other incidental charges @ 0.15 5,958.75
25%
45,683.75
Add for Water Charges @ 1% Lumpsum 9902 0.01 456.84
46,140.59
Add for GST @ 12% (multiplying factor 0.1405) Lumpsum 9903 0.14 6,482.75
52,623.34
Add for Contractor’s Overheads and Profit @ 15% Lumpsum 9904 0.15 7,893.50
60,516.84
Add for Cess @ 1% Lumpsum 9905 0.01 605.17
Cost of each test Each 61,122.01
022123 Initial load test above 100 ton and upto 250 T capacity pile
Detail of cost of each
Considring requirement of load on loading platform as 150% of pile capacity and
further 25% more for stability of the load, total load required on the platform on the
average of the range i.e. 175 T = 175*1.5*1.25 - 328.125 say 328 mt
Material:
Cost of filled bags including material as sand or earth for kentledge purpose. 1000 nos. 0200 5000.00 3.00 15,000.00
Machinery:
Hire Charges of JCB of 0.92 cum bucket Capacity Hour 0058 800.00 8.00 6,400.00
Labour:
(i) For making preparatory arrangement like erecting platform, kentledge etc. for
conducting load test
Mate (Semi skilled) Day 0003 505.00 1.00 505.00
Coolie (Un skilled) Day 0026 431.00 45.00 19,395.00
Fitter Grade - 2 (Semi-skilled) Day 0011 505.00 1.00 505.00
(ii) labour for clearing the site after completion of the test and removing an disposing
the materials.
Draft IR Unified Standard Analysis of Rates - 2021 Chapter - 2: Bridge Works (Sub-structure)
63,526.00
Add for Water Charges @ 1% Lumpsum 9902 0.01 635.26
64,161.26
Add for GST @ 12% (multiplying factor 0.1405) Lumpsum 9903 0.14 9,014.66
73,175.92
Add for Contractor’s Overheads and Profit @ 15% Lumpsum 9904 0.15 10,976.39
84,152.30
Add for Cess @ 1% Lumpsum 9905 0.01 841.52
Cost of each test Each 84,993.83
022124 Extra for every increase of 50 ton in pile capacity or part thereof over 250 ton
Additional hours of Loader required for loading and unloading @ 50MT/hour for
increse of average of additional loading of 25 MT, machine hour required for both
loading/unloading i.e. 25MT + 25 MT = 50 MT is 1 hour
Hire Charges of JCB of 0.92 cum bucket Capacity Hour 0058 800.00 1.00 800.00
Coolie (Un skilled) Day 0026 431.00 6.00 2,586.00
Sundries Lumpsum 9901 1.00 230.00 230.00
3,616.00
Add for Water Charges @ 1% Lumpsum 9902 0.01 36.16
3,652.16
Add for GST @ 12% (multiplying factor 0.1405) Lumpsum 9903 0.14 513.13
4,165.29
Add for Contractor’s Overheads and Profit @ 15% Lumpsum 9904 0.15 624.79
4,790.08
Add for Cess @ 1% Lumpsum 9905 0.01 47.90
Rate per every increase of 50 ton. Each 4,837.98
022126 Routine Load Test above 50 ton capacity upto 100 ton capacity pile
50% of Rate of Initial Test of Pile vide item No. 022122 022122 61122.01 0.50 30,561.00
Rate for each test Each 30,561.00
022127 Routine Load Test above 100 ton capacity upto 250 ton capacity pile
50% of Rate of Initial Test of Pile vide item No. 022123 022123 84993.83 0.50 42,496.91
Rate for each test Each 42,496.91
022130 Lateral load testing of single pile in accordance with "IS Code of practice IS:2911
(Part-IV) for determining safe allowable lateral load of pile” with all labour, material,
tool & plants, equipment, machinery, etc complete as per drawing and specification
as directed by the Engineer
022132 Piles with lateral load capacity of above 50 ton and upto 100 ton
Machinery:
Hire Charges of Hydraulic Jack of 100 t capacity for lateral load testing of piles Day 0113 5000.00 2.00 10,000.00
Cost of reusable material for arrangement of reactive force @ 20% of Hire charges 0.20 2,000.00
of jack
Labour:
Blacksmith - 2nd Class (Semi-skilled) Day 0009 505.00 4.00 2,020.00
Coolie (Un skilled) Day 0026 431.00 16.00 6,896.00
20,916.00
Sundries Lumpsum 9901 1.00 700.00 700.00
21,616.00
Add for Water Charges @ 1% Lumpsum 9902 0.01 216.16
21,832.16
Add for GST @ 12% (multiplying factor 0.1405) Lumpsum 9903 0.14 3,067.42
24,899.58
Add for Contractor’s Overheads and Profit @ 15% Lumpsum 9904 0.15 3,734.94
28,634.52
Add for Cess @ 1% Lumpsum 9905 0.01 286.35
Rate per Test Each 28,920.86
022140 Pulse Echo Test (PET) for integrity testing of piles with contractor’s men, materials
and machines. The rate includes cost of Inspection of site, preparation of pile head
and any other unforeseen cost required for the test, submission of reports in triplicate
as per satisfaction of the Engineer in Charge at site.
Pulse Echo Test (PET) for integrity testing of piles with contractor’s men, materials Each 0111 2000.00 1.00 2,000.00
and machines. The rate includes cost of Inspection of site, preparation of pile head
and any other unforeseen cost required for the test, submission of reports in triplicate
as per satisfaction of the Engineer in Charge at site.
023020 Providing and constructing Temporary Earthen Island / coffer dam for construction of
well foundations of dia. upto 10m (longest dimension) , including bailing and pumping
out of water, provision of sand bags, wooden ballies, sheet piling, earth, sand or any
other suitable material, as required with all labour and material complete job.
023022 Extra for every 1.00m additional depth and part thereof over item 023021 upto water
depth of 4.00m.
Assuming depth of water 4m and height of island 4.5 mts. Island dia = 16mts
average
Assuming depth of water 4.0 m and height of island 4.5 m
Unit = 1 No.
Taking output = 1No.
Material:
Soil Quality Class SQ1 suitable for sub grade of embankment as per RDSO Cum 0168 75.00 904.32 67,824.00
Specifications RDSO/2020/GE: IRS-0004
Filled sand bags (30 kg weight) Each 0201 9.00 6000.00 54,000.00
Hollock Ballies 150mm diameter Metre 0481 150.00 95.00 14,250.00
Draft IR Unified Standard Analysis of Rates - 2021 Chapter - 2: Bridge Works (Sub-structure)
023023 Providing and constructing 10m wide service road to reach island location from one
pier location to another pier location.
Assuming span length of 30 m, width of service road 10m and depth of water 1m
Taking Output = 1 MT
Material:
Structural Steel Plates conforming to Grade Designation E 250; Quality "A" as per IS Quintal 0223 6300.00 10.50 66,150.00
2062
Nut & Bolts with washers of all sizes Kg 0234 80.00 20.00 1,600.00
Electrodes, cutting gas and other consumables @10% of cost of Structural Steel and 0.10 6,775.00
nuts and Bolts above
Labour:
(for cutting, bending, making holes, joining, welding and erecting in position)
Mate (Semi skilled) Day 0003 505.00 1.32 666.60
Fitter Grade - 1 (Skilled) Day 0010 609.00 5.50 3,349.50
Blacksmith - 1st Class (Skilled) Day 0008 609.00 5.50 3,349.50
Fitter Grade - 2 (Semi-skilled) Day 0011 505.00 5.50 2,777.50
Beldar (Un skilled) Day 0025 431.00 16.50 7,111.50
91,779.60
Add for Water Charges @ 1% Lumpsum 9902 0.01 917.80
92,697.40
Add for GST @ 12% (multiplying factor 0.1405) Lumpsum 9903 0.14 13,023.98
105,721.38
Add for Contractor’s Overheads and Profit @ 15% Lumpsum 9904 0.15 15,858.21
121,579.59
Add for Cess @ 1% Lumpsum 9905 0.01 1,215.80
Rate per MT MT 122,795.38
023040 Dry/Wet Sinking of Circular Wells (Other than pneumatic method) in all types of
strata except hard rock requiring ballasting, including bailing and pumping out water,
removal of excavated soil with all labour and material required for sinking as per
drawing and direction of the Engineer in charge, disposal of surplus soil in the
adjoining bank/embankment (compaction to be paid separately under the relevant
item).
8,123.70
Add water charges @ 1% + dewatering charges @5% 0.06 487.42
8,611.12
Add for GST @ 12% (multiplying factor 0.1405) Lumpsum 9903 0.14 1,209.86
9,820.98
Draft IR Unified Standard Analysis of Rates - 2021 Chapter - 2: Bridge Works (Sub-structure)
Hire charges of air compressor 250 cfm capacity with two leads for pneumatic cutters Day 0065 1600.00 0.83 1,328.00
/ hammers
10,750.53
Add water charges @ 1% + dewatering charges @5% 0.06 645.03
11,395.57
Add for GST @ 12% (multiplying factor 0.1405) Lumpsum 9903 0.14 1,601.08
12,996.64
Add for Contractor’s Overheads and Profit @ 15% Lumpsum 9904 0.15 1,949.50
14,946.14
Add for Cess @ 1% Lumpsum 9905 0.01 149.46
Rate per Meter for 63.64 Cum 15,095.60
Rate per Cum Cum 237.29
023050 Extra for above 50m for every 1m or part thereof over item no 023049
12.5% for every additional meter depth of sinking over the rate of 023049 0.13 885.13
Additional cost for 1m Cum 885.13
023060 Dry/Wet Sinking of Twin D type Wells (Other than pneumatic method) in all types of
strata except hard rock requiring ballasting, including bailing and pumping out water,
removal of excavated soil, with all labour and material required for sinking as per
drawing and direction of the Engineer in charge including disposal of surplus soil in
the adjoining bank/embankment (compaction to be paid separately under the
relevant item).
11,868.60
Add water charges @ 1% + dewatering charges @5% 0.06 712.12
12,580.72
Add for GST @ 12% (multiplying factor 0.1405) Lumpsum 9903 0.14 1,767.59
14,348.31
Add for Contractor’s Overheads and Profit @ 15% Lumpsum 9904 0.15 2,152.25
16,500.55
Add for Cess @ 1% Lumpsum 9905 0.01 165.01
Rate per Meter for 64.28 Cum 16,665.56
Rate per Cum Cum 259.27
Hire charges of air compressor 250 cfm capacity with two leads for pneumatic cutters Day 0065 1600.00 1.00 1,600.00
/ hammers
13,468.60
Add water charges @ 1% + dewatering charges @5% 0.06 808.12
14,276.72
Add for GST @ 12% (multiplying factor 0.1405) Lumpsum 9903 0.14 2,005.88
Draft IR Unified Standard Analysis of Rates - 2021 Chapter - 2: Bridge Works (Sub-structure)
023070 Extra for above 50m for every 1m or part thereof over item no 023069
12.5% for every extra metre beyond 50m depth over 023069 0.13 1,097.45
Additional cost for 1m Cum 1,097.45
023080 Extra for sinking of wells in hard rock requiring controlled blasting including cost of
explosive, detonators, chiselling including all other ancillary works
Taking output = 1m
a) Materials
Blasting Powder Kg 0171 50.00 15.00 750.00
Blasting Fuse (Fuse Wire) Each 0172 20.00 60.00 1,200.00
b) Labour
Mate (Semi skilled) Day 0003 505.00 2.00 1,010.00
Rock Hole Driller (Semi skilled) Day 0016 505.00 4.00 2,020.00
Rock Breaker (Semi skilled) Day 0015 505.00 0.40 202.00
Coolie (Un skilled) Day 0026 431.00 40.00 17,240.00
Draft IR Unified Standard Analysis of Rates - 2021 Chapter - 2: Bridge Works (Sub-structure)
023090 Providing and laying in position machine batched, machine mixed and machine
vibrated Cement Concrete of specified grade as per approved Design Mix (Cast in-
Situ) using 20mm graded crushed stone aggregate and coarse sand of approved
quality in the following elements of well including finishing, using Admixtures in
approved proportions (as per IS:9103), to modify workability & other properties
without impairing strength and durability complete as per drawings and technical
specifications as directed by Engineer. Payment for cement, reinforcement and
shuttering shall be made extra.
Unit = cum
Rate same as for item no. 022040 2,602.39
Add 10 per cent of cost of material and labour towards cost of forming sump, 0.10 260.24
protective bunds, chiselling and making arrangements for under water concreting
with tremie pipe..
Rate per Cum Cum 2,862.63
023100 Supplying and filling ordinary sand in between bottom plug and top plug in wells
including all lead lift handling, re-handling, as a complete job as per specification and
guidelines.
023102 Using sand from other than River bed (This item is to be operated if suitable sand is
not available in River Bed for filling
Unit = Cum
Taking output = 1 cum
a) Materials
Fine Sand (Zone IV) Cum 0203 1000.00 1.20 1,200.00
b) Labour
Mate (Semi skilled) Day 0003 505.00 0.01 5.05
Beldar (Un skilled) Day 0025 431.00 0.30 129.30
1,334.35
Add for Water Charges @ 1% Lumpsum 9902 0.01 13.34
1,347.69
Add for GST @ 12% (multiplying factor 0.1405) Lumpsum 9903 0.14 189.35
1,537.04
Add for Contractor’s Overheads and Profit @ 15% Lumpsum 9904 0.15 230.56
1,767.60
Add for Cess @ 1% Lumpsum 9905 0.01 17.68
Rate per Cubic Meter 1,785.28
Rate per Cum Cum 1,785.28
024030 Launching of precast RCC box segments of any size and barrel length for
single/double line as per approved drawings to the correct alignment and position in
electrified / non-electrified sections safeguarding all utilities ( S&T cable, power
cable, OHE, pipelines etc.) including transportation of box segments from casting
yard to site of launching, dismantling of the existing track, removing & stacking of
ballast, removing surcharge, dismantling of existing bridge built with stone masonry /
cement concrete, placing of Box segments in position either on base slab or
prepared foundation, backfilling after launching of precast box segment and
compaction of earth in surcharge, ballasting & re-laying of track to correct alignment
and geometry, packing and further maintenance till allowing non-stop 20 KMPH over
the re-laid track, complete in all respect as per approved drawing to the satisfaction
of Engineer-in-charge. The rate is all inclusive except the cost of RCC Box
Segments, Base Slabs (if required) and backfill material which shall either be
supplied by railway or paid extra under relevant item.
Note: Unit of 'Each' here means bridge of span(s) with a total linear waterway upto
3m.
Machineriy:
{Considering wastage of machinery-days in transportation to site of work as 50%,
total nos. for Excavator = 4.5, for Hammer Drill / Compressor = 1.5, for Tipper = 3
and for JCB = 3}
Crawler mounted Hydraulic Excavator 200 HP (2.5 cum bucket) Day 0045 16000.00 4.50 72,000.00
Hire charges of air compressor 250 cfm capacity with two leads for pneumatic cutters Day 0065 1600.00 1.50 2,400.00
/ hammers
Hire charges of Power driven hammer drill Day 0083 1500.00 1.50 2,250.00
Hire Charges of JCB of 0.92 cum bucket Capacity Hour 0058 800.00 24.00 19,200.00
Hire and running charges of Tipper 12 Cum Capacity Day 0048 7000.00 3.00 21,000.00
Hire charges of tractor with Ripper arrangement Day 0082 1200.00 2.00 2,400.00
{Considering wastage of machinery-days in transportation to site of work as 50%,
total nos. for Cranes = 4.5 and for Trailer = 1.5}
Hiring charges of 150 MT capacity crane Day 0097 100000.00 4.50 450,000.00
For compaction of surcharge after placement of box
Hire Charges of Slope Vibrator to be attached to Hydralic Excavator for rolling of Day 0054 2000.00 1.00 2,000.00
slope surfaces of embankment.
Hire charges of Hydraulic Excavator (0.9 Cum Bucket Capacity) Day 0044 6400.00 1.00 6,400.00
Labour:
Mate (Skilled) Day 0002 609.00 3.00 1,827.00
Helper (Semi-skilled) Day 0021 505.00 5.00 2,525.00
Mason 1st class (Skilled) Day 0004 609.00 2.00 1,218.00
Rock Breaker (Semi skilled) Day 0015 505.00 2.00 1,010.00
Labour Unskilled Day 0020 431.00 40.00 17,240.00
Sundries Lumpsum 9901 1.00 1500.00 1,500.00
602,970.00
Draft IR Unified Standard Analysis of Rates - 2021 Chapter - 2: Bridge Works (Sub-structure)
Machineriy:
{Considering wastage of machinery-days in transportation to site of work as 50%,
total nos. for Excavator = 4.5, for Hammer Drill / Compressor = 1.5, for Tipper = 3
and for JCB = 3}
Crawler mounted Hydraulic Excavator 200 HP (2.5 cum bucket) Day 0045 16000.00 4.50 72,000.00
Hire charges of air compressor 250 cfm capacity with two leads for pneumatic cutters Day 0065 1600.00 1.50 2,400.00
/ hammers
Hire charges of Power driven hammer drill Day 0083 1500.00 1.50 2,250.00
Hire Charges of JCB of 0.92 cum bucket Capacity Hour 0058 800.00 24.00 19,200.00
Hire and running charges of Tipper 12 Cum Capacity Day 0048 7000.00 3.00 21,000.00
Hire charges of tractor with Ripper arrangement Day 0082 1200.00 2.00 2,400.00
{Considering wastage of machinery-days in transportation to site of work as 50%,
total nos. for Crane days =4.5 and for Trailer = 1.5}
Hiring charges of 200 MT capacity crane Day 0098 175000.00 4.50 787,500.00
For compaction of surcharge after placement of box
Hire Charges of Slope Vibrator to be attached to Hydralic Excavator for rolling of Day 0054 2000.00 2.00 4,000.00
slope surfaces of embankment.
Hire charges of Hydraulic Excavator (0.9 Cum Bucket Capacity) Day 0044 6400.00 2.00 12,800.00
Labour:
Mate (Skilled) Day 0002 609.00 5.00 3,045.00
Helper (Semi-skilled) Day 0021 505.00 7.00 3,535.00
Mason 1st class (Skilled) Day 0004 609.00 4.00 2,436.00
Rock Breaker (Semi skilled) Day 0015 505.00 4.00 2,020.00
Labour Unskilled Day 0020 431.00 60.00 25,860.00
Sundries Lumpsum 9901 1.00 3000.00 3,000.00
963,446.00
Add for Water Charges @ 1% Lumpsum 9902 0.01 9,634.46
973,080.46
Add for GST @ 12% (multiplying factor 0.1405) Lumpsum 9903 0.14 136,717.80
1,109,798.26
Add for Contractor’s Overheads and Profit @ 15% Lumpsum 9904 0.15 166,469.74
1,276,268.00
Add for Cess @ 1% Lumpsum 9905 0.01 12,762.68
Cost for Double Line Each 1,289,030.68
025000 MISCELLANEOUS
025010 Deduct if 40mm graded stone aggregate is used in place of 20mm graded stone
aggregate in any grade of concrete. (deduction to be made for quantity of concrete)
Material:
Stone Aggregate (Single size) : 20 mm nominal size Cum 0207 825.00 1.00 825.00
Stone Aggregate (Single size) : 40 mm nominal size Cum 0206 754.00 1.00 754.00
Difference of Cost of 40mm and 20mm size stone aggregates -71.00
Add for Water Charges @ 1% Lumpsum 9902 0.01 -0.71
Draft IR Unified Standard Analysis of Rates - 2021 Chapter - 2: Bridge Works (Sub-structure)
025020 Providing and applying two coats of coal tar or bitumen confirming to IS:3117– latest
version on the top and sides of RCC box/slabs @ 1.70 kg/sqm after cleaning the
surface with all labour and materials complete job as directed by the Engineer.
025030 Centering and shuttering including strutting, propping etc. and removal of form for :
025031 All types of bridge sub-structures, e.g. pier, abutment, wing wall, retaining wall, RCC
box type foundations, Abutment cap, Pier Cap, Inspection Platform & Pedestal over
Pier cap, Fender wall, Diaphragm wall etc. upto 5m above ground level
Aluminium washer 2mm thick & 15 mm dia (Shuttering material) 100 nos. 0259 28.75 1.00 28.75
Sundries Lumpsum 9901 1.00 100.00 100.00
Labour:
Carpenter (Semi skilled) Day 0007 505.00 3.00 1,515.00
Beldar (Un skilled) Day 0025 431.00 3.00 1,293.00
Total "B" 4,451.30
Add for Water Charges @ 1% Lumpsum 9902 0.01 44.51
4,495.81
Add for GST @ 12% (multiplying factor 0.1405) Lumpsum 9903 0.14 631.66
Draft IR Unified Standard Analysis of Rates - 2021 Chapter - 2: Bridge Works (Sub-structure)
025032 All types of bridge super-structures, e.g. slabs, I-girders, T-girders, Box girders etc.
upto 5m above ground level.
Details of cost for 10 sqm:
Materials:
Cost of Shuttering Material:
Wall form Panel 1250mm x 450mm (Shuttering material) Each 0255 1150.00 20.00 23,000.00
MS tube 40mm dia (Shuttering material) Metre 0254 293.25 40.00 11,730.00
100mm channel shoulder 2.5 m long (Shuttering material) Each 0253 1322.50 8.00 10,580.00
Adjustable telescopic prop 3m (2.02m-3.75m) (Shuttering material) Each 0256 1265.00 16.00 20,240.00
Beam Clamp 300-380mm (450mm-1070mm) (Shuttering material) Set 0257 454.25 12.00 5,451.00
Sub-Total: 71,001.00
Material:
Considering the above shuttering material can be used 40 times, Cost of using Once, 1,775.03
Aluminium washer 2mm thick & 15 mm dia (Shuttering material) 100 nos. 0259 28.75 1.00 28.75
Sundries Lumpsum 9901 1.00 100.00 100.00
Labour:
(Labour element has been increased by 25% of substructure due to slow progress of
work)
Carpenter (Semi skilled) Day 0007 505.00 4.00 2,020.00
Beldar (Un skilled) Day 0025 431.00 4.00 1,724.00
5,786.93
Add for Water Charges @ 1% Lumpsum 9902 0.01 57.87
5,844.79
Add for GST @ 12% (multiplying factor 0.1405) Lumpsum 9903 0.14 821.19
6,665.99
Add for Contractor’s Overheads and Profit @ 15% Lumpsum 9904 0.15 999.90
7,665.89
Add for Cess @ 1% Lumpsum 9905 0.01 76.66
Cost of 10 sqm 7,742.54
Cost per sqm Sqm 774.25
025033 Extra for additional height over item no. 025031 & 025032 wherever required with
adequate bracing, propping etc. over initial height of 5 metres for every additional
height of 1 metre or part thereof.
Detail of cost for 10 sqms of shuttering for average height of 10 metres - initial
heights 5 metres = 5 metres extra height
Materials
MS tube 40mm dia (Shuttering material) Metre 0254 293.25 40.00 11,730.00
Adjustable telescopic prop 3m (2.02m-3.75m) (Shuttering material) Each 0256 1265.00 12.00 15,180.00
26,910.00
Considering the above shuttering material can be used 40 times, Cost of using Once 672.75
025040 Providing and laying in position machine batched, machine mixed and machine
vibrated Design Mix Cement Concrete of specified grade (Cast in-Situ) using 20mm
graded crushed stone aggregate and coarse sand of approved quality in jacketing of
piers and abutments from bottom of foundation upto a height of 10m including
finishing for designed thickness of jacketing. Payment for reinforcement, cement,
wire mesh, shuttering, drilling of holes and insertion of rods will be made extra.
025041 Extra for drilling 32mm dia. holes for jacketing / anchoring
Taking out put 50 mts.
Labour:
Mate (Semi skilled) Day 0003 505.00 1.00 505.00
Rock Hole Driller (Semi skilled) Day 0016 505.00 2.00 1,010.00
Coolie (Un skilled) Day 0026 431.00 2.00 862.00
Beldar (Semi Skilled) Day 0024 505.00 2.00 1,010.00
Machinery:
Hire charges of air compressor 250 cfm capacity with two leads for pneumatic cutters Day 0065 1600.00 0.50 800.00
/ hammers
Sundries Lumpsum 9901 1.00 60.00 60.00
4,247.00
Add for Water Charges @ 1% Lumpsum 9902 0.01 42.47
4,289.47
Add for GST @ 12% (multiplying factor 0.1405) Lumpsum 9903 0.14 602.67
4,892.14
Add for Contractor’s Overheads and Profit @ 15% Lumpsum 9904 0.15 733.82
5,625.96
Add for Cess @ 1% Lumpsum 9905 0.01 56.26
Cost for 50 mts. 5,682.22
Rate per Metre Metre 113.64
Draft IR Unified Standard Analysis of Rates - 2021 Chapter - 2: Bridge Works (Sub-structure)
025042 Extra for inserting of dowel bars of specified dia. (cost of rods to be paid extra)
Taking output 200 M
Labour:
Mate (Semi skilled) Day 0003 505.00 1.00 505.00
Mason 2nd class (Semi-skilled) Day 0005 505.00 1.00 505.00
Coolie (Un skilled) Day 0026 431.00 2.00 862.00
Sundries Lumpsum 9901 1.00 20.00 20.00
1,892.00
Add for Water Charges @ 1% Lumpsum 9902 0.01 18.92
1,910.92
Add for GST @ 12% (multiplying factor 0.1405) Lumpsum 9903 0.14 268.48
2,179.40
Add for Contractor’s Overheads and Profit @ 15% Lumpsum 9904 0.15 326.91
2,506.31
Add for Cess @ 1% Lumpsum 9905 0.01 25.06
Cost for 200 M 2,531.38
Rate per Metre Metre 12.66
025050 Supplying, spreading and compacting well graded hard stone of 63mm average size
(maximum upto 80mm size) in the bottom of foundation of box culverts, bridges etc.
including all lead, lift, ascent, descent etc. complete job as per directions of Engineer
In-charge.
031012 With Soffit level From 9m above Bed Level to12m above Bed Level
Cost of concrete as per item 031011 up to 9 m 2,710.90
Average increase in height beyond 9 metres = (9+12)/2 - 9 m = 1.5 m
Additional cost as per item no. 022055 for 1.5 m height Cum 022055 72.34 1.50 108.51
Rate per cum Cum 2,819.42
Draft IR Unified Stadard Analysis of Rates - 2021 Chapter - 3: Bridge Works (Super-structure)
031014 Extra over USSOR Item no. 031013 for Soffit level beyond 15m above Bed Level for
every 1m or part thereof
Same rate as per item no. 022055 Cum 022055 72.34 1.00 72.34
Rate per cum per metre height Cum 72.34
031015 Deduct for casting of Slab in place of Girders (for any heights)
Deduct 5% for casting of slabs in place of girders for any height on the Cost of Cum 031011 723.43 -0.05 -36.17
labour and machinery of item 031011 for 1 cum,
i.e 5% of basic Cost of labour and machinery for 120 Cum before adding CPOH,
GST etc multiplied by (1.01*1.1405*1.15*1.01) /120.
031020 Providing and launching in position machine batched, machine mixed and machine
vibrated Cement Concrete of specified grade as per approved Design Mix (mixed in
Mobile Concrete Batching/Mixing Plant at site or RMC from approved plants) using
20mm graded crushed stone aggregate and coarse sand of approved quality for the
Precast Prestressed (Post-tensioned) Concrete Girder/Box Girders/Slabs in
contactor’s casting yard in the vicinity of worksite, including finishing, using
Admixtures in approved proportions (as per IS:9103), to modify workability & other
properties without impairing strength and durability, complete as per drawings,
specifications and direction of the Engineer.
Note:
1. Payment for Shuttering, Cement, Reinforcement, HTS cables, Sheathing,
Anchorage Cones, stressing of cables, grouting of the ducts and launching of
girder/slab in position shall be made extra under relevant items.
2. For pre-cast item, loading in transport vehicle in casting yard is included and shall
not be paid extra.
Deduction 5% for Lesser cost in slabs than beams and girders cum -0.05 -36.49
Cost per cum Cum -36.49
031030 Providing and launching in position machine batched, machine mixed and machine
vibrated Cement Concrete of specified grade as per approved Design Mix (mixed in
Mobile Concrete Batching/Mixing Plant at site or RMC from approved plants) using
20mm graded crushed stone aggregate and coarse sand of approved quality for the
Precast Prestressed (Pre-tensioned) concrete girder/slab in contractor’s casting yard,
including finishing, using Admixtures in approved proportions (as per IS:9103), to
modify workability & other properties without impairing strength and durability,
complete as per specifications and direction of the Engineer.
Note:
1. Payment for Shuttering, Cement, Reinforcement, HTS cables including stressing
and launching of girder/slab in position shall be made extra under relevant items.
2. For pre-cast item, loading in transport vehicle in casting yard is included and shall
not be paid extra.
Draft IR Unified Stadard Analysis of Rates - 2021 Chapter - 3: Bridge Works (Super-structure)
Deduct 5% for lesser cost in slabs than beams and girders -0.05 -36.17
Rate per cum Cum -36.17
031040 Providing, fabricating & fixing in position to exact design profiles, H.T.S. cables of all
classification made from Low Relaxation strands conforming to IS:14268– latest
version in Prestressed (Post-tensioned) Concrete girders/slabs etc. including
supplying, cutting, making into cables with necessary spacers, colour coding,
protecting with water soluble oil at all time, anchoring of cables, supplying and placing
spiral corrugated type galvanized metal steel ducts sheathing made up of Cold
Rolled Cold Annealed (CRCA) mild steel conforming to IS:513 of required diameter/
thickness, vent pipe, placing, bending, routing, fixing, stressing & grouting of cable
ducts with cement grout, Anchorage sets in required number with provision for future
prestressing if any including all lead and lift with contractor’s own materials, labour,
equipments etc. complete as per drawings & specifications. Rate also includes
covering anchorage pads with epoxy mortar of approved quality to avoid corrosion.
Cement for grouting to be paid separately. Payment shall be made in terms of weight
of HTS cables as per drawing.
Unit = 1 MT
Taking output for 18.30m span 2 Girder system RDSO Drg = 1.269MT including
wastage of 10%. Weight without wastages = 1.269/1.1=1.15 MT
031050 Providing, fabricating & fixing in position to exact design profiles, H.T.S. cables of all
classification made from Low Relaxation strands conforming to IS:14268– latest
version in Pretensioned Prestressed Concrete girders/slabs etc. including supplying,
cutting, making into cables with necessary spacers, colour coding, protecting with
water soluble oil at all time, placing, bending, routing, fixing, stressing including all
lead and lift with contractor’s own materials, labour, equipments etc. complete as per
drawings & specifications. Payment shall be made in terms of weight of HTS cables
as per drawing.
Unit = 1 MT
Taking output for PSC Slab 1.000 MT including wastage of 10%. Weight with
wastages = 1.10MT
Materials:
Low relaxation H T Strands conforming to IS 14268 latest version for prestressed MT 0216 57000.00 1.10 62,700.00
concrete
(Wastage 10% considered)
Labour:
(i) For making and fixing cables
Mate (Semi skilled) Day 0003 505.00 0.16 80.80
Blacksmith - 1st Class (Skilled) Day 0008 609.00 1.00 609.00
Coolie (Un skilled) Day 0026 431.00 3.00 1,293.00
(ii) For prestressing
Mate (Semi skilled) Day 0003 505.00 0.50 252.50
Fitter Grade - 1 (Skilled) Day 0010 609.00 1.00 609.00
Coolie (Un skilled) Day 0026 431.00 2.00 862.00
Machinery:
Hire charges of stressing jack with pump for stressing of HTS cables in PSC Day 0109 11500.00 0.50 5,750.00
girders/slabs.
Hire charges of Generator of 250 KVA capacity Day 0077 3000.00 0.60 1,800.00
Sundries Lumpsum 9901 1.00 1100.00 1,100.00
75,056.30
Add 10% of total cost for component of stressing frame Lumpsum 0.10 7,505.63
82,561.93
Add for Water Charges @ 1% Lumpsum 9902 0.01 825.62
83,387.55
Add for GST @ 12% (multiplying factor 0.1405) Lumpsum 9903 0.14 11,715.95
95,103.50
Add for Contractor’s Overheads and Profit @ 15% Lumpsum 9904 0.15 14,265.52
109,369.02
Add for Cess @ 1% Lumpsum 9905 0.01 1,093.69
Cost of 1.00 MT 110,462.72
Rate per MT MT 110,462.72
031070 Making suitable designed staging for cast in-situ PSC girders/slabs upto 10.5m
height from bed level upto soffit of girder/slab with all contractors materials,
machinery, tools and plants, transportation complete in all respects required for
casting and removal of the same after completing the work and restoring the site to
original. The payment for staging shall be made on the cubical quantity of main
Girders/slabs.
Considering cost of staging for 24.4 m PSC Box girder (Concrete qnty: 160.00 Cum)
Material:
Concrete Pedestal for CC cribs as per item no. 022060 Cum 022060 2550.08 18.00 45,901.48 A
(PCC 1:3:6) 10.00x4.00x2.00 x 0.75x0.30
Ordinary Portland Cement 43 grade MT 0188 4940.00 4.04 19,962.54
(18.00x4.49/20=4.041 MT)
Quantity of steel used in CC crib and ISMB/ISMC support for centering and
shuttering.
1. CC Cribs 244 Nos @ 180kg each =244*180/100 = 439.20 q
2. ISMB 200 length 66m @ 24.2kg/m = 66 x 24.2/100 =15.97 q
3. ISMC 100 length 120m @ 9.56kg/m =120x9.56/100 =11.47q
Total weight = 439.20+15.97+11.47 = 466.64 q.
Considering 25% salvage value and number of uses befire being unserviceable as 20
time, the weight to be charged for using once = 0.75 x 466.64/20 = 17.499 Say 17.50
q.
Considering fabrication cost of crib as 50% of the cost of steel, the quantity of steel to
be charged for using once = 1.50 x 17.50 = 26.25 q
Structural steel such as T, Angles, Channels and R S Joists conforming to Grade Quintal 0224 4950.00 26.25 129,937.50
Designation E 250; Quality "A" as per IS 2062
Machinery:
Transportation of cribs to site of work (One truck, 3 days each for transportation to
site and back after dismantling
Hire charges of Diesel Truck - 9 tonne Day 0060 3940.00 6.00 23,640.00
Hire charges of 12 MT Hydra Day 0090 5000.00 4.00 20,000.00
Hire charges of 12 MT Hydra Day 0090 5000.00 2.00 10,000.00
Labour:
Beldar (Un skilled) Day 0025 431.00 60.00 25,860.00
Sundries Lumpsum 9901 1.00 1000.00 1,000.00
Total 276,301.52
Total except A 230,400.04
Add for Water Charges @ 1% Lumpsum 9902 0.01 2,304.00
232,704.04
Add for GST @ 12% (multiplying factor 0.1405) Lumpsum 9903 0.14 32,694.92
265,398.96
Add for Contractor’s Overheads and Profit @ 15% Lumpsum 9904 0.15 39,809.84
305,208.80
Add for Cess @ 1% Lumpsum 9905 0.01 3,052.09
Total except A with water charges, overheads etc. 308,260.89
Cost including A with water charges, overheads etc. 354,162.37
Cost for 160 Cum (24.4 metres span) 354,162.37
Rate per Cum Cum 2,213.51
031080 Supplying and laying in position specified grade precast prestressed cement concrete
ballast retainers of size, as directed by Engineer In-charge. Payment for Shuttering,
Cement, reinforcement, HTS cables, anchorage cones, stressing of cables and
grouting of the ducts will be done extra.
Labour:
Mate (Semi skilled) Day 0003 505.00 0.06 30.30
Mason 1st class (Skilled) Day 0004 609.00 0.50 304.50
Coolie (Un skilled) Day 0026 431.00 0.50 215.50
Machinery:
Hire charges for 200 MT capacity Jack Day 0107 1500.00 0.50 750.00
Sudries, adhesives misc. T & P and consumables Lumpsum 9901 1.00 500.00 500.00
17,160.30
Add for Water Charges @ 1% Lumpsum 9902 0.01 171.60
17,331.90
Add for GST @ 12% (multiplying factor 0.1405) Lumpsum 9903 0.14 2,435.13
19,767.04
Add for Contractor’s Overheads and Profit @ 15% Lumpsum 9904 0.15 2,965.06
22,732.09
Add for Cess @ 1% Lumpsum 9905 0.01 227.32
Cost of volume of elastometer = 19200 cu.cm. 22,959.41
Rate per cucm Cu Cm 1.20
031100 Providing and fixing in position of standard preformed sealed and slab type or strip
seal elastomeric type expansion joints for Railway bridge or Road Over Bridges as
per approved drawings and latest MOST/IRC specifications complete in all respect as
directed by Engineer in-charge.
031110 Load testing of one or more spans of bridge as selected by the Engineer as per
approved load test procedure following relevant IS/IRC/Railway codes with
contractor’s labour, deflection measuring instruments, loading materials, recoding and
analyzing the load testing results including all lead & lift, etc. complete as required.
The rates are all inclusive and will be paid after load test is finished and girder is
cleared of the kentledges/loading material etc. The load shall be 1.25 times the
stipulated design load.
031112 Extra for every increase 1 MT or part thereof in the span design load capacity upto
800 MT
Draft IR Unified Stadard Analysis of Rates - 2021 Chapter - 3: Bridge Works (Super-structure)
Labour:
Coolie (Un skilled) Day 0026 431.00 4.00 1,724.00
Add for Water Charges @ 1% Lumpsum 9902 0.01 17.24
1,741.24
Add for GST @ 12% (multiplying factor 0.1405) Lumpsum 9903 0.14 244.64
1,985.88
Add for Contractor’s Overheads and Profit @ 15% Lumpsum 9904 0.15 297.88
2,283.77
Add for Cess @ 1% Lumpsum 9905 0.01 22.84
Cost of 9 MT 2,306.60
Rate per MT MT 256.29
031120 Casting and installation of single/twin RCC box of all sizes with or without common
web section including design of pushing scheme, thrust bed, casting of all RCC
components, with specified grade of controlled concrete, pushing it in correct position
and alignment below Railway track/Road following all measures of track safety by
“Box pushing technique" as per approved drawings/scheme, with or without
surcharge in all types of soils with disposal of surplus earth away from vent up to 1
Km, fixing arrangement for all services & utilities including parapet walls on both
sides,wearing course, foot paths, plaques, drainage arrangements etc. and all other
incidental works to complete the ROB/RUB/Canal crossing in all respect as per
specifications to the satisfaction of Engineer-in-Charge.
Note:
1. The rate includes all items of work/supplies for complete job in all respects except
"cost of Reinforced cement concrete, cement, reinforcement & shuttering" of (i) main
RCC Box; (ii) Thrust Bed; (iii) Footpath and (v) wearing Course only, which shall be
paid extra under relevant items of USSOR.
2. The payment for this item shall be made for the clear inner cross section area of
the parent RCC Box/Boxes per unit barrel length i.e. clear inner volume of parent
RCC Box/Boxes.
Box Dimensions
Clear span: 5.50M
Height of the box : 5.0M
Wall thickness: 60 cm
Slab thickness: 60 cm
Barrel length for three track of BG (34.8+35.8)/2=35.3m
Inside dimensions of box: 5.5 X5.0 X35.3m
Out side dimenshions of box: 6.7 X6.35 X 35.3m
Thrust Bed Dimensions
Length of thrust bed: 34.8 Mts
width of thrust bed: 7.6 mts
Thickness of thrust bed: 0.75 Mts
Cost of Box pushing except the cost of concrete, cement, reinforcement & shuttering
of RCC Box and Thrust Bed.
Earth work in excavation all types of soil and disposal of surplus soil upto a lead of Cum 022011 169.23 3937.68 666,359.29 A
50 M as per item no. 022011
(i) for thrust bed ( 34.80 X 7.60 X 8.00) = 2115.84
(ii) For Box Portion ( 6.70 X6.35 X 35.30) = 1501.84
(iii ) for approach formation ( 8.00 x20.00 x2.00) =320.00
Draft IR Unified Stadard Analysis of Rates - 2021 Chapter - 3: Bridge Works (Super-structure)
Dewatering of accumulated water from any location.Payment to be done for horse HP Hour 052260 40.58 150.00 6,087.62 A
power of pump multiplied by pumping hour 10 days x 3 hours per day x 5 hp =150 as
per item no. 052260
Providing and laying Cement Concrete 1:4:8 using 40 mm aggregate in base Cum 022036 2549.73 13.22 33,717.67 A
course below thrust bed 34.80 X 7.60 X 0.05 = 13.224 Cum as per item no. 022036
Providing 50 mm thick screed with CC 1:2:4 using 12.5 mm aggregate thrust bed Cum 022032 2520.20 13.22 33,327.15 A
34.80 X 7.60 X 0.05 = 13.224 as per item no.022032
Cutting edge total qty 12000 kg - 3.00MT for each box out of which 1500 kg will be MT 023030 122795.38 2.78 341,371.16 A
embeded in concrete and cannot be reused and balance 1500 kg wiil be useful as
scrap after pushing as per item no 023030.
- Salvage value of 50% of steel quantity i.e 3000/2 = 1500 kg.@15%
Net quantity = 1500 x 1.85 = 2775 kg = 2.775 MT Say 2.78 MT
Polyvinyl chloride sheet 400 micron. Sqm 0248 40.25 536.56 21,596.54
Supplying of polyvinyl chloride sheet 400 micron. Thrust bed area 35.3 X 7.6 X 2
times
Grease MP-2 or equivalent of HPCL/BPCL/IOCL Kg 0187 153.00 120.00 18,360.00
Structural Steel Plates conforming to Grade Designation E 250; Quality "A" as per IS Quintal 0223 6300.00 16.00 100,800.00
2062
(Pins and packings plate total qty 16000 Kgs this can be used for 10 box pushings
works Net qty for each box pushing = 16000/10 =1600 Kg- 16 Quintals)
Hire charges for 200 MT capacity Jack Day 0107 1500.00 735.00 1,102,500.00
(21 Jacks required per day X 35 Days at the rate of 1.0 m length of pushing per
day)
Hire charges for Power pack with 200 litres capacity tank with 10 HP 3 phase Day 0078 5265.00 35.00 184,275.00
induction mortar, inlet, out let valves pressure gauges, hose pipes etc for pushing
arrangement including consumables, tools, plants, operator, and transportation to
site of work
Hire charges for 3 phase generator (60 KVA) Day 0075 2000.00 35.00 70,000.00
Providing road crane ( hydra ) of 12 MT capacity for mobilization heavy machinery
like pins, packs and jacks etc
Hire charges of 12 MT Hydra Day 0090 5000.00 35 175,000.00
(P) Providing and removing barricading with the help of portable fencing with self Metre 013041 191.89 100.00 19,188.53 A
supporting steel angles of size 50 x50x6mm, 1.5m long provided with hooks etc.
and embedded in CCreflective tapes in Horizontal & vertical direction. Note :
Released material will be the property of the contractor after the completion of work.
Cost of cement to be paid separately as per item no 013041
Hire charges of 7.5 KVA Generator Day 0073 1000.00 35.00 35,000.00
Hire Charges of Halogen Lamps 500 Watt Nos. 0488 40.00 420.00 16,800.00
slewing of disturbed track to correct alignment , lifting /lowering of track under traffic
condition and maintenance of track to required standard during the entire period of
box pushing with all contractors tools and plants ( daily 6+1+1 labour for 35 days.
Labour shall work for track correction for half day and other works in remaining
period.
Labour:
Highly Skilled labour Day 0018 714.00 35.00 24,990.00
Mate (Skilled) Day 0002 609.00 18.00 10,962.00
Labour Unskilled Day 0020 431.00 122.00 52,582.00
Coolie (Un skilled) Day 0026 431.00 20.00 8,620.00
Draft IR Unified Stadard Analysis of Rates - 2021 Chapter - 3: Bridge Works (Super-structure)
031121 Extra for using GI Drag Sheet for protection of track support from subsidence while
pushing the box as per design over item no. 031120.
Note:The payment for this item shall be made for the clear inner cross section area of
the parent RCC Box/Boxes and barrel length.
Material:
Drag sheets: 1.50 mm thick GI Sheet in ribbons of 50 cm width 36 x 6.7 = 241.2 Sq.M x
11.77 kg/sq.m=2840 kgs
GI Sheet 1.50 mm thick Quintal 0246 4600.00 28.39 130,594.00
Supporting frame and ancillary arrangement for fixing of drag sheet MT 023030 122795.38 5.74 704,845.50 A
Total qty 9000 kg - 9.00MT. After completing the work, 85% of structural steel shall
be salvaged and considering scrap value @ 25% of the original cost, quantity to be
charged for providing arrangement = 9000 x 0.85 x (1-0.25) = 5737.5 kg Say 5.74
MT. Rate of fabricated arrangement as per item no. 023030.
Box Dimensions
Adopting appoved GAD Drg No GM/W/SC/BR/RUB/SC/3903/2018 dimensions
Excavation in formation and insertion of Temporary girder , cribs and for air pushing
as per item no. 022011
(ii) Main Box Portion = 2500 Cum
All kinds of soils Cum 022011 169.23 2500.00 423,065.92 A
(B) Leading of excavated earth up to 1km i.e. average lead of 0.5 km. Cost as per Cum 012015 3.12 2150.40 6,713.24 A
50% of the rate of item No. 011015 for 70% of the excavated quantity considering
30% as backfill
(a) for thrust bed = 572.00
(b) For Box Portion = 2500
(c) for approach formation = 320.00
Total quantity of excavation = 3072.00 cum
Quantity taken for leading = 70% x 3072.00 cum = 2150.40
(C) Providing and laying Cement Concrete 1:4:8 using 40 mm aggregate in base Cum 022036 2549.73 7.93 20,219.38 A
course below thrust bed 20.875.00 X 7.60 X 0.05 = 7.933 Cum as per item no.
022036
Draft IR Unified Stadard Analysis of Rates - 2021 Chapter - 3: Bridge Works (Super-structure)
RH /Temporary girder of length varying from 12.2m to 16.3m using road crane Each 191041 91124.59 1.00 91,124.59
capacity of 80 tons
Note:- Excavated earth from Rly area will be used
Quantity of sleepers for 56 Sleepers= 56 x 2.74 x 0.20 x 0.15 = 4603 Cudm = 460.32
Manufacturing and using wooden sleepers/blocks required for matting and bearing as Cum 191030 936.56 4.60 4,310.97 A
per approved design for use below and above CC Crib for insertion of Temporary
Girder.
Note: The item is for one time use and released wooden sleepers/blocks shall be the
property of the Contractor.
Rolling of box
JACKS
Jacks ( One jack of 200 MT capacity is required for jacking of 100 MT weight of
box. Wieght per 1 mt length of 5.5 x 5.375 m box = 37.75 MT for 16.85 mt length
636 Mt +1/4 of 636 MT for friction total 795 MT ie 8 jacks + 2spare 10 jacks
required x (5+3) days for rolling 10 jacks per day x 8 days =80 jacks
Hire charges for 200 MT capacity Jack Day 0107 1500.00 80.00 120,000.00
031140 Fabrication, insertion and removal of rail cluster below the running track to ensure
safety of track during box pushing in correct position and alignment with Railway rails
and contractors MS flats, wooden blocks, and 12 mm dia bolts etc., as per approved
drawing including removing and filling back of ballast below track under traffic
conditions of Electrified/Non-Electrified section with all contractors, labour, tools,
tackles, consumables plants, and 50MT capacity crane and any other material
required for execution of work in all respect with all lead and lift, transportation and as
directed by Engineer in-charge. Payment quantity shall be as per the weight of rail in
rail cluster used at site or as per approved drawing, whichever is minimum.
Note:
(i) Insulated Elastomeric pad (Railway supplied) shall be used between Running rails
and cross rails to prevent failure of track circuit.
(ii)CC Cribs will be supplied by the railways at free of cost, if they are required to be
inserted under the track.
Transportation to the site and back to the required location will be paid by Railways
under relevant agreement item
(iii)Rail cluster should be properly maintained by proper packing under wooden blocks
/mattings during passage of trains and de assemble after completion of work
Hard Variety Jungle Wood blocks 10 Cudm 0343 350.00 86.40 30,240.00
Supply of 12 mm dia screws ( .35 length 16 Nos )
Nut & Bolts with washers of all sizes Kg 0234 80.00 0.96 76.48
Providing road crane of 50 MT capacity for Day 041203 27561.52 3.00 82,684.55
insetion /removal of rail cluster and handling of rails
Handling of rails during insertion /removal and De assemblibg rail cluster
Labour Unskilled Day 0020 431.00 8.00 3,448.00
Sundries Lumpsum 9901 1.00 25.00 25.00
Sub-Total Including 'A' 137,534.03
Draft IR Unified Stadard Analysis of Rates - 2021 Chapter - 3: Bridge Works (Super-structure)
031150 Launching of precast RCC box segments for RUBs/Limited Height Subways (LHS) of
any size and barrel length for single/double line as per approved drawings to the
correct alignment and position in electrified / non-electrified sections safeguarding all
utilities ( S&T cable, power cable, OHE, pipelines etc.) including transportation of box
segments from casting yard to site of launching, dismantling of the existing track,
removing & stacking of ballast, cutting of formation and approach road below or
above bed level, placing of base slabs & Box segments in position, backfilling after
launching of precast box segment, ballasting & re-laying of track to correct alignment
and geometry, packing and further maintenance till allowing non-stop 20 KMPH over
the re-laid track, complete in all respect to the satisfaction of Engineer-in-charge. The
rate is all inclusive except the cost of RCC Box Segments, Base Slabs and backfill
material which shall either be supplied by railway or paid extra under relevant item.
Note: Minimum equipment required during block shall be (i) Crawler mounted
Hydraulic excavator of min 200 HP and bucket capacity 2.5 cum - 3 numbers and (ii)
3 cranes of adequate boom length suitable for launching box segments in position
(min capacity of each crane - 200 MT for Single Line and 300 MT for Double Line)
apart from other equipments, tools, plants and machinery required to complete the job
within the allowed block period.
Crawler mounted Hydraulic Excavator 200 HP (2.5 cum bucket) Day 0045 16000.00 4.50 72,000.00
Hiring charges of 200 MT capacity crane Day 0098 175000.00 4.50 787,500.00
Hire charges of Power driven hammer drill Day 0083 1500.00 1.50 2,250.00
Hire charges of air compressor 250 cfm capacity with two leads for pneumatic cutters Day 0065 1600.00 1.50 2,400.00
/ hammers
Hire and running charges of Tipper 12 Cum Capacity Day 0048 7000.00 1.50 10,500.00
Hiring of Trailor truck of 20 MT capacity Day 0102 18000.00 1.00 18,000.00
Hire charges of 7.5 KVA Generator Day 0073 1000.00 3.00 3,000.00
Hire Charges of Halogen Lamps 500 Watt Nos. 0488 40.00 12.00 480.00
Sundries Lumpsum 9901 1.00 5000.00 5,000.00
921,518.00
Add for Water Charges @ 1% Lumpsum 9902 0.01 9,215.18
930,733.18
Add for GST @ 12% (multiplying factor 0.1405) Lumpsum 9903 0.14 130,768.01
1,061,501.19
Draft IR Unified Stadard Analysis of Rates - 2021 Chapter - 3: Bridge Works (Super-structure)
031160 Loading, tranportation of Precast RCC Girders / Slabs / Ballast retainers / Steel
Girders etc. from Casting Yard to Site of Work, unloading and stacking at site of work
at prescibed location as directed by Engineer-in-Charge.
031190 Providing and fixing in position GI Drainage Spouts of required length with Grating in
RCC slab and filling bitumen along kerb as shown in drawing with contractor's pipes,
bitumen, tools, equipment, lead, lifts etc. complete as per specifications and as
directed by Engineer in-charge.
031200 Applying Epoxy Poly-sulphate Paint three coats on existing bottom surface of deck
slab including cleaning surface of dirt, dust & other foreign matter, sand papering,
wire brushing as required with all contractor’s materials tools, machinery, scaffolding,
lead, lifts etc. complete as per specifications and as directed by Engineer in-charge
031210 Supplying and laying 160mm dia. PVC Pipes Class-I, capable for a pressure of 2.5
kg/sqm in footpath of ROB for laying cable with all contractor’s materials labour, tools,
plant, machinery, vehicles, consumables, lead, lift etc. complete as per specifications
and as directed by Engineer in-charge.
Structural steel plates conforming to Grade Designation E250; Quality "B0" as per Quintal 0225 7330.00 147.60 1,081,908.00
IS:2062,
Structural steel such as T, Angles, Channels and R S Joists conforming to Grade Quintal 0226 5730.00 6.65 38,104.50
Designation E250; Quality "B0" as per IS:2062,
(B) Cutting:
(i) Plates
Cutting length : 243.748 m (All Thicknesses)
Gas Required for Cutting
DA Gas in cylinder @ 1 Cylinder of 19 Kg per 26m length of Cutting
Acetylene Gas (in cylinder) Kg 0341 65.00 178.12 11,578.03
Oxygen Cylinder @ 7 Cylinders ( 7 Cum) per 26m length of Cutting (Density of Gas
1.429 Kg/M3. Qnty of Gas in Kgs = 243.748/26*7*7*1.429 =656.44 Kg)
Oxygen Gas (in cylinder) Kg 0340 50.00 656.44 32,822.07
Hire Charges of CNC Gas Cutting machine @ 0.400m/1min = 243.748/0.40/60 = 10.15
Hours Say12 Hours
Hire Charges of CNC gas cutting Machine Day 0115 4500.00 1.50 6,750.00
Highly Skilled labour Day 0018 714.00 1.50 1,071.00
Labour Skilled (For Steel Fabrication i.e. Machine Operator/Welder/Machinist etc.) Day 0019 609.00 1.50 913.50
(ii) Angles
Total Number of Cuts = 120
Hack Saw Blades Each 0458 593.22 2.00 1,186.44
Time required @ 1 Cut in 5 minutes
Labour Skilled (For Steel Fabrication i.e. Machine Operator/Welder/Machinist etc.) Day 0019 609.00 2.00 1,218.00
Labour Unskilled Day 0020 431.00 2.00 862.00
Edge finishing by Grinding
Total length for finishing = 2,43,748 mm i.e 243.748m
Grinding of 12 meters requires 20 min
Time required @ 12m in 20 minutes = 243.748/12*20/60 = 6.77 Hours
Cup Grinding Stone Each 0236 900.00 1.00 900.00
Draft IR Unified Stadard Analysis of Rates - 2021 Chapter - 4: Bridge Work (SuperStructure-Steel)
Electrodes for steel fabrication work Metre 0238 24.00 789.14 18,939.36
A Welder can do 3m length of FCAW/GMAW mig welding per hour
No of Welders required = 1238.95/3.0 = 412.98 Hours i.e. 51.62 Days say52 Days
Highly Skilled labour Day 0018 714.00 52.00 37,128.00
Labour Skilled (For Steel Fabrication i.e. Machine Operator/Welder/Machinist etc.) Day 0019 609.00 52.00 31,668.00
Labour Unskilled Day 0020 431.00 52.00 22,412.00
Hire Charges of MMAW machine ( Manual Metal Arc Welding Machine) - 80 to 500 Day 0117 25.00 45.00 1,125.00
Amperes.
(ii) SAW Welding
SAW total length = 3716908 mm of 6mm fillet weld
Volume of Wire required = 1/2*6*6*37,16,908 = 6,69,04,344 mm3
Weight of Wire required = 6,69,04,344 / 109*7850 = 525.199 Kg Say 525
SAW Welding Wire Kg 0240 66.00 525.00 34,650.00
Flux used =1/3 rd of weight of wire = 575/3 = 175 kg
Draft IR Unified Stadard Analysis of Rates - 2021 Chapter - 4: Bridge Work (SuperStructure-Steel)
Hire Charges of SAW machine - Tornado Make, current range - 150 to 1250 Amperes. Day 0118 7500.00 20.00 150,000.00
Hire Charges of Angle grinder - 230mm dia. Disc, 6000 rpm, CP make. Day 0119 11.00 38.00 418.00
(D) Trial Assembly of Girder & Inspection; 1 span will take 25 days for assembly
and 5 days for dismantling i.e total 30 days
Cost of Service Bolts for assembling of Girders Each 0243 35.00 1800.00 63,000.00
Highly Skilled labour Day 0018 714.00 60.00 42,840.00
Labour Skilled (For Steel Fabrication i.e. Machine Operator/Welder/Machinist etc.) Day 0019 609.00 60.00 36,540.00
041013 Extra for using steel conforming to Grade Designation E350 instead of Grade
Designation E250 of Quality "B0" as per IS: 2062
Structural Steel such as T, Angles, Channels and R S Joists Grade Designation Quintal 0229 6000.00 1.00 6,000.00
E350; Quality 'B0' as per IS 2062
Structural steel such as T, Angles, Channels and R S Joists conforming to Grade Quintal 0226 5730.00 1.00 5,730.00
Designation E250; Quality "B0" as per IS:2062,
Rate Difference 270.00
Add for Water Charges @ 1% Lumpsum 9902 0.01 2.70
272.70
Add for GST @ 12% (multiplying factor 0.1405) Lumpsum 9903 0.14 38.31
311.01
Add for Contractor’s Overheads and Profit @ 15% Lumpsum 9904 0.15 46.65
357.67
Add for Cess @ 1% Lumpsum 9905 0.01 3.58
Rate for 1 Quintal 361.24
Rate per MT MT 3,612.43
041014 Deduct for using steel conforming to Quality "BR" instead of Quality "B0" of Grade
designation E250 as per IS:2062.
Structural steel such as T, Angles, Channels and R S Joists conforming to Grade Quintal 0226 5730.00 1.00 5,730.00
Designation E250; Quality "B0" as per IS:2062,
Structural steel such as T, Angles, Channels and R S Joists conforming to Grade Quintal 0228 5500.00 1.00 5,500.00
Designation E250; Quality "BR" as per IS:2062,
Rate Difference -230.00
Sub Total -230.00
Add for Water Charges @ 1% Lumpsum 9902 0.01 -2.30
-232.30
Add for GST @ 12% (multiplying factor 0.1405) Lumpsum 9903 0.14 -32.64
-264.94
Add for Contractor’s Overheads and Profit @ 15% Lumpsum 9904 0.15 -39.74
-304.68
Add for Cess @ 1% Lumpsum 9905 0.01 -3.05
Rate for 1 Quintal -307.73
Rate per MT MT -3,077.26
041015 Extra for using steel conforming to Quality "C" Grade Designation E250 instead of
Quality "B0" Grade Designation E250 of as per IS: 2062
tructural steel such as T, Angles, Channels and R S Joists conforming to Grade Quintal 0227 5860.00 1.00 5,860.00
Designation E 250; Quality "C" as per IS 2062
Structural steel such as T, Angles, Channels and R S Joists conforming to Grade Quintal 0226 5730.00 1.00 5,730.00
Designation E250; Quality "B0" as per IS:2062,
Rate Difference 130.00
Sub Total 130.00
Add for Water Charges @ 1% Lumpsum 9902 0.01 1.30
131.30
Add for GST @ 12% (multiplying factor 0.1405) Lumpsum 9903 0.14 18.45
149.75
Add for Contractor’s Overheads and Profit @ 15% Lumpsum 9904 0.15 22.46
172.21
Add for Cess @ 1% Lumpsum 9905 0.01 1.72
Rate for Qtl Qtl 173.93
Rate per MT MT 1,739.32
041020 Supplying and fixing HSFG bolts of any dia and any length with suitable nuts including
DTI washers conforming to IRS-B1-2001 for bridges and steel structures with
contractors labour, tools and plants and lead and lift etc., complete.
041030 Assembling and erection of fabricated Steel girders on bearings at site with
crane/derrick / any other approved means at site on sub structure with labour,
equipment, T&P including site bolting with all temporary arrangements, scaffolding etc.
with contractors design and scheme for longitudinal launching/side slewing (not
requiring traffic block) approved by Railway. Rate includes drifts, service bolts, Holding
down bolts etc. as per drawings.
Note: Payment for HSFG bolts used if any will be made separately under relevant item.
041031 Plate Girder/Semi Through Girder /Composite Girder more than 12.2 m span
Take a Plate girder of 24.4m of MBG Loading standard weighing 443 Qtl weight
Material:
Holding down HTS bolts with plates, nuts etc. Quintal 0235 7500.00 0.25 1,875.00
20 mm dia holding down bolts 16nos.x460 mm 1840 mm Add wastage @ 5%
Total = 7.728 m @ 2.74kg/m = 21.17 kg = 0..21 quintal say 0.25 Qtls with nuts etc.
Labour:
Labour for errecton or launching
Blacksmith - 1st Class (Skilled) Day 0008 609.00 10.00 6,090.00
Blacksmith - 2nd Class (Semi-skilled) Day 0009 505.00 20.00 10,100.00
Fitter Grade - 1 (Skilled) Day 0010 609.00 10.00 6,090.00
Beldar (Semi Skilled) Day 0024 505.00 20.00 10,100.00
Beldar (Un skilled) Day 0025 431.00 20.00 8,620.00
Machinery:
Hiring charges of Crane 20 MT capacity Day 0092 8000.00 10.00 80,000.00
Hire charges of air compressor 250 cfm capacity with two leads for pneumatic cutters / Day 0065 1600.00 5.00 8,000.00
hammers
Hire charges of Camber Jacks etc. Day 0108 500.00 30.00 15,000.00
145,875.00
Sudries, adhesives misc. T & P and consumables Lumpsum 9901 1.00 2000.00 2,000.00
147,875.00
Add for Water Charges @ 1% Lumpsum 9902 0.01 1,478.75
149,353.75
Add for GST @ 12% (multiplying factor 0.1405) Lumpsum 9903 0.14 20,984.20
170,337.95
Add for Contractor’s Overheads and Profit @ 15% Lumpsum 9904 0.15 25,550.69
195,888.64
Add for Cess @ 1% Lumpsum 9905 0.01 1,958.89
cost of 443 Qtls. 197,847.53
Cost of Staging as per item no. 031070 for 24.40m 031070 354162.37 1.00 354,162.37
Total cost for 443 qtl 552,009.90
Rate Per Qtl. Quintal 1,246.07
Rate per MT MT 12,460.72
041040 Metalizing of steel work of girders with sprayed aluminium after surface preparation by
Sand/grit blasting, followed by one coat of etch primer (IS:5666) & one coat of Zinc
Chrome primer (IS:104) and two coats of aluminium paint (IS:2339) with all labour, T&P
and material as a complete job duly conforming to all relevant specifications and
process given under Clause 39 of IRS-B1-2001.
Note: Nominal Thickness of Aluminium coating shall be 150 microns. DFT of Zinc
chrome primer shall be 25-30 microns and DFT of each coat of Aluminium paint shall
be 12-14 microns.
Material:
Coarse Sand (Zone III) Cum 0202 1200.00 0.20 240.00
(Consumption at the rate of 50sqm/cum; total quantity required-2.0cum)
Hire charges of air compressor 250 cfm capacity with two leads for pneumatic cutters / Day 0065 1600.00 0.20 320.00
hammers
Hire changes for sand receiver and sand blasting pipes with gun and all accessories Day 0130 500.00 0.20 100.00
complete
Hire charges for metalising gun with all accessories Day 0131 600.00 0.20 120.00
Aluminium wire for spraying Kg 0268 219.93 5.06 1,112.85
150 microns thick(The quantiy required for 10sqm is-10x0.00015X2700=4.05kg + 25%
wastage = 5.06 Kg
Oxygen Gas (in cylinder) Kg 0340 50.00 9.00 450.00
Commercial LPG (in cylinder) Kg 0339 73.71 1.60 117.94
Labour:
labour inculding sand blasting or grit blasting and application of sprayed molten
aluminium
Coolie (Un skilled) Day 0026 431.00 1.00 431.00
Machine Operator (Machine) (Skilled) Day 0041 609.00 0.35 213.15
Add extra for grit blasting Lumpsum 9901 1.00 50.00 50.00
Cost of labour and material for 10 sqm 10 Sqm 3,154.93
Cost of only Sand Blasting for 10 Sqm 10 sqm 925.50
(i) Cost of only Sand Blasting Considering 15 Sqm/MT for Plate Girder 12.2 m Span MT 1,388.25
(ii) Cost of only Sand Blasting Considering 35 Sqm/MT for Open Web Girder 45.70 m MT 3,239.25
Span
041050 Providing and fixing railing used in rows for footpath or anti-crash barrier railing with B
class G.I. pipe 65/50 mm nominal dia including cost of M.S. angle and channels in
vertical posts, welding / bolting, priming painting with one coat ready mix Zinc
Chromate conforming to IS:104 with DFT of 25-30Microns, followed by one coat of Zinc
Chrome red oxide conforming to IS:2074 with DFT of 25 Microns with all material,
labour, T&P as a complete job.
Note: Cost of painting shall be paid extra under relevant item.
041060 Supplying and fixing M.S. Angles 65mmx 65mmx 8mm or any other size conforming to
IS:2062 in the nosing of steps of stair cases of Foot Over Bridges including provision of
10mm dia, anchor bar 600mm c/c and fixing with main girder with M.S. flat, making anti-
slip arrangements over the top of nosing as per approved scheme given by Engineer in
charge with all material, labour, T&P as a complete job.
041070 Providing and fixing various size HTS holding down bolts conforming to IS:1364 in
concrete column or in other structures with proper nuts, bolts, washers/plates,
grouting of holes cement or epoxy concrete with all material, labour, T&P as a complete
job.
041080 Supplying, Fabricating and fixing access ladders, inspection platforms, Trolley refuges
etc., on bridges with structural steel conforming to IS:2062 including welding / bolting,
priming painting with one coat of ready mixed paint of Zinc Chromate (IS:104) with
DFT of 25-30 microns followed by one coat of Zinc Chrome Red Oxide (IS:2074) with
DFT of 25 microns with all material, labour, T&P as a complete job.
Note: Painting shall be paid seperately under relevant item.
Total weight=2.806+.964+.18+.15=4.10MT
Unit = MT
Taking output = 2 x 50 m span = 100 m
Material:
Structural steel such as T, Angles, Channels and R S Joists conforming to Grade Quintal 0224 4950.00 29.50 146,025.00
Designation E 250; Quality "A" as per IS 2062
(ISMC 100 = 2.806 x 1.05 = 2.946 MT)
M S Flat upto 10 mm thickness Quintal 0230 6300.00 10.10 63,630.00
(MS Flat = 0.964 x 1.05 = 1.012 MT)
MS round bar for reinforcement- average rate for various dia Quintal 0220 3600.00 1.80 6,480.00
(MS bars = 0.17 x 1.05 = 0.180 MT)
MS bolts & nuts more than 10 mm dia Quintal 0252 8500.00 1.50 12,750.00
Add for electricity charges, welding and drilling equipment, electrodes and other 228885.00 0.01 2,288.85
consumables @ 1 per cent of cost of material.
Draft IR Unified Stadard Analysis of Rates - 2021 Chapter - 4: Bridge Work (SuperStructure-Steel)
041090 Supplying, fitting and fixing in position true to line and level cast steel rocker/roller
bearing of different load bearing capacity conforming to IS :7666, IS:9565, IS:1030,
IS:919, IS:3073 and IRS Bridge Code including all accessories as per drawing and
Technical Specifications with all material, labour, T&P as a complete job. The payment
shall be made for the load bearing capacity in Metric Tonne as per approved drawing.
041100 Supplying, fitting and fixing in position true to line and level forged steel roller bearing of
different load bearing capacity conforming to IS :7666, IS:9565, IS:1030, IS:919,
IS:3073 and IRS Bridge Code including all accessories as per drawing and Technical
Specifications with all material, labour, T&P as a complete job. The payment shall be
made for the load bearing capacity in Metric Tonne as per approved drawing.
041110 Supplying, fitting and fixing in position true to line and level sliding plate bearing of
different load bearing capacity with PTFE Surface sliding on stainless steel as per
BS:3784, BS 5400, complete including all accessories as per Drawing and Technical
Specifications with all material, labour, T&P as a complete job.The payment shall be
made for the load bearing capacity in Metric Tonne as per approved drawing.
Add 2 per cent for foundation anchorage bolts and consumables. 0.02 480.00
Hire charges for 200 MT capacity Jack Day 0107 1500.00 2.00 3,000.00
28,550.30
Add for Water Charges @ 1% Lumpsum 9902 0.01 285.50
28,835.80
Add for GST @ 12% (multiplying factor 0.1405) Lumpsum 9903 0.14 4,051.43
32,887.23
Add for Contractor’s Overheads and Profit @ 15% Lumpsum 9904 0.15 4,933.08
37,820.32
Add for Cess @ 1% Lumpsum 9905 0.01 378.20
Cost of 80 MT Capacity Bearing 38,198.52
Rate per MT MT 477.48
041120 Design, supply, fitting and fixing in position true to line and level POT-PTFE bearing of
300MT Capacity, consisting of a metal piston supported by a disc or un reinforced
elastomer confined within a metal cylinder, sealing rings, dust seals, PTFE surface
sliding against stainless steel mating surface, complete assembly to be of cast steel /
fabricated structural steel, metal and elastomer elements complete as per IS:2062,
IS:1030, AISI:304, AISI:316, IS:6911, BS:3784, IS:3400, IS:226, BS-5400, Bridge Code
and as per approved drawing and Technical Specifications. The design of the
bearings shall be submitted by the manufacturers / contractor and got approved from
Railway before fixing. Test report after inspection of the bearings shall be submitted
and got approved before the materials are lifted from the manufacturer premises.
Add 2 % of cost of bearing assembly, foundation anchorage bolts, transportation and 0.02 1,157.60
misc. items required during fixing.
Hire charges for 200 MT capacity Jack Day 0107 1500.00 2.00 3,000.00
Sub Total 63,364.77
63,364.77
Add for Water Charges @ 1% Lumpsum 9902 0.01 633.65
63,998.42
Add for GST @ 12% (multiplying factor 0.1405) Lumpsum 9903 0.14 8,991.78
72,990.20
Add for Contractor’s Overheads and Profit @ 15% Lumpsum 9904 0.15 10,948.53
83,938.72
Add for Cess @ 1% Lumpsum 9905 0.01 839.39
Rate of 300 MT Capacity Bearing Each 84,778.11
Add 2 % of cost of bearing assembly, foundation anchorage bolts, transportation and 0.02 1,660.90
misc. items required during fixing.
Hire charges for 200 MT capacity Jack Day 0107 1500.00 2.00 3,000.00
Sub Total 89,033.07
89,033.07
Add for Water Charges @ 1% Lumpsum 9902 0.01 890.33
89,923.40
Add for GST @ 12% (multiplying factor 0.1405) Lumpsum 9903 0.14 12,634.24
102,557.64
Add for Contractor’s Overheads and Profit @ 15% Lumpsum 9904 0.15 15,383.65
117,941.28
Add for Cess @ 1% Lumpsum 9905 0.01 1,179.41
Rate of 300 MT Capacity Bearing Each 119,120.70
Add 2 % of cost of bearing assembly, foundation anchorage bolts, transportation and 0.02 2,023.70
misc. items required during fixing.
Hire charges for 200 MT capacity Jack Day 0107 1500.00 2.00 3,000.00
Sub Total 107,535.87
107,535.87
Add for Water Charges @ 1% Lumpsum 9902 0.01 1,075.36
108,611.23
Add for GST @ 12% (multiplying factor 0.1405) Lumpsum 9903 0.14 15,259.88
123,871.11
Add for Contractor’s Overheads and Profit @ 15% Lumpsum 9904 0.15 18,580.67
142,451.77
Add for Cess @ 1% Lumpsum 9905 0.01 1,424.52
Rate of 300 MT Capacity Bearing Each 143,876.29
Add 2 % of cost of bearing assembly, foundation anchorage bolts, transportation and 0.02 1,935.80
misc. items required during fixing.
Hire charges for 200 MT capacity Jack Day 0107 1500.00 2.00 3,000.00
Sub Total 103,052.97
103,052.97
Add for Water Charges @ 1% Lumpsum 9902 0.01 1,030.53
104,083.50
Add for GST @ 12% (multiplying factor 0.1405) Lumpsum 9903 0.14 14,623.73
118,707.23
Add for Contractor’s Overheads and Profit @ 15% Lumpsum 9904 0.15 17,806.08
136,513.32
Add for Cess @ 1% Lumpsum 9905 0.01 1,365.13
Rate of 300 MT Capacity Bearing Each 137,878.45
Draft IR Unified Stadard Analysis of Rates - 2021 Chapter - 4: Bridge Work (SuperStructure-Steel)
Add 2 % of cost of bearing assembly, foundation anchorage bolts, transportation and 0.02 947.60
misc. items required during fixing.
Hire charges for 200 MT capacity Jack Day 0107 1500.00 2.00 3,000.00
Sub Total 52,433.58
52,433.58
Add for Water Charges @ 1% Lumpsum 9902 0.01 524.34
52,957.91
Add for GST @ 12% (multiplying factor 0.1405) Lumpsum 9903 0.14 7,440.59
60,398.50
Add for Contractor’s Overheads and Profit @ 15% Lumpsum 9904 0.15 9,059.77
69,458.27
Add for Cess @ 1% Lumpsum 9905 0.01 694.58
Rate of 250 MT Capacity Bearing Each 70,152.85
Add 2 % of cost of bearing assembly, foundation anchorage bolts, transportation and 0.02 1,240.90
misc. items required during fixing.
Hire charges for 200 MT capacity Jack Day 0107 1500.00 2.00 3,000.00
Sub Total 67,391.88
67,391.88
Add for Water Charges @ 1% Lumpsum 9902 0.01 673.92
68,065.79
Draft IR Unified Stadard Analysis of Rates - 2021 Chapter - 4: Bridge Work (SuperStructure-Steel)
Add 2 % of cost of bearing assembly, foundation anchorage bolts, transportation and 0.02 1,547.80
misc. items required during fixing.
Hire charges for 200 MT capacity Jack Day 0107 1500.00 2.00 3,000.00
Sub Total 83,043.78
83,043.78
Add for Water Charges @ 1% Lumpsum 9902 0.01 830.44
83,874.21
Add for GST @ 12% (multiplying factor 0.1405) Lumpsum 9903 0.14 11,784.33
95,658.54
Add for Contractor’s Overheads and Profit @ 15% Lumpsum 9904 0.15 14,348.78
110,007.32
Add for Cess @ 1% Lumpsum 9905 0.01 1,100.07
Rate of 250 MT Capacity Bearing Each 111,107.39
Add 2 % of cost of bearing assembly, foundation anchorage bolts, transportation and 0.02 1,453.90
misc. items required during fixing.
Hire charges for 200 MT capacity Jack Day 0107 1500.00 2.00 3,000.00
Sub Total 78,254.88
78,254.88
Add for Water Charges @ 1% Lumpsum 9902 0.01 782.55
79,037.42
Draft IR Unified Stadard Analysis of Rates - 2021 Chapter - 4: Bridge Work (SuperStructure-Steel)
041140 Design, supply, fitting and fixing in position true to line and level POT-PTFE bearing of
200 MT Capacity, consisting of a metal piston supported by a disc or un reinforced
elastomer confined within a metal cylinder, sealing rings, dust seals, PTFE surface
sliding against stainless steel mating surface, complete assembly to be of cast steel /
fabricated structural steel, metal and elastomer elements complete as per IS:2062,
IS:1030, AISI:304, AISI:316, IS:6911, BS:3784, IS:3400, IS:226, BS-5400, Bridge Code
and as per approved drawing and Technical Specifications. The design of the
bearings shall be submitted by the manufacturers / contractor and got approved from
Railway before fixing. Test report after inspection of the bearings shall be submitted
and got approved before the materials are lifted from the manufacturer premises.
Add 2 % of cost of bearing assembly, foundation anchorage bolts, transportation and 0.02 733.10
misc. items required during fixing.
Hire charges for 200 MT capacity Jack Day 0107 1500.00 2.00 3,000.00
Sub Total 41,272.88
41,272.88
Add for Water Charges @ 1% Lumpsum 9902 0.01 412.73
41,685.61
Add for GST @ 12% (multiplying factor 0.1405) Lumpsum 9903 0.14 5,856.83
47,542.44
Add for Contractor’s Overheads and Profit @ 15% Lumpsum 9904 0.15 7,131.37
54,673.80
Add for Cess @ 1% Lumpsum 9905 0.01 546.74
Rate of 250 MT Capacity Bearing Each 55,220.54
Add 2 % of cost of bearing assembly, foundation anchorage bolts, transportation and 0.02 900.50
misc. items required during fixing.
Draft IR Unified Stadard Analysis of Rates - 2021 Chapter - 4: Bridge Work (SuperStructure-Steel)
Add 2 % of cost of bearing assembly, foundation anchorage bolts, transportation and 0.02 1,142.80
misc. items required during fixing.
Hire charges for 200 MT capacity Jack Day 0107 1500.00 2.00 3,000.00
Sub Total 62,167.58
62,167.58
Add for Water Charges @ 1% Lumpsum 9902 0.01 621.68
62,789.26
Add for GST @ 12% (multiplying factor 0.1405) Lumpsum 9903 0.14 8,821.89
71,611.15
Add for Contractor’s Overheads and Profit @ 15% Lumpsum 9904 0.15 10,741.67
82,352.82
Add for Cess @ 1% Lumpsum 9905 0.01 823.53
Rate per 200 MT Capacity Bearing Each 83,176.35
Add 2 % of cost of bearing assembly, foundation anchorage bolts, transportation and 0.02 1,056.10
misc. items required during fixing.
Draft IR Unified Stadard Analysis of Rates - 2021 Chapter - 4: Bridge Work (SuperStructure-Steel)
041150 Design, supply, fitting and fixing in position true to line and level POT-PTFE bearing of
150 MT Capacity, consisting of a metal piston supported by a disc or un reinforced
elastomer confined within a metal cylinder, sealing rings, dust seals, PTFE surface
sliding against stainless steel mating surface, complete assembly to be of cast steel /
fabricated structural steel, metal and elastomer elements complete as per IS:2062,
IS:1030, AISI:304, AISI:316, IS:6911, BS:3784, IS:3400, IS:226, BS-5400, Bridge Code
and as per approved drawing and Technical Specifications. The design of the
bearings shall be submitted by the manufacturers / contractor and got approved from
Railway before fixing. Test report after inspection of the bearings shall be submitted
and got approved before the materials are lifted from the manufacturer premises.
Add 2 % of cost of bearing assembly, foundation anchorage bolts, transportation and 0.02 506.40
misc. items required during fixing.
Hire charges for 200 MT capacity Jack Day 0107 1500.00 2.00 3,000.00
Sub Total 29,489.99
29,489.99
Add for Water Charges @ 1% Lumpsum 9902 0.01 294.90
29,784.88
Add for GST @ 12% (multiplying factor 0.1405) Lumpsum 9903 0.14 4,184.78
33,969.66
Add for Contractor’s Overheads and Profit @ 15% Lumpsum 9904 0.15 5,095.45
39,065.11
Add for Cess @ 1% Lumpsum 9905 0.01 390.65
Rate per 150 MT Capacity Bearing Each 39,455.76
Add 2 % of cost of bearing assembly, foundation anchorage bolts, transportation and 0.02 599.70
misc. items required during fixing.
Hire charges for 200 MT capacity Jack Day 0107 1500.00 2.00 3,000.00
Sub Total 34,248.29
34,248.29
Add for Water Charges @ 1% Lumpsum 9902 0.01 342.48
34,590.77
Add for GST @ 12% (multiplying factor 0.1405) Lumpsum 9903 0.14 4,860.00
39,450.77
Add for Contractor’s Overheads and Profit @ 15% Lumpsum 9904 0.15 5,917.62
45,368.39
Add for Cess @ 1% Lumpsum 9905 0.01 453.68
Rate per 150 MT Capacity Bearing Each 45,822.07
Add 2 % of cost of bearing assembly, foundation anchorage bolts, transportation and 0.02 774.90
misc. items required during fixing.
Hire charges for 200 MT capacity Jack Day 0107 1500.00 2.00 3,000.00
Sub Total 43,183.49
43,183.49
Add for Water Charges @ 1% Lumpsum 9902 0.01 431.83
43,615.32
Add for GST @ 12% (multiplying factor 0.1405) Lumpsum 9903 0.14 6,127.95
49,743.27
Add for Contractor’s Overheads and Profit @ 15% Lumpsum 9904 0.15 7,461.49
57,204.76
Add for Cess @ 1% Lumpsum 9905 0.01 572.05
Rate of 150 MT Capacity Bearing Each 57,776.81
Add 2 % of cost of bearing assembly, foundation anchorage bolts, transportation and 0.02 715.20
misc. items required during fixing.
Hire charges for 200 MT capacity Jack Day 0107 1500.00 2.00 3,000.00
Sub Total 40,138.79
40,138.79
Add for Water Charges @ 1% Lumpsum 9902 0.01 401.39
40,540.17
Add for GST @ 12% (multiplying factor 0.1405) Lumpsum 9903 0.14 5,695.89
46,236.07
Add for Contractor’s Overheads and Profit @ 15% Lumpsum 9904 0.15 6,935.41
53,171.48
Add for Cess @ 1% Lumpsum 9905 0.01 531.71
Rate of 150 MT Capacity Bearing Each 53,703.19
041160 Design, supply, fitting and fixing in position true to line and level POT-PTFE bearing of
100 MT Capacity, consisting of a metal piston supported by a disc or un reinforced
elastomer confined within a metal cylinder, sealing rings, dust seals, PTFE surface
sliding against stainless steel mating surface, complete assembly to be of cast steel /
fabricated structural steel, metal and elastomer elements complete as per IS:2062,
IS:1030, AISI:304, AISI:316, IS:6911, BS:3784, IS:3400, IS:226, BS-5400, Bridge Code
and as per approved drawing and Technical Specifications. The design of the
bearings shall be submitted by the manufacturers / contractor and got approved from
Railway before fixing. Test report after inspection of the bearings shall be submitted
and got approved before the materials are lifted from the manufacturer premises.
Add 2 % of cost of bearing assembly, foundation anchorage bolts, transportation and 0.02 327.00
misc. items required during fixing.
Hire charges for 200 MT capacity Jack Day 0107 1500.00 2.00 3,000.00
Sub Total 20,119.39
20,119.39
Add for Water Charges @ 1% Lumpsum 9902 0.01 201.19
20,320.58
Add for GST @ 12% (multiplying factor 0.1405) Lumpsum 9903 0.14 2,855.04
23,175.63
Add for Contractor’s Overheads and Profit @ 15% Lumpsum 9904 0.15 3,476.34
Draft IR Unified Stadard Analysis of Rates - 2021 Chapter - 4: Bridge Work (SuperStructure-Steel)
Add 2 % of cost of bearing assembly, foundation anchorage bolts, transportation and 0.02 347.70
misc. items required during fixing.
Hire charges for 200 MT capacity Jack Day 0107 1500.00 2.00 3,000.00
Sub Total 21,175.09
21,175.09
Add for Water Charges @ 1% Lumpsum 9902 0.01 211.75
21,386.84
Add for GST @ 12% (multiplying factor 0.1405) Lumpsum 9903 0.14 3,004.85
24,391.69
Add for Contractor’s Overheads and Profit @ 15% Lumpsum 9904 0.15 3,658.75
28,050.45
Add for Cess @ 1% Lumpsum 9905 0.01 280.50
Rate of 100 MT Capacity Bearing Each 28,330.95
Add 2 % of cost of bearing assembly, foundation anchorage bolts, transportation and 0.02 512.50
misc. items required during fixing.
Hire charges for 200 MT capacity Jack Day 0107 1500.00 2.00 3,000.00
Sub Total 29,579.89
29,579.89
Add for Water Charges @ 1% Lumpsum 9902 0.01 295.80
29,875.69
Add for GST @ 12% (multiplying factor 0.1405) Lumpsum 9903 0.14 4,197.53
34,073.22
Add for Contractor’s Overheads and Profit @ 15% Lumpsum 9904 0.15 5,110.98
39,184.21
Add for Cess @ 1% Lumpsum 9905 0.01 391.84
Rate of 100 MT Capacity Bearing Each 39,576.05
Draft IR Unified Stadard Analysis of Rates - 2021 Chapter - 4: Bridge Work (SuperStructure-Steel)
Add 2 % of cost of bearing assembly, foundation anchorage bolts, transportation and 0.02 467.00
misc. items required during fixing.
Hire charges for 200 MT capacity Jack Day 0107 1500.00 2.00 3,000.00
Sub Total 27,259.39
27,259.39
Add for Water Charges @ 1% Lumpsum 9902 0.01 272.59
27,531.98
Add for GST @ 12% (multiplying factor 0.1405) Lumpsum 9903 0.14 3,868.24
31,400.23
Add for Contractor’s Overheads and Profit @ 15% Lumpsum 9904 0.15 4,710.03
36,110.26
Add for Cess @ 1% Lumpsum 9905 0.01 361.10
Rate of 100 MT Capacity Bearing Each 36,471.36
041170 Design, supply and fixing 300MT capacity Spherical Bearing in position true to line
and level consisting of set of concave and convex mating steel backing plate with a low
friction sliding interface, flat sliding elements ,guides and restraining rings; with all
components conforming to approved drawing and technical specifications & Bridge
Code including grouting of holes for anchor bolts and underside of baseplate with
approved non-shrink epoxy grout with all material, labour, T&P as a complete job.
Note: Sliding surface with PTFE or UHMWPE low friction thermoplastic material and
steel for backing plate of Mild steel in accordance to IS:2062 grade-B. Cast steel in
accordance with IS 1030 Grade 280-520W. Stain less steel in accordance with AISI
304/316.Low friction thermo -plastic sliding PTFE material either pure
polytetrafluroethalyne (PTFE) Or Ultra High Molecular weight Polythylene (UHMWPE).
Austanitic steel is of stainless steel for the sliding interface shall be in accordance with
AISI 316L or O2 Cr17 NI12 of IS-6911. The thickness of the stain less steel sheet shall
be 3mm minimum.The stainless steel sheet shall be attached to its backing plate either
by screwing/riveting or by continuous fillet weld.Hard chromium plated surface shall be
entire curved surface of the convex steel plate mating with hard chromium plated
concave sliding surface .The thickness of the hard chromium plating shall be at least
100 microns and the final surface roughness of the plated surface shall not exceed 3
microns.Bearing manufacturer shall give the guarantee for satisfactory performance of
bearing for period specified.
Add 2 % of cost of bearing assembly, foundation anchorage bolts, transportation and 0.02 1,303.70
misc. items required during fixing.
Hire charges for 200 MT capacity Jack Day 0107 1500.00 2.00 3,000.00
Sub Total 70,815.87
70,815.87
Add for Water Charges @ 1% Lumpsum 9902 0.01 708.16
71,524.03
Add for GST @ 12% (multiplying factor 0.1405) Lumpsum 9903 0.14 10,049.13
81,573.15
Add for Contractor’s Overheads and Profit @ 15% Lumpsum 9904 0.15 12,235.97
93,809.13
Add for Cess @ 1% Lumpsum 9905 0.01 938.09
Rate of 300 MT Capacity Bearing Each 94,747.22
Add 2 % of cost of bearing assembly, foundation anchorage bolts, transportation and 0.02 1,117.20
misc. items required during fixing.
Hire charges for 200 MT capacity Jack Day 0107 1500.00 2.00 3,000.00
Sub Total 61,304.37
61,304.37
Add for Water Charges @ 1% Lumpsum 9902 0.01 613.04
61,917.41
Add for GST @ 12% (multiplying factor 0.1405) Lumpsum 9903 0.14 8,699.40
70,616.81
Add for Contractor’s Overheads and Profit @ 15% Lumpsum 9904 0.15 10,592.52
81,209.33
Add for Cess @ 1% Lumpsum 9905 0.01 812.09
Rate of 300 MT Capacity Bearing Each 82,021.43
Add 2 % of cost of bearing assembly, foundation anchorage bolts, transportation and 0.02 1,588.00
misc. items required during fixing.
Hire charges for 200 MT capacity Jack Day 0107 1500.00 2.00 3,000.00
Sub Total 85,315.17
c) Sudries, adhesives misc. T & P and consumables @ 3 per cent on a+b 0.03 2,559.46
87,874.63
Add for Water Charges @ 1% Lumpsum 9902 0.01 878.75
88,753.37
Add for GST @ 12% (multiplying factor 0.1405) Lumpsum 9903 0.14 12,469.85
101,223.22
Add for Contractor’s Overheads and Profit @ 15% Lumpsum 9904 0.15 15,183.48
116,406.70
Add for Cess @ 1% Lumpsum 9905 0.01 1,164.07
Cost of 300 MT Capacity Bearing Each 117,570.77
Add 2 % of cost of bearing assembly, foundation anchorage bolts, transportation and 0.02 1,511.20
misc. items required during fixing.
Hire charges for 200 MT capacity Jack Day 0107 1500.00 2.00 3,000.00
81,398.37
Sudries, adhesives misc. T & P and consumables @ 3 per cent on a+b 0.03 2,441.95
83,840.32
Draft IR Unified Stadard Analysis of Rates - 2021 Chapter - 4: Bridge Work (SuperStructure-Steel)
041180 Extra over items 041090 to 041170 for fixing bearings under running traffic /traffic block
including removing of existing bearings and handing over at location as directed..
041190 Supply & applying two coats of bitumen emulsion of Grade RS-1, conforming to
IS:8887 on the top surface of concrete deck slab (New bridges) @ 1.70 kg/sqm after
cleaning surface with all materials, labour, tools and plants, equipment etc. complete.
041200 Providing road crane of specified lifting capacity with specified jib length revolving type
for material handling, assembly & erection of girders/slab/RCC Box etc.
041201 12 MT capacity
Hire charges of 12 MT crane and accessories Day 0091 6000.00 1.00 6,000.00
Sundries including misc tools and plants (@ 3% of above) 0.03 180.00
6,180.00
Add for Water Charges @ 1% Lumpsum 9902 0.01 61.80
6,241.80
Add for GST @ 12% (multiplying factor 0.1405) Lumpsum 9903 0.14 876.97
7,118.77
Add for Contractor’s Overheads and Profit @ 15% Lumpsum 9904 0.15 1,067.82
8,186.59
Add for Cess @ 1% Lumpsum 9905 0.01 81.87
Rate per Day Day 8,268.45
041202 20 MT capacity
Hiring charges of Crane 20 MT capacity Day 0092 8000.00 1.00 8,000.00
Sundries including misc tools and plants (@ 3% of above) 0.03 240.00
8,240.00
Add for Water Charges @ 1% Lumpsum 9902 0.01 82.40
8,322.40
Add for GST @ 12% (multiplying factor 0.1405) Lumpsum 9903 0.14 1,169.30
9,491.70
Draft IR Unified Stadard Analysis of Rates - 2021 Chapter - 4: Bridge Work (SuperStructure-Steel)
041203 50 MT capacity
Hiring charges of Crane 50 MT capacity Day 0094 20000.00 1.00 20,000.00
Sundries including misc tools and plants (@ 3% of above) 0.03 600.00
20,600.00
Add for Water Charges @ 1% Lumpsum 9902 0.01 206.00
20,806.00
Add for GST @ 12% (multiplying factor 0.1405) Lumpsum 9903 0.14 2,923.24
23,729.24
Add for Contractor’s Overheads and Profit @ 15% Lumpsum 9904 0.15 3,559.39
27,288.63
Add for Cess @ 1% Lumpsum 9905 0.01 272.89
Rate per Day Day 27,561.52
041204 80 MT capacity
Hiring charges of 80MT capacity crane Day 0095 35000.00 1.00 35,000.00
Sundries including misc tools and plants (@ 3% of above) 0.03 1,050.00
36,050.00
Add for Water Charges @ 1% Lumpsum 9902 0.01 360.50
36,410.50
Add for GST @ 12% (multiplying factor 0.1405) Lumpsum 9903 0.14 5,115.68
41,526.18
Add for Contractor’s Overheads and Profit @ 15% Lumpsum 9904 0.15 6,228.93
47,755.10
Add for Cess @ 1% Lumpsum 9905 0.01 477.55
Rate per Day Day 48,232.65
041210 Extra for increase in road crane capacity over Item 041209 for every additional 1 MT
capacity or part there of
Details of cost for 1 MT
Machinery
Hiring charges of 400 MT capacity crane Day 0101 350000.00 1.00 350,000.00
Hiring charges of 300 MT capacity crane Day 0100 250000.00 1.00 250,000.00
Cost difference for 100 MT 100,000.00
Add for Water Charges @ 1% Lumpsum 9902 0.01 1,000.00
101,000.00
Add for GST @ 12% (multiplying factor 0.1405) Lumpsum 9903 0.14 14,190.50
115,190.50
Add for Contractor’s Overheads and Profit @ 15% Lumpsum 9904 0.15 17,278.58
132,469.08
Add for Cess @ 1% Lumpsum 9905 0.01 1,324.69
Cost for 100 MT 133,793.77
Rate per 1 MT Day 1,337.94
041220 Surface preparation of steel work of bridge plate/composite girders by cleaning with
scrappers and/or wire brushes to remove all rust and loose or perished paint to prepare
perfectly clean & dry bare metal surface free from all dirt/foreign material & ready for
initial coat of paint. Rate includes cost of labour, consumables, brushes, tools & plants,
ladders, scaffoldings, jhoola, hanging scaffolding staging etc.
a)Taking output=100Sqm
Beldar (Un skilled) Day 0025 431.00 2.00 862.00
Coolie (Un skilled) Day 0026 431.00 2.00 862.00
Draft IR Unified Stadard Analysis of Rates - 2021 Chapter - 4: Bridge Work (SuperStructure-Steel)
041230 Surface preparation of steel work of bridge triangulated girders by cleaning with
scrappers and/or wire brushes to remove all rust and loose or perished paint to prepare
perfectly clean & dry bare metal surface free from all dirt/foreign material & ready for
initial coat of paint. Rate includes cost of labour, consumables, brushes, misc. tools and
plants, ladders, scaffoldings, jhoola, hanging scaffolding, staging etc.
041240 Surface preparation for painting of bridge plate/composite girders and other steel
structures where the finishing coat shows signs of deterioration; but primer coat of paint
is sufficiently in good condition and there are no signs of rusting etc. Surface shall be
cleaned free from oil grease, scaling and other foreign matters without disturbing the
primer coat {Rate includes cost of labour, consumables, tools & plants, scaffolding,
jhoola, ladder etc.}
041260 Painting cleaned plate/composite bridge girders including all scaffolding along with
provision of Jhoola / hanging scaffolding ladders etc. where required.
041261 With one coat ready mix Zinc Chromate conforming to IS:104 with DFT of 25-30
Microns followed by one coat of Zinc Chromate red oxide conforming to IS:2074 DFT of
25 Microns
Detail of cost for 10 Sqm
Material:
Red oxide primer in two coats
Ready mix Zinc Chromate primer as per IS 104 Litre 0307 100.00 1.00 100.00
Zinc Chromate red oxide Primer to IS:2074 Litre 0308 130.00 0.90 117.00
Labour:
Painter (Skilled) Day 0012 609.00 0.25 152.25
Coolie (Un skilled) Day 0026 431.00 0.25 107.75
Add for providing, maintainence, slow progress and danger element by using jhoola etc Lumpsum 9901 1.00 80.00 80.00
557.00
Sundries including misc tools and plants (@ 3% of sub-total) 0.03 16.71
573.71
Add for Water Charges @ 1% Lumpsum 9902 0.01 5.74
579.45
Add for GST @ 12% (multiplying factor 0.1405) Lumpsum 9903 0.14 81.41
660.86
Add for Contractor’s Overheads and Profit @ 15% Lumpsum 9904 0.15 99.13
759.99
Add for Cess @ 1% Lumpsum 9905 0.01 7.60
Cost for 10 Sqm. 767.59
Rate per Sqm Sqm 76.76
041262 With two cover coats of ready-mixed paint conforming to IS:13607 with colour/shades,
as decided by Engineer-incharge
Note: DFT of each coat shall be 20-25 microns
Detail of cost for 10 Sqm
Material:
Ready-mixed paint to IS:13607 with colour/shades, as decided by Engineer-incharge
Ready Mixed Paint as per IS:13607 Litre 0312 230.00 0.91 209.30
Ready Mixed Paint as per IS:13607 Litre 0312 230.00 0.77 177.10
Labour:
Painter (Skilled) Day 0012 609.00 0.25 152.25
Coolie (Un skilled) Day 0026 431.00 0.25 107.75
Add for providing, maintainence, slow progress and danger element by using jhoola etc Lumpsum 9901 1.00 80.00 80.00
726.40
Sundries including misc tools and plants (@ 3% of sub-total) 0.03 21.79
748.19
Add for Water Charges @ 1% Lumpsum 9902 0.01 7.48
755.67
Add for GST @ 12% (multiplying factor 0.1405) Lumpsum 9903 0.14 106.17
861.85
Add for Contractor’s Overheads and Profit @ 15% Lumpsum 9904 0.15 129.28
991.12
Draft IR Unified Stadard Analysis of Rates - 2021 Chapter - 4: Bridge Work (SuperStructure-Steel)
041263 With two coats Aluminium paints in dual containers conforming to IS:2339 with DFT of
12 - 14 Microns for each coat.
Detail of cost for 10 Sqm
Material:
Aluminium paint Litre 0309 160.00 0.91 145.60
Aluminium paint Litre 0309 160.00 0.77 123.20
Labour:
Painter (Skilled) Day 0012 609.00 0.25 152.25
Coolie (Un skilled) Day 0026 431.00 0.25 107.75
Add for providing, maintainence, slow progress and danger element by using jhoola etc Lumpsum 9901 1.00 80.00 80.00
608.80
Sundries including misc tools and plants (@ 3% of sub-total) 0.03 18.26
627.06
Add for Water Charges @ 1% Lumpsum 9902 0.01 6.27
633.33
Add for GST @ 12% (multiplying factor 0.1405) Lumpsum 9903 0.14 88.98
722.32
Add for Contractor’s Overheads and Profit @ 15% Lumpsum 9904 0.15 108.35
830.67
Add for Cess @ 1% Lumpsum 9905 0.01 8.31
Cost for 10 Sqm. 838.97
Rate per Sqm Sqm 83.90
041264 With two coats of epoxy paint conforming to RDSO spec M&C/PCN/123-11
Note: DFT of each coat shall be 60 microns.
Detail of cost for 10 Sqm
Material:
Epoxy paint as per RDSO Spec M&C/PCN/123-11 Litre 0311 440.00 1.25 550.00
Epoxy paint as per RDSO Spec M&C/PCN/123-11 Litre 0311 440.00 1.10 484.00
Labour:
Painter (Skilled) Day 0012 609.00 0.25 152.25
Coolie (Un skilled) Day 0026 431.00 0.25 107.75
Add for providing, maintainence, slow progress and danger element by using jhoola etc Lumpsum 9901 1.00 80.00 80.00
1,374.00
Sundries including misc tools and plants (@ 3% of sub-total) 0.03 41.22
1,415.22
Add for Water Charges @ 1% Lumpsum 9902 0.01 14.15
1,429.37
Add for GST @ 12% (multiplying factor 0.1405) Lumpsum 9903 0.14 200.83
1,630.20
Add for Contractor’s Overheads and Profit @ 15% Lumpsum 9904 0.15 244.53
1,874.73
Add for Cess @ 1% Lumpsum 9905 0.01 18.75
Cost for 10 Sqm. 1,893.48
Rate per Sqm Sqm 189.35
041265 With one coat Aluminium paint in dual containers conforming to IS:2339 with DFT of 12 -
14 Microns .
Detail of cost for 10 Sqm
Material:
Aluminium paint Litre 0309 160.00 0.90 144.00
Labour:
Painter (Skilled) Day 0012 609.00 0.15 91.35
Coolie (Un skilled) Day 0026 431.00 0.15 64.65
Draft IR Unified Stadard Analysis of Rates - 2021 Chapter - 4: Bridge Work (SuperStructure-Steel)
041270 Painting cleaned triangulated bridge girders including all scaffolding, along with
provision of Jhoola / hanging scaffolding ladder where required.
041271 With one coat ready mix Zinc Chromate conforming to IS:104 with DFT of 25-30
Microns followed by one coat of Zinc Chrome red oxide conforming to IS:2074 with
DFT of 25 Microns.
Detail of cost for 10 Sqm
Material:
Ready mix Zinc Chromate primer as per IS 104 Litre 0307 100.00 1.00 100.00
Zinc Chromate red oxide Primer to IS:2074 Litre 0308 130.00 0.90 117.00
Labour:
Painter (Skilled) Day 0012 609.00 0.36 219.24
Coolie (Un skilled) Day 0026 431.00 0.36 155.16
Add for providing, maintainence, slow progress and danger element by using jhoola etc Lumpsum 9901 1.00 80.00 80.00
671.40
Sundries including misc tools and plants (@ 3% of sub-total) 0.03 20.14
691.54
Add for Water Charges @ 1% Lumpsum 9902 0.01 6.92
698.46
Add for GST @ 12% (multiplying factor 0.1405) Lumpsum 9903 0.14 98.13
796.59
Add for Contractor’s Overheads and Profit @ 15% Lumpsum 9904 0.15 119.49
916.08
Add for Cess @ 1% Lumpsum 9905 0.01 9.16
Cost for 10 Sqm. 925.24
Rate per Sqm Sqm 92.52
041272 With two cover coats of ready-mixed paint conforming to IS:13607 with colour/shades,
as decided by Engineer-incharge.
Note: DFT of each coat shall be 20-25 microns.
Detail of cost for 10 Sqm
Material:
Ready Mixed Paint as per IS:13607 Litre 0312 230.00 0.91 209.30
Ready Mixed Paint as per IS:13607 Litre 0312 230.00 0.77 177.10
Labour:
Painter (Skilled) Day 0012 609.00 0.36 219.24
Coolie (Un skilled) Day 0026 431.00 0.36 155.16
Add for providing, maintainence, slow progress and danger element by using jhoola etc Lumpsum 9901 1.00 80.00 80.00
840.80
Sundries including misc tools and plants (@ 3% of sub-total) 0.03 25.22
866.02
Add for Water Charges @ 1% Lumpsum 9902 0.01 8.66
874.68
Add for GST @ 12% (multiplying factor 0.1405) Lumpsum 9903 0.14 122.89
Draft IR Unified Stadard Analysis of Rates - 2021 Chapter - 4: Bridge Work (SuperStructure-Steel)
041273 With two coats Aluminium paint in dual containers conforming to IS:2339 with DFT of
12-14 Microns for each coat.
Detail of cost for 10 Sqm
Material:
Aluminium paint Litre 0309 160.00 0.91 145.60
Aluminium paint Litre 0309 160.00 0.77 123.20
Labour:
Painter (Skilled) Day 0012 609.00 0.36 219.24
Coolie (Un skilled) Day 0026 431.00 0.36 155.16
Add for providing, maintainence, slow progress and danger element by using jhoola etc Lumpsum 9901 1.00 80.00 80.00
723.20
Sundries including misc tools and plants (@ 3% of sub-total) 0.03 21.70
744.90
Add for Water Charges @ 1% Lumpsum 9902 0.01 7.45
752.34
Add for GST @ 12% (multiplying factor 0.1405) Lumpsum 9903 0.14 105.70
858.05
Add for Contractor’s Overheads and Profit @ 15% Lumpsum 9904 0.15 128.71
986.76
Add for Cess @ 1% Lumpsum 9905 0.01 9.87
Cost for 10 Sqm. 996.62
Rate per Sqm Sqm 99.66
041274 With two coats of epoxy paint conforming to RDSO spec M&C/PCN/123-11
Note: DFT of each coat shall be 60 microns.
Detail of cost for 10 Sqm
Material:
Epoxy paint as per RDSO Spec M&C/PCN/123-11 Litre 0311 440.00 1.25 550.00
Epoxy paint as per RDSO Spec M&C/PCN/123-11 Litre 0311 440.00 1.10 484.00
Labour:
Painter (Skilled) Day 0012 609.00 0.36 219.24
Coolie (Un skilled) Day 0026 431.00 0.36 155.16
Add for providing, maintainence, slow progress and danger element by using jhoola etc Lumpsum 9901 1.00 80.00 80.00
1,488.40
Sundries including misc tools and plants (@ 3% of sub-total) 0.03 44.65
1,533.05
Add for Water Charges @ 1% Lumpsum 9902 0.01 15.33
1,548.38
Add for GST @ 12% (multiplying factor 0.1405) Lumpsum 9903 0.14 217.55
1,765.93
Add for Contractor’s Overheads and Profit @ 15% Lumpsum 9904 0.15 264.89
2,030.82
Add for Cess @ 1% Lumpsum 9905 0.01 20.31
Cost for 10 Sqm. 2,051.13
Rate per Sqm Sqm 205.11
041280 Extra for working under traffic conditions over items 041220 to 041274
Add 10% over above items Sqm 0.10 0.10
Draft IR Unified Stadard Analysis of Rates - 2021 Chapter - 4: Bridge Work (SuperStructure-Steel)
041294 Supply of HTS holding down bolts with nuts, washer etc.
Considering cost of 1 quintal HTS holding down bolts
Holding down HTS bolts with plates, nuts etc. Quintal 0235 7500.00 1.00 7,500.00
Add for Water Charges @ 1% Lumpsum 9902 0.01 75.00
7,575.00
Add for GST @ 12% (multiplying factor 0.1405) Lumpsum 9903 0.14 1,064.29
8,639.29
Add for Contractor’s Overheads and Profit @ 15% Lumpsum 9904 0.15 1,295.89
9,935.18
Add for Cess @ 1% Lumpsum 9905 0.01 99.35
Cost for 1 quintal 10,034.53
Rate per Kg Kg 100.35
041300 Assembling and erecting pre-fabricated structures, such as columns, beams, girders,
other members of FOBs and sheds; including leading all structural elements within 1
Km lead, bolting, riveting or welding as per approved drawing or as directed by
Engineer In-charge. Rate shall include cost of labour, materials, tools & plants and only
pre-fabricated structural elements shall be given by Railway. (Work not requiring traffic
or power block).
041301 Extra over item no 041300, if the work is to be executed under traffic or power block.
041310 Cleaning and greasing of free end and fixed end of steel girder Bridge bearings with
Grease Graphite, Kerosene oil and other materials as per Para 222 of Indian Railway
Bridge Manual 1998 with painting of Bearing as per requirement complete as directed
by engineer in-charge.
Note: One unit shall consists of all bearing of one girder.
041320 Launching in position, by any approved method, pre-fabricated Steel Girders, precast
PSC girders/slabs, casted at casting bed developed at site, to correct alignment and
level over the bed block / pedestal with all required arrangements, complete in all
respect.
Draft IR Unified Stadard Analysis of Rates - 2021 Chapter - 4: Bridge Work (SuperStructure-Steel)
041323 Extra over item no. 041320 if the work is to be executed under traffic/power block.
041330 DeLaunching of all types of Steel girders, PSC girders/Slabs and stacking away from
river stream or passage as directed by Engineer in charge with all labour, tools and
plant, equipment etc., complete.
041331 PSC girders / slabs
Detail of cost for 200.48 MT girder ( for 4 spans of 12.2m with 2 Girder system) =
8*25.06=200.48 MT)
Draft IR Unified Stadard Analysis of Rates - 2021 Chapter - 4: Bridge Work (SuperStructure-Steel)
041333 Extra over item no. 041330 if the work is to be executed under traffic/power block.
Extra 10% over 041330
Rate per MT MT 0.10 0.10
Draft IR Unified Stadard Analysis of Rates - 2021 Chapter - 4: Bridge Work (SuperStructure-Steel)
041341 Delaunching of existing PSC girders / slabs and Launching New PSC girders / slabs
041342 Delaunching of existing PSC girders / slabs and Launching New Structural steel plate
girders.
Considering reduction of 20% in cost due to saving in manpower/machinery
simaltaneous delaunching and launching. Cost for 1 MT delaunching with 1 MT
launching
Basic cost of Delaunching of existing PSC girders/Slabs (041331) 1,107.25
Basic cost of Launching New Structural steel plate girders (041322) 1,392.28
Total 2,499.53
Deduct 20% for simultaneous working with the same machinery 0.20 499.91
Net Cost for 2 MT 1,999.62
Rate per MT MT 999.81
041343 Delaunching of existing Structural steel plate girders / slabs and Launching New
Structural steel plate girders
Considering reduction of 20% in cost due to saving in manpower/machinery
simaltaneous delaunching and launching. Cost for 1 MT delaunching with 1 MT
launching
Basic cost of Delaunching of existing Structural steel plate girders (041332) 1,066.98
Basic cost of Launching New Structural steel plate girders (041322) 1,392.28
Total 2,459.26
Deduct 20% for simultaneous working with the same machinery 0.20 491.85
Net Cost for 2 MT 1,967.41
Rate per MT MT 983.70
041344 Delaunching of existing Structural steel plate girders / slabs and Launching New PSC
girders / slabs
Considering reduction of 20% in cost due to saving in manpower/machinery
simaltaneous delaunching and launching. Cost for 1 MT delaunching with 1 MT
launching
Basic cost of Delaunching of existing Structural steel plate girders (041332) 1,066.98
Basic cost of Launching New New PSC girders / slabs (041321) 1,459.06
Total 2,526.05
Deduct 20% for simultaneous working with the same machinery 0.20 505.21
Net Cost for 2 MT 2,020.84
Rate per MT MT 1,010.42
041345 Extra over item no. 041340 if the work is to be executed under traffic/power block.
Material:
Stone boulder, weighing minimum 35 kg each Cum 0213 750.00 1.00 750.00
Stone Spalls Cum 0214 445.00 0.20 89.00
Labour:
Mate (Semi skilled) Day 0003 505.00 0.04 20.20
Mason 2nd class (Semi-skilled) Day 0005 505.00 0.35 176.75
Beldar (Un skilled) Day 0025 431.00 0.35 150.85
Sundries Lumpsum 9901 1.00 20.00 20.00
1,206.80
Add for Water Charges @ 1% Lumpsum 9902 0.01 12.07
1,218.87
Add for GST @ 12% (multiplying factor 0.1405) Lumpsum 9903 0.1405 171.25
1,390.12
Add for Contractor’s Overheads and Profit @ 15% Lumpsum 9904 0.15 208.52
1,598.64
Add for Cess @ 1% Lumpsum 9905 0.01 15.99
Rate per cum Cum 1,614.62
051020 Laying of boulder apron laid in wire crates of approved size including overlaps at
joints, laid with stone boulders, all loose ends to be tied with 4mm galvanised steel
wire. Payment for boulders & wire crates to be done extra.
051030 Supplying of stone boulders weighing not less than 35 kg each at specified bridge
locations.
Taking output = 1 cum
Material:
Stone boulder, weighing minimum 35 kg each Cum 0213 750.00 1.00 750.00
750.00
Add for Water Charges @ 1% Lumpsum 9902 0.01 7.50
757.50
Add for GST @ 12% (multiplying factor 0.1405) Lumpsum 9903 0.14 106.43
863.93
Add for Contractor’s Overheads and Profit @ 15% Lumpsum 9904 0.15 129.59
993.52
Add for Cess @ 1% Lumpsum 9905 0.01 9.94
Rate per cum Cum 1,003.45
051040 Supplying Galvanized Wire Net Trungers made from 4mm galvanised steel wire @ 32
kg/10sqm having minimum tensile strength of 300 Mpa conforming to IS:280 and
galvanizing coating conforming to IS:4826, woven into mesh with double twist, mesh
size not exceeding 100mm x 100mm.
Draft IR Unified Stadard Analysis of Rates - 2021 Chapter - 5: Bridge Works (Misc.)
Material:
G.I. wire 4mm dia Kg 0250 70.00 59.20 4,144.00
Labour:
Mate (Semi skilled) Day 0003 505.00 0.18 90.90
Mason 2nd class (Semi-skilled) Day 0005 505.00 1.00 505.00
Beldar (Un skilled) Day 0025 431.00 1.00 431.00
Sundries Lumpsum 9901 1.00 100.00 100.00
5,270.90
Add for Water Charges @ 1% Lumpsum 9902 0.01 52.71
5,323.61
Add for GST @ 12% (multiplying factor 0.1405) Lumpsum 9903 0.1405 747.97
6,071.58
Add for Contractor’s Overheads and Profit @ 15% Lumpsum 9904 0.15 910.74
6,982.31
Add for Cess @ 1% Lumpsum 9905 0.01 69.82
Cost of 18.5 sqm 7,052.14
Rate per sqm Sqm 381.20
051050 Providing and laying of Apron with cement concrete blocks cast in-situ and made with
nominal mix of 1:2:4 with all material , labour, tools and plants.
Note: (1) Payment to be made for concrete only; (2) Cement and shuttering to be paid
extra.
051060 Providing and laying Pitching with Stone Boulders, weighing not less than 35kg each
with voids filled with spalls on slopes, laid over prepared filter media including boulder
apron laid dry in front of toe of embankment complete as per drawing and Technical
Specifications (filter media to be paid separately under the relevant item).
051070 Providing and laying Pitching with Stone Boulders, weighing not less than 35kg each
with voids filled with cement sand mortar 1:4 on slopes laid over prepared filter media
including boulder apron laid dry in front of toe of embankment complete as per
drawing and Technical Specifications (filter media to be paid separately under the
relevant item). Rate is excluding cost of cement which shall be paid extra under
relevant item.
051080 Providing and laying Filter Material as per RDSO Specifications underneath pitching
in slopes complete as per drawing and Technical Specification.
Taking output = 1 cum
Material:
Filter media of stone aggregate confirming to RDSO specification (12 cum loose to be Cum 0215 1200.00 1.20 1,440.00
taken as 10 cum after compaction)
Labour:
Mate (Semi skilled) Day 0003 505.00 0.05 25.25
Mason 2nd class (Semi-skilled) Day 0005 505.00 0.25 126.25
Beldar (Un skilled) Day 0025 431.00 1.00 431.00
Sundries Lumpsum 9901 1.00 30.00 30.00
2,052.50
Add for Water Charges @ 1% Lumpsum 9902 0.01 20.53
2,073.03
Draft IR Unified Stadard Analysis of Rates - 2021 Chapter - 5: Bridge Works (Misc.)
051090 Laying Boulder Apron on river bed for protection against scour with stone boulders
supplied by Railway with voids filled with spalls complete as per drawings and
Technical Specifications.
Taking output = 1cum
Labour:
Mate (Semi skilled) Day 0003 505.00 0.04 20.20
Mason 2nd class (Semi-skilled) Day 0005 505.00 0.04 20.20
Beldar (Un skilled) Day 0025 431.00 0.50 215.50
Sundries Lumpsum 9901 1.00 20.00 20.00
275.90
Add for Water Charges @ 1% Lumpsum 9902 0.01 2.76
278.66
Add for GST @ 12% (multiplying factor 0.1405) Lumpsum 9903 0.1405 39.15
317.81
Add for Contractor’s Overheads and Profit @ 15% Lumpsum 9904 0.15 47.67
365.48
Add for Cess @ 1% Lumpsum 9905 0.01 3.65
Rate per cum Cum 369.14
051100 Laying Pitching with Stone Boulders supplied by Railway with voids filled with spalls
on slopes, laid over prepared filter media including boulder apron laid dry in front of
toe of embankment as per drawings and technical specifications.
Note: Filter media to be paid under relevant item.
051110 Stenciling of Girders with black / blue lettering over yellow background with ready mix
paint w.r.t. details of executed inspection, greasing and painting, other details as
directed by Engineer in-charge
Note: Payment will be per cm height of each letter
051120 Cleaning Surface of Abutment and Piers upto bed level under water with brush or any
other tools to remove all traces of moss, loose materials, fungus, algae, vegetational
growth etc. Cleaning shall be carried out with contractor's trained staff, tools & plants,
safety equipments etc. complete job including arranging safe approach.
051130 Inspecting Sub-structure and Foundation in and around piers & abutments, using
trained and qualified staff, under-water cameras, monitoring sensors & safety
equipments, recording observed defects, e.g. cracks, cavities, bulging, leaning
spalling and other defects noticed in the structure on DVD/Pen drives & photographs
and submitting detailed inspection report to Engineer in-charge. Payment shall be
made on hourly basis of videography & photography.The work shall be executed as
per BS-96.
052020 Providing and laying 300mm thick (average) Dry Stone flooring with boulders of not
less than 35kg each in weight, hand packed with surface levelled off to the correct
section with hammer dressing as necessary on the ground including filling the gaps
with quarry spalls and ordinary sand complete including cost of supply of all materials,
labour, lead, lift, tools, plants, crossing of tracks and the like as per drawing and
technical specification as directed by Engineer in charge.
052030 Supply and laying of quarry dust including consolidation, supply of all materials,
labour, lead, lift, tools, plants, crossing of tracks as per drawing and technical
specification as directed by the Engineer in charge in case loose slush is encountered
at site of foundation before casting the foundation or laying the filtering media.
052040 Supply and laying of coarse sand including consolidation with all labour, lead, lift,
tools, plants, crossing of tracks as per drawing and technical specification as directed
by the Engineer in charge in case loose slush is encountered at site of foundation
before casting the foundation or laying the filtering media.
052060 Providing and inserting nipples of size 12 to 20 mm dia. with approved fixing
compound after drilling holes for grouting as per Technical Specifications including
subsequent cutting/removal and sealing of the hole as necessary after completion of
grouting.
052071 Neat Cement Grout with 20% anti shrinkage compound w.r.t. cement.
Taking output for using 1 kg of cement.
Material:
Admixture (anti shrinkage compound) for CC/RCC work Kg 0193 140.00 0.22 30.80
Labour:
Mate (Semi skilled) Day 0003 505.00 0.08 40.40
Mason 2nd class (Semi-skilled) Day 0005 505.00 0.10 50.50
Beldar (Un skilled) Day 0025 431.00 0.10 43.10
Machinery:
Hire charges of grout pump with agitator and accessories Hour 0110 500.00 0.10 50.00
Sundries Lumpsum 9901 1.00 5.00 5.00
219.80
Add for Water Charges @ 1% Lumpsum 9902 0.01 2.20
222.00
Add for GST @ 12% (multiplying factor 0.1405) Lumpsum 9903 0.14 31.19
253.19
Add for Contractor’s Overheads and Profit @ 15% Lumpsum 9904 0.15 37.98
291.17
Add for Cess @ 1% Lumpsum 9905 0.01 2.91
Rate per kg Kg 294.08
052072 Cement Sand Mortar (1:1) Grout with 20% anti-shrinkage compound w.r.t. cement.
052080 Applying epoxy mortar over leached, honey combed and spalled concrete surface
and exposed steel reinforcement complete as per Technical Specification with
average thickness of 10mm including priming coat, mortar plaster and seal coat of
epoxy.
052090 Applying shotcrete mixture of average thickness 40mm over masonry / concrete
including removal of defective concrete, raking the mortar in joints, cleaning the
surface thoroughly, fixing 50x50x3mm wire mesh over the surface for application of
grout mixture comprising cement, sand,coarse aggregate, water, quick setting
compoud complete as per procedures and specifications given in IRBM Para No
209(3) including curing. Rate is excluding the cost of cement which shall be paid
extra.
052100 Applying pre-packed cement based polymer mortar of strength 45 Mpa (28 days) for
replacement of spalled concrete with average thickness of 10mm as per
manufacturer's specification and approved procedure.
Taking output = 10 sqm
Assumed thickness - 10 mm maximum
Material:
Acrylic polymer bonding coat Litre 0352 150.00 1.40 210.00
Pre packed cement based polymer mortar of strength 45 Mpa at 28 days Kg 0353 22.00 120.00 2,640.00
Labour:
Mate (Semi skilled) Day 0003 505.00 0.04 20.20
Mason 1st class (Skilled) Day 0004 609.00 0.50 304.50
Beldar (Un skilled) Day 0025 431.00 0.50 215.50
Sundries Lumpsum 9901 1.00 70.00 70.00
3,460.20
Add for Water Charges @ 1% Lumpsum 9902 0.01 34.60
3,494.80
Add for GST @ 12% (multiplying factor 0.1405) Lumpsum 9903 0.14 491.02
3,985.82
Add for Contractor’s Overheads and Profit @ 15% Lumpsum 9904 0.15 597.87
4,583.69
Add for Cess @ 1% Lumpsum 9905 0.01 45.84
Cost for 10 sqm 4,629.53
Rate per sqm Sqm 462.95
052110 Providing & applying epoxy with pot life not less than 60-90 minutes for bonding of
new concrete with old concrete @ 0.80 kg/sqm and as per specifications including
cleaning the surfaces complete as per approved procedure.
052120 Providing & fixing 12 mm rabbit wire mesh at the junction of RCC where specifically
ordered or as shown in the drawing
Draft IR Unified Stadard Analysis of Rates - 2021 Chapter - 5: Bridge Works (Misc.)
052130 Providing weep holes by making suitable opening or drilling in existing Brick Masonry
/ Plain / Reinforced Concrete abutment, wing wall/return wall with 110 mm dia UPVC
pipe (working pressure 4kg/sqcm) extending through the full width of the structure
complete and repairing the same with cement mortar 1:2 (1 cement : 2 coarse sand).
Rate is excluding the cost of cement which shall be paid extra.
052140 Providing and fixing of Drainage Spouts of 110mm UPVC Type A ISI marked
(Working pressure 4 kg/sqcm) using suitable clamps and adhesive etc., complete.
052150 Providing and laying of filter media consisting of granular materials of GW, GP, SW
groups as per IS:1498 (latest) in required profile behind boulder filling of abutments,
wing walls / return walls etc. above bed level with all labour and material complete job
as per drawing and technical specification of RDSO Guidelines.
052160 Removing all loose concrete, cleaning rust with dusting compound & water jet, drying,
replacing worn out reinforcements by welding new reinforcement for making up lost
steel section, applying approved anti-corrosive polymer coating over the damaged
area to proper profile, providing polymer mortar (upto 20mm thickness) or polymer
concrete (more than 20mm thickness) consisting of cement, sand, 6mm down chips
where required and polymer as per manufacturers' specification. The rate includes
curing for 14 days, all materials, consumables, labours, tools and plants,
scaffolding/staging with all lead and lift. Cost of cement & inforcement to be paid
separately.
Draft IR Unified Stadard Analysis of Rates - 2021 Chapter - 5: Bridge Works (Misc.)
052170 Supply, fabrication and erection of steel members to replace existing corroded
members of built up section made up of MS plate, angles, channels of different
thickness and sizes including painting with one coat of ready mix paint Zinc Chromate
priming to IS:104 followed by one coat of ready mix paint red-oxide Zinc Chrome
primining paint to IS:2074. Structural steel should conform to IS:2062 E250-
Grade'B0'. Fabrication and erection to be as per existing design initially by bolts and
nuts and finally by rivetting during the sanctioned traffic block. Rate includes cutting
of new steel work, removal of rivets by drilling, dismantling of any existing members
required for inserting fabricated members, fixing of new fabricated built up members
with all tools, plants, labour, consumables, machinery and accessories etc. Work will
be executed as per IRS:B 1-2001.
Note: Painting shall be paid extra under relevant item.
Draft IR Unified Stadard Analysis of Rates - 2021 Chapter - 5: Bridge Works (Misc.)
052180 Supplying and changing of corroded worn-out and loose rivets of any size at any
location of the bridges with or without traffic blocks including all tools, plants,
machinery complete in all respects.
052181 For Rivets of size upto 25mm dia.
Taking Output=100 nos
Material:
Mild steel rivets for steel girders Quintal 0232 6540.00 0.50 3,270.00
Labour:
Mate (Semi skilled) Day 0003 505.00 1.00 505.00
Blacksmith - 2nd Class (Semi-skilled) Day 0009 505.00 2.00 1,010.00
Fitter Grade - 1 (Skilled) Day 0010 609.00 2.00 1,218.00
Fitter Grade - 2 (Semi-skilled) Day 0011 505.00 4.00 2,020.00
Beldar (Semi Skilled) Day 0024 505.00 8.00 4,040.00
Machinery:
Hire charges of air compressor 250 cfm capacity with two leads for pneumatic cutters Day 0065 1600.00 2.00 3,200.00
/ hammers
Sundries Lumpsum 9901 1.00 200.00 200.00
15,463.00
Add for Water Charges @ 1% Lumpsum 9902 0.01 154.63
15,617.63
Add for GST @ 12% (multiplying factor 0.1405) Lumpsum 9903 0.14 2,194.28
17,811.91
Add for Contractor’s Overheads and Profit @ 15% Lumpsum 9904 0.15 2,671.79
20,483.69
Add for Cess @ 1% Lumpsum 9905 0.01 204.84
cost per 100 Rivets 20,688.53
Rate per Rivet Each 206.89
052200 Painting the HFL mark and Danger level mark, year of HFL on bridge abutments and
piers with ready mixed paint as per standard in two coats over one coat of primer with
all materials, labour, tools, scaffolding, all lead and lift etc. including writing complete.
Taking progress as 10 marks/day including base and two coats of paint with markings
Material:
Enamel Paint as per RDSO's Spec. no.M&C/PCN/120-2011 Litre 0306 190.00 1.00 190.00
Sundries Lumpsum 9901 1.00 200.00 200.00
Labour:
Painter (Skilled) Day 0012 609.00 1.00 609.00
Beldar (Un skilled) Day 0025 431.00 2.00 862.00
Sundries Lumpsum 9901 1.00 30.00 30.00
1,891.00
Add for Water Charges @ 1% Lumpsum 9902 0.01 18.91
1,909.91
Add for GST @ 12% (multiplying factor 0.1405) Lumpsum 9903 0.14 268.34
2,178.25
Add for Contractor’s Overheads and Profit @ 15% Lumpsum 9904 0.15 326.74
2,504.99
Add for Cess @ 1% Lumpsum 9905 0.01 25.05
Cost of 10 mark 2,530.04
Rate per mark Each 253.00
052210 Providing cast in situ bridge number plaques as per Railway drawing in cement
concrete 1:2:4 mix using 20mm hard stone aggregate embedded in 30mm notch in
Bridge parapet coping duly engraving the letter and figures and an arrow indicating
the direction of flow and finishing the top exposed surface with cement mortar 1:3,
painting letters and figures with two coats of black enamel paint on two coats of white
background with all labour, tools, cement, paint etc. with all leads and lifts.
Taking progress as 10 Bridge No plaques including fi and two coats of paint with
markings
Material:
Enamel Paint as per RDSO's Spec. no.M&C/PCN/120-2011 Litre 0306 190.00 1.00 190.00
Precast Concrete bridge No plaque/ stone Each 0498 287.50 10.00 2,875.00
Labour:
Painter (Skilled) Day 0012 609.00 1.00 609.00
Beldar (Un skilled) Day 0025 431.00 4.00 1,724.00
Sundries Lumpsum 9901 1.00 100.00 100.00
5,498.00
Add for Water Charges @ 1% Lumpsum 9902 0.01 54.98
5,552.98
Add for GST @ 12% (multiplying factor 0.1405) Lumpsum 9903 0.14 780.19
Draft IR Unified Stadard Analysis of Rates - 2021 Chapter - 5: Bridge Works (Misc.)
052220 Providing cast in-situ plaques for bridge foundations details of size 45cmx45cmx5cm
in cement concrete 1:2:4 mix using 20mm hard stone aggregate embedded in 30mm
deep notch over abutment & piers, engraving the letters & figures with CM 1:3 and
finished smooth including painting letters and figures with 2 coats of black enamel and
plaque with white enamel with all labour, tools, cement, paint, curing etc. as a
complete job.
052230 Providing & laying non pressure NP-4 Class RCC pipe with collars, jointing with 1:2
cement and ordinary sand mortar including testing of joints, but excluding earthwork
with all labour and material as a complete job. Cement for mortar will be paid
separately.(Pipes of 600mm dia and above will be laid using crane/hydra).
052240 Supplying, spreading and filling coarse sand (no cohesive materials to be used) of
approved quality including watering and ramming in foundation, behind the abutment,
wing wall, retaining wall in layers not exceeding 150mm thick including its compaction
as per direction of Engineer-in-charge. The rate includes all lead, lift, ascent, descent,
crossing of Railway line etc. complete with contractor’s labour, materials, tools and
plant.
052250 Providing Boulder Backing behind wing wall, return wall, retaining wall with hand
packed boulders & cobbles with smaller size boulders toward the back including all
lead, lift, labour & other incidental charges as complete work in all respect. Payment
for boulder/cobbles will be done extra.
052260 Dewatering of natural or accumulated water from any location. Payment to be done
for Horse power of pump multiplied by pumping hours.
Taking output HP Hours = 5X6 = 30 HP Hours
Hire charges of pump set of capacity 4000 litre per hour Day 0086 900.00 1.00 900.00
Sundries Lumpsum 9901 1.00 10.00 10.00
910.00
Add for Water Charges @ 1% Lumpsum 9902 0.01 9.10
919.10
Add for GST @ 12% (multiplying factor 0.1405) Lumpsum 9903 0.14 129.13
1,048.23
Add for Contractor’s Overheads and Profit @ 15% Lumpsum 9904 0.15 157.24
1,205.47
Add for Cess @ 1% Lumpsum 9905 0.01 12.05
Cost of 30 hrs 1,217.52
Rate per hour per HP HP Hour 40.58
052270 Supplying & fixing Galvanised Steel Wire Ropenet, made of 9mm dia. steel wire rope
having aperture size of 45cm x 60cm with 6m long hangs for top anchoring and 5m
wide alongwith chain-link mesh-netting of 80mm x 80mm mesh size made from
2.4mm dia galvanised wire, joining of chain-link mesh & steel wire ropenet and joining
of adjacent nets with galvanised spiral lock springs of steel wire dia 2.2mm; inner dia.
of springs 18mm; total length 50mm ± 0.5mm; pitch 4mm & open end length 60mm
including cutting of tree/shrub etc. in rope-netting location and also, excavation /
filling-back of trenches in all types of soil after anchoring ropenet with RCC pre-cast
beam of size 15cm x 15cm x 2m of M-15 concrete & 30cm thick M-10 PCC. This work
also includes supply of 200mm x 200mm x 6mm epoxy coated washer plates with
12.5mm / 18mm dia. hole at centre and supplying & fixing of anchor bolts/fastners of
10mm dia. including drilling of holes upto a depth of 110mm in rock; cleaning of holes;
fixing of fastners with nut & epoxy coated washer plates; applying torque 65 to 70
N/mm for fixing of ropenet for intermediate anchoring on the surface of cutting,
bottom anchoring upto 1m depth by using 16mm dia. HYSD steel bolts, threaded upto
200mm on top and fixing epoxy coated washer plate, fabrication & fixing of U-pin on
top of cutting for top anchoring and joining of adjacent nets with spiral spring and
fixing at the ratio of 1 no. per 0.6m in longitudinal direction of net portion and
additional locks for lacing chain link netting with ropenet with contractor's materials,
machinery, tools & plants, cement, steel, labour, lead, lift, transportation, ascent,
descent, taxes, royalty etc. complete as per directions of engineer-in-charge.
Note: Concrete will be paid separately under relevant item.
Material:
Galvanised steel wire mesh rope net made of 9mm dia steel wire rope having Sqm 0362 468.00 100.00 46,800.00
aperture size of 45cm x 60cm with 6m length hangs
Galvanised chain link mesh netting of 80mm x 80mm mesh size Sqm 0357 180.00 100.00 18,000.00
Galvanised spiral lock spring Each 0358 19.20 15.00 288.00
Epoxy coated washer plate of 200mm x 200mm x 6mm size Each 0359 156.00 32.00 4,992.00
Anchor fastener of 10mm dia and 110mm length Each 0360 72.00 20.00 1,440.00
Bottom anchors of 16mm dia HYSD & 1m length Each 0361 276.00 12.00 3,312.00
U pin of 6mm dia mild steel of 0.3m length for stone cladding work Each 0493 14.00 33.00 462.00
Labour:
Fitter Grade - 1 (Skilled) Day 0010 609.00 2.00 1,218.00
Blacksmith - 2nd Class (Semi-skilled) Day 0009 505.00 2.00 1,010.00
Draft IR Unified Stadard Analysis of Rates - 2021 Chapter - 5: Bridge Works (Misc.)
052280 Supplying & placing of Mechanically Woven Double Twisted Hexagonal Shaped Wire
Mesh Gabion Boxes of required sizes, Mesh Type 10cm x 12cm, Zn and PVC coated
Mesh Wire dia. 2.7/3.7mm (ID/OD), edges of meshes mechanically edged / selvedged
with heavy coating of galvanization as per EN 10223-3/ASTM A 975 with partitions at
every 1m interval and properly packed with approx. 150mm size boulders including
transportation and placing at indicated places as per direction of engineer-in-charge
including contractor's tools, plants, labour, royalty charges etc. complete in all respect
and stitching with lacing wire of dia. 2.2/3.2mm (ID/OD) @ 5% by weight of Gabion
boxes, carrying the material by head load from nearest approach with all safety
precautions and all leads and lifts.
053020 Surface protection of Underside of Bridge Decks, Girders, Inside of Box Girders,
Railings etc. of Bridges and Piers and Substructures which are not in River Bed by
cleaning and drying the surface; repairing local defects, e.g. honeycombs with a paste
of cement admixed with 5% by weight of cement of Polymer bonding agent, applying
(@ 0.30 litre/sqm) a coat (DFT of 100-150 micron) of a translucent brown coloured
modified phenolic resin based single component high performance polymeric
waterproofing compound (sp. gr. 0.87, resin content nil and a solid content of
minimum 0.47%), applying (@ 0.25 litre/sqm) a top coat of a modified phenolic resin
based single component waterproofing compound of grey or other shades (sp. gr.
0.85) before the base coat becomes tack-free; permitting the coatings to cure and dry
naturally; the 2-coat system shall be impermeable under a water head of 20m,
complete as per specification.
Cost of 1 sqm
Material:
Surface protection material ESI Permaproof Litre 0197 253.00 0.30 75.90
Surface protection material ESI Permacil -GA Litre 0198 272.55 0.25 68.14
Surface protection material ESI Bond Litre 0199 278.30 0.05 13.92
Sundries Lumpsum 9901 1.00 10.00 10.00
Labour:
Stone Chiseller (Semi skilled) Day 0017 505.00 0.06 30.30
Mason 2nd class (Semi-skilled) Day 0005 505.00 0.04 20.20
Painter (Skilled) Day 0012 609.00 0.06 36.54
Beldar (Un skilled) Day 0025 431.00 0.10 43.10
Mate (Semi skilled) Day 0003 505.00 0.02 10.10
Sundries Lumpsum 9901 1.00 20.00 20.00
328.19
Add for Water Charges @ 1% Lumpsum 9902 0.01 3.28
331.47
Add for GST @ 12% (multiplying factor 0.1405) Lumpsum 9903 0.14 46.57
378.05
Add for Contractor’s Overheads and Profit @ 15% Lumpsum 9904 0.15 56.71
Draft IR Unified Stadard Analysis of Rates - 2021 Chapter - 5: Bridge Works (Misc.)
053030 Surface protection of Bridge Deck by cleaning and preparing the surface by acid
etching; treating the surface with a two-layer plaster; first layer of 5mm thick with
cement (OPC or slag), admixed with an octadecanoic acid based cementitious
waterproofing compound (bulk density not greater than 0.5 gm/cc) in the weight ratio
of 50:3 for cement and waterproofing compound, further enriched with specially
fabricated deformed galvanized steel fibre @ 150 gm/sqm of treated surface and
second layer of 12mm thick cement-sand (1:2.5) plaster, enriched with polyester fibre
(to be paid separately) and curing the plastered surface. Treatment shall be
impermeable under a water head of 20m complete as per specifications. Rate is
excluding cost of cement which shall be paid extra.
Cost of 1sqm
Material:
Waterproofing compound Kg 0195 207.00 0.60 124.20
Fine Sand (Zone IV) Cum 0203 1000.00 0.01 11.00
Muriatic Acid Kg 0196 23.00 1.00 23.00
Galvanised steel fibre Kg 0356 200.00 0.15 30.00
Tools, implements and other consumbables Lumpsum 9901 1.00 10.00 10.00
Labour:
Mason 2nd class (Semi-skilled) Day 0005 505.00 0.20 101.00
Stone Chiseller (Semi skilled) Day 0017 505.00 0.10 50.50
Beldar (Un skilled) Day 0025 431.00 0.25 107.75
Mate (Semi skilled) Day 0003 505.00 0.08 40.40
Sundries Lumpsum 9901 1.00 30.00 30.00
527.85
Add for Water Charges @ 1% Lumpsum 9902 0.01 5.28
533.13
Add for GST @ 12% (multiplying factor 0.1405) Lumpsum 9903 0.14 74.90
608.03
Add for Contractor’s Overheads and Profit @ 15% Lumpsum 9904 0.15 91.20
699.24
Add for Cess @ 1% Lumpsum 9905 0.01 6.99
Rate per sqm Sqm 706.23
053040 Designing and developing Detailed structural and working Drawings for following
items for ROB/RUB/Bridge based on Railway's approved GADs, duly collecting
necessary data from Railways and R&B authorities, duly designing members and
submission of check plot duly getting proof-checked by Railway approved institutes,
submitting for Railway's verification and approval, making corrections duly
incorporating suggestions in drawings/designs, further submission of original in
transparent film paper and soft copy (CD) for Railways approval etc. with contractor's
technical expertise and instruments, labour, consumables, repeatedly attending till
final approval etc., complete as directed by Engineer in-charge.
053043 Foundation and sub-structure for RCC retaining wall, abutment and approach slab
053050 Extra for providing and mixing synthetic Polyester triangular synthetic fibre in
specified ratio (@ 0.25% of cement by weight), 6 to 18mm in length, designed for
melting point 240°C to 260°C and specific gravity of 1.33 to 1.40 in all types of work
CC/RCC/plaster etc., This item shall only be used on specific instructions of
Engineer-in-Charge.
Material:
Synthetic polyester triangular fibre of length 6 mm, effective diameter 10-40 microns Kg 0194 400 1.000 400.00
and specific gravity of 1.34 to 1.40.
400.00
Add for Water Charges @ 1% Lumpsum 9902 0.01 4.00
404.00
Add for GST @ 12% (multiplying factor 0.1405) Lumpsum 9903 0.14 56.76
460.76
Add for Contractor’s Overheads and Profit @ 15% Lumpsum 9904 0.15 69.11
529.88
Add for Cess @ 1% Lumpsum 9905 0.01 5.30
Rate per 1 kg of fibre Kg 535.18
Draft IR Unified Stadard Analysis of Rates - 2021 Chapter - 6: Rail, Sleepers Fittings Renewals
Labour:
Mate (Skilled) Day 0002 609.00 1.00 609.00
Look Out Man (Un-skilled) Day 0033 431.00 1.00 431.00
Waterman (Un-skilled) Day 0034 431.00 1.00 431.00
Labour Unskilled Day 0020 431.00 24.00 10,344.00
Misc.:
T & P (Rail tongue, Crow bar, Rail Dolly etc.) @1% on labour cost Lumpsum 9901 1.00 120.00 120.00
11,935.00
Add for Water Charges @ 1% Lumpsum 9902 0.01 119.35
12,054.35
Add for GST @ 12% (multiplying factor 0.1405) Lumpsum 9903 0.14 1,693.64
13,747.99
Add for Contractor’s Overheads and Profit @ 15% Lumpsum 9904 0.15 2,062.20
15,810.18
Add for Cess @ 1% Lumpsum 9905 0.01 158.10
Cost for 1040 Running Metre 15,968.29
Rate per RM RM 7.68
Labour:
Mate (Skilled) Day 0002 609.00 4.00 2,436.00
Look Out Man (Un-skilled) Day 0033 431.00 1.00 431.00
Waterman (Un-skilled) Day 0034 431.00 4.00 1,724.00
Labour Unskilled Day 0020 431.00 120.00 51,720.00
Misc.:
T & P (Rail tongue, Crow bar, Rail Dolly etc.) Lumpsum 9901 1.00 240.00 240.00
56,551.00
Add for Water Charges @ 1% Lumpsum 9902 0.01 565.51
57,116.51
Add for GST @ 12% (multiplying factor 0.1405) Lumpsum 9903 0.14 8,024.87
65,141.38
Add for Contractor’s Overheads and Profit @ 15% Lumpsum 9904 0.15 9,771.21
74,912.59
Add for Cess @ 1% Lumpsum 9905 0.01 749.13
Cost for 3120 TM 75,661.71
Cost for 1 Running Metre RM 12.13
Labour:
Labour Unskilled Day 0020 431.00 60.00 25,860.00
Misc.:
T & P (Rail tongue, Crow bar, Rail Dolly etc.) Lumpsum 9901 1.00 120.00 120.00
25,980.00
Add for Water Charges @ 1% Lumpsum 9902 0.01 259.80
26,239.80
Add for GST @ 12% (multiplying factor 0.1405) Lumpsum 9903 0.14 3,686.69
29,926.49
Add for Contractor’s Overheads and Profit @ 15% Lumpsum 9904 0.15 4,488.97
34,415.47
Add for Cess @ 1% Lumpsum 9905 0.01 344.15
Cost for 3120 Track Metre 34,759.62
Cost for 1 Running Metre RM 5.57
061020 Dismantling and removing rail of all types & length from track, laid on any type &
density of sleeper by removing fish plates, fastenings & fish bolts and other materials
including stacking all released materials as directed by Engineer in-charge.
Note:
1.Cutting of rails shall be paid separately.
2.Work to be done under traffic block.
061030 Insertion of rails of all types & length in track, laid on any type & density of sleeper to
the specified gauge under traffic block. Rates include fastning of rail with sleepers
with standard set of fastenings and fixing of fish plates and bolts or, if required,
providing gap for welding.
Note: Rail drilling and cutting to be paid separately.
062000 2. Sleepers
062010 Through Sleeper Renewal (TSR) with normal PSC sleepers involving removal
existing sleepers of any type along with fittings from track, insertion of PSC sleepers
lying along the cess / formation / slope / toe within 5 metres height with all fittings to
specified spacing, gauge and squareness, one round of thorough packing to make
track fit for 20 kmph speed, dressing of ballast to standard profile, all in accordance
with the latest provisions of IRPWM and stacking of all released material neatly at
specified places as directed by Engineer in-charge.
062012 For location of work involving deep screening (deep screening to be paid separately).
Details of cost for 80 sleepers
Deep screening involve complete removal of ballast making free space for removal
and innsertion and initial packing is a part of deep screening, TSR will involve only
insertion and removal without obstruction sleepers. Therefore, one group of 2 persons
will remove 20 sleepers in a day and another group of 2 persons will insert 16
sleepers in a day.
Labour:
(i) For removing sleeper & fittings
Labour Unskilled Day 0020 431.00 8.00 3,448.00
(ii) For inserting sleeper with fixing fittings etc.
Labour Unskilled Day 0020 431.00 10.00 4,310.00
(iii) For stacking of released materials
Labour Unskilled Day 0020 431.00 4.00 1,724.00
Misc.:
T&P Lumpsum 9901 1.00 30.00 30.00
9,512.00
Add for Water Charges @ 1% Lumpsum 9902 0.01 95.12
9,607.12
Add for GST @ 12% (multiplying factor 0.1405) Lumpsum 9903 0.14 1,349.80
10,956.92
Add for Contractor’s Overheads and Profit @ 15% Lumpsum 9904 0.15 1,643.54
12,600.46
Add for Cess @ 1% Lumpsum 9905 0.01 126.00
Cost for 80 sleepers 12,726.46
Rate of each sleeper Each 159.08
062013 For PSC wider base sleepers - For location of work not involving deep screening
Considering 2.5% extra over 062011, Cost of Each sleeper
Rate of each sleeper Each 062011 285.43 1.03 292.57
062014 For PSC wider base sleepers - For location of work involving deep screening. (deep
screening to be paid separately)
Considering 2.5% Extra over item No 062012, Cost of Each sleeper
Rate of each sleeper Each 062012 159.08 1.03 163.06
062015 Extra to item no. 062011, 062012, 062013 and 062014 for sleepers lying on slope /
toe of bank beyond initial height of 5 metres.
Details of cost for 100 sleepers
Labour:
Labour Unskilled Day 0020 431.00 4.00 1,724.00
1,724.00
Add for Water Charges @ 1% Lumpsum 9902 0.01 17.24
1,741.24
Add for GST @ 12% (multiplying factor 0.1405) Lumpsum 9903 0.14 244.64
1,985.88
Add for Contractor’s Overheads and Profit @ 15% Lumpsum 9904 0.15 297.88
2,283.77
Add for Cess @ 1% Lumpsum 9905 0.01 22.84
Cost for 100 sleepers 2,306.60
Rate of each sleeper Each 23.07
Draft IR Unified Stadard Analysis of Rates - 2021 Chapter - 6: Rail, Sleepers Fittings Renewals
062020 Re-spacing of existing PSC sleepers for Increasing Sleeper Density (ISD) work in
track after marking of sleeper spacing as per required sleeper density, including
fixing all fastenings and initial packing, as directed.
Note: Insertion of new sleeper will be paid extra under relevant item.
062022 For location of work involving deep screening (deep screening to be paid separately).
Considering cost for 240 TM (For 1660 density, 240 TM = 400 Sleepers)
Group of additional 4 persons will do re-spacing of 80 sleepers. Additional labour
required for 400 sleepers = 4 x 400/80 = 20 nos.
Labour:
(i) Pre marking of sleeper spacing as per required density
Painter (Skilled) Day 0012 609.00 0.25 152.25
Helper (Semi-skilled) Day 0021 505.00 0.50 252.50
(ii) Re spacing of sleepers with fixing fittings
Labour Unskilled Day 0020 431.00 20.00 8,620.00
Misc.:
T & P and consumables Lumpsum 9901 1.00 100.00 100.00
9,124.75
Add for Water Charges @ 1% Lumpsum 9902 0.01 91.25
9,216.00
Add for GST @ 12% (multiplying factor 0.1405) Lumpsum 9903 0.14 1,294.85
10,510.85
Add for Contractor’s Overheads and Profit @ 15% Lumpsum 9904 0.15 1,576.63
12,087.47
Add for Cess @ 1% Lumpsum 9905 0.01 120.87
Cost for 240 TM 12,208.35
Cost for 1 TM TRM 50.87
062030 Replacement of any type of sleepers in track with PSC sleepers lying on cess or at
Bridge Approaches for casual renewal at isolated locations with all fittings complete to
specified gauge & cross level with contractor’s tools including packing and dressing of
ballast, as directed by Engineer in-charge. Released materials shall be neatly stacked
and handed over at specified location or near either side of Bridge approaches as
directed.
Draft IR Unified Stadard Analysis of Rates - 2021 Chapter - 6: Rail, Sleepers Fittings Renewals
063020 Through renewal of Metal / GFN liners in running track condition after cleaning of rail
foot at liner seat, greasing of liner and liner seat at rail foot including removing,
cleaning & lubrication of ER Clip & Insert Eye and re-driving the same with
contractor's grease graphite of approved quality with all lead & lift.
Details of cost for 1660 nos. sleeper (For renewal Metal / GFN liners one group of 2
persons will renew liners of 300 sleepers in a day)
Material:
Grease Graphite Grade 'O' (IS:408) Kg 0184 240.00 70.00 16,800.00
Kerosene Oil Litre 0185 56.00 5.00 280.00
Cotton Jute Kg 0494 40.00 2.00 80.00
Wire Brush - 25cm long Each 0313 15.00 6.00 90.00
Sand Paper Nos. 0496 5.00 10.00 50.00
Soft Brush for painting - 25cm long Each 0314 33.00 6.00 198.00
Labour:
Mate (Skilled) Day 0002 609.00 2.00 1,218.00
Look Out Man (Un-skilled) Day 0033 431.00 1.00 431.00
Waterman (Un-skilled) Day 0034 431.00 1.00 431.00
(i) For Leading & distibution of materials in 1 Km stretch & collection of released
materials.
Draft IR Unified Stadard Analysis of Rates - 2021 Chapter - 6: Rail, Sleepers Fittings Renewals
29,877.00
Add for Water Charges @ 1% Lumpsum 9902 0.01 298.77
30,175.77
Add for GST @ 12% (multiplying factor 0.1405) Lumpsum 9903 0.14 4,239.70
34,415.47
Add for Contractor’s Overheads and Profit @ 15% Lumpsum 9904 0.15 5,162.32
39,577.79
Add for Cess @ 1% Lumpsum 9905 0.01 395.78
Cost for 1660 nos.sleeper 39,973.56
Rate per Sleeper Sleeper 24.08
063030 Through Fitting Renewal (TFR) on PSC track, comprising of renewal of Grooved
Rubber Pads, Liners and ERCs without damaging PSC sleepers. Scope includes
removal of all fittings, cleaning of rail seat, rail flange at liner seats, and eye of Inserts
with wire brushes and applying Grease Graphite Grade "O" (IS:408) to eye of insert
and central leg of ERC with contractor's grease of Railway’s specification, fixing all
fitings in correct position and sealing liner edges with grease all complete including
collection and stacking of released materials at nominated locations within SSE
Jurisdiction as directed by Engineer-in-Charge.
Note: All the fittings will be supplied at SSE/Stores/Depot.
Details of cost for 1660 nos. sleeper (For TFR on PSC track one group of 3 persons
will renew fittings for 185 sleepers in a day).
Material:
Grease Graphite Grade 'O' (IS:408) Kg 0184 240.00 70.00 16,800.00
Kerosene Oil Litre 0185 56.00 5.00 280.00
Cotton Jute Kg 0494 40.00 2.00 80.00
Wire Brush - 25cm long Each 0313 15.00 6.00 90.00
Sand Paper Nos. 0496 5.00 10.00 50.00
Soft Brush for painting - 25cm long Each 0314 33.00 6.00 198.00
Labour:
(i) For Leading & distibution of materials in 1 Km stretch & collection of released
Labour Unskilled Day 0020 431.00 10.00 4,310.00
(ii) For Fitting renewal & greasing of ERC's, liners & sealing liner edges.
Mate (Skilled) Day 0002 609.00 2.00 1,218.00
Waterman (Un-skilled) Day 0034 431.00 2.00 862.00
Look Out Man (Un-skilled) Day 0033 431.00 1.00 431.00
Labour Unskilled Day 0020 431.00 27.00 11,637.00
Misc.:
T & P ( Hammer, Crow bars, Tami bar, beater, Wire claws, etc.) Lumpsum 9901 1.00 80.00 80.00
Hire charges for tractor with trolley Day 0081 1200.00 1.00 1,200.00
37,236.00
Add for Water Charges @ 1% Lumpsum 9902 0.01 372.36
37,608.36
Add for GST @ 12% (multiplying factor 0.1405) Lumpsum 9903 0.14 5,283.97
42,892.33
Add for Contractor’s Overheads and Profit @ 15% Lumpsum 9904 0.15 6,433.85
49,326.18
Add for Cess @ 1% Lumpsum 9905 0.01 493.26
Cost for 1660 nos. sleeper 49,819.45
Rate per Sleeper Sleeper 30.01
Draft IR Unified Stadard Analysis of Rates - 2021 Chapter - 6: Rail, Sleepers Fittings Renewals
Details of cost for 1660 nos. sleeper (For Through replacement of GRSP one group
of 3 persons will renew GRSP for 200 sleepers in a day).
Material:
Grease Graphite Grade 'O' (IS:408) Kg 0184 240.00 70.00 16,800.00
Kerosene Oil Litre 0185 56.00 5.00 280.00
Cotton Jute Kg 0494 40.00 2.00 80.00
Wire Brush - 25cm long Each 0313 15.00 6.00 90.00
Sand Paper Nos. 0496 5.00 10.00 50.00
Soft Brush for painting - 25cm long Each 0314 33.00 6.00 198.00
Labour:
(i) For Leading & distibution of materials in 1 Km stretch & collection of released
Labour Unskilled Day 0020 431.00 7.00 3,017.00
(ii) For GRSP renewal & greasing of ERC's, liners & sealing liner edges.
Mate (Skilled) Day 0002 609.00 2.00 1,218.00
Waterman (Un-skilled) Day 0034 431.00 1.00 431.00
Look Out Man (Un-skilled) Day 0033 431.00 1.00 431.00
Labour Unskilled Day 0020 431.00 25.00 10,775.00
Misc.:
T & P ( Hammer, Crow bars, Tami bar, beater, Wire claws, etc.) Lumpsum 9901 1.00 80.00 80.00
Hire charges for tractor with trolley Day 0081 1200.00 1.00 1,200.00
34,650.00
Add for Water Charges @ 1% Lumpsum 9902 0.01 346.50
34,996.50
Add for GST @ 12% (multiplying factor 0.1405) Lumpsum 9903 0.14 4,917.01
39,913.51
Add for Contractor’s Overheads and Profit @ 15% Lumpsum 9904 0.15 5,987.03
45,900.53
Add for Cess @ 1% Lumpsum 9905 0.01 459.01
Cost for 1660 nos. sleeper 46,359.54
Rate per Sleeper Sleeper 27.93
063050 Lubrication of fish plated rail joints under traffic by using Grease Graphite Grade 'O'
(IS:408) and Black oil, tools & plants, supplied by contractor for all types of rail
sections as per procedure laid down in latest version of IRPWM and as directed by
Engineer In charge.
Note: Release U/S bolt & nuts is to be deposited back. If any fish bolts is jammed it
should be cut with chisel and hammer and replaced with fresh fish bolt supplied.
063060 Opening and refixing of Joggled fish plates provided to weld joints/rail of any rail
section under traffic to enable examination of weld/rail by departmental official
nominated by Engineer Incharge and lubrication of fishplates by applying
departmental Grease graphite grade 'O' (IS:408) to fishing planes and bolts by
departmental black oil as per procedure laid down in latest version of IRPWM,
including all tools required and as directed by Engineer-in-charge.
Note:
1. Grease Graphite, black oil, fish bolts, K.Oil, wire brush, required for work shall be
given by department and issued at concerned SSE/PW Stores.
2.Jammed fish bolts shall be cut using chisel and hammer and replaced with new
Details of cost for 40 sets considering 1 group of 3 persons shall do 40 Sets
Labour:
Labour Unskilled Day 0020 431.00 3.00 1,293.00
Misc.: 0.00
T & P (Spanner set, Chisel, Hammer, Beater etc.) Lumpsum 9901 1.00 20.00 20.00
1,313.00
Add for Water Charges @ 1% Lumpsum 9902 0.01 13.13
Draft IR Unified Stadard Analysis of Rates - 2021 Chapter - 6: Rail, Sleepers Fittings Renewals
063070 Lubrication of Elastic Rail Clips on PSC sleepers with contractor’s grease, conforming
to Railway’s specifications, labour etc. complete as per procedure prescribed in
latest edition of IRPWM.
Details of cost for 6640 nos. ERC (For Lubrication of ERC's one group of 2 persons
will do 1200 ERC's in a day)
Material:
Grease Graphite Grade 'O' (IS:408) Kg 0184 240.00 40.00 9,600.00
Kerosene Oil Litre 0185 56.00 3.00 168.00
Cotton Jute Kg 0494 40.00 2.00 80.00
Wire Brush - 25cm long Each 0313 15.00 6.00 90.00
Sand Paper Nos. 0496 5.00 10.00 50.00
Soft Brush for painting - 25cm long Each 0314 33.00 6.00 198.00
Labour:
Mate (Skilled) Day 0002 609.00 1.00 609.00
Look Out Man (Un-skilled) Day 0033 431.00 1.00 431.00
Waterman (Un-skilled) Day 0034 431.00 1.00 431.00
Labour Unskilled Day 0020 431.00 12.00 5,172.00
Misc.:
T&P Lumpsum 9901 1.00 24.00 24.00
16,853.00
Add for Water Charges @ 1% Lumpsum 9902 0.01 168.53
17,021.53
Add for GST @ 12% (multiplying factor 0.1405) Lumpsum 9903 0.14 2,391.52
19,413.05
Add for Contractor’s Overheads and Profit @ 15% Lumpsum 9904 0.15 2,911.96
22,325.01
Add for Cess @ 1% Lumpsum 9905 0.01 223.25
Cost for 6640 nos. ERC 22,548.26
Rate per ERC Each 3.40
063080 Lubrication of Elastic Rail Clips on PSC sleepers with Railway’s grease, conforming
to Railway’s specifications, labour etc. complete as per procedure prescribed in latest
edition of IRPWM.
Details of cost for 6640 nos. ERC (For Lubrication of ERC's one group of 2 persons
Material:
Kerosene Oil Litre 0185 56.00 3.00 168.00
Cotton Jute Kg 0494 40.00 2.00 80.00
Wire Brush - 25cm long Each 0313 15.00 6.00 90.00
Sand Paper Nos. 0496 5.00 10.00 50.00
Soft Brush for painting - 25cm long Each 0314 33.00 6.00 198.00
Labour:
Mate (Skilled) Day 0002 609.00 1.00 609.00
Look Out Man (Un-skilled) Day 0033 431.00 1.00 431.00
Waterman (Un-skilled) Day 0034 431.00 1.00 431.00
Labour Unskilled Day 0020 431.00 12.00 5,172.00
Misc.:
T&P Lumpsum 9901 1.00 24.00 24.00
7,253.00
Add for Water Charges @ 1% Lumpsum 9902 0.01 72.53
7,325.53
Add for GST @ 12% (multiplying factor 0.1405) Lumpsum 9903 0.14 1,029.24
8,354.77
Draft IR Unified Stadard Analysis of Rates - 2021 Chapter - 6: Rail, Sleepers Fittings Renewals
063090 Lubrication of ERCs and its liner contact area by removal of ERCs and Metal / GFN
liners in rail panel, cleaning of rust / scale of ERC, Metal / GFN liners & SGCI insert
by using wire brush, scrapper / sand emery paper etc supply and application of
graphite grease, as prescribed by Railway for under side of liners & corresponding
area of rail foot & SGCI insert with ERCs and re-fixing the same as per procedure
prescribed in latest edition of IRPWM with contractors grease and all other tools &
plants complete and as directed.
Details of cost for 1660 sleepers i..e. 6640 nos. ERC (For Lubrication of ERC with
liner contact area one group of 5 persons will do 1000 ERC's in a day)
Material:
For greasing of ERCs and liner contact area of 1 sleeper requires 35 gram grease
graphite.
Grease Graphite Grade 'O' (IS:408) Kg 0184 240.00 58.00 13,920.00
Wire Brush - 25cm long Each 0313 15.00 6.00 90.00
Soft Brush for painting - 25cm long Each 0314 33.00 6.00 198.00
Sand Paper Nos. 0496 5.00 10.00 50.00
Cotton Jute Kg 0494 40.00 4.00 160.00
Labour:
Mate (Skilled) Day 0002 609.00 1.00 609.00
Look Out Man (Un-skilled) Day 0033 431.00 1.00 431.00
Labour Unskilled Day 0020 431.00 33.00 14,223.00
Misc.:
T&P Lumpsum 9901 1.00 20.00 20.00
29,701.00
Add for Water Charges @ 1% Lumpsum 9902 0.01 297.01
29,998.01
Add for GST @ 12% (multiplying factor 0.1405) Lumpsum 9903 0.14 4,214.72
34,212.73
Add for Contractor’s Overheads and Profit @ 15% Lumpsum 9904 0.15 5,131.91
39,344.64
Add for Cess @ 1% Lumpsum 9905 0.01 393.45
Cost for 1660 Sleepers 39,738.09
Rate per sleeper Sleeper 23.94
063100 Removing seized ERC from SGCI inserts of existing track by using suitable approved
chemicals or by using heavy duty extractoror or by using any approved method and
re-fixing it with lubrication of insert eye and ERC as per provisions of IRPWM, as
directed by engineer in-charge
Note:
1.Due care shall be taken to avoid any damage to the sleeper
2.A penality of 50% of the basic cost of new sleeper in nearest sleeper factory shall
be levied on each, if SGCI inseret is broken or sleeper gets cracked in the process.
063110 Lubrication of gauge face of rail on curves, cross overs, points & crossings,turn-in
curves and at locations as required with contractor's grease graphite grade "O" IS 408
and as directed.
Details of cost for 1000 RM
Material:
Grease Graphite Grade 'O' (IS:408) Kg 0184 240.00 10.00 2,400.00
Cotton Jute Kg 0494 40.00 0.25 10.00
Wire Brush - 25cm long Each 0313 15.00 1.00 15.00
Labour:
Mate (Skilled) Day 0002 609.00 0.25 152.25
Look Out Man (Un-skilled) Day 0033 431.00 1.00 431.00
Labour Unskilled Day 0020 431.00 2.00 862.00
Misc.:
T&P Lumpsum 9901 1.00 10.00 10.00
3,880.25
Add for Water Charges @ 1% Lumpsum 9902 0.01 38.80
3,919.05
Add for GST @ 12% (multiplying factor 0.1405) Lumpsum 9903 0.14 550.63
4,469.68
Add for Contractor’s Overheads and Profit @ 15% Lumpsum 9904 0.15 670.45
5,140.13
Add for Cess @ 1% Lumpsum 9905 0.01 51.40
Cost for 1000 RM 5,191.53
Rate per RM RM 5.19
063120 Lubrication of Plate/Rail screws of Points and crossings, SEJs, Bridges, Curves etc,
including removal of screws carefully without damaging sleepers cleaning with wire
brush etc both screws and dowel hole applying Railways grease graphite, refixing the
screw and sealing the top and sides of screw with Railway's grease graphite to
prevent ingress of moisture and corrosion with contractors labour, tools, consumables
under traffic condition all lead and lift complete.
063130 Scattered renewal or replacement of missing / worn-out fittings with Railway's fittings
for track/Points & Crossings sleepers including leading to required location for the
work and the released fittings shall be collected and neatly stacked, as directed by
the Engineer Incharge.
063131 GRSP
Details of cost for 200 nos
Labour:
Look Out Man (Un-skilled) Day 0033 431.00 1.00 431.00
Labour Unskilled Day 0020 431.00 5.00 2,155.00
Misc.:
T & P ( Hammer, Crow bars, Tami bar, beater, etc.) Lumpsum 9901 1.00 10.00 10.00
2,596.00
Add for Water Charges @ 1% Lumpsum 9902 0.01 25.96
2,621.96
Add for GST @ 12% (multiplying factor 0.1405) Lumpsum 9903 0.14 368.39
2,990.35
Add for Contractor’s Overheads and Profit @ 15% Lumpsum 9904 0.15 448.55
3,438.90
Add for Cess @ 1% Lumpsum 9905 0.01 34.39
Cost for 200 nos 3,473.29
Rate per GRSP Each 17.37
063140 Renewal of seized/corroded Plate/Rail screws on PSC Sleepers by using gas or any
approved methods, duly drilling holes in broken screw and removing existing screw
pieces from the holes alongwith existing dowels and fixing new contractor's dowels
(procured from RDSO approved sources) and grouting around dowel with Epoxy
materials and refixing new Railway's rail/Plate screws duly greasing the screw with
specified grease with all contractor's materials, consumables, tools & plants, labour
with all lead, lif
Note:
1.Due care shall be taken to avoid any damage to the sleeper
2.A penality of 10% of the basic cost of new sleeper in nearest sleeper factory shall
be levied on each, if sleeper gets damaged in the process.
064011 On Cess
Details of cost for 15 cuts in a day
Material:
Draft IR Unified Stadard Analysis of Rates - 2021 Chapter - 6: Rail, Sleepers Fittings Renewals
064020 Cutting / cropping of rail of 52Kg – 90 UTS, manually and perfectly vertical with
contractor’s labour, hacksaw blade and tools & plants -
Note:
1.Manual cutting should be used only in emergencies with prior permission of
sectional ADEN where machine cutting can not be arranged in time.
2. Cutting of Rails with blade and forcing to part by using other means to break the
rails is prohibited.
3.Rails should be cut right through hacksaw blades only.
064021 On Cess
Details of cost for 13 cuts in a day
Material:
High Speed Hacksaw Blade of size 300mm x 12.5mm x 0.63mm (18TPI) as per as Nos. 0457 160.00 2.00 320.00
per RDSO's Spec. no. TM/SM/26 (latest Rev.)
Labour:
Blacksmith - 1st Class (Skilled) Day 0008 609.00 1.00 609.00
Helper (Semi-skilled) Day 0021 505.00 1.00 505.00
Labour Unskilled Day 0020 431.00 1.50 646.50
Misc.:
T&P Lumpsum 9901 1.00 10.00 10.00
Draft IR Unified Stadard Analysis of Rates - 2021 Chapter - 6: Rail, Sleepers Fittings Renewals
064030 Cutting / cropping of rail of 60Kg – 90 UTS, manually and perfectly vertical with
contractor’s labour, hacksaw blade and tools & plants -
Note:
1.Manual cutting should be used only in emergencies with prior permission of
sectional ADEN where machine cutting can not be arranged in time.
2. Cutting of Rails with blade and forcing to part by using other means to break the
rails is prohibited.
3.Rails should be cut right through hacksaw blades only.
064031 On Cess
Details of cost for 10 cuts in a day
Material:
High Speed Hacksaw Blade of size 300mm x 12.5mm x 0.63mm (18TPI) as per as Nos. 0457 160.00 2.00 320.00
Labour:
Blacksmith - 1st Class (Skilled) Day 0008 609.00 1.00 609.00
Helper (Semi-skilled) Day 0021 505.00 1.00 505.00
Labour Unskilled Day 0020 431.00 1.50 646.50
Misc.:
T&P Lumpsum 9901 1.00 10.00 10.00
2,090.50
Add for Water Charges @ 1% Lumpsum 9902 0.01 20.91
2,111.41
Add for GST @ 12% (multiplying factor 0.1405) Lumpsum 9903 0.14 296.65
2,408.06
Add for Contractor’s Overheads and Profit @ 15% Lumpsum 9904 0.15 361.21
2,769.27
Add for Cess @ 1% Lumpsum 9905 0.01 27.69
Cost for 10 cuts 2,796.96
Draft IR Unified Stadard Analysis of Rates - 2021 Chapter - 6: Rail, Sleepers Fittings Renewals
064033 Extra to item no. 064031 for cutting 110 UTS rail
Take 15% of relevant item rate
Extra Rate per cut Each 41.95
064034 Extra to item no. 064032 for cutting 110 UTS rail
Take 15 % of relevant item rate
Extra Rate per cut Each 61.25
064040 Drilling of hole of different diameter and chamfering, in rail of any section and any
UTS manually only in emergencies only with contractor's labours, tools & plants,
consumables etc.
064041 Hole of dia. 26.5mm and above
Details of cost for 15 holes in a day
Material:
Drill twist made of high speed steel for size 26.5mm dia of Addison / I T make Each 0466 2852.30 0.50 1,426.15
Labour:
Blacksmith - 1st Class (Skilled) Day 0008 609.00 1.00 609.00
Helper (Semi-skilled) Day 0021 505.00 1.00 505.00
Labour Unskilled Day 0020 431.00 1.00 431.00
Misc.:
T & P (Ratchet & Chamfering kit etc.) Lumpsum 9901 1.00 10.00 10.00
2,981.15
Add for Water Charges @ 1% Lumpsum 9902 0.01 29.81
3,010.96
Add for GST @ 12% (multiplying factor 0.1405) Lumpsum 9903 0.14 423.04
3,434.00
Add for Contractor’s Overheads and Profit @ 15% Lumpsum 9904 0.15 515.10
3,949.10
Add for Cess @ 1% Lumpsum 9905 0.01 39.49
Cost for 15 Holes 3,988.59
Rate per Hole Each 265.91
064050 Gas cutting of rail of various sections with contractor’s tools & plants, as directed by
engineer in-charge :
064051 Rail section of 90R and below
Details of cost for 60 Cut
Material:
Oxygen Gas (in cylinder) Kg 0340 50.00 30.00 1,500.00
Commercial LPG (in cylinder) Kg 0339 73.71 8.00 589.68
Labour:
Welder (Skilled) Day 0029 609.00 1.00 609.00
Helper (Semi-skilled) Day 0021 505.00 1.00 505.00
Labour Unskilled Day 0020 431.00 2.00 862.00
Misc.:
T & P (Gas Cutting equipments) Lumpsum 9901 1.00 20.00 20.00
4,085.68
Add for Water Charges @ 1% Lumpsum 9902 0.01 40.86
4,126.54
Add for GST @ 12% (multiplying factor 0.1405) Lumpsum 9903 0.14 579.78
4,706.32
Add for Contractor’s Overheads and Profit @ 15% Lumpsum 9904 0.15 705.95
5,412.26
Add for Cess @ 1% Lumpsum 9905 0.01 54.12
Cost for 60 Cut 5,466.39
Rate per Cut Each 91.11
10,044.10
Add for Water Charges @ 1% Lumpsum 9902 0.01 100.44
10,144.54
Add for GST @ 12% (multiplying factor 0.1405) Lumpsum 9903 0.14 1,425.31
11,569.85
Add for Contractor’s Overheads and Profit @ 15% Lumpsum 9904 0.15 1,735.48
13,305.33
Add for Cess @ 1% Lumpsum 9905 0.01 133.05
Cost for 2 sets 13,438.38
Rate per set Set 6,719.19
065020 Renewal of existing SEJ with improved SEJ with PSC sleepers under traffic block
conditions as per approved drawing including fixing of special size bearing plate,
rubber pad and other sleeper / rail fittings, greasing to the fittings,leading
rails,sleepers & fittings to site, leading and stacking of released materials within a
lead of 250m, cutting of Rails,drilling of holes,fixing of related fittings, providing
temporary connection with fishplates till welding of SEJ is done and sleepers shall be
given initial packing to make track fit for 20KMPH speed.
Note:
(1) Rail cutting and hole dilling shall be paid seperately.
(2) One set comprise complete SEJ on both rails at SEJ.
065030 Assembling and Laying of Improved Switch Expansion Joint (SEJ) on PSC sleepers
of any rail section as per RDSO drawing including leading of SEJ rails, sleepers,
fittings for a free lead of 250 metres, cutting of rails,drilling of holes as required and
lubrication of SEJ, gauging, aligning rails, providing temporary connection with
adequate welding gap with adjoining rails,providing reference posts at SEJ, first
through packing of SEJ potion to make track geometry fit for 30 kmph speed and
making ballast profile as per IRPWM.
Note:
(1) Rail cutting and hole dilling shall be paid seperately.
(2) One set comprise complete SEJ on both rails at SEJ.
065040 Dismantling & removing existing SEJ (Switch Expansion Joint) assembly during line
block and its replacement with plain track as of adjoining section with all fittings
including rail cutting and drilling of holes and renewal of special sleepers with PSC
Sleepers as directed and aligning rails, providing fishplates and bolts/ temporary
connection with adequate welding gap with adjoining rail and ensuring proper track
geometry for 30 kmph speed.The release material shall be stacked as directed by
Engineer incharge.
071011 1 in 8½ Turnout
Details of cost for 1 set
Labour:
Mate (Skilled) Day 0002 609.00 1.00 609.00
Blacksmith - 1st Class (Skilled) Day 0008 609.00 1.00 609.00
Helper (Semi-skilled) Day 0021 505.00 1.00 505.00
Look Out Man (Un-skilled) Day 0033 431.00 1.00 431.00
Waterman (Un-skilled) Day 0034 431.00 1.00 431.00
(i) Removing Lead Rails, Switches, Crossing, Fittings and stacking etc.
Labour Unskilled Day 0020 431.00 12.00 5,172.00
(ii) Removing Sleepers, Transporting & Stacking at store.
Labour Unskilled Day 0020 431.00 12.00 5,172.00
(iii) Levelling of ballast
Labour Unskilled Day 0020 431.00 8.00 3,448.00
(iv) Stacking rails, switches, crossing etc.
Misc.:
T & P (Crow bar, tami bar, beater, Rake ballast , hammer etc.) Lumpsum 9901 1.00 92.00 92.00
Hire charges for tractor with trolley Day 0081 1200.00 1.00 1,200.00
17,669.00
Add for working under traffic block @ 10% Lumpsum 9992 0.10 1,766.90
19,435.90
Add for Water Charges @ 1% Lumpsum 9902 0.01 194.36
19,630.26
Add for GST @ 12% (multiplying factor 0.1405) Lumpsum 9903 0.14 2,758.05
22,388.31
Add for Contractor’s Overheads and Profit @ 15% Lumpsum 9904 0.15 3,358.25
25,746.56
Add for Cess @ 1% Lumpsum 9905 0.01 257.47
Rate per set Set 26,004.02
071012 1 in 12 Turnout
Details of cost for 1 set
Labour:
Mate (Skilled) Day 0002 609.00 1.00 609.00
Blacksmith - 1st Class (Skilled) Day 0008 609.00 1.00 609.00
Helper (Semi-skilled) Day 0021 505.00 1.00 505.00
Look Out Man (Un-skilled) Day 0033 431.00 1.00 431.00
Waterman (Un-skilled) Day 0034 431.00 1.00 431.00
(i) Removing Lead Rails, Switches, Crossing, Fittings and stacking etc.
Labour Unskilled Day 0020 431.00 14.00 6,034.00
(ii) Removing Sleepers, Transporting & Stacking at store.
Labour Unskilled Day 0020 431.00 14.00 6,034.00
Draft IR Unified Stadard Analysis of Rates - 2021 Chapter - 7: Turnouts and Renewals
071013 1 in 16 Turnout
Details of cost for 1 set
Labour:
Mate (Skilled) Day 0002 609.00 1.00 609.00
Blacksmith - 1st Class (Skilled) Day 0008 609.00 1.00 609.00
Helper (Semi-skilled) Day 0021 505.00 1.00 505.00
Look Out Man (Un-skilled) Day 0033 431.00 1.00 431.00
Waterman (Un-skilled) Day 0034 431.00 1.00 431.00
(i) Removing Lead Rails, Switches, Crossing, Fittings and stacking etc.
Labour Unskilled Day 0020 431.00 16.00 6,896.00
(ii) Removing Sleepers, Transporting & Stacking at store.
Labour Unskilled Day 0020 431.00 16.00 6,896.00
(iii) Levelling of ballast
Labour Unskilled Day 0020 431.00 12.00 5,172.00
Misc.:
T & P (Crow bar, tami bar, beater, Rake ballast , hammer etc.) Lumpsum 9901 1.00 120.00 120.00
Hire charges for tractor with trolley Day 0081 1200.00 1.00 1,200.00
22,869.00
Add for working under traffic block @ 10% Lumpsum 9992 0.10 2,286.90
25,155.90
Add for Water Charges @ 1% Lumpsum 9902 0.01 251.56
25,407.46
Add for GST @ 12% (multiplying factor 0.1405) Lumpsum 9903 0.14 3,569.75
28,977.21
Add for Contractor’s Overheads and Profit @ 15% Lumpsum 9904 0.15 4,346.58
33,323.79
Add for Cess @ 1% Lumpsum 9905 0.01 333.24
Cost for 1 set Set 33,657.03
071014 1 in 20 Turnout
Details of cost for 1 set
Labour:
Mate (Skilled) Day 0002 609.00 1.00 609.00
Blacksmith - 1st Class (Skilled) Day 0008 609.00 1.00 609.00
Helper (Semi-skilled) Day 0021 505.00 1.00 505.00
Look Out Man (Un-skilled) Day 0033 431.00 1.00 431.00
Waterman (Un-skilled) Day 0034 431.00 1.00 431.00
(i) Removing Lead Rails, Switches, Fittings and stackingetc.
Labour Unskilled Day 0020 431.00 18.00 7,758.00
(ii) Removing Sleepers, Transporting & Stacking at store.
Labour Unskilled Day 0020 431.00 18.00 7,758.00
(iii) Levelling of ballast
Labour Unskilled Day 0020 431.00 14.00 6,034.00
Draft IR Unified Stadard Analysis of Rates - 2021 Chapter - 7: Turnouts and Renewals
071020 Dismantling of existing BG turnouts, diamond crossings and derailing switches with all
types of rails and sleeper layout, removing rails, switches, crossings, sleepers &
fastenings, leveling of ballast to correct profile & stacking all the released materials,
sleepers, fastenings, rails, switches & crossings including segregating & stacking at
specified locations in a neat and countable manner, within the lead of 250m & all lift,
clear of infringements, crossing of track, if any complete, as directed, under conditions
not requiring Traffic Block.
Note:
1. This item shall be operated only when existing turnout is replaced either with new
turnout in case of TTR or with plain track when existing turnout is no more required at
that location.
2. Rail cutting will be paid extra under relevant item.
3. Laying of new turnout or plain track shall be paid under relavent item for laying on
already prepared ballst bed with initial packing to make it fit for 20 kmph.
071021 1 in 8½ Turnout
Details of cost for 1 set
Draft IR Unified Stadard Analysis of Rates - 2021 Chapter - 7: Turnouts and Renewals
071022 1 in 12 Turnout
Details of cost for 1 set
Labour:
Mate (Skilled) Day 0002 609.00 1.00 609.00
Blacksmith - 1st Class (Skilled) Day 0008 609.00 1.00 609.00
Helper (Semi-skilled) Day 0021 505.00 1.00 505.00
Waterman (Un-skilled) Day 0034 431.00 1.00 431.00
(i) Removing Lead Rails, Switches, Crossing, Fittings and stacking etc.
071023 1 in 16 Turnout
Details of cost for 1 set
Labour:
Mate (Skilled) Day 0002 609.00 1.00 609.00
Blacksmith - 1st Class (Skilled) Day 0008 609.00 1.00 609.00
Helper (Semi-skilled) Day 0021 505.00 1.00 505.00
Waterman (Un-skilled) Day 0034 431.00 1.00 431.00
Draft IR Unified Stadard Analysis of Rates - 2021 Chapter - 7: Turnouts and Renewals
071024 1 in 20 Turnout
Details of cost for 1 set
Labour:
Mate (Skilled) Day 0002 609.00 1.00 609.00
Blacksmith - 1st Class (Skilled) Day 0008 609.00 1.00 609.00
Helper (Semi-skilled) Day 0021 505.00 1.00 505.00
Waterman (Un-skilled) Day 0034 431.00 1.00 431.00
(i) Removing Lead Rails, Switches, Fittings and stacking etc.
Labour Unskilled Day 0020 431.00 16.00 6,896.00
(ii) Removing Sleepers, Transporting & Stacking at store.
Labour Unskilled Day 0020 431.00 13.00 5,603.00
(iii) Levelling of ballast
Labour Unskilled Day 0020 431.00 12.00 5,172.00
Misc.:
T & P (Crow bar, tami bar, beater, Rake ballast , hammer etc.) Lumpsum 9901 1.00 112.00 112.00
Hire charges for tractor with trolley Day 0081 1200.00 1.00 1,200.00
21,137.00
Add for Water Charges @ 1% Lumpsum 9902 0.01 211.37
21,348.37
Add for GST @ 12% (multiplying factor 0.1405) Lumpsum 9903 0.14 2,999.45
24,347.82
Add for Contractor’s Overheads and Profit @ 15% Lumpsum 9904 0.15 3,652.17
27,999.99
Add for Cess @ 1% Lumpsum 9905 0.01 280.00
Cost for 1 set Set 28,279.99
071030 Dismantling the existing BG Buffer-stop laid with rails & wooden/ST sleepers including
leading the dismantled Bufferstop materials to nominated places within station yard
limits and stacking as material-wise and classification-wise duly releasing all fittings
carefully without causing any damage with all contractor's labour, tools, with all lead
and lifts, crossing of tracks if any, etc., complete as directed by the Engineer-in-charge.
072011 1 in 8½ Turnout
Details of cost for 1 set
Labour:
Mate (Skilled) Day 0002 609.00 1.00 609.00
Blacksmith - 1st Class (Skilled) Day 0008 609.00 2.00 1,218.00
Helper (Semi-skilled) Day 0021 505.00 2.00 1,010.00
Waterman (Un-skilled) Day 0034 431.00 1.00 431.00
(i) Leading of special size PSC sleepers, switches, crossing, fitting, fastenings etc.
072012 1 in 12 Turnout
Details of cost for 1 set
Labour:
Mate (Skilled) Day 0002 609.00 1.00 609.00
Blacksmith - 1st Class (Skilled) Day 0008 609.00 2.00 1,218.00
Helper (Semi-skilled) Day 0021 505.00 2.00 1,010.00
Waterman (Un-skilled) Day 0034 431.00 1.00 431.00
(i) Leading of special size PSC sleepers, switches, crossing, fitting, fastenings etc.
072013 1 in 16 Turnout
Details of cost for 1 set
Labour:
Mate (Skilled) Day 0002 609.00 1.00 609.00
Blacksmith - 1st Class (Skilled) Day 0008 609.00 2.00 1,218.00
Helper (Semi-skilled) Day 0021 505.00 2.00 1,010.00
Waterman (Un-skilled) Day 0034 431.00 1.00 431.00
(i) Leading of special size PSC sleepers, switches, crossing, fitting, fastenings etc.
Labour Unskilled Day 0020 431.00 16.00 6,896.00
(ii) Preparing stage for putting new PSC sleepers, Switches, Lead rails, crossings etc.
072014 1 in 20 Turnout
Details of cost for 1 set
Labour:
Mate (Skilled) Day 0002 609.00 1.00 609.00
Blacksmith - 1st Class (Skilled) Day 0008 609.00 2.00 1,218.00
Helper (Semi-skilled) Day 0021 505.00 2.00 1,010.00
Waterman (Un-skilled) Day 0034 431.00 1.00 431.00
(i) Leading of special size PSC sleepers, switches, crossing, fitting, fastenings etc.
072020 Assembling all types of Switches with 52Kg / 60Kg rails on PSC sleepers on
temporary staging, with railway's sleepers, rails etc. at indicated location as per
standard drawing duly leading sleepers, rails, switches, fastenings etc. with lead and
lift including cutting, drilling, fixing of all components, fittings etc. with housing of
tongue rails as per requirement of signaling etc. etc. complete as directed by engineer
in-charge.
Note:
Required P.way fittings shall be supplied at SSE/P.Way stores.
072021 1 in 8½ Turnouts
Details of cost for 1 set
Material:
Drill twist made of high speed steel for size 26.5mm dia of Addison / I T make Each 0466 2852.30 0.50 1,426.15
High Speed Hacksaw Blade of size 300mm x 12.5mm x 0.63mm (18TPI) as per as per Nos. 0457 160.00 0.50 80.00
RDSO's Spec. no. TM/SM/26 (latest Rev.)
Normal unleaded Petrol Litre 0182 105.00 0.50 52.50
Kerosene Oil Litre 0185 56.00 3.00 168.00
Labour:
(i)preparation of staging,leading rails,sleepers and fittings and assembling of switch
including rail cuting and hole drilling
Mate (Skilled) Day 0002 609.00 0.50 304.50
Waterman (Un-skilled) Day 0034 431.00 1.00 431.00
Blacksmith - 1st Class (Skilled) Day 0008 609.00 1.00 609.00
Helper (Semi-skilled) Day 0021 505.00 1.00 505.00
Labour Unskilled Day 0020 431.00 18.00 7,758.00
Misc.:
T & P (Crow bar, Spanner, Hammer, Rail tounge, Pan iron mortar etc.) Lumpsum 9901 1.00 76.00 76.00
Hire charges of Rail Drill Machine Day 0137 300.00 0.50 150.00
Hire charges of Rail Cutting Machine Day 0142 300.00 0.50 150.00
11,710.15
Add for Water Charges @ 1% Lumpsum 9902 0.01 117.10
11,827.25
Add for GST @ 12% (multiplying factor 0.1405) Lumpsum 9903 0.14 1,661.73
13,488.98
Add for Contractor’s Overheads and Profit @ 15% Lumpsum 9904 0.15 2,023.35
15,512.33
Add for Cess @ 1% Lumpsum 9905 0.01 155.12
Cost for 1 set 15,667.45
Rate per set Set 15,667.45
072022 1 in 12 Turnouts
Details of cost for 1 set
Material:
Drill twist made of high speed steel for size 26.5mm dia of Addison / I T make Each 0466 2852.30 0.50 1,426.15
High Speed Hacksaw Blade of size 300mm x 12.5mm x 0.63mm (18TPI) as per as per Nos. 0457 160.00 0.50 80.00
RDSO's Spec. no. TM/SM/26 (latest Rev.)
Normal unleaded Petrol Litre 0182 105.00 0.50 52.50
Kerosene Oil Litre 0185 56.00 3.00 168.00
Draft IR Unified Stadard Analysis of Rates - 2021 Chapter - 7: Turnouts and Renewals
072023 1 in 16 Turnouts
Details of cost for 1 set
Material:
Drill twist made of high speed steel for size 26.5mm dia of Addison / I T make Each 0466 2852.30 0.50 1,426.15
High Speed Hacksaw Blade of size 300mm x 12.5mm x 0.63mm (18TPI) as per as per Nos. 0457 160.00 0.50 80.00
RDSO's Spec. no. TM/SM/26 (latest Rev.)
Normal unleaded Petrol Litre 0182 105.00 0.50 52.50
Kerosene Oil Litre 0185 56.00 3.00 168.00
Labour:
(i)preparation of staging,leading rails,sleepers and fittings and assembling of switch
including rail cuting and hole drilling
Mate (Skilled) Day 0002 609.00 1.00 609.00
Waterman (Un-skilled) Day 0034 431.00 1.00 431.00
Blacksmith - 1st Class (Skilled) Day 0008 609.00 1.00 609.00
Helper (Semi-skilled) Day 0021 505.00 1.00 505.00
Labour Unskilled Day 0020 431.00 24.00 10,344.00
Misc.:
T & P (Crow bar, Spanner, Hammer, Rail tounge, Pan iron mortar etc.) Lumpsum 9901 1.00 96.00 96.00
Hire charges of Rail Drill Machine Day 0137 300.00 0.50 150.00
Hire charges of Rail Cutting Machine Day 0142 300.00 0.50 150.00
14,620.65
Add for Water Charges @ 1% Lumpsum 9902 0.01 146.21
14,766.86
Add for GST @ 12% (multiplying factor 0.1405) Lumpsum 9903 0.14 2,074.74
16,841.60
Add for Contractor’s Overheads and Profit @ 15% Lumpsum 9904 0.15 2,526.24
19,367.84
Add for Cess @ 1% Lumpsum 9905 0.01 193.68
Rate per set Set 19,561.52
072024 1 in 20 Turnouts
Details of cost for 1 set
Material:
Drill twist made of high speed steel for size 26.5mm dia of Addison / I T make Each 0466 2852.30 0.50 1,426.15
High Speed Hacksaw Blade of size 300mm x 12.5mm x 0.63mm (18TPI) as per as per Nos. 0457 160.00 0.50 80.00
RDSO's Spec. no. TM/SM/26 (latest Rev.)
Normal unleaded Petrol Litre 0182 105.00 0.50 52.50
Kerosene Oil Litre 0185 56.00 3.00 168.00
Draft IR Unified Stadard Analysis of Rates - 2021 Chapter - 7: Turnouts and Renewals
072031 1 in 8½ Turnouts
Details of cost for 1 set
Material:
Drill twist made of high speed steel for size 26.5mm dia of Addison / I T make Each 0466 2852.30 1.00 2,852.30
High Speed Hacksaw Blade of size 300mm x 12.5mm x 0.63mm (18TPI) as per as per Nos. 0457 160.00 1.00 160.00
RDSO's Spec. no. TM/SM/26 (latest Rev.)
Normal unleaded Petrol Litre 0182 105.00 1.00 105.00
Kerosene Oil Litre 0185 56.00 5.00 280.00
Labour:
Mate (Skilled) Day 0002 609.00 2.00 1,218.00
Blacksmith - 1st Class (Skilled) Day 0008 609.00 2.00 1,218.00
Helper (Semi-skilled) Day 0021 505.00 2.00 1,010.00
Look Out Man (Un-skilled) Day 0033 431.00 1.00 431.00
Waterman (Un-skilled) Day 0034 431.00 1.00 431.00
(i) Leading of sleepers,switches,rails,crossings and fittings
Labour Unskilled Day 0020 431.00 16.00 6,896.00
(ii) Preparing stage for assembling turnout
Labour Unskilled Day 0020 431.00 6.00 2,586.00
(iii) Linking of switch,lead and crossing portion on stage
Labour Unskilled Day 0020 431.00 16.00 6,896.00
(iv) Filling of ballast in crib and shoulder portion
Labour Unskilled Day 0020 431.00 4.00 1,724.00
(v) Insertion of assembled Turnout
Labour Unskilled Day 0020 431.00 12.00 5,172.00
(vi) Linking of Track and initial packing
Labour Unskilled Day 0020 431.00 8.00 3,448.00
Misc.:
T & P (Crow bar, Spanner, Hammer, Rail tounge, Pan iron mortar etc.) Lumpsum 9901 1.00 200.00 200.00
Hire charges for tractor with trolley Day 0081 1200.00 1.00 1,200.00
Hire charges of Rail Drill Machine Day 0137 300.00 0.50 150.00
Hire charges of Rail Cutting Machine Day 0142 300.00 0.50 150.00
36,127.30
Add for working under traffic block @ 5% Lumpsum 9991 0.05 1,806.37
37,933.67
Add for Water Charges @ 1% Lumpsum 9902 0.01 379.34
38,313.00
Add for GST @ 12% (multiplying factor 0.1405) Lumpsum 9903 0.14 5,382.98
43,695.98
Add for Contractor’s Overheads and Profit @ 15% Lumpsum 9904 0.15 6,554.40
50,250.38
Add for Cess @ 1% Lumpsum 9905 0.01 502.50
Rate per set Set 50,752.88
072032 1 in 12 Turnouts
Details of cost for 1 set
Material:
Drill twist made of high speed steel for size 26.5mm dia of Addison / I T make Each 0466 2852.30 1.00 2,852.30
Draft IR Unified Stadard Analysis of Rates - 2021 Chapter - 7: Turnouts and Renewals
072033 1 in 16 Turnouts
Details of cost for 1 set
Material:
Drill twist made of high speed steel for size 26.5mm dia of Addison / I T make Each 0466 2852.30 1.25 3,565.38
High Speed Hacksaw Blade of size 300mm x 12.5mm x 0.63mm (18TPI) as per as per Nos. 0457 160.00 1.50 240.00
RDSO's Spec. no. TM/SM/26 (latest Rev.)
Normal unleaded Petrol Litre 0182 105.00 1.50 157.50
Kerosene Oil Litre 0185 56.00 6.00 336.00
Labour:
Mate (Skilled) Day 0002 609.00 2.00 1,218.00
Blacksmith - 1st Class (Skilled) Day 0008 609.00 2.00 1,218.00
Helper (Semi-skilled) Day 0021 505.00 2.00 1,010.00
Look Out Man (Un-skilled) Day 0033 431.00 1.00 431.00
Waterman (Un-skilled) Day 0034 431.00 1.00 431.00
(i) Leading of sleepers,switches,rails,crossings and fittings
Labour Unskilled Day 0020 431.00 20.00 8,620.00
(ii) Preparing stage for assembling turnout
Labour Unskilled Day 0020 431.00 10.00 4,310.00
(iii) Linking of switch,lead and crossing portion on stage
Labour Unskilled Day 0020 431.00 21.00 9,051.00
Draft IR Unified Stadard Analysis of Rates - 2021 Chapter - 7: Turnouts and Renewals
072034 1 in 20 Turnouts
Details of cost for 1 set
Material:
Drill twist made of high speed steel for size 26.5mm dia of Addison / I T make Each 0466 2852.30 1.50 4,278.45
High Speed Hacksaw Blade of size 300mm x 12.5mm x 0.63mm (18TPI) as per as per Nos. 0457 160.00 2.00 320.00
RDSO's Spec. no. TM/SM/26 (latest Rev.)
Normal unleaded Petrol Litre 0182 105.00 1.75 183.75
Kerosene Oil Litre 0185 56.00 6.50 364.00
Labour:
Mate (Skilled) Day 0002 609.00 2.00 1,218.00
Blacksmith - 1st Class (Skilled) Day 0008 609.00 2.00 1,218.00
Helper (Semi-skilled) Day 0021 505.00 2.00 1,010.00
Look Out Man (Un-skilled) Day 0033 431.00 1.00 431.00
Waterman (Un-skilled) Day 0034 431.00 1.00 431.00
(i) Leading of sleepers,switches,rails,crossings and fittings
Labour Unskilled Day 0020 431.00 21.00 9,051.00
(ii) Preparing stage for assembling turnout
Labour Unskilled Day 0020 431.00 13.00 5,603.00
(iii) Linking of switch,lead and crossing portion on stage
Labour Unskilled Day 0020 431.00 24.00 10,344.00
(iv) Filling of ballast in crib and shoulder portion
Labour Unskilled Day 0020 431.00 7.00 3,017.00
(v) Insertion of assembled Turnout
Labour Unskilled Day 0020 431.00 15.00 6,465.00
(vi) Linking of Track and initial packing
Labour Unskilled Day 0020 431.00 14.00 6,034.00
Misc.:
T & P (Crow bar, Spanner, Hammer, Rail tounge, Pan iron mortar etc.) Lumpsum 9901 1.00 275.00 275.00
Hire charges for tractor with trolley Day 0081 1200.00 1.00 1,200.00
Hire charges of Rail Drill Machine Day 0137 300.00 0.50 150.00
Hire charges of Rail Cutting Machine Day 0142 300.00 0.50 150.00
51,743.20
Add for working under traffic block @ 5% Lumpsum 9991 0.05 2,587.16
54,330.36
Add for Water Charges @ 1% Lumpsum 9902 0.01 543.30
54,873.66
Draft IR Unified Stadard Analysis of Rates - 2021 Chapter - 7: Turnouts and Renewals
072040 Laying and linking of turnouts of all types including diamond crossings & Derailing
switches with 52Kg / 60Kg rail section on PSC sleepers on prepared ballast bed for
New lines or during total closure of section at indicated location as per standard
drawing, duly leading sleepers, rails, switches, crossings, fastenings including rail
cutting, drilling, fixing of all components, fittings with housing of tongue rails as per
requirement of signalin, preparing ballast bed, filling and spreading of ballast as
required, linking of turnout with track, attending track parameters including lifting,
providing one round of packing to make track fit for 20 kmph speed complete as
directed by engineer in-charge.
072041 1 in 8½ Turnouts
Details of cost for 1 set
Material:
Drill twist made of high speed steel for size 26.5mm dia of Addison / I T make Each 0466 2852.30 1.00 2,852.30
High Speed Hacksaw Blade of size 300mm x 12.5mm x 0.63mm (18TPI) as per as per Nos. 0457 160.00 1.00 160.00
RDSO's Spec. no. TM/SM/26 (latest Rev.)
Normal unleaded Petrol Litre 0182 105.00 1.00 105.00
Kerosene Oil Litre 0185 56.00 5.00 280.00
Labour:
Mate (Skilled) Day 0002 609.00 2.00 1,218.00
Blacksmith - 1st Class (Skilled) Day 0008 609.00 2.00 1,218.00
Helper (Semi-skilled) Day 0021 505.00 2.00 1,010.00
Waterman (Un-skilled) Day 0034 431.00 1.00 431.00
(i) Leading of sleepers,switches,rails,crossings and fittings
Labour Unskilled Day 0020 431.00 16.00 6,896.00
(ii) Linking of switch, lead and crossing portion on stage
Labour Unskilled Day 0020 431.00 16.00 6,896.00
Draft IR Unified Stadard Analysis of Rates - 2021 Chapter - 7: Turnouts and Renewals
072042 1 in 12 Turnouts
Details of cost for 1 set
Material:
Drill twist made of high speed steel for size 26.5mm dia of Addison / I T make Each 0466 2852.30 1.00 2,852.30
High Speed Hacksaw Blade of size 300mm x 12.5mm x 0.63mm (18TPI) as per as per Nos. 0457 160.00 1.00 160.00
RDSO's Spec. no. TM/SM/26 (latest Rev.)
Normal unleaded Petrol Litre 0182 105.00 1.25 131.25
Kerosene Oil Litre 0185 56.00 5.50 308.00
Labour:
Mate (Skilled) Day 0002 609.00 2.00 1,218.00
Blacksmith - 1st Class (Skilled) Day 0008 609.00 2.00 1,218.00
Helper (Semi-skilled) Day 0021 505.00 2.00 1,010.00
Waterman (Un-skilled) Day 0034 431.00 1.00 431.00
(i) Leading of sleepers,switches,rails,crossings and fittings
Labour Unskilled Day 0020 431.00 18.00 7,758.00
(ii) Linking of switch,lead and crossing portion on stage
Labour Unskilled Day 0020 431.00 20.00 8,620.00
(iii) Filling ballast in crib and shoulder for initial packing
Labour Unskilled Day 0020 431.00 6.00 2,586.00
(iv) Linking of Track and initial packing
Labour Unskilled Day 0020 431.00 11.00 4,741.00
Misc.:
T & P (Crow bar, Spanner, Hammer, Rail tounge, Pan iron mortar etc.) Lumpsum 9901 1.00 250.00 250.00
Hire charges for tractor with trolley Day 0081 1200.00 1.00 1,200.00
Hire charges of Rail Drill Machine Day 0137 300.00 0.50 150.00
Hire charges of Rail Cutting Machine Day 0142 300.00 0.50 150.00
32,783.55
Add for Water Charges @ 1% Lumpsum 9902 0.01 327.84
33,111.39
Add for GST @ 12% (multiplying factor 0.1405) Lumpsum 9903 0.14 4,652.15
37,763.54
Add for Contractor’s Overheads and Profit @ 15% Lumpsum 9904 0.15 5,664.53
43,428.07
Add for Cess @ 1% Lumpsum 9905 0.01 434.28
Rate per set Set 43,862.35
072043 1 in 16 Turnouts
Details of cost for 1 set
Material:
Drill twist made of high speed steel for size 26.5mm dia of Addison / I T make Each 0466 2852.30 1.25 3,565.38
Draft IR Unified Stadard Analysis of Rates - 2021 Chapter - 7: Turnouts and Renewals
072044 1 in 20 Turnouts
Details of cost for 1 set
Material:
Drill twist made of high speed steel for size 26.5mm dia of Addison / I T make Each 0466 2852.30 1.50 4,278.45
High Speed Hacksaw Blade of size 300mm x 12.5mm x 0.63mm (18TPI) as per as per Nos. 0457 160.00 2.00 320.00
RDSO's Spec. no. TM/SM/26 (latest Rev.)
Normal unleaded Petrol Litre 0182 105.00 1.75 183.75
Kerosene Oil Litre 0185 56.00 6.50 364.00
Labour:
Mate (Skilled) Day 0002 609.00 2.00 1,218.00
Blacksmith - 1st Class (Skilled) Day 0008 609.00 2.00 1,218.00
Helper (Semi-skilled) Day 0021 505.00 2.00 1,010.00
Waterman (Un-skilled) Day 0034 431.00 1.00 431.00
(i) Leading of sleepers,switches,rails,crossings and fittings
Labour Unskilled Day 0020 431.00 21.00 9,051.00
(ii) Linking of switch,lead and crossing portion on stage
Labour Unskilled Day 0020 431.00 24.00 10,344.00
(iii) Filling ballast in crib and shoulder for initial packing
Labour Unskilled Day 0020 431.00 7.00 3,017.00
(iv) Linking of Track and initial packing
Labour Unskilled Day 0020 431.00 14.00 6,034.00
Misc.:
T & P (Crow bar, Spanner, Hammer, Rail tounge, Pan iron mortar etc.) Lumpsum 9901 1.00 275.00 275.00
Hire charges for tractor with trolley Day 0081 1200.00 1.00 1,200.00
Hire charges of Rail Drill Machine Day 0137 300.00 0.50 150.00
Hire charges of Rail Cutting Machine Day 0142 300.00 0.50 150.00
39,244.20
Draft IR Unified Stadard Analysis of Rates - 2021 Chapter - 7: Turnouts and Renewals
072050 Laying and linking of turnouts of all types including diamond crossings & Derailing
switches with 52Kg / 60Kg rail section on PSC sleepers on ballast bed prepared after
dismantling & removal of existing turnout/normal line during TTR/yard remodelling
under traffic block, as per standard drawing, duly leading sleepers, rails, switches,
crossings, fastenings including rail cutting, drilling, fixing of all components, fittings
with housing of tongue rails as per requirement of signalin, preparing ballast bed, filling
and spreading of ballast as required, linking of turnout with track, attending track
parameters including lifting, providing one round of packing to make track fit for 20
kmph speed complete as directed by engineer in-charge.
Note: Removal of existing turnout/normal line, lavelling ballast bed for laying
transportation of released material and stacking shall be paid extra under relevant
sum.
072051 1 in 8½ Turnouts
Considering 10% additional for working under block over similar items where there is
no need of traffic block
Rate per set Set 072041 37781.08 1.10 41,559.19
072052 1 in 12 Turnouts
Considering 10% additional for working under block over similar items where there is
no need of traffic block
Rate per set Set 072042 43862.35 1.10 48,248.58
072053 1 in 16 Turnouts
Considering 10% additional for working under block over similar items where there is
no need of traffic block
Rate per set Set 072043 47912.72 1.10 52,703.99
072054 1 in 20 Turnouts
Considering 10% additional for working under block over similar items where there is
no need of traffic block
Rate per set Set 072044 52506.29 1.10 57,756.92
072061 1 in 8½ Turnouts
Details of cost for 1 set
Material:
Drill twist made of high speed steel for size 18mm dia of Addison / I T make Each 0467 1866.40 0.50 933.20
High Speed Hacksaw Blade of size 300mm x 12.5mm x 0.63mm (18TPI) as per as per Nos. 0457 160.00 0.50 80.00
RDSO's Spec. no. TM/SM/26 (latest Rev.)
Normal unleaded Petrol Litre 0182 105.00 0.50 52.50
Kerosene Oil Litre 0185 56.00 3.00 168.00
Labour:
i) Leading switches, sleepers etc., assembling switches on temporary staging,
removing ballast muck upto required level, and
Labour Unskilled Day 0020 431.00 6.00 2,586.00
ii) Fixing, inserting of switch, filling ballast, levelling & packing
Mate (Skilled) Day 0002 609.00 1.00 609.00
Waterman (Un-skilled) Day 0034 431.00 1.00 431.00
Blacksmith - 1st Class (Skilled) Day 0008 609.00 1.00 609.00
Helper (Semi-skilled) Day 0021 505.00 1.00 505.00
Look Out Man (Un-skilled) Day 0033 431.00 1.00 431.00
Labour Unskilled Day 0020 431.00 10.00 4,310.00
Misc.:
T & P (Crow bar, Spanner, Hammer, Rail tounge, Pan iron mortar etc.) Lumpsum 9901 1.00 76.00 76.00
Hire charges of Rail Drill Machine Day 0137 300.00 0.50 150.00
Hire charges of Rail Cutting Machine Day 0142 300.00 0.50 150.00
11,090.70
Add for working under traffic block @ 5% Lumpsum 9991 0.05 554.54
11,645.24
Add for Water Charges @ 1% Lumpsum 9902 0.01 116.45
11,761.69
Add for GST @ 12% (multiplying factor 0.1405) Lumpsum 9903 0.14 1,652.52
13,414.20
Add for Contractor’s Overheads and Profit @ 15% Lumpsum 9904 0.15 2,012.13
15,426.34
Add for Cess @ 1% Lumpsum 9905 0.01 154.26
Rate per set Set 15,580.60
072062 1 in 12 Turnouts
Details of cost for 1 set
Material:
Drill twist made of high speed steel for size 18mm dia of Addison / I T make Each 0467 1866.40 0.50 933.20
High Speed Hacksaw Blade of size 300mm x 12.5mm x 0.63mm (18TPI) as per as per Nos. 0457 160.00 0.50 80.00
RDSO's Spec. no. TM/SM/26 (latest Rev.)
Normal unleaded Petrol Litre 0182 105.00 0.50 52.50
Kerosene Oil Litre 0185 56.00 3.00 168.00
Draft IR Unified Stadard Analysis of Rates - 2021 Chapter - 7: Turnouts and Renewals
072063 1 in 16 Turnouts
Details of cost for 1 set
Material:
Drill twist made of high speed steel for size 18mm dia of Addison / I T make Each 0467 1866.40 0.50 933.20
High Speed Hacksaw Blade of size 300mm x 12.5mm x 0.63mm (18TPI) as per as per Nos. 0457 160.00 0.50 80.00
RDSO's Spec. no. TM/SM/26 (latest Rev.)
Normal unleaded Petrol Litre 0182 105.00 0.50 52.50
Kerosene Oil Litre 0185 56.00 3.00 168.00
Labour:
i) Assembling switch,removing ballast muck upto required level ,and leading switches
and sleepers etc
Labour Unskilled Day 0020 431.00 14.00 6,034.00
(ii) Fixing, laying of switch, filling ballast, levelling & packing
Mate (Skilled) Day 0002 609.00 1.00 609.00
Waterman (Un-skilled) Day 0034 431.00 1.00 431.00
Blacksmith - 1st Class (Skilled) Day 0008 609.00 1.00 609.00
Helper (Semi-skilled) Day 0021 505.00 1.00 505.00
Look Out Man (Un-skilled) Day 0033 431.00 1.00 431.00
Labour Unskilled Day 0020 431.00 14.00 6,034.00
Misc.:
T & P (Crow bar, Spanner, Hammer, Rail tounge, Pan iron mortar etc.) Lumpsum 9901 1.00 96.00 96.00
Hire charges of Rail Drill Machine Day 0137 300.00 0.50 150.00
Hire charges of Rail Cutting Machine Day 0142 300.00 0.50 150.00
16,282.70
Add for working under traffic block @ 5% Lumpsum 9991 0.05 814.14
17,096.84
Add for Water Charges @ 1% Lumpsum 9902 0.01 170.97
17,267.80
Add for GST @ 12% (multiplying factor 0.1405) Lumpsum 9903 0.14 2,426.13
19,693.93
Add for Contractor’s Overheads and Profit @ 15% Lumpsum 9904 0.15 2,954.09
22,648.02
Draft IR Unified Stadard Analysis of Rates - 2021 Chapter - 7: Turnouts and Renewals
072064 1 in 20 Turnouts
Details of cost for 1 set
Material:
Drill twist made of high speed steel for size 26.5mm dia of Addison / I T make Each 0466 2852.30 0.50 1,426.15
High Speed Hacksaw Blade of size 300mm x 12.5mm x 0.63mm (18TPI) as per as per Nos. 0457 160.00 0.50 80.00
RDSO's Spec. no. TM/SM/26 (latest Rev.)
Normal unleaded Petrol Litre 0182 105.00 0.50 52.50
Kerosene Oil Litre 0185 56.00 3.00 168.00
Labour:
i) Assembling switch,removing ballast muck upto required level ,and leading switches
and sleepers etc
Labour Unskilled Day 0020 431.00 15.00 6,465.00
(ii) Fixing, laying of switch, filling ballast, levelling & packing
Mate (Skilled) Day 0002 609.00 1.00 609.00
Waterman (Un-skilled) Day 0034 431.00 1.00 431.00
Blacksmith - 1st Class (Skilled) Day 0008 609.00 1.00 609.00
Helper (Semi-skilled) Day 0021 505.00 1.00 505.00
Look Out Man (Un-skilled) Day 0033 431.00 1.00 431.00
Labour Unskilled Day 0020 431.00 15.00 6,465.00
Misc.:
T & P (Crow bar, Spanner, Hammer, Rail tounge, Pan iron mortar etc.) Lumpsum 9901 1.00 104.00 104.00
Hire charges of Rail Drill Machine Day 0137 300.00 0.50 150.00
Hire charges of Rail Cutting Machine Day 0142 300.00 0.50 150.00
17,645.65
Add for working under traffic block @ 5% Lumpsum 9991 0.05 882.28
18,527.93
Add for Water Charges @ 1% Lumpsum 9902 0.01 185.28
18,713.21
Add for GST @ 12% (multiplying factor 0.1405) Lumpsum 9903 0.14 2,629.21
21,342.42
Add for Contractor’s Overheads and Profit @ 15% Lumpsum 9904 0.15 3,201.36
24,543.78
Add for Cess @ 1% Lumpsum 9905 0.01 245.44
Rate per set Set 24,789.22
073017 Extra over item nos. 073011 to 073015 for additional lift beyond 75mm for every Each 0.15
50mm or part thereof upto 225mm for each set
073020 Lifting the newly inserted BG 60 Kg. / 52 Kg. turnouts/ trap switches to required level
to provide a ballast cushion upto 225mm from existing level with Railway's stone
ballast in convenient stages including one round of through packing after completion of
final stage of lift, levelling, aligning, gauging and boxing etc., with contractor's labour,
tools, with all lead and lifts etc., complete and as directed by the Engineer-in-charge.
Note:
1. The item shall be used only when UNIMAT is not available for the work before the
turnout is opened for operation.
2. Leading and dumping of ballast will be paid separately under relevant item.
Labour:
Mate (Skilled) Day 0002 609.00 1.00 609.00
Waterman (Un-skilled) Day 0034 431.00 1.00 431.00
Look Out Man (Un-skilled) Day 0033 431.00 1.00 431.00
(i) For replacement of sleeper including fixing fastenings,packing,dressing etc.
Labour:
Mate (Skilled) Day 0002 609.00 1.00 609.00
Waterman (Un-skilled) Day 0034 431.00 1.00 431.00
Look Out Man (Un-skilled) Day 0033 431.00 1.00 431.00
(i) For replacement of sleeper including fixing fastenings,packing,dressing etc.
Labour:
Mate (Skilled) Day 0002 609.00 1.00 609.00
Waterman (Un-skilled) Day 0034 431.00 1.00 431.00
Look Out Man (Un-skilled) Day 0033 431.00 1.00 431.00
(i) For replacement of sleeper including fixing fastenings,packing,dressing etc.
074021 1 in 8½ Turnout
Details of cost for 2 sets
Labour:
Leading of CMS Crossing, opening of fittings, renewal of X-ing, fittings, packing etc.
074022 1 in 12 Turnout
Details of cost for 2 sets
Labour:
Leading of CMS Crossing, opening of fittings, renewal of X-ing, fittings, packing etc.
074023 1 in 16 Turnout
Details of cost for 2 sets
Draft IR Unified Stadard Analysis of Rates - 2021 Chapter - 7: Turnouts and Renewals
074024 1 in 20 Turnout
Details of cost for 2 sets
Labour:
Leading of CMS Crossing, opening of fittings, renewal of X-ing, fittings, packing etc.
074030 Renewal of Switch Rails (Tongue rails & Stock rails) and its fittings of all rail sections
complete with fittings, under line block conditions ensuring proper housing & changing
of stretcher bars and fittings as required,Work also includes drilling of hole if any,
required and fixing of fish plates with leading of rails.Released switch rails shall be
stacked at indicated place in a countable manner within the lead of 250m & all lift,
clear of infringements, crossing of track, if any complete, as directed. with contractor's
vehicles, consumables, stores, labour etc. complete, as directed by engineer in-
charge.
Note:
1).One set means Two Tongue rails and Two Stock rails
(2) In case when only one tongue & stock rail are replaced, only 50% of the quantity
shall be payable.
(3) If only one tongue rail is replaced, only 25% of the quantity of switch assembly
shall be payable for respective item.
Draft IR Unified Stadard Analysis of Rates - 2021 Chapter - 7: Turnouts and Renewals
074050 Through renewal of Liners and ERCs on PSC turnouts without damaging PSC
sleepers. Scope includes removal of all ERCs and Liners, cleaning rail seat, rail
flange at liner seats, and eye of Inserts with wire brushes and applying grease to eye
of insert and central leg of ERC with contractor's grease of Railway’s specification,
fixing all fitings in correct position and sealing liner edges with grease all complete
including collection and stacking of released materials at nominated locations within
SSE Jurisdiction as directed by Engineer-in-Charge.
Note: All the fittings will be supplied at SSE/Stores/Depot.
Draft IR Unified Stadard Analysis of Rates - 2021 Chapter - 7: Turnouts and Renewals
074052 1 in 12 Turnout
Details of cost for 3 set's ( In one set having 480 ERC's approximately ) 10 gram
grease required for 1 ERC, For 3 sets 3 X 480 X 10 = 15 Kg grease.
Material:
Grease Graphite Grade 'O' (IS:408) Kg 0184 240.00 15.00 3,600.00
Kerosene Oil Litre 0185 56.00 1.00 56.00
Cotton Jute Kg 0494 40.00 1.00 40.00
Wire Brush - 25cm long Each 0313 15.00 2.00 30.00
Sand Paper Nos. 0496 5.00 8.00 40.00
Soft Brush for painting - 25cm long Each 0314 33.00 2.00 66.00
Labour:
(i) For leading & distribution of materials & collection of released materials
Labour Unskilled Day 0020 431.00 2.00 862.00
(ii) For Fitting renewal & greasing of ERC's, liners & sealing liner edges.( one group of
four persons will renew 200 rail seats in a day )
Mate (Skilled) Day 0002 609.00 0.50 304.50
Waterman (Un-skilled) Day 0034 431.00 0.50 215.50
Look Out Man (Un-skilled) Day 0033 431.00 0.50 215.50
Labour Unskilled Day 0020 431.00 8.00 3,448.00
Misc.:
T & P ( Hammer, Crow bars, Tami bar, beater, Wire claws, etc.) Lumpsum 9901 1.00 40.00 40.00
LS for Transportation Charges Lumpsum 9901 1.00 175.00 175.00
9,092.50
Add for Water Charges @ 1% Lumpsum 9902 0.01 90.93
9,183.43
Add for GST @ 12% (multiplying factor 0.1405) Lumpsum 9903 0.14 1,290.27
10,473.70
Draft IR Unified Stadard Analysis of Rates - 2021 Chapter - 7: Turnouts and Renewals
074053 1 in 16 Turnout
Details of cost for 3 set's ( In one set having 580 ERC's approximately ) 10 gram
grease required for 1 ERC, For 3 sets 3 X 580 X 10 = 18 Kg grease.
Material:
Grease Graphite Grade 'O' (IS:408) Kg 0184 240.00 18.00 4,320.00
Kerosene Oil Litre 0185 56.00 1.00 56.00
Cotton Jute Kg 0494 40.00 1.00 40.00
Wire Brush - 25cm long Each 0313 15.00 2.00 30.00
Sand Paper Nos. 0496 5.00 8.00 40.00
Soft Brush for painting - 25cm long Each 0314 33.00 2.00 66.00
Labour:
(i) For leading & distribution of materials & collection of released materials
Labour Unskilled Day 0020 431.00 2.00 862.00
(ii) For Fitting renewal & greasing of ERC's, liners & sealing liner edges.( one group of
four persons will renew 200 rail seats in a day )
Mate (Skilled) Day 0002 609.00 0.50 304.50
Waterman (Un-skilled) Day 0034 431.00 0.50 215.50
Look Out Man (Un-skilled) Day 0033 431.00 0.50 215.50
Labour Unskilled Day 0020 431.00 8.00 3,448.00
Misc.:
T & P ( Hammer, Crow bars, Tami bar, beater, Wire claws, etc.) Lumpsum 9901 1.00 46.00 46.00
LS for Transportation Charges Lumpsum 9901 1.00 200.00 200.00
9,843.50
Add for Water Charges @ 1% Lumpsum 9902 0.01 98.44
9,941.94
Add for GST @ 12% (multiplying factor 0.1405) Lumpsum 9903 0.14 1,396.84
11,338.78
Add for Contractor’s Overheads and Profit @ 15% Lumpsum 9904 0.15 1,700.82
13,039.59
Add for Cess @ 1% Lumpsum 9905 0.01 130.40
Cost for 3 set's 13,169.99
Rate per set Set 4,390.00
074054 1 in 20 Turnout
Details of cost for 3 set's ( In one set having 660 ERC's approximately ) 10 gram
grease required for 1 ERC, For 3 sets 3 X 660 X 10 = 20 Kg grease.
Material:
Grease Graphite Grade 'O' (IS:408) Kg 0184 240.00 20.00 4,800.00
Kerosene Oil Litre 0185 56.00 1.00 56.00
Cotton Jute Kg 0494 40.00 1.00 40.00
Wire Brush - 25cm long Each 0313 15.00 2.00 30.00
Sand Paper Nos. 0496 5.00 8.00 40.00
Soft Brush for painting - 25cm long Each 0314 33.00 2.00 66.00
Labour:
(i) For leading & distribution of materials & collection of released materials
Labour Unskilled Day 0020 431.00 2.00 862.00
(ii) For Fitting renewal & greasing of ERC's, liners & sealing liner edges.( one group of
four persons will renew 200 rail seats in a day )
Mate (Skilled) Day 0002 609.00 2.00 1,218.00
Waterman (Un-skilled) Day 0034 431.00 0.50 215.50
Look Out Man (Un-skilled) Day 0033 431.00 0.50 215.50
Labour Unskilled Day 0020 431.00 10.00 4,310.00
Misc.:
T & P ( Hammer, Crow bars, Tami bar, beater, Wire claws, etc.) Lumpsum 9901 1.00 52.00 52.00
Draft IR Unified Stadard Analysis of Rates - 2021 Chapter - 7: Turnouts and Renewals
074060 Through fitting renewal (TFR) with new Grooved Rubber Sole pads(GRSP), Liners
and ERC or through renewal with new GRSPs using existing ERCs and liners after
cleaning and greasing on entire Turnout of PSC Fan shaped layout including
approach & exit sleepers comprising of removing & refixing or replacement of plate
screws, ERCs and liners including seized ERCs, replacing the GRSP after cleaning
rail seat, refixing slide chairs, lubrication of ERCs, applying grease to plate screws
and Liner contact area with contractor's Grease Graphite Grade 'O' (IS:408) after
cleaning of rust/scale on liner contact area etc., as per provisions of IRPWM of latest
version with all contractor’s labour, tools, plants and stacking all the releaded materials
etc .complete and as directed by Engineer in charge.
Note: GRSP will be supplied at at SSE/stores/depot.
074070 Through renewal of Grooved Rubber Sole pads(GRSP) on Switch portion of PSC fan
shaped layout comprising of removing & refixing Plate screws,ERCs including seized
ERCs and liners, and replacing the GRSP after cleaning rail seat,refixing Slide chairs,
liner and ERC after greasing and lubrication of ERCs,applying grease to liners and
Liner contact area with contractor's Grease Graphite Grade 'O' (IS:408) after cleaning
of rust/scale on liner contact area and on ERC, with all contractor’s labour, tools,
plants, leading of GRSP and stacking all the releaed materials etc .complete and as
directed by Engineer in charge.
Note: GRSP will be supplied at at SSE/stores/depot.
074072 For 1 in 8.5 Turnouts & Derailng switches (Sleeper No 1 to 22 and 5 approach
sleepers)
Considering rate as 20% more less that for 1 in 12 turnout
Rate per set Set 074071 1507.28 0.80 1,205.82
074081 For 1 in 12 Lead portion (Sleeper Nos 26 to 64 & 74 to 83 and 8 approach sleepers) :
Details of cost for 3 set's
Material:
( In one set having 400 ERC's approximately ) 10 gram grease required for 1 ERC,
For 3 sets 3 X 40 X 10 = 12 Kg grease.
Grease Graphite Grade 'O' (IS:408) Kg 0184 240.00 12.00 2,880.00
Kerosene Oil Litre 0185 56.00 1.00 56.00
Cotton Jute Kg 0494 40.00 1.00 40.00
Wire Brush - 25cm long Each 0313 15.00 1.00 15.00
Sand Paper Nos. 0496 5.00 6.00 30.00
Soft Brush for painting - 25cm long Each 0314 33.00 1.00 33.00
Labour:
(i) For leading & distribution of materials & collection of released materials and renewal
of materials
Mate (Skilled) Day 0002 609.00 1.00 609.00
Waterman (Un-skilled) Day 0034 431.00 1.00 431.00
Look Out Man (Un-skilled) Day 0033 431.00 1.00 431.00
Labour Unskilled Day 0020 431.00 10.00 4,310.00
Misc.:
T & P ( Hammer, Crow bars, Tami bar, beater, Wire claws, etc.) Lumpsum 9901 1.00 30.00 30.00
8,865.00
Add for Water Charges @ 1% Lumpsum 9902 0.01 88.65
8,953.65
Add for GST @ 12% (multiplying factor 0.1405) Lumpsum 9903 0.14 1,257.99
10,211.64
Add for Contractor’s Overheads and Profit @ 15% Lumpsum 9904 0.15 1,531.75
11,743.38
Add for Cess @ 1% Lumpsum 9905 0.01 117.43
Cost for 3 sets 11,860.82
Cost for 1 set Set 3,953.61
Take 20% less of Relavaent item rate 074081 Set 074081 3953.61 0.80 3,162.88
Take 20% extra of Relavaent item rate 074081 Set 074081 3953.61 1.20 4,744.33
074090 Through renewal of Grooved Rubber Sole pads(GRSP) on Crossing portion of PSC
Sleeper turnout duly removing the Liners,ERCs including seized ERCs, and replacing
the GRSP after cleaning rail seat,refixing the liner and ERC after lubrication of ERCs,
liners and Liner contact area with contractor's Grease Graphite Grade 'O' (IS:408)
after cleaning of rust/scale on liner contact area etc., with all contractor’s labour, tools,
plants, transportation of GRSP, and stacking all the releaed materials etc. complete
and as directed by Engineer in charge.
Note: GRSP will be supplied at at SSE/stores/depot.
Take 20% less of Relavant item rate 074091 Set 074091 1122.84 0.80 898.27
Take 20% extra of Relavant item rate 074091 Set 074091 1122.84 1.20 1,347.41
074100 Renewal of corroded slide chairs duly removing the old slide chairs by heating using
contractors gas and equipments or any approved methods and inserting Railways new
slide chairs and plate screws including crossing of tracks, leading all required materials
to site, stacking all released materials, with all contractor's tools,consumables,labour,
lead, lift and incidental charges etc complete as directed by the Engineer in charge.
Note: All the fittings will be supplied at SSE/Stores/Depot.
074110 Fabrication, supply and fixing of hand operated lever boxes with pull rod of 33mm dia
to Drg.No. MA3040 including lead, lift, loading, unloading, tools and plants,
transportation, crossing of track wherever necessary as directed by Engineer-in-
charge at site.
Note:
1. Rate including Fabrication, Supply and Fixing of hand operated boxes.
2. Spring point lever (Self reversing type) as per drawing no. TMC-12 (Sheet 1,2,3).
074120 Fabrication, supply and fixing of MS lock pins/bolts for stock and tongue rails made out
of MS 40mm dia of length 200mm with head cutting, lathe machining, milling, drilling,
welding the rod with MS flat of 6mm thick of suitable size as required at site with MS
split pins/bolts and supplying of remaining ancillary materials required at for locking,
including all taxes, lead, lift, loading and un loading , tools and plants, transportation,
crossing of track whenever necessary etc., complete and as directed by Engineer-in-
charge at site.
Labour:
Mate (Skilled) Day 0002 609.00 0.50 304.50
Waterman (Un-skilled) Day 0034 431.00 0.50 215.50
(i) Pre marking of sleeper spacing as required
Painter (Skilled) Day 0012 609.00 0.25 152.25
(ii) Re spacing of sleepers with fixing fittings and packing
Labour Unskilled Day 0020 431.00 8.00 3,448.00
Misc.:
T & P and consumables Lumpsum 9901 1.00 30.00 30.00
4,150.25
Add for Water Charges @ 1% Lumpsum 9902 0.01 41.50
4,191.75
Add for GST @ 12% (multiplying factor 0.1405) Lumpsum 9903 0.14 588.94
4,780.69
Add for Contractor’s Overheads and Profit @ 15% Lumpsum 9904 0.15 717.10
5,497.80
Add for Cess @ 1% Lumpsum 9905 0.01 54.98
Cost for 48 Sleepers 5,552.78
Rate per sleeper Each 115.68
081020 Manual deep screening of Plain track/ turnouts as per procedure prescribed in
IRPWM, June 2020 or lates, on PSC sleepers of any density and throwing away
screened muck arising out of screening on toe of bank or on cess, if low or on spoil
banks above top of cutting (including throwing and leveling, if required beyond
minimum 5m from the edge of cutting which are upto 3m deep or alternatively carting
it upto 50m for disposing it off beyond cutting or platforms) as per direction of
Engineer in-charge, including cutting cess for effective drainage on both sides, one
round of kutcha packing with screened ballast and further attending to track
parameter to make track fit for 20 kmph speed complete in all respect.
Note : Payment shall be made for length along main line only for turnouts.
081030 Extra to item nos. from 081011 to 081018 and from 081021 to 081028 for disposal of
muck at a distance beyond 50m for every additional lead of 50 metres or part thereof
upto 500 metres for 1 TRM in station yard / cutting.
Details of cost for 250 Track Metre (Extra labour element required for additional
average lead of 250 metre for dispoal of muck)(@ one man per 25 TRM)
Labour:
Labour Unskilled Day 0020 431.00 10.00 4,310.00
Misc.:
T&P Lumpsum 9901 1.00 20.00 20.00
4,330.00
Add for Water Charges @ 1% Lumpsum 9902 0.01 43.30
4,373.30
Add for GST @ 12% (multiplying factor 0.1405) Lumpsum 9903 0.14 614.45
4,987.75
Add for Contractor’s Overheads and Profit @ 15% Lumpsum 9904 0.15 748.16
5,735.91
Add for Cess @ 1% Lumpsum 9905 0.01 57.36
Cost for 250 TRM / 250 metres lead 5,793.27
Cost for 250 TRM / every 50 metres lead 1,158.65
Rate per TRM for every 50 metres Each 4.63
081040 Extra to item nos. from 081011 to 081018 and from 081021 to 081028 for disposal of
muck for additional lift of 1 metre or part thereof beyond 3 metre lift in case of
disposal of muck from track for 1 TRM in station yard / cutting.
Details of cost for 200 Track Metre (Extra labour element required for additional
average lift of 3 metre for dispoal of muck)(@ one man per 20 TRM)
Labour:
Labour Unskilled Day 0020 431.00 10.00 4,310.00
Misc.:
T&P Lumpsum 9901 1.00 20.00 20.00
4,330.00
Add for Water Charges @ 1% Lumpsum 9902 0.01 43.30
Draft IR Unified Stadard Analysis of Rates - 2021 Chapter - 8: Deep Screening Ballast Related Activities
081050 Deep screening of turnout under line block within stipulated time by way of removing
the Points and Crossing assembly by using T-28 cranes, removing the entire stone
ballast bed by excavators up to shoulders to depth of 200/250/300 mm, limiting the
digging up to original formation level only, screening the removed ballast, putting back
the screened ballast on the formation in uniform layer, placing the points and crossing
assembly in designed position, dumping and spreading newly collected ballast in
cribs and shoulders, lifting of track as required so as to get a clean cushion of
300mm, shifting of sleepers to correct spacing including removal and re-fixing of
fittings wherever necessary, aligning of sleepers as per prescribed layout, initial
packing, aligning, dressing/ lowering the cess to deep screened depth up to the edge
of bank with a slope of 1 in 30, boxing of ballast to profile and making fit to run the
trains at a speed of non stop 20 KMPH as specified in IRPWM - June 2020 or latest
complete in all respect as directed by the Engineer - in - charge.
Note: Rail cutting and Rail hole drilling shall be paid under relevant items
082012 Extra over item no. 082011 for each additional average lead of 50m or part thereof
when total average lead exceeds 50m, but upto 250m.
Note: This item may be used only in exceptional circumstance under prior order on
record.
082013 Extra to item no. 082011 for each additional average lift of 1m or part thereof when
total average lift exceeds 5m.
Details of cost for 250 Track Metres for regrading by lifting and packing of track
(sleeper density of 1540 sleepers/km)
Material:
Enamel Paint as per RDSO's Spec. no.M&C/PCN/120-2011 Litre 0306 190.00 0.25 47.50
Labour:
Mate (Skilled) Day 0002 609.00 2.00 1,218.00
Look Out Man (Un-skilled) Day 0033 431.00 1.00 431.00
Waterman (Un-skilled) Day 0034 431.00 2.00 862.00
(i) Fixing & marking of rail level posts (Tie bar at every 30 m)
Painter (Skilled) Day 0012 609.00 0.10 60.90
Helper (Semi-skilled) Day 0021 505.00 0.10 50.50
Labour Unskilled Day 0020 431.00 0.50 215.50
(ii) Lifting of track upto 75 mm at a time including insertion of moorum/sand/stone
ballast Considering output of 12 sleepers per man (385 sleeper in 250 TRM)
083011 Extra for additional lift over 75mm for every 50mm lift or part thereof upto 275mm for
item nos. 083010 for each TRM.
Draft IR Unified Stadard Analysis of Rates - 2021 Chapter - 8: Deep Screening Ballast Related Activities
083020 Regrading the existing track by lowering upto required depth in stages, not exceeding
75mm in one stage including one round of through packing and making track fit for
30kmph speed at each stage of lowering as per procedure prescribed in latest edition
of IRPWM and subsequent picking up of sags / slacks and attending to misalignment
/ cross level defects during train operation, providing required ramp-in and ramp-out
for safe passage of trains, including cutting trenches across track at every 30m
interval to the required final formation level complete, and fixing, marking, painting
rail level posts, tiebars at every 30m interval as directed by engineer in-charge.
Details of cost for 250 Track Metres for regrading by lowering of track (sleeper density
of 1540 sleepers/km)
Material:
Enamel Paint as per RDSO's Spec. no.M&C/PCN/120-2011 Litre 0306 190.00 0.25 47.50
Labour:
Mate (Skilled) Day 0002 609.00 2.00 1,218.00
Look Out Man (Un-skilled) Day 0033 431.00 1.00 431.00
Waterman (Un-skilled) Day 0034 431.00 2.00 862.00
(i) Fixing & marking of rail level posts (Tie bar at every 30 m)
Painter (Skilled) Day 0012 609.00 0.10 60.90
Helper (Semi-skilled) Day 0021 505.00 0.10 50.50
Labour Unskilled Day 0020 431.00 0.50 215.50
(ii) Lowering of track upto 75 mm at a time including picking up slacks Considering
output of 7 sleepers per man (384 sleeper in 250 TRM)
Labour Unskilled Day 0020 431.00 55.00 23,705.00
(iii) For one round Through packing ( For Through packing 15 sleeper per man)
083030 Boxing of ballast as per procedure prescribed in latest edition of IRPWM including
cess dressing on both sides of track. The work will include removing excess ballast
from track and putting the same in crib and shoulder by leading to a maximum of 50m
including crossing of track, deweeding on ballast section etc and as directed by
Engineer-In charge.
Details of cost for 500Track Metre ( Considering output of 25 TRM per man on both
sides )
Labour:
Mate (Skilled) Day 0002 609.00 0.50 304.50
Waterman (Un-skilled) Day 0034 431.00 1.00 431.00
Labour Unskilled Day 0020 431.00 20.00 8,620.00
Misc.:
T & P ( Rake iron ballast, fork, beater, Phowrah, etc. ) Lumpsum 9901 1.00 40.00 40.00
9,395.50
Add for Water Charges @ 1% Lumpsum 9902 0.01 93.96
9,489.46
Add for GST @ 12% (multiplying factor 0.1405) Lumpsum 9903 0.14 1,333.27
10,822.72
Add for Contractor’s Overheads and Profit @ 15% Lumpsum 9904 0.15 1,623.41
12,446.13
Add for Cess @ 1% Lumpsum 9905 0.01 124.46
Cost for 500 Track Metre 12,570.59
Rate per TRM TRM 25.14
083040 Removing, screening and salvaging ballast from track, duly digging / scarifying ballast
by beaters / wire brushes, leveling and dressing formation with specified cross slope
after salvaging ballast, separating muck by screening the salvaged ballast with
contractor's 20mm size sieve, stacking of sieved ballast for measurement on or
outside the formation along track, disposing off muck at specified locations under non-
traffic conditions with all ascents, descents, as directed by Engineer in-charge.
Note: Payment shall be made for quantity of ballast stacked after screening of
retrieved ballst from track.
084020 Leading and loading Railway's Ballast collected at yard / depot / mid-section into
Railway's covered wagon, using any approved method with all ascents, descents,
taxes etc. with lead of 250m & all lifts complete, as per specifications and as directed
by Engineer in-charge.
084030 Leading and loading Railway's Sand collected at yard / depot into Railway's covered
wagon, using any approved method with all ascents, descents, taxes etc. with lead of
250m & all lifts complete, as per specifications and as directed by Engineer in-charge
Details of cost for 700 cum for 20 BCN (1 BCN covered wagon = 35 cum)
Labour:
Mate (Skilled) Day 0002 609.00 1.00 609.00
Blacksmith - 1st Class (Skilled) Day 0008 609.00 0.50 304.50
Helper (Semi-skilled) Day 0021 505.00 0.50 252.50
(i) For loading of Sand(Considering 6 persons all the time with JCB )
Labour Unskilled Day 0020 431.00 22.00 9,482.00
Machinery:
Hire Charges of JCB of 0.92 cum bucket Capacity Hour 0058 800.00 30.00 24,000.00
Misc.:
T&P Lumpsum 9901 1.00 122.00 122.00
34,770.00
Add for Water Charges @ 1% Lumpsum 9902 0.01 347.70
35,117.70
Add for GST @ 12% (multiplying factor 0.1405) Lumpsum 9903 0.14 4,934.04
40,051.74
Add for Contractor’s Overheads and Profit @ 15% Lumpsum 9904 0.15 6,007.76
46,059.50
Add for Cess @ 1% Lumpsum 9905 0.01 460.59
Draft IR Unified Stadard Analysis of Rates - 2021 Chapter - 8: Deep Screening Ballast Related Activities
084040 Unloading of ballast from Railway's Hopper Wagons and distributing the unloaded
ballast uniformly over the track, taking out jammed ballast and profiling and boxing.
084060 Unloading of sand / quarry dust during block from Railway's wagons other than
Hopper wagons by opening the doors of boxes and pulling & pushing down sand with
rake irons / phowrahs taking out jammed sand and distributing unloaded sand
uniformly over the track.
Draft IR Unified Stadard Analysis of Rates - 2021 Chapter - 8: Deep Screening Ballast Related Activities
085016 When distance of nearest quarry is more than 50 km and upto 100 km
Details of Ballast for 100Cum
Material:
Production cost of Track Ballast in quarry including loading in truck Cum 0212 569.00 100.00 56,900.00
Transportation:
Considering average distance of 75 km. Quantity = 100 x 75 = 7500 cum.Km
Rate as per Working Sheet " Tr. Ballast"
Cost of transportation for 100 Cum Cum/km 4.33 7500 32,465.02
Labour:
For stacking
Coolie (Un skilled) Day 0026 431.00 3.00 1,293.00
90,658.02
Add for Water Charges @ 1% Lumpsum 9902 0.01 906.58
91,564.60
Add for GST @ 12% (multiplying factor 0.1405) Lumpsum 9903 0.1405 12,864.83
104,429.43
Add for Contractor’s Overheads and Profit @ 15% Lumpsum 9904 0.15 15,664.41
120,093.85
Add for Cess @ 1% Lumpsum 9905 0.01 1,200.94
121,294.78
Cost for 100 Cum 121,294.78
Rate per Cum Cum 1,212.95
085017 When distance of nearest quarry is more than 100 km and upto 150 km
Details of Ballast for 100Cum
Material:
Production cost of Track Ballast in quarry including loading in truck Cum 0212 569.00 100.00 56,900.00
Transportation:
Considering average distance of 125 km. Quantity = 100 x 125 = 12500 cum.Km
Rate as per Working Sheet " Tr. Ballast"
Cost of transportation for 100 Cum Cum/km 4.14 12500 51,703.81
Labour:
For stacking
Coolie (Un skilled) Day 0026 431.00 3.00 1,293.00
109,896.81
Add for Water Charges @ 1% Lumpsum 9902 0.01 1,098.97
110,995.78
Add for GST @ 12% (multiplying factor 0.1405) Lumpsum 9903 0.1405 15,594.91
126,590.68
Draft IR Unified Stadard Analysis of Rates - 2021 Chapter - 8: Deep Screening Ballast Related Activities
085018 When distance of nearest quarry is more than 150 km and upto 200 km
Details of Ballast for 100Cum
Material:
Production cost of Track Ballast in quarry including loading in truck Cum 0212 569.00 100.00 56,900.00
Transportation:
Considering average distance of 175 km. Quantity = 100 x 175 = 17500 cum.Km
Rate as per Working Sheet " Tr. Ballast"
085019 When distance of nearest quarry is more than 200 km and upto 250 km
Details of Ballast for 100Cum
Material:
Production cost of Track Ballast in quarry including loading in truck Cum 0212 569.00 100.00 56,900.00
Transportation:
Considering average distance of 225 km. Quantity = 100 x 225 = 22500 cum.Km
Rate as per Working Sheet " Tr. Ballast"
Cost of transportation for 100 Cum Cum/km 4.09 22500 91,978.38
Labour:
For stacking
Coolie (Un skilled) Day 0026 431.00 3.00 1,293.00
150,171.38
Add for Water Charges @ 1% Lumpsum 9902 0.01 1,501.71
151,673.09
Add for GST @ 12% (multiplying factor 0.1405) Lumpsum 9903 0.1405 21,310.07
172,983.16
Add for Contractor’s Overheads and Profit @ 15% Lumpsum 9904 0.15 25,947.47
198,930.64
Add for Cess @ 1% Lumpsum 9905 0.01 1,989.31
200,919.95
Cost for 100 Cum 200,919.95
Rate per Cum Cum 2,009.20
Draft IR Unified Stadard Analysis of Rates - 2021 Chapter - 9: Welding Activities
Add for GST @ 12% (multiplying factor 0.1405) Lumpsum 9903 0.14 2,262.05
18,362.05
Add for Contractor’s Overheads and Profit @ 15% Lumpsum 9904 0.15 2,754.31
21,116.36
Add for Cess @ 1% Lumpsum 9905 0.01 211.16
Cost for 10 portion 21,327.52
Rate per portion Each 2,132.75
Add for GST @ 12% (multiplying factor 0.1405) Lumpsum 9903 0.14 2,211.47
17,951.47
Add for Contractor’s Overheads and Profit @ 15% Lumpsum 9904 0.15 2,692.72
20,644.19
Add for Cess @ 1% Lumpsum 9905 0.01 206.44
Cost for 10 portion 20,850.63
Rate per portion Each 2,085.06
Add for GST @ 12% (multiplying factor 0.1405) Lumpsum 9903 0.14 2,211.47
17,951.47
Add for Contractor’s Overheads and Profit @ 15% Lumpsum 9904 0.15 2,692.72
Draft IR Unified Stadard Analysis of Rates - 2021 Chapter - 9: Welding Activities
Anti-corrosive Bituminous Paint (Black) confirming to IS:9862 Litre 0304 80.00 0.25 20.00
Enamel Paint as per RDSO's Spec. no.M&C/PCN/120-2011 Litre 0306 190.00 0.10 19.00
Soft Brush for painting - 25cm long Each 0314 33.00 0.10 3.30
Labour:
Welder (Skilled) Day 0029 609.00 1.00 609.00
Chipper (Skilled) Day 0030 609.00 1.00 609.00
Luter (Skilled) Day 0031 609.00 1.00 609.00
Look Out Man (Un-skilled) Day 0033 431.00 1.00 431.00
Labour Unskilled Day 0020 431.00 5.00 2,155.00
Machinery:
Hire charges of Generator 5 KVA (without POL) Day 0072 500.00 0.20 100.00
Hire charges of Weld Trimmer Machine Day 0152 300.00 0.50 150.00
Hire charges of Rail Profile Weld Grinder Day 0151 100.00 0.20 20.00
Sundries Lumpsum 9901 1.00 10.00 10.00
13,800.30
Add for working under traffic block @ 10% Lumpsum 9992 0.10 1,380.03
15,180.33
Add for Water Charges @ 1% Lumpsum 9902 0.01 151.80
15,332.13
Add for GST @ 12% (multiplying factor 0.1405) Lumpsum 9903 0.14 2,154.16
17,486.30
Add for Contractor’s Overheads and Profit @ 15% Lumpsum 9904 0.15 2,622.94
20,109.24
Add for Cess @ 1% Lumpsum 9905 0.01 201.09
Cost of 5 joints 20,310.34
Rate per joint Each 4,062.07
Anti-corrosive Bituminous Paint (Black) confirming to IS:9862 Litre 0304 80.00 0.25 20.00
Enamel Paint as per RDSO's Spec. no.M&C/PCN/120-2011 Litre 0306 190.00 0.10 19.00
Soft Brush for painting - 25cm long Each 0314 33.00 0.10 3.30
Labour:
Welder (Skilled) Day 0029 609.00 1.00 609.00
Chipper (Skilled) Day 0030 609.00 1.00 609.00
Luter (Skilled) Day 0031 609.00 1.00 609.00
Look Out Man (Un-skilled) Day 0033 431.00 1.00 431.00
Labour Unskilled Day 0020 431.00 5.00 2,155.00
Machinery:
Hire charges of Generator 5 KVA (without POL) Day 0072 500.00 0.20 100.00
Hire charges of Weld Trimmer Machine Day 0152 300.00 0.50 150.00
Hire charges of Rail Profile Weld Grinder Day 0151 100.00 0.20 20.00
Sundries Lumpsum 9901 1.00 10.00 10.00
13,620.30
Add for working under traffic block @ 10% Lumpsum 9992 0.10 1,362.03
14,982.33
Add for Water Charges @ 1% Lumpsum 9902 0.01 149.82
15,132.15
Add for GST @ 12% (multiplying factor 0.1405) Lumpsum 9903 0.14 2,126.07
17,258.22
Add for Contractor’s Overheads and Profit @ 15% Lumpsum 9904 0.15 2,588.73
19,846.95
Add for Cess @ 1% Lumpsum 9905 0.01 198.47
20,045.42
Rate per joint Each 4,009.08
Anti-corrosive Bituminous Paint (Black) confirming to IS:9862 Litre 0304 80.00 0.25 20.00
Enamel Paint as per RDSO's Spec. no.M&C/PCN/120-2011 Litre 0306 190.00 0.10 19.00
Soft Brush for painting - 25cm long Each 0314 33.00 0.10 3.30
Labour:
Welder (Skilled) Day 0029 609.00 1.00 609.00
Chipper (Skilled) Day 0030 609.00 1.00 609.00
Luter (Skilled) Day 0031 609.00 1.00 609.00
Look Out Man (Un-skilled) Day 0033 431.00 1.00 431.00
Labour Unskilled Day 0020 431.00 5.00 2,155.00
Machinery:
Hire charges of Generator 5 KVA (without POL) Day 0072 500.00 0.20 100.00
Hire charges of Weld Trimmer Machine Day 0152 300.00 0.50 150.00
Hire charges of Rail Profile Weld Grinder Day 0151 100.00 0.20 20.00
Sundries Lumpsum 9901 1.00 10.00 10.00
Draft IR Unified Stadard Analysis of Rates - 2021 Chapter - 9: Welding Activities
092020 Alumino Thermic 25mm gap 'in-situ' welding of rail joint with welding portion supplied
by Railway, during traffic block, as per IR's AT Welding Manual with latest correction
slips, complete in all respect including restoration of track near weld joint to original
position and fixing of joggled fish plate at new weld, to be removed after passing of
weld in USFD test.
Note:
1. Only welding portion and related accessories shall be supplied by Railways.
2. Welding shall be carried out only by trained welder having valid competency
certificate.
3. Hydraulic Weld trimmer shall be used for chipping and profile Grinder for finishing.
4. Required nos. of Joggled fish plates shall be issued by Railway at nearest P. Way
Store which shall be returned at the same place after release from track.
092021 For 60 Kg Rail, Single shot crucible fitted with Automatic Tapping Thimble , 3 pieces
Mould (Zircon washed) and Compressed Air Petrol/LPG pre heating technique
Enamel Paint as per RDSO's Spec. no.M&C/PCN/120-2011 Litre 0306 190.00 0.10 19.00
Soft Brush for painting - 25cm long Each 0314 33.00 0.10 3.30
Shearing Blade for weld trimming machine Each 0462 150.00 1.00 150.00
Hydraulic oil SS-68 or equivalent of HPCL/BPCL/IOCL Litre 0183 100.00 0.13 13.00
Grinding Stone wheel GQ6 of 150mm dia Nos. 0461 490.00 0.30 147.00
Labour:
Welder (Skilled) Day 0029 609.00 1.00 609.00
Chipper (Skilled) Day 0030 609.00 1.00 609.00
Luter (Skilled) Day 0031 609.00 1.00 609.00
Look Out Man (Un-skilled) Day 0033 431.00 1.00 431.00
Labour Unskilled Day 0020 431.00 5.00 2,155.00
Machinery:
Hire charges of Weld Trimmer Machine Day 0152 300.00 0.50 150.00
Hire charges of Generator 5 KVA (without POL) Day 0072 500.00 0.20 100.00
Hire charges of Rail Profile Weld Grinder Day 0151 100.00 0.20 20.00
Sundries Lumpsum 9901 1.00 50.00 50.00
6,100.30
Add for working under traffic block @ 10% Lumpsum 9992 0.10 610.03
6,710.33
Add for Water Charges @ 1% Lumpsum 9902 0.01 67.10
Draft IR Unified Stadard Analysis of Rates - 2021 Chapter - 9: Welding Activities
092022 For 60 Kg/60EI-R260 grade Rail, Single shot crucible fitted with Automatic Tapping
Thimble Technology, 3 pieces Mould (Zircon washed) and Compressed Air Petrol
heating technique.
Details of cost for 5 Joints
Material:
Normal unleaded Petrol Litre 0182 105.00 9.00 945.00
Kerosene Oil Litre 0185 56.00 1.25 70.00
Anti-corrosive Bituminous Paint (Black) confirming to IS:9862 Litre 0304 80.00 0.25 20.00
Enamel Paint as per RDSO's Spec. no.M&C/PCN/120-2011 Litre 0306 190.00 0.10 19.00
Soft Brush for painting - 25cm long Each 0314 33.00 0.10 3.30
Shearing Blade for weld trimming machine Each 0462 150.00 1.00 150.00
Hydraulic oil SS-68 or equivalent of HPCL/BPCL/IOCL Litre 0183 100.00 0.13 13.00
Grinding Stone wheel GQ6 of 150mm dia Nos. 0461 490.00 0.30 147.00
Labour:
Welder (Skilled) Day 0029 609.00 1.00 609.00
Chipper (Skilled) Day 0030 609.00 1.00 609.00
Luter (Skilled) Day 0031 609.00 1.00 609.00
Look Out Man (Un-skilled) Day 0033 431.00 1.00 431.00
Labour Unskilled Day 0020 431.00 4.00 1,724.00
Machinery:
Hire charges of Weld Trimmer Machine Day 0152 300.00 0.50 150.00
Hire charges of Generator 5 KVA (without POL) Day 0072 500.00 0.20 100.00
Hire charges of Rail Profile Weld Grinder Day 0151 100.00 0.20 20.00
Sundries Lumpsum 9901 1.00 50.00 50.00
5,669.30
Add for working under traffic block @ 10% Lumpsum 9992 0.10 566.93
6,236.23
Add for Water Charges @ 1% Lumpsum 9902 0.01 62.36
6,298.59
Add for GST @ 12% (multiplying factor 0.1405) Lumpsum 9903 0.14 884.95
7,183.54
Add for Contractor’s Overheads and Profit @ 15% Lumpsum 9904 0.15 1,077.53
8,261.08
Add for Cess @ 1% Lumpsum 9905 0.01 82.61
Cost for 5 Joints 8,343.69
Rate per joint Each 1,668.74
092023 For 52 Kg - 90 UTS or 52 Kg 72UTS Rail, Single shot crucible fitted with Automatic
Tapping Thimble Technology, 3 pieces Mould (Zircon washed) and Compressed Air
Petrol heating technique.
Details of cost for 5 Joints
Material:
Normal unleaded Petrol Litre 0182 105.00 9.00 945.00
Kerosene Oil Litre 0185 56.00 1.25 70.00
Anti-corrosive Bituminous Paint (Black) confirming to IS:9862 Litre 0304 80.00 0.25 20.00
Enamel Paint as per RDSO's Spec. no.M&C/PCN/120-2011 Litre 0306 190.00 0.10 19.00
Soft Brush for painting - 25cm long Each 0314 33.00 0.10 3.30
Shearing Blade for weld trimming machine Each 0462 150.00 1.00 150.00
Hydraulic oil SS-68 or equivalent of HPCL/BPCL/IOCL Litre 0183 100.00 0.13 13.00
Grinding Stone wheel GQ6 of 150mm dia Nos. 0461 490.00 0.30 147.00
Labour:
Draft IR Unified Stadard Analysis of Rates - 2021 Chapter - 9: Welding Activities
092024 For 90R Rail, Single shot crucible fitted with Automatic Tapping Thimble
Technology, 3 pieces Mould (Zircon washed) and Compressed Air Petrol heating
technique.
Rate same as 52 Kg rail
Rate per joint Each 092023 1,668.74
092030 Alumino Thermic 25mm gap 'in-situ' welding of rail joint with welding portion supplied
by Railway along with welder for any cross section and grade of Rail, during traffic
block, as per IR's AT Welding Manual with latest correction slips, complete in all
respect including restoration of track near weld joint to original position and fixing of
joggled fish plate at new weld, to be removed after passing of weld in USFD test.
Note:
1. Only welding portion and related accessories shall be supplied by Railways.
2. Welding shall be carried out only by trained welder having valid competency
certificate.
3. Hydraulic Weld trimmer shall be used for chipping and profile Grinder for finishing.
4. Required nos. of Joggled fish plates shall be issued by Railway at nearest P. Way
Store which shall be returned at the same place after release from track.
092040 Alumino Thermic 25mm gap 'in-situ' welding of rail joint at cess as per IR's AT
Welding Manual with latest correction slips, complete in all respect including
restoration of track near weld joint to original position and fixing of joggled fish plate
at new weld, to be removed after passing of weld in USFD test.
Note:
1. Welding shall be carried out only by trained welder having valid competency
certificate using RDSO approved Alumino Thermit Welding Portions, 3 piece
prefabricated mould (Zircon washed) manully pressed, Single shot cricible fitted with
auto tapping thimble and Compressed Air Petrol/LPG preheating technique as per
RDSO Specification No IRST/19-2020 with latest amendment.
2. Hydraulic Weld trimmer shall be used for chipping and profile Grinder for finishing.
3. Only required nos. of Joggled fish plates shall be issued by Railway at nearest P.
Way Store which shall be returned at the same place after release from track.
Anti-corrosive Bituminous Paint (Black) confirming to IS:9862 Litre 0304 80.00 0.50 40.00
Normal unleaded Petrol Litre 0182 105.00 18.00 1,890.00
Kerosene Oil Litre 0185 56.00 2.50 140.00
Enamel Paint as per RDSO's Spec. no.M&C/PCN/120-2011 Litre 0306 190.00 0.20 38.00
Soft Brush for painting - 25cm long Each 0314 33.00 0.10 3.30
Labour:
Welder (Skilled) Day 0029 609.00 1.00 609.00
Chipper (Skilled) Day 0030 609.00 1.00 609.00
Luter (Skilled) Day 0031 609.00 1.00 609.00
Labour Unskilled Day 0020 431.00 6.00 2,586.00
Machinery:
Hire charges of Weld Trimmer Machine Day 0152 300.00 1.00 300.00
Hire charges of Generator 5 KVA (without POL) Day 0072 500.00 0.50 250.00
Hire charges of Rail Profile Weld Grinder Day 0151 100.00 0.50 50.00
Sundries Lumpsum 9901 1.00 10.00 10.00
23,234.30
Add for Water Charges @ 1% Lumpsum 9902 0.01 232.34
23,466.64
Add for GST @ 12% (multiplying factor 0.1405) Lumpsum 9903 0.14 3,297.06
26,763.71
Add for Contractor’s Overheads and Profit @ 15% Lumpsum 9904 0.15 4,014.56
30,778.26
Draft IR Unified Stadard Analysis of Rates - 2021 Chapter - 9: Welding Activities
Anti-corrosive Bituminous Paint (Black) confirming to IS:9862 Litre 0304 80.00 0.50 40.00
Normal unleaded Petrol Litre 0182 105.00 18.00 1,890.00
Kerosene Oil Litre 0185 56.00 2.50 140.00
Enamel Paint as per RDSO's Spec. no.M&C/PCN/120-2011 Litre 0306 190.00 0.10 19.00
Soft Brush for painting - 25cm long Each 0314 33.00 0.10 3.30
Labour:
Welder (Skilled) Day 0029 609.00 1.00 609.00
Chipper (Skilled) Day 0030 609.00 1.00 609.00
Luter (Skilled) Day 0031 609.00 1.00 609.00
Labour Unskilled Day 0020 431.00 6.00 2,586.00
Machinery:
Hire charges of Weld Trimmer Machine Day 0152 300.00 1.00 300.00
Hire charges of Generator 5 KVA (without POL) Day 0072 500.00 0.50 250.00
Hire charges of Rail Profile Weld Grinder Day 0151 100.00 0.50 50.00
Sundries Lumpsum 9901 1.00 100.00 100.00
22,945.30
Add for Water Charges @ 1% Lumpsum 9902 0.01 229.45
23,174.75
Add for GST @ 12% (multiplying factor 0.1405) Lumpsum 9903 0.14 3,256.05
26,430.81
Add for Contractor’s Overheads and Profit @ 15% Lumpsum 9904 0.15 3,964.62
30,395.43
Add for Cess @ 1% Lumpsum 9905 0.01 303.95
Cost for 10 Joints 30,699.38
Rate per Joint Each 3,069.94
Anti-corrosive Bituminous Paint (Black) confirming to IS:9862 Litre 0304 80.00 0.50 40.00
Normal unleaded Petrol Litre 0182 105.00 18.00 1,890.00
Kerosene Oil Litre 0185 56.00 2.50 140.00
Enamel Paint as per RDSO's Spec. no.M&C/PCN/120-2011 Litre 0306 190.00 0.10 19.00
Soft Brush for painting - 25cm long Each 0314 33.00 0.10 3.30
Labour:
Welder (Skilled) Day 0029 609.00 1.00 609.00
Chipper (Skilled) Day 0030 609.00 1.00 609.00
Luter (Skilled) Day 0031 609.00 1.00 609.00
Labour Unskilled Day 0020 431.00 6.00 2,586.00
Machinery:
Hire charges of Weld Trimmer Machine Day 0152 300.00 1.00 300.00
Hire charges of Generator 5 KVA (without POL) Day 0072 500.00 0.50 250.00
Hire charges of Rail Profile Weld Grinder Day 0151 100.00 0.50 50.00
Draft IR Unified Stadard Analysis of Rates - 2021 Chapter - 9: Welding Activities
092050 Alumino Thermic 25mm gap 'in-situ' welding of rail joint at cess with welding portion
supplied by Railway, during traffic block, as per IR's AT Welding Manual with latest
correction slips, complete in all respect including restoration of track near weld joint
to original position and fixing of joggled fish plate at new weld, to be removed after
passing of weld in USFD test.
Note:
1. Only welding portion and related accessories shall be supplied by Railways.
2. Welding shall be carried out only by trained welder having valid competency
certificate.
3. Hydraulic Weld trimmer shall be used for chipping and profile Grinder for finishing.
4. Only required nos. of Joggled fish plates shall be issued by Railway at nearest P.
Way Store which shall be returned at the same place after release from track.
092051 For 60 Kg Rail, Single shot crucible fitted with Automatic Tapping Thimble, 3 pieces
Mould (Zircon washed) and Compressed Air Petrol/LPG pre heating technique
092052 For 60 Kg/60EI-R260 grade Rail, Single shot crucible fitted with Automatic Tapping
Thimble, 3 pieces Mould (Zircon washed) and Compressed Air Petrol/LPG pre
heating technique.
Details of cost for 10 Joints
Material:
Normal unleaded Petrol Litre 0182 105.00 18.00 1,890.00
Kerosene Oil Litre 0185 56.00 2.50 140.00
Anti-corrosive Bituminous Paint (Black) confirming to IS:9862 Litre 0304 80.00 0.50 40.00
Enamel Paint as per RDSO's Spec. no.M&C/PCN/120-2011 Litre 0306 190.00 0.10 19.00
Soft Brush for painting - 25cm long Each 0314 33.00 0.10 3.30
Shearing Blade for weld trimming machine Each 0462 150.00 2.00 300.00
Hydraulic oil SS-68 or equivalent of HPCL/BPCL/IOCL Litre 0183 100.00 0.25 25.00
Grinding Stone wheel GQ6 of 150mm dia Nos. 0461 490.00 0.60 294.00
Labour:
Welder (Skilled) Day 0029 609.00 1.00 609.00
Chipper (Skilled) Day 0030 609.00 1.00 609.00
Luter (Skilled) Day 0031 609.00 1.00 609.00
Labour Unskilled Day 0020 431.00 6.00 2,586.00
Machinery:
Hire charges of Weld Trimmer Machine Day 0152 300.00 1.00 300.00
Hire charges of Generator 5 KVA (without POL) Day 0072 500.00 0.50 250.00
Hire charges of Rail Profile Weld Grinder Day 0151 100.00 0.50 50.00
Sundries Lumpsum 9901 1.00 100.00 100.00
7,824.30
Add for Water Charges @ 1% Lumpsum 9902 0.01 78.24
7,902.54
Add for GST @ 12% (multiplying factor 0.1405) Lumpsum 9903 0.14 1,110.31
9,012.85
Add for Contractor’s Overheads and Profit @ 15% Lumpsum 9904 0.15 1,351.93
10,364.78
Add for Cess @ 1% Lumpsum 9905 0.01 103.65
Cost for 10 Joints 10,468.43
Rate per Joint Each 1,046.84
092053 For 52 Kg - 90 UTS or 52 Kg-72 UTS Rail, Single shot crucible fitted with Automatic
Tapping Thimble Technology, 3 pieces Mould (Zircon washed) and Compressed Air
Petrol heating technique.
Details of cost for 10 Joints
Material:
Normal unleaded Petrol Litre 0182 105.00 18.00 1,890.00
Kerosene Oil Litre 0185 56.00 2.50 140.00
Anti-corrosive Bituminous Paint (Black) confirming to IS:9862 Litre 0304 80.00 0.50 40.00
Grinding Stone wheel GQ6 of 150mm dia Nos. 0461 490.00 0.60 294.00
Enamel Paint as per RDSO's Spec. no.M&C/PCN/120-2011 Litre 0306 190.00 0.10 19.00
Soft Brush for painting - 25cm long Each 0314 33.00 0.10 3.30
Shearing Blade for weld trimming machine Each 0462 150.00 2.00 300.00
Hydraulic oil SS-68 or equivalent of HPCL/BPCL/IOCL Litre 0183 100.00 0.25 25.00
Labour:
Welder (Skilled) Day 0029 609.00 1.00 609.00
Chipper (Skilled) Day 0030 609.00 1.00 609.00
Luter (Skilled) Day 0031 609.00 1.00 609.00
Labour Unskilled Day 0020 431.00 6.00 2,586.00
Machinery:
Hire charges of Weld Trimmer Machine Day 0152 300.00 1.00 300.00
Draft IR Unified Stadard Analysis of Rates - 2021 Chapter - 9: Welding Activities
093011 52 Kg on Cess
Details of cost for 40 welds
Material:
Grinding Stone wheel GQ6 of 150mm dia Nos. 0461 490.00 2.50 1,225.00
Anti-corrosive Paint as per RDSO's Specn. No. M&C/PCN/123/2012 Litre 0305 280.00 2.00 560.00
Normal unleaded Petrol Litre 0182 105.00 1.00 105.00
Black Oil (used lubricating oil) Litre 0475 15.00 3.00 45.00
Diesel (HSD) Oil Litre 0181 101.62 200.00 20,324.00
Cotton Jute Kg 0494 40.00 2.00 80.00
Labour:
(a) For welding
Machinist (operator) (Skilled) Day 0040 609.00 2.00 1,218.00
Helper (Semi-skilled) Day 0021 505.00 2.00 1,010.00
Hammer man (Semi-skilled) Day 0032 505.00 1.00 505.00
Grinderman (Skilled) Day 0028 609.00 1.00 609.00
Track Machine Maintainer (Semi skilled) Day 0042 505.00 2.00 1,010.00
Labour Unskilled Day 0020 431.00 16.00 6,896.00
(b) For USFD testing
USFD Operator (With approved Certificate) Day 0043 1500.00 1.00 1,500.00
Helper (Semi-skilled) Day 0021 505.00 2.00 1,010.00
Labour Unskilled Day 0020 431.00 2.00 862.00
Machinery:
Hire Charges for Mobile Flash Butt Welding Plant Day 0126 55000.00 1.00 55,000.00
Hire charges for tractor with trolley Day 0081 1200.00 1.00 1,200.00
Hire charges of Road Cum Rail vehicle for transporting Flash Butt Welding plant Day 0125 1000.00 1.00 1,000.00
Hire charges of Crane 10T capacity Day 0089 5000.00 1.00 5,000.00
Hire charges of Rail Profile Weld Grinder Day 0151 100.00 1.00 100.00
Hire charges of Angle Grinder Day 0150 200.00 1.00 200.00
Hire charges of USFD testing machine Day 0129 800.00 1.00 800.00
Misc.:
T&P Lumpsum 9901 1.00 500.00 500.00
LS for Training charges at LKO Lumpsum 9901 1.00 200.00 200.00
100,959.00
Add for Water Charges @ 1% Lumpsum 9902 0.01 1,009.59
101,968.59
Add for GST @ 12% (multiplying factor 0.1405) Lumpsum 9903 0.14 14,326.59
116,295.18
Add for Contractor’s Overheads and Profit @ 15% Lumpsum 9904 0.15 17,444.28
133,739.45
Add for Cess @ 1% Lumpsum 9905 0.01 1,337.39
Draft IR Unified Stadard Analysis of Rates - 2021 Chapter - 9: Welding Activities
093012 60 Kg on Cess
Details of cost for 35 welds
Material:
Grinding Stone wheel GQ6 of 150mm dia Nos. 0461 490.00 2.50 1,225.00
Anti-corrosive Bituminous Paint (Black) confirming to IS:9862 Litre 0304 80.00 2.00 160.00
Normal unleaded Petrol Litre 0182 105.00 1.00 105.00
Black Oil (used lubricating oil) Litre 0475 15.00 3.00 45.00
Diesel (HSD) Oil Litre 0181 101.62 150.00 15,243.00
Cotton Jute Kg 0494 40.00 2.00 80.00
Hydraulic oil SS-68 or equivalent of HPCL/BPCL/IOCL Litre 0183 100.00 5.00 500.00
Labour:
(a) For welding
Machinist (operator) (Skilled) Day 0040 609.00 1.00 609.00
Helper (Semi-skilled) Day 0021 505.00 2.00 1,010.00
Grinderman (Skilled) Day 0028 609.00 1.00 609.00
Track Machine Maintainer (Semi skilled) Day 0042 505.00 2.00 1,010.00
Labour Unskilled Day 0020 431.00 16.00 6,896.00
(b) For USFD testing
USFD Operator (With approved Certificate) Day 0043 1500.00 1.00 1,500.00
Helper (Semi-skilled) Day 0021 505.00 2.00 1,010.00
Labour Unskilled Day 0020 431.00 2.00 862.00
Machinery:
Hire Charges for Mobile Flash Butt Welding Plant Day 0126 55000.00 1.00 55,000.00
Hire charges for tractor with trolley Day 0081 1200.00 1.00 1,200.00
Hire charges of Road Cum Rail vehicle for transporting Flash Butt Welding plant Day 0125 1000.00 1.00 1,000.00
Hire charges of Crane 10T capacity Day 0089 5000.00 1.00 5,000.00
Hire charges of Rail Profile Weld Grinder Day 0151 100.00 1.00 100.00
Hire charges of Angle Grinder Day 0150 200.00 1.00 200.00
Hire charges of USFD testing machine Day 0129 800.00 1.00 800.00
Misc.:
LS for Training charges at LKO Lumpsum 9901 1.00 200.00 200.00
T&P Lumpsum 9901 1.00 500.00 500.00
94,864.00
Add for Water Charges @ 1% Lumpsum 9902 0.01 948.64
95,812.64
Add for GST @ 12% (multiplying factor 0.1405) Lumpsum 9903 0.14 13,461.68
109,274.32
Add for Contractor’s Overheads and Profit @ 15% Lumpsum 9904 0.15 16,391.15
125,665.46
Add for Cess @ 1% Lumpsum 9905 0.01 1,256.65
Cost for 35 welds 126,922.12
Rate per weld Each 3,626.35
Material:
H3 Electrodes as per RDSO's Spec. no. IRS M:28-2011 Nos. 0427 20.00 120.00 2,400.00
Grinding Stone wheel GQ6 of 150mm dia Nos. 0461 490.00 1.00 490.00
Labour:
Welder (Skilled) Day 0029 609 2.00 1,218.00
Helper (Semi-skilled) Day 0021 505.00 2.00 1,010.00
Look Out Man (Un-skilled) Day 0033 431.00 1.00 431.00
Grinderman (Skilled) Day 0028 609.00 1.00 609.00
Labour Unskilled Day 0020 431.00 2.00 862.00
Machinery:
Hire charges of Arc Welding Machine 500 Amp Day 0132 300.00 1.00 300.00
Hire charges of Grinding Machine for 150 mm dia wheel Day 0149 300.00 1.00 300.00
Misc.:
Electricity Charges ( 1 Unit ) KWH 0505 7.50 120.00 900.00
T&P Lumpsum 9901 1.00 10.00 10.00
8,530.00
Add for Water Charges @ 1% Lumpsum 9902 0.01 85.30
8,615.30
Add for GST @ 12% (multiplying factor 0.1405) Lumpsum 9903 0.14 1,210.45
9,825.75
Add for Contractor’s Overheads and Profit @ 15% Lumpsum 9904 0.15 1,473.86
11,299.61
Add for Cess @ 1% Lumpsum 9905 0.01 113.00
Cost for 3 crossings 11,412.61
Rate per crossing Each 3,804.20
101020 In-situ reconditioning of worn out 1:12 or flatter built-up / fabricated crossing on all
types of rail sections under traffic condition by RDSO approved agency, as
prescribed in ‘IR's Reconditioning of Points & Crossings Manual’ with RDSO
approved electrodes and suppliers, finishing & grinding within permissible tolerance
limit, as directed by engineer in-charge :
102020 Reconditioning of worn out 1:12 or flatter CMS (Cast Manganese Steel) crossing on
all types of rail sections on Cess or Depot, as prescribed in ‘IR's Reconditioning of
Points & Crossings Manual’ with RDSO approved electrodes and suppliers, finishing
& grinding within permissible tolerance limit, as directed by engineer in-charge.
Details of cost for 1 crossing (6.5 Kg of 1.6mm dia core flux wire required for each
crossing)
Material:
1.6mm dia core flux wire of cast manganese steel Kg 0428 916.00 6.50 5,954.00
Grinding Stone wheel GQ6 of 150mm dia Nos. 0461 490.00 1.00 490.00
Labour:
Welder (Skilled) Day 0029 609 1.00 609.00
Machinist (operator) (Skilled) Day 0040 609.00 1.00 609.00
Helper (Semi-skilled) Day 0021 505.00 2.00 1,010.00
Grinderman (Skilled) Day 0028 609.00 1.00 609.00
Look Out Man (Un-skilled) Day 0033 431.00 1.00 431.00
Labour Unskilled Day 0020 431.00 2.00 862.00
Machinery:
Hire charges of Diesel Truck - 9 tonne Day 0060 3940.00 1.00 3,940.00
Hire charges of translamatic robotic welding machine Day 0134 5000.00 1.00 5,000.00
Hire charges of Grinding Machine for 150 mm dia wheel Day 0149 300.00 1.00 300.00
T&P Lumpsum 9901 1.00 1000.00 1,000.00
20,814.00
Add for Water Charges @ 1% Lumpsum 9902 0.01 208.14
21,022.14
Add for GST @ 12% (multiplying factor 0.1405) Lumpsum 9903 0.14 2,953.61
23,975.75
Add for Contractor’s Overheads and Profit @ 15% Lumpsum 9904 0.15 3,596.36
27,572.11
Add for Cess @ 1% Lumpsum 9905 0.01 275.72
Cost for 1 crossing 27,847.83
Rate per crossing Each 27,847.83
103020 In-situ reconditioning of worn out 1:12 or flatter tongue rail (only one tongue rail
alongwith connected stock rail) of all rail sections under traffic, as prescribed in ‘IR's
Reconditioning of Points & Crossings Manual’ with RDSO approved electrodes and
suppliers, finishing & grinding within permissible tolerance limit, as directed by
engineer in-charge :
103030 Reconditioning of worn out 1:8½ tongue rail (only one tongue rail alongwith
connected stock rail) of all rail sections on Cess or Depot, as prescribed in ‘IR's
Reconditioning of Points & Crossings Manual’ with RDSO approved electrodes and
suppliers, finishing & grinding within permissible tolerance limit, as directed by
engineer in-charge.
103040 Reconditioning of worn out 1:12 or flatter tongue rail (only one tongue rail alongwith
connected stock rail) of all rail sections on Cess or Depot, as prescribed in ‘IR's
Reconditioning of Points & Crossings Manual’ with RDSO approved electrodes and
suppliers, finishing & grinding within permissible tolerance limit, as directed by
engineer in-charge.
104020 Re-conditioning of cupped welded joints 'in-situ' by using CP-3032 powder under
traffic conditions as per RDSO’s guidelines for ‘IR's Reconditioning Of Scabs, Wheel
Burns Of Rail And Cupped AT Welded Joint’
104030 Repairs/Reconditioning of scabbed rails & wheel burns on tongue rails / running
rails/stock rails etc in situ using Micro flow thermal spray technology by using CP –
3032 powder as approved and as per RDSO / LKO and as per specifications with all
Contractor’s material, labour, tools, powder, equipment and consumable, with all lead
and lift complete and as per the instructions of the Engineer-in-charge at site.
104040 Insitu reconditioning of MCI insert of points & crossings sleeper by reclaimimg the
wornout portion to the desired height, grinding of the finished profile for regaining the
toe load lost. The reconditioning to be done by using TERRA C I-94 - Electrodes of
make L & T, AdvaniOerlicon, Diffusion, SHARP - 650, or equivalent approved by
RDSO for reconditioning of Cast iron alloys. removing and refixing the required
fittings for reconditioning in traffic condition. The cost includes all labour, lead lift,
transportation of men and material, cost of consumables, hiring of machinery
required etc, complete and as directed by the Engineer-in -charge.
112011 Embankment
For Lab test on collected soil samples as per relevant IS code Rates are avaliable in
Works SOR item no. 021140
Detail of cost for samples of 20 cross sections
Labour:
Draftsman / Surveyor Day 0001 1500.00 2.00 3,000.00
Helper (Semi-skilled) Day 0021 505.00 5.00 2,525.00
Labour Unskilled Day 0020 431.00 2.00 862.00
Waterman (Un-skilled) Day 0034 431.00 1.00 431.00
Misc.:
T&P Lumpsum 9901 1.00 50.00 50.00
Hire charges of Laptop / Computer with software & Printer Day 0166 300.00 1.00 300.00
7,168.00
Add for Water Charges @ 1% Lumpsum 9902 0.01 71.68
7,239.68
Add for GST @ 12% (multiplying factor 0.1405) Lumpsum 9903 0.14 1,017.18
8,256.86
Add for Contractor’s Overheads and Profit @ 15% Lumpsum 9904 0.15 1,238.53
9,495.38
Add for Cess @ 1% Lumpsum 9905 0.01 94.95
Cost for samples of 20 cross sections 9,590.34
Rate for each cross sections Each 479.52
112012 Cutting
Draft IR Unified Stadard Analysis of Rates - 2021 Chapter - 11: Formation Rehabilation
113012 With Rail Clusters, fabricated by contractor with rails supplied by Railways
Details of cost for 40 cum
Labour:
(i) For excavation of soil
Mate (Skilled) Day 0002 609.00 1.00 609.00
Look Out Man (Un-skilled) Day 0033 431.00 1.00 431.00
Waterman (Un-skilled) Day 0034 431.00 1.00 431.00
Labour Unskilled Day 0020 431.00 30.00 12,930.00
(ii) For leading wooden sleeper
Labour Unskilled Day 0020 431.00 10.00 4,310.00
(iii) For inserting crib both side
Mate (Skilled) Day 0002 609.00 2.00 1,218.00
Carpenter (Skilled) Day 0006 609.00 1.00 609.00
Helper (Semi-skilled) Day 0021 505.00 1.00 505.00
Waterman (Un-skilled) Day 0034 431.00 2.00 862.00
Labour Unskilled Day 0020 431.00 40.00 17,240.00
(iv) For preparation of rail cluster (with carting of rail)
Blacksmith - 1st Class (Skilled) Day 0008 609.00 2.00 1,218.00
Helper (Semi-skilled) Day 0021 505.00 2.00 1,010.00
Labour Unskilled Day 0020 431.00 20.00 8,620.00
(iv) For insertion of rail cluster
Mate (Skilled) Day 0002 609.00 1.50 913.50
Look Out Man (Un-skilled) Day 0033 431.00 1.00 431.00
Waterman (Un-skilled) Day 0034 431.00 1.00 431.00
Labour Unskilled Day 0020 431.00 30.00 12,930.00
(v) For removal of cluster & crib
Mate (Skilled) Day 0002 609.00 2.00 1,218.00
Look Out Man (Un-skilled) Day 0033 431.00 1.00 431.00
Waterman (Un-skilled) Day 0034 431.00 1.00 431.00
Labour Unskilled Day 0020 431.00 30.00 12,930.00
(vi) For carting of all materials back to store
Mate (Skilled) Day 0002 609.00 1.00 609.00
Labour Unskilled Day 0020 431.00 20.00 8,620.00
(vii) For lifting and packing of track
Mate (Skilled) Day 0002 609.00 1.00 609.00
Look Out Man (Un-skilled) Day 0033 431.00 1.00 431.00
Labour Unskilled Day 0020 431.00 40.00 17,240.00
Misc.:
T&P Lumpsum 9901 1.00 452.00 452.00
Hire charges for tractor with trolley Day 0081 1200.00 1.00 1,200.00
Draft IR Unified Stadard Analysis of Rates - 2021 Chapter - 11: Formation Rehabilation
113020 Laying and spreading blanketing material from stacks by the side of track after
removing ballast and filling the same in 15cm thick layer in track, levelling, watering,
ramming with hand rammers upto the formation top during formation treatment,
putting back ballast and packing in running traffic condition at speed restriction of 20
kmph for lead upto 250m and lift upto 5m.
113021 Extra to item no. 113020 for every 50 metres lead or part thereof when the lead
exceeds the initial 250 metres per Cum.
Details of cost for 20 Cum (Extra labour element required for additional average lead
of 250 metre for leading of blanket material)(@ one man per 2 Cum)
Labour:
Labour Unskilled Day 0020 431.00 10.00 4,310.00
Misc.:
T&P Lumpsum 9901 1.00 20.00 20.00
4,330.00
Add for Water Charges @ 1% Lumpsum 9902 0.01 43.30
4,373.30
Add for GST @ 12% (multiplying factor 0.1405) Lumpsum 9903 0.14 614.45
4,987.75
Add for Contractor’s Overheads and Profit @ 15% Lumpsum 9904 0.15 748.16
5,735.91
Add for Cess @ 1% Lumpsum 9905 0.01 57.36
Cost for 20 Cum / 250 metres lead 5,793.27
Cost for 20 Cum / every 50 metres lead 1,158.65
Rate per Cum per 50m lead Each 57.93
Draft IR Unified Stadard Analysis of Rates - 2021 Chapter - 11: Formation Rehabilation
113022 Extra to item no. 113020 for every 1 metres height / lift or part thereof, when the lift
exceeds initial 5 metres per Cum.
Details of cost for 20 Cum (Extra labour element required for additional average lift of
3 metre for leading of blanket material)(@ one man per 2 Cum)
Details of cost for 20 cum
Labour:
Labour Unskilled Day 0020 431.00 10.00 4,310.00
Misc.:
T&P Lumpsum 9901 1.00 20.00 20.00
4,330.00
Add for Water Charges @ 1% Lumpsum 9902 0.01 43.30
4,373.30
Add for GST @ 12% (multiplying factor 0.1405) Lumpsum 9903 0.14 614.45
4,987.75
Add for Contractor’s Overheads and Profit @ 15% Lumpsum 9904 0.15 748.16
5,735.91
Add for Cess @ 1% Lumpsum 9905 0.01 57.36
Cost for 20 cum / 3 metre lift 5,793.27
Cost for 20 Cum / every 1 metre lift 1,931.09
Rate per Cum per 1 m lift Each 96.55
113030 Repairing of embankment with contractor's own earth including , excavation / loading
into contractor's vehicle as per RDSO latest Specifications and guidelines
RDSO/2020/GE: IRS-0004 of Soil Quality Class SQ1 in cess / formation / level
crossing, rain cuts etc. in running line to make surface to the desired level and slope
to entire satisfaction of Engineer in-charge. Rate shall include uprooting and
disposing of all the vegitation, benching at every 30 Cm vertical height, earthwork for
benching cut portion, adding moisture to earth to bring it to Optimum Moisture
Content, , sectioning to profile, all lift, descends, ascends, crossing of track / road /
nallah etc. including breaking of clods etc. and compaction by slope vibratory
Rollers/Compactors etc.
Note: (1) Payment of cess repairs shall be based on the quantities worked out from
the cross sectional calculations only and worked out from the initial ground levels
before doing benching and final levels as done for new embankment. The earth work
in benching portion shall not be paid.
(2) The earth work shall be started only after Completing of the benching and
certified.
(3) The benching Work shall be done for a maximum height of 1.50 m at any time
based on the the progress of earthwork starting from toe of the embankment.
Material:
Soil Quality Class SQ1 suitable for sub grade of embankment as per RDSO Cum 0168 75 130 9,750.00
Specifications RDSO/2020/GE: IRS-0004
Labour:
Unskilled Labour for removing vegitation and Benching
Benching quantity for 33m length (100 Cum /3.00 sqm) = 33.33* 0.90 =30.00 Cum
Hire Charges of Slope Vibrator to be attached to Hydralic Excavator for rolling of Day 0054 2000 0.40 800.00
slope surfaces of embankment.
Draft IR Unified Stadard Analysis of Rates - 2021 Chapter - 11: Formation Rehabilation
113040 Excavation for widening of existing formation in cuttings in hard soils which require
picks or crow bars for hacking including soils containing stones or boulders of size
under 0.03 cum without infringing the nearby track, as directed by engineer-in-charge
at site including cutting of earth, loading, leading by contractor’s vehicles, unloading
at site, dumping on spoil bank by head loads and utilising same excavated earth for
widening of existing formation in embankment as per standards, duly rolling manually
at 2:1 slope and levelling bank to the required profile including watering and
compaction with contractor's labour or mechanically operated rollers with all
contractor's labour, clearing of jungle, benching etc., tools, plants, vehicles etc.
Detail of cost for 40 cum
Labour:
Mate (Skilled) Day 0002 609.00 1.00 609.00
Labour Unskilled Day 0020 431.00 10.00 4,310.00
Misc.:
T&P Lumpsum 9901 1.00 20.00 20.00
Hire charges for tractor with trolley Day 0081 1200.00 3.00 3,600.00
Hire Charges of JCB of 0.92 cum bucket Capacity Hour 0058 800.00 8.00 6,400.00
14,939.00
Add for Water Charges @ 1% Lumpsum 9902 0.01 149.39
15,088.39
Add for GST @ 12% (multiplying factor 0.1405) Lumpsum 9903 0.14 2,119.92
17,208.31
Add for Contractor’s Overheads and Profit @ 15% Lumpsum 9904 0.15 2,581.25
19,789.56
Add for Cess @ 1% Lumpsum 9905 0.01 197.90
Cost for 40 cum 19,987.45
Rate per Cum Cum 499.69
113050 Extra over item 113030 for earth-work for making cess on other side of the track
(when no approaches available along track or no road vehicles to work at site) by
dumping contractor's own earth, collected along toe of bank of any height on to other
side of track & side slope of the existing bank by head load, duly crossing of tracks
with all contractor's materials, labour, tools, plant including loading of earth in
baskets, lifting, leading to the non-cess side of bank including crossing of tracks &
dumping etc. and as directed by the Engineer in-charge.
Take 10% of relevant item rate Cum 113030 233.74 0.10 23.37
113060 Removal of the existing track panels of each of about 12.60m length from track
formations with Contractor's 30T capacity crawler cranes of three Nos, placing the
removed track panels on level ground along the toe of the formation and and bringing
back the removed track panels and placing on the track formation after completion of
laying of blanketing and spreading the ballast duly deploying the three nos of 30T
capacity crawler cranes (including one stand by crane) and one round of initial
packing during traffic block with all contractor's men, machinery, operators and
supporting staff to machinery, fuel, comsumable, tools and plants and all incidental
charges etc ., as directed by the Engineeer-in -charge.
Note:
Contractor has to make ramps to take machines onto formation and back, removing
the ramp and making formation slope and dressing to standard profile after
It is considered that this work of 1Km length can be carried out with 3 nos of 30T
capacity crawler cranes in 10 days.
Labour:
Mate (Skilled) Day 0002 609 10.00 6,090.00
Labour required to assist to machine working while removing track panels and
placing on level ground- 2 men to each machine)
For 10 days two machines being deployed in block and one machine for stand by.
Draft IR Unified Stadard Analysis of Rates - 2021 Chapter - 11: Formation Rehabilation
113070 Excavation of existing formation, after removal of track structure and removal of
ballast, to a width and depth as proposed to a length posiible to carryout in the given
period of time, duly deploying the four number of 200 HP Excavators (including one
stand by) and required no. of tippers, leading and dumping the excavated soil out
side railway boundary, laying of ramps at appropriate locations for movement of
machinery and levelling the formation after excavation during traffic block with all
contractor's men, machinery, operators and supporting staff to machinery, fuel,
consumable, tools and plants and all incidental charges etc., as directed by the
Engineer-in-charge.
Note: Contractor has to make ramps to take machines onto formation and back,
removing the ramp and making formation slope and dressing to standard profile after
completion of formation and ramps to outside railway boundary.
It is considered that this work of 1 km length can be carried out with 3 nos of Hitachi
of 210 capacity (and one stand by) in 10 days.(Quantity of earth to be excavated
from the existing formation (L=1000M,W=7.00M and D=0.55M) =3850 CuM
Labour:
Mate (Skilled) Day 0002 609 10.00 6,090.00
Men required to assist machine working
Labour Unskilled Day 0020 431 50.00 21,550.00
Look Out Man (Un-skilled) Day 0033 431 10.00 4,310.00
T & P ( Hammer, Crow bars, Tami bar, beater, Wire claws, etc.) Lumpsum 9901 1 500.00 500.00
Machinery:
Hire charges of Hydraulic Excavator (0.9 Cum Bucket Capacity) Day 0044 6400 40.00 256,000.00
Hire and running charges of Tipper 12 Cum Capacity Day 0048 7000 60.00 420,000.00
708,450.00
Add for working under traffic block @ 10% Lumpsum 9992 0.1 70,845.00
779,295.00
Add for Water Charges @ 1% Lumpsum 9902 0.01 7,792.95
787,087.95
Add for GST @ 12% (multiplying factor 0.1405) Lumpsum 9903 0.14 110,585.86
897,673.81
Add for Contractor’s Overheads and Profit @ 15% Lumpsum 9904 0.15 134,651.07
1,032,324.88
Add for Cess @ 1% Lumpsum 9905 0.01 10,323.25
Cost for 3850 CuM 1,042,648.13
Rate per Cum Cum 270.82
Draft IR Unified Stadard Analysis of Rates - 2021 Chapter - 12: Activities at Construction Sites
121020 Dismantling of existing rail / metal fencing, fixed adjoining running lines of track, duly
excavating and levelling the foundation by hand compaction, removing connections
and carting the released material up to a lead of 250m by suitable means and
stacking the same, as directed by engineer in-charge.
Note:1.The released materials shall be handed over duly stacking the same in
measurable fashion.
121030 Dismantling existing sand humps in yards from end of turnout to end of sand hump.
Scope includes dismantling of track and brick / stone masonry on either sides of
track, removing sand and earth to the required level including clearing site and
stacking released materials clear of infringement, complete and as directed.
Labour:
Mate (Skilled) Day 0002 609.00 1.00 609.00
Look Out Man (Un-skilled) Day 0033 431.00 1.00 431.00
Waterman (Un-skilled) Day 0034 431.00 1.00 431.00
Labour Unskilled Day 0020 431.00 8.00 3,448.00
For Dismantling masonry and collecting and stacking released materials and for
removing sand and earth to the required level.
Labour Unskilled Day 0020 431.00 8.00 3,448.00
Misc.:
T & P (Crow bar, Rail tongue, Chisel, Hammer, Spanner, etc.) Lumpsum 9901 1.00 16.00 16.00
8,383.00
Add for Water Charges @ 1% Lumpsum 9902 0.01 83.83
8,466.83
Add for GST @ 12% (multiplying factor 0.1405) Lumpsum 9903 0.14 1,189.59
9,656.42
Add for Contractor’s Overheads and Profit @ 15% Lumpsum 9904 0.15 1,448.46
11,104.88
Add for Cess @ 1% Lumpsum 9905 0.01 111.05
Cost for each 11,215.93
Rate per Sand Hump Each 11,215.93
122012 Rail length upto 13m 'Under Conditions not requiring Traffic Block -
Details of cost for 1000 RM
Labour:
Mate (Skilled) Day 0002 609.00 1.00 609.00
Waterman (Un-skilled) Day 0034 431.00 1.00 431.00
Labour Unskilled Day 0020 431.00 21.00 9,051.00
Misc.:
T&P Lumpsum 9901 1.00 80.00 80.00
10,171.00
Add for Water Charges @ 1% Lumpsum 9902 0.01 101.71
10,272.71
Add for GST @ 12% (multiplying factor 0.1405) Lumpsum 9903 0.14 1,443.32
11,716.03
Add for Contractor’s Overheads and Profit @ 15% Lumpsum 9904 0.15 1,757.40
13,473.43
Add for Cess @ 1% Lumpsum 9905 0.01 134.73
Cost for 1000 RM 13,608.16
Rate per RM RM 13.61
122013 For rails/panels of more than 13m and upto 40m length Under Traffic Block
Conditions.
Details of cost for 1000 RM
Labour:
Mate (Skilled) Day 0002 609.00 2.00 1,218.00
Waterman (Un-skilled) Day 0034 431.00 2.00 862.00
Look Out Man (Un-skilled) Day 0033 431.00 1.00 431.00
Labour Unskilled Day 0020 431.00 33.00 14,223.00
Misc.:
T&P Lumpsum 9901 1.00 80.00 80.00
16,814.00
Add for working under traffic block @ 10% Lumpsum 9992 0.10 1,681.40
18,495.40
Add for Water Charges @ 1% Lumpsum 9902 0.01 184.95
18,680.35
Add for GST @ 12% (multiplying factor 0.1405) Lumpsum 9903 0.14 2,624.59
21,304.94
Add for Contractor’s Overheads and Profit @ 15% Lumpsum 9904 0.15 3,195.74
24,500.69
Add for Cess @ 1% Lumpsum 9905 0.01 245.01
Cost for 1000 RM 24,745.69
Rate per RM RM 24.75
122014 For rails/panels of more than 13m and upto 40m length Under Conditions not
requiring Traffic Block
Details of cost for 1000 RM
Labour:
Mate (Skilled) Day 0002 609.00 1.00 609.00
Waterman (Un-skilled) Day 0034 431.00 1.00 431.00
Draft IR Unified Stadard Analysis of Rates - 2021 Chapter - 12: Activities at Construction Sites
122015 For rails/panels of more than 40m length : Under Traffic Block Conditions -
Details of cost for 1000 RM
Labour:
Mate (Skilled) Day 0002 609.00 1.00 609.00
Waterman (Un-skilled) Day 0034 431.00 1.00 431.00
Look Out Man (Un-skilled) Day 0033 431.00 1.00 431.00
Labour Unskilled Day 0020 431.00 51.00 21,981.00
Misc.:
T&P Lumpsum 9901 1.00 80.00 80.00
23,532.00
Add for working under traffic block @ 15% Lumpsum 9993 0.15 3,529.80
27,061.80
Add for Water Charges @ 1% Lumpsum 9902 0.01 270.62
27,332.42
Add for GST @ 12% (multiplying factor 0.1405) Lumpsum 9903 0.14 3,840.20
31,172.62
Add for Contractor’s Overheads and Profit @ 15% Lumpsum 9904 0.15 4,675.89
35,848.52
Add for Cess @ 1% Lumpsum 9905 0.01 358.49
Cost for 1000 RM 36,207.00
Rate per RM RM 36.21
122016 For rails/panels of more than 40m length Under Conditions not requiring Traffic Block
-
Details of cost for 1000 RM
Labour:
Mate (Skilled) Day 0002 609.00 1.00 609.00
Waterman (Un-skilled) Day 0034 431.00 1.00 431.00
Labour Unskilled Day 0020 431.00 42.00 18,102.00
Misc.:
T&P Lumpsum 9901 1.00 80.00 80.00
19,222.00
Add for Water Charges @ 1% Lumpsum 9902 0.01 192.22
19,414.22
Add for GST @ 12% (multiplying factor 0.1405) Lumpsum 9903 0.14 2,727.70
22,141.92
Add for Contractor’s Overheads and Profit @ 15% Lumpsum 9904 0.15 3,321.29
25,463.21
Add for Cess @ 1% Lumpsum 9905 0.01 254.63
Cost for 1000 RM 25,717.84
Rate per RM RM 25.72
122017 Extra over item No 122011 for crossing each additional line
Rate as per Item No 122011
Considering additional cost per crossing one line at the rate of 10% of item no
122011
Draft IR Unified Stadard Analysis of Rates - 2021 Chapter - 12: Activities at Construction Sites
122018 Extra over item No 122013 for crossing each additional line
Rate as per Item No 122013
Considering additional cost per crossing one line at the rate of 10% of item no
122013for crossing each additional line per Running metre
Rate RM 122013 24.75 10% 2.47
122019 Extra over item No 122015 for crossing each additional line
Rate as per Item No 122015
Considering additional cost per crossing one line at the rate of 10% of item no
122015
Rate for crossing each additional line per Running metre RM 122015 36.21 10% 3.62
123020 Installation of reference points for track centre line in main and loop lines, in straight
or curve portion, SRJ for turnouts, heel of crossing (HOC), locations of derailing
switches, switch expansion joints etc. away from formation on firm ground at known
offset with MS Angles of 50mmx50mmx5mm thick of length 1.80 m each, protected
by surrounding concrete of size 30cm x 30cm x 45cm of nominal mix 1:3:6, including
painting to pegs, as directed by Engineer In charge.
Note: Earth work and Cement concrete will be paid under relevant items.
Details of cost for 80 pegs {For one peg requires 50mmx50mmx5mm angle of 1.80 m
length ngle)=3.80 Kgs/metre length.1.80mx80 Nos=144Rmx3.80=547.2 Kg.Wastage
5%.Total = 574.56 Kg
Material:
Structural steel such as T, Angles, Channels and R S Joists conforming to Grade Quintal 0224 4950.00 5.75 28,462.50
Designation E 250; Quality "A" as per IS 2062
Enamel Paint as per RDSO's Spec. no.M&C/PCN/120-2011 Litre 0306 190.00 0.25 47.50
Draft IR Unified Stadard Analysis of Rates - 2021 Chapter - 12: Activities at Construction Sites
123030 Spreading of ballast, from existing stacks available along formation on top or at
cess, in required uniform thickness, compaction of ballast layer laid on new
formation at all the locations with smooth wheeled power roller of 8-10 tonne capacity
to sufficient number of passes to form consolidated ballast bed of approximately
250mm thickness to a width of 4m symmetrical to centre line of proposed track in
correct line & level with all ascents & descents, as directed by Engineer in-charge.
Note: Item is inclusive of (a) providing ramp for taking roller to formation and
removing the same & making good formation after completion of work; (b)
redistribution & leveling of excess ballast while rolling to obtain uniform plane
cambered surface.
Considering ballast heaped over top of formation in stackes as required for 200 mm
of ballast layer. One Dozer D-6 can doze 750 sqm/hrs i.e. 0.25*750 = 187.50
cum/hour.
Details of cost for 1000 m (For 250 mm thickness, 4 metre width and 1km length,
quantity of ballast to be spread and rolled = 0.25 x 4 x 1000 = 1000 cum)
Labour:
Mate (Skilled) Day 0002 609.00 1.00 609.00
Labour Unskilled Day 0020 431.00 10.00 4,310.00
Machinery:
Hire charges of dozer 215 HP capacity Hour 0057 1500.00 8.00 12,000.00
Hire Charges of JCB of 0.92 cum bucket Capacity Hour 0058 800.00 16.00 12,800.00
Hire charges of Road Roller 8 to10 tonnes Hour 0053 300.00 8.00 2,400.00
32,119.00
Add for Water Charges @ 1% Lumpsum 9902 0.01 321.19
32,440.19
Add for GST @ 12% (multiplying factor 0.1405) Lumpsum 9903 0.1405 4,557.85
36,998.04
Add for Contractor’s Overheads and Profit @ 15% Lumpsum 9904 0.15 5,549.71
42,547.74
Add for Cess @ 1% Lumpsum 9905 0.01 425.48
Cost for 1000 cum 42,973.22
Rate per cum Cum 42.97
Draft IR Unified Stadard Analysis of Rates - 2021 Chapter - 12: Activities at Construction Sites
123050 Linking of track at level crossing locations as per RDSO drawings with any type of
rail section and sleeper on prepared formation including leading free rails/welded
panels avilable along the alignment on to formation,leading and spreading all fittings
and fastenings, spreading of sleepers at specified spacing, squaring ,placing of rails
over sleepers and fixing rails to sleepers with all types of fittings and fastenings to
correct gauge & alignment,excavating level crosing portion as necessary,fixing check
rails to running rails,providing C.C blocks,chairs, drilling holes to sleepers,fixing
dowels,anti corrosive painting to running rails and check rails,lubrication of fittings
and fastenings with contractor's grease as per IRPWM standards with contractors
labour, tools, consumables, with all lead, lifts etc. complete and raising, levelling and
initial packing of track to make it fit for 30 kmph and meet other prequisites
prescribed in Indidian Railway Track Machine Manual for deployment of Tamping
Machine.
Note:
1.Rail cutting and Hole drilling shall be paid seperately.
2.Spreading of ballast and compaction shall be paid seperately under relevant item.
123060 Linking of BG track over ballasted deck bridges with any type of rail section and
PSC sleeper including leading free rails/welded panels avilable along the alignment
on to bridge, leading and spreading all fittings and fastenings, spreading of sleepers
at specified spacing, squaring, placing of rails over sleepers and fixing rails & guard
rails to sleepers with all types of fittings and fastenings to correct gauge &
alignment, lubrication of fittings and fastenings with contractor's grease as per
IRPWM standards with contractors labour, tools, consumables, with all lead, lifts etc.
complete and raising, levelling and initial packing of track to make it fit for 30 kmph
and meet other prequisites prescribed in Indidian Railway Track Machine Manual for
deployment of Tamping Machine.
Note:
1.Rail cutting and Hole drilling shall be paid seperately
2.Spreading of ballast and compaction shall be paid seperately under relevant item.
123070 Linking of track on Girder Bridge with Steel Channel/H-beam sleepers as per
approved drawings including leading of running and guard rails, sleepers and fittings,
bending of guard rails, notching, drilling of holes, cutting of rails etc. as per IRPWM
with latest correction slips and making track structure fit for normal speed.
Note:
1) Rails, Steel Channel/H-beam sleeper and all fittings will be supplied by Railways.
2)Transportation of track material if supplied beyond 250m of bridge appraches, shall
be paid seperately under relevant item.
Labour:
(i) Leading Channel sleepers, running Rails & Guard Rails ,fittings over the bridge
and leading back the released rails & fittings to bridge approaches over the bridge
123090 Shifting / Slewing the existing or newly assembled track of any rail section with any
type of sleepers and any density under line block to correct locations & alignment
and attending to one round kutcha packing to run safely at 20KMPH speed with all
contractors tools and consumables complete and as directed by Engineer in-charge.
123092 Maximum Shifting / Slewing for more than 1 metre & upto 2 metres
Details of cost for 100 TRM (24 laborers for slewing + 14 laborers for packing &
ballast bed)
Labour:
Mate (Skilled) Day 0002 609.00 1.00 609.00
Waterman (Un-skilled) Day 0034 431.00 1.00 431.00
Blacksmith - 1st Class (Skilled) Day 0008 609.00 1.00 609.00
Helper (Semi-skilled) Day 0021 505.00 1.00 505.00
Look Out Man (Un-skilled) Day 0033 431.00 1.00 431.00
Labour Unskilled Day 0020 431.00 30.00 12,930.00
Misc.:
T&P Lumpsum 9901 1.00 80.00 80.00
15,595.00
Add for Water Charges @ 1% Lumpsum 9902 0.01 155.95
15,750.95
Add for GST @ 12% (multiplying factor 0.1405) Lumpsum 9903 0.14 2,213.01
17,963.96
Add for Contractor’s Overheads and Profit @ 15% Lumpsum 9904 0.15 2,694.59
20,658.55
Add for Cess @ 1% Lumpsum 9905 0.01 206.59
Cost for 100 TRM 20,865.14
Rate per TRM TRM 208.65
123100 Assembling, laying and linking of Broad Gauge track over Inspection Pit lines/CC
apron, RCC/CC Bed Blocks etc. to correct level & alignment, fixing of all fittings with
rails / panels, aligning & leveling correctly, as directed by engineer in-charge .Rate is
inclusive of cutting rails, drilling holes for fixing fish plates, lubrication of fittings &
fastenings, fixing reference pillars, arrangement for keeping assembly in correct
position while concreting, as required.
123110 Fixing all types of free rails / rail panels over pit line for BG track with inserts, elastic
rail clips, MS liners and grooved rubber pads below rail to correct spacing, gauge,
alignment and level with above fittings & fastenings in position, duly providing full
complements of rail fittings. Required nos. of inserts per bearing shall be fixed at the
time of concreting bed block over pit wall to correct spacing, centre to centre,
alignment & levels as per IR’s approved drawing.
124020 Working of the Railway Push Trolley by arranging one Head trollyman along with 3
trollymen as per Railway's rules and stipulations for conducting inspections by
Railway officials and as directed by Engineer in-charge.
Note:
1) Labourers supplied should be of skilled in case of head trollyman and semiskilled
in case of trollymen and capable of pushing trolley in all gradients, and levels duly
observing all safety precautions as per the manual.
2) The labour engaged should be physically fit for strenous work and literate.
124050 Dismantling / removing the existing bearing plate and fixing new bearing plates
supplied by Railways in pit lines, duly breaking / chiselling CC to required depth, so
as to fix new bearing plates etc. with all contractor's labour, tools, lead, lift,
transportation etc. including crossing of tracks complete and as directed by Engineer
in-charge (concrete work for fixing will be paid separately)
131012 For PSC sleeper Track with Sleeper Density of less than 1540 Sleepers/Km
Details of cost for 180 TRM ( 1 Person will do Through packing 12 sleepers of 1340
density in a day)
Labour:
Mate (Skilled) Day 0002 609.00 1.00 609.00
Waterman (Un-skilled) Day 0034 431.00 1.00 431.00
Labour Unskilled Day 0020 431.00 21.00 9,051.00
Misc.:
T & P (Beater, Wire claws, Rake ballast, Hydraulic jacks etc.) Lumpsum 9901 1.00 40.00 40.00
10,131.00
Add for Water Charges @ 1% Lumpsum 9902 0.01 101.31
10,232.31
Add for GST @ 12% (multiplying factor 0.1405) Lumpsum 9903 0.14 1,437.64
11,669.95
Add for Contractor’s Overheads and Profit @ 15% Lumpsum 9904 0.15 1,750.49
13,420.44
Add for Cess @ 1% Lumpsum 9905 0.01 134.20
Cost for 180 TRM Sleepers 13,554.65
Rate per TRM TRM 75.30
131014 For other than PSC Sleeper Track with Sleeper Density of 1340 Sleepers/Km (M+4)
Details of cost for 209 TRM ( 1 Person will do Through packing 14 sleepers of 1340
density in a day)
Labour:
Mate (Skilled) Day 0002 609.00 1.00 609.00
Look Out Man (Un-skilled) Day 0033 431.00 1.00 431.00
Waterman (Un-skilled) Day 0034 431.00 1.00 431.00
Labour Unskilled Day 0020 431.00 21.00 9,051.00
Misc.:
T & P (Beater, Wire claws, Rake ballast, Hydraulic jacks etc.) Lumpsum 9901 1.00 40.00 40.00
10,562.00
Add for Water Charges @ 1% Lumpsum 9902 0.01 105.62
10,667.62
Add for GST @ 12% (multiplying factor 0.1405) Lumpsum 9903 0.14 1,498.80
12,166.42
Add for Contractor’s Overheads and Profit @ 15% Lumpsum 9904 0.15 1,824.96
13,991.38
Add for Cess @ 1% Lumpsum 9905 0.01 139.91
Cost for 209 TRM 14,131.30
Rate per TRM TRM 67.61
131030 First or Second Through Packing of track for all sleeper density including giving a
general lift, as desired to eliminate sag after Deep Screening work, lifting of track,
lowering of track and major realignment of curves and formation rehabilitation as per
procedure prescribed in latest edition of IRPWM.
Note: General lift is normally 25 mm and isolated lift may be upto 50 mm.
131035 For other than PSC Sleeper Track with Sleeper Density of 1660
Rate 10% extra over item no. 131034
Rate per TRM TRM 131034 86.89 1.10 95.58
131036 For other than PSC Sleeper Track with Sleeper Density of 1340
Rate 20% less than item no. 131034
Rate per TRM TRM 131034 86.89 0.80 69.51
131040 Third or subsequent Through Packing of track for all sleeper density including
picking of slacks, as required after second through packing, subsequent to Deep
Screening work as per procedure prescribed in latest edition of IRPWM.This item can
also be used after lifting/regrading/realignement works also.
Note: General lift is normally 25 mm and isolated lift may be upto 50 mm.
131044 For other than PSC Sleeper Track with Sleeper Density of 1540
Details of cost for 195 TRM ( 1 Person will do Through packing 15 sleepers of 1540
density in a day)
Labour:
Mate (Skilled) Day 0002 609.00 1.00 609.00
Look Out Man (Un-skilled) Day 0033 431.00 1.00 431.00
Waterman (Un-skilled) Day 0034 431.00 1.00 431.00
Labour Unskilled Day 0020 431.00 20.00 8,620.00
Misc.:
T & P (Beater, Wire claws, Rake ballast, Hydraulic jacks etc.) Lumpsum 9901 1.00 40.00 40.00
10,131.00
Add for Water Charges @ 1% Lumpsum 9902 0.01 101.31
10,232.31
Add for GST @ 12% (multiplying factor 0.1405) Lumpsum 9903 0.14 1,437.64
11,669.95
Add for Contractor’s Overheads and Profit @ 15% Lumpsum 9904 0.15 1,750.49
13,420.44
Add for Cess @ 1% Lumpsum 9905 0.01 134.20
Cost for 195 TRM 13,554.65
Rate per TRM TRM 69.51
131045 For other than PSC Sleeper Track with Sleeper Density of 1660
Rate 10% extra over item no. 131044
Rate per TRM TRM 131044 69.51 1.10 76.46
131046 For other than PSC Sleeper Track with Sleeper Density of 1340
Rate 20% less than item no. 131044
Rate per TRM TRM 131044 69.51 0.80 55.61
131050 Through packing of points and crossings, derailing switches including gauging,
fittings recoupment, elimination of sag and to the required alignment after Deep
Screenining as per procedure prescribed in latest edition of IRPWM complete as per
direction of Engineer-in-charge.
Note: This work shall be operated in exceptional cases with written approval at DEN
level when UNIMAT is not availble and immediate packing is required to maintain
safety.
Labour:
(i) For opening, packing & aligning of track
Mate (Skilled) Day 0002 609.00 1.00 609.00
Look Out Man (Un-skilled) Day 0033 431.00 1.00 431.00
Waterman (Un-skilled) Day 0034 431.00 1.00 431.00
Labour Unskilled Day 0020 431.00 13.00 5,603.00
Misc.:
T & P ( Crow bar,Wire claws, Rake ballast, Hydraulic jacks, Gauge cum level,Shovel Lumpsum 9901 1.00 120.00 120.00
etc.)
7,194.00
Add for Water Charges @ 1% Lumpsum 9902 0.01 71.94
7,265.94
Add for GST @ 12% (multiplying factor 0.1405) Lumpsum 9903 0.14 1,020.86
8,286.80
Add for Contractor’s Overheads and Profit @ 15% Lumpsum 9904 0.15 1,243.02
9,529.83
Add for Cess @ 1% Lumpsum 9905 0.01 95.30
Draft IR Unified Standard Analysis of Rates - 2021 Chapter - 13: Maintenance Activities
Labour:
(i) For opening, packing & aligning of track
Mate (Skilled) Day 0002 609.00 1.00 609.00
Look Out Man (Un-skilled) Day 0033 431.00 1.00 431.00
Waterman (Un-skilled) Day 0034 431.00 1.00 431.00
Labour Unskilled Day 0020 431.00 18.00 7,758.00
Misc.:
T & P ( Crow bar,Wire claws, Rake ballast, Hydraulic jacks, Gauge cum level,Shovel Lumpsum 9901 1.00 125.00 125.00
etc.)
9,354.00
Add for Water Charges @ 1% Lumpsum 9902 0.01 93.54
9,447.54
Add for GST @ 12% (multiplying factor 0.1405) Lumpsum 9903 0.14 1,327.38
10,774.92
Add for Contractor’s Overheads and Profit @ 15% Lumpsum 9904 0.15 1,616.24
12,391.16
Add for Cess @ 1% Lumpsum 9905 0.01 123.91
Rate per set Set 12,515.07
Labour:
(i) For opening, packing & aligning of track
Mate (Skilled) Day 0002 609.00 1.00 609.00
Look Out Man (Un-skilled) Day 0033 431.00 1.00 431.00
Waterman (Un-skilled) Day 0034 431.00 1.00 431.00
Labour Unskilled Day 0020 431.00 21.00 9,051.00
Misc.:
T & P ( Crow bar,Wire claws, Rake ballast, Hydraulic jacks, Gauge cum level,Shovel Lumpsum 9901 1.00 150.00 150.00
etc.)
10,672.00
Add for Water Charges @ 1% Lumpsum 9902 0.01 106.72
10,778.72
Add for GST @ 12% (multiplying factor 0.1405) Lumpsum 9903 0.14 1,514.41
12,293.13
Add for Contractor’s Overheads and Profit @ 15% Lumpsum 9904 0.15 1,843.97
14,137.10
Add for Cess @ 1% Lumpsum 9905 0.01 141.37
Rate per set Set 14,278.47
131060 Packing of isolated loose PSC sleepers on plain track below the bottom of the
sleepers and surrounding through out its length duly opening two galas on either side
of the renewed sleepers and packing the sleeper to bring the track to normal speed
including gauging, aligning, squaring of sleepers and sectioning of ballast to the
required profile with all contractor's labour, tools and plant etc. including all lead and
lift and crossing of tracks where ever necessary complete and as directed by the
Engineer-in-charge.
131070 Slack picking of joint sleepers and 3 approach sleepers on either sides giving
required lift to make up general track level, packing and profiling as directed.
Details of cost for 30 Joints.( One group of two persons will do 3 joints in a day)
Labour:
Mate (Skilled) Day 0002 609.00 1.00 609.00
Helper (Semi-skilled) Day 0021 505.00 1.00 505.00
Look Out Man (Un-skilled) Day 0033 431.00 1.00 431.00
Waterman (Un-skilled) Day 0034 431.00 1.00 431.00
Labour Unskilled Day 0020 431.00 20.00 8,620.00
Draft IR Unified Standard Analysis of Rates - 2021 Chapter - 13: Maintenance Activities
Labour:
Mate (Skilled) Day 0002 609.00 1.00 609.00
Look Out Man (Un-skilled) Day 0033 431.00 1.00 431.00
Waterman (Un-skilled) Day 0034 431.00 1.00 431.00
(i) For shallow screening works:
Labour Unskilled Day 0020 431.00 20.00 8,620.00
(ii) Other Works, e.g. removal/spreading of muck, replacing rounded ballast,
recouping deficient ballast & cess attention etc. (@ one man per 13 TRM) :
Labour Unskilled Day 0020 431.00 7.00 3,017.00
Misc.:
T & P (Beater, Wire claws, Rake ballast, Pan iron mortar, Hydraulic jacks etc.) Lumpsum 9901 1.00 54.00 54.00
13,162.00
Add for Water Charges @ 1% Lumpsum 9902 0.01 131.62
13,293.62
Add for GST @ 12% (multiplying factor 0.1405) Lumpsum 9903 0.14 1,867.75
15,161.37
Add for Contractor’s Overheads and Profit @ 15% Lumpsum 9904 0.15 2,274.21
17,435.58
Add for Cess @ 1% Lumpsum 9905 0.01 174.36
Cost for 91 TRM 17,609.94
Rate per TRM TRM 193.52
132012 For PSC sleeper Track with Sleeper Density less than 1540 sleepers/Km
Details of cost for 120 TRM ( 8 sleeper per head sleeper density of 1340
sleepers/km)
Labour:
Mate (Skilled) Day 0002 609.00 1.00 609.00
Look Out Man (Un-skilled) Day 0033 431.00 1.00 431.00
Waterman (Un-skilled) Day 0034 431.00 1.00 431.00
(i) For shallow screening works:
Labour Unskilled Day 0020 431.00 20.00 8,620.00
(ii) Other Works, e.g. removal/spreading of muck, replacing rounded ballast,
recouping deficient ballast & cess attention etc. (@ one man per 13 TRM) :
Draft IR Unified Standard Analysis of Rates - 2021 Chapter - 13: Maintenance Activities
132014 For other than PSC sleeper Track with Sleeper Density of 1340 sleepers/Km (M+4)
Details of cost for 135 TRM ( 9 sleeper per head sleeper density of 1340
sleepers/km)
Labour:
Mate (Skilled) Day 0002 609.00 1.00 609.00
Look Out Man (Un-skilled) Day 0033 431.00 1.00 431.00
Waterman (Un-skilled) Day 0034 431.00 1.00 431.00
(i) For shallow screening works:
Labour Unskilled Day 0020 431.00 20.00 8,620.00
(ii) Other Works, e.g. removal/spreading of muck, replacing rounded ballast,
recouping deficient ballast & cess attention etc. (@ one man per 13 TRM) :
Labour Unskilled Day 0020 431.00 10.00 4,310.00
Misc.:
T & P (Beater, Wire claws, Rake ballast, Pan iron mortar, Hydraulic jacks etc.) Lumpsum 9901 1.00 60.00 60.00
14,461.00
Add for Water Charges @ 1% Lumpsum 9902 0.01 144.61
14,605.61
Add for GST @ 12% (multiplying factor 0.1405) Lumpsum 9903 0.14 2,052.09
16,657.70
Add for Contractor’s Overheads and Profit @ 15% Lumpsum 9904 0.15 2,498.65
Draft IR Unified Standard Analysis of Rates - 2021 Chapter - 13: Maintenance Activities
132020 Systematic Overhauling (shallow screening) of fish plated / welded joint track
sleepers including 3 approach sleepers on either sides upto 50mm below bottom of
sleepers in crib & shoulder, replacing rounded ballast, recouping deficient ballast
within 50m lead, replacement of worn-out fittings supplied by Railway, as directed as
per procedure prescribed in latest edition of IRPWM.
Details of cost for 16 Joints. ( One group of four persons will do 4 joints in a day)
Labour:
(i) For shallow screening of joint sleepers including 3 approach sleepers:
Mate (Skilled) Day 0002 609.00 1.00 609.00
Look Out Man (Un-skilled) Day 0033 431.00 1.00 431.00
Waterman (Un-skilled) Day 0034 431.00 1.00 431.00
Labour Unskilled Day 0020 431.00 16.00 6,896.00
(ii) For recoupment of ballast:
Labour Unskilled Day 0020 431.00 10.00 4,310.00
Misc.:
T & P (Crow bar, Beater, Wire claws,Wire basket, Rake ballast, Hydraulic jacks, off Lumpsum 9901 1.00 60.00 60.00
track tamper etc.)
12,737.00
Add for Water Charges @ 1% Lumpsum 9902 0.01 127.37
Draft IR Unified Standard Analysis of Rates - 2021 Chapter - 13: Maintenance Activities
133020 Pulling of single rail / welded rail panels to create a specified gap under traffic block,
including opening of fittings & fastenings and re-fixing them on track after pulling of
rail and creating standard gap for welding.
133021 For Rails more than 13m and upto 40m length
Details of cost for 300 RM
Labour:
Mate (Skilled) Day 0002 609.00 1.00 609.00
Blacksmith - 1st Class (Skilled) Day 0008 609.00 1.00 609.00
Helper (Semi-skilled) Day 0021 505.00 1.00 505.00
Look Out Man (Un-skilled) Day 0033 431.00 1.00 431.00
Waterman (Un-skilled) Day 0034 431.00 1.00 431.00
Labour Unskilled Day 0020 431.00 8.00 3,448.00
Misc.:
T&P Lumpsum 9901 1.00 20.00 20.00
6,053.00
Add for working under traffic block @ 5% Lumpsum 9991 0.05 302.65
6,355.65
Add for Water Charges @ 1% Lumpsum 9902 0.01 63.56
6,419.21
Add for GST @ 12% (multiplying factor 0.1405) Lumpsum 9903 0.14 901.90
7,321.11
Add for Contractor’s Overheads and Profit @ 15% Lumpsum 9904 0.15 1,098.17
8,419.27
Add for Cess @ 1% Lumpsum 9905 0.01 84.19
Cost for 300 RM 8,503.46
Rate per RM RM 28.34
8,174.25
Add for Water Charges @ 1% Lumpsum 9902 0.01 81.74
8,255.99
Add for GST @ 12% (multiplying factor 0.1405) Lumpsum 9903 0.14 1,159.97
9,415.96
Add for Contractor’s Overheads and Profit @ 15% Lumpsum 9904 0.15 1,412.39
10,828.35
Add for Cess @ 1% Lumpsum 9905 0.01 108.28
10,936.64
Cost for 300 RM 10,936.64
Rate per RM RM 36.46
134011 Other than PSC Sleeper track - Maximum slew upto 50mm
Details of cost for 390 TRM ( 1 Person will do Through packing including slewing 12
sleepers of 1540 density in a day)
Labour:
Mate (Skilled) Day 0002 609.00 1.00 609.00
Look Out Man (Un-skilled) Day 0033 431.00 1.00 431.00
Waterman (Un-skilled) Day 0034 431.00 2.00 862.00
Labour Unskilled Day 0020 431.00 50.00 21,550.00
Misc.:
T&P Lumpsum 9901 1.00 100.00 100.00
23,552.00
Add for working under traffic block @ 10% Lumpsum 9992 0.10 2,355.20
25,907.20
Add for Water Charges @ 1% Lumpsum 9902 0.01 259.07
26,166.27
Add for GST @ 12% (multiplying factor 0.1405) Lumpsum 9903 0.14 3,676.36
29,842.63
Add for Contractor’s Overheads and Profit @ 15% Lumpsum 9904 0.15 4,476.39
34,319.03
Add for Cess @ 1% Lumpsum 9905 0.01 343.19
Cost for 390 TRM 34,662.22
Rate per TRM TRM 88.88
134012 Other than PSC Sleeper track - Maximum slew more than 50mm and upto 100mm
Details of cost for 364 TRM ( 1 Person will do Through packing including slewing 10
sleepers of 1540 density in a day)
Labour:
Mate (Skilled) Day 0002 609.00 1.00 609.00
Look Out Man (Un-skilled) Day 0033 431.00 1.00 431.00
Waterman (Un-skilled) Day 0034 431.00 2.00 862.00
Labour Unskilled Day 0020 431.00 56.00 24,136.00
T&P Lumpsum 9901 1.00 112.00 112.00
26,150.00
Draft IR Unified Standard Analysis of Rates - 2021 Chapter - 13: Maintenance Activities
134013 Other than PSC Sleeper track - Maximum slew more than 100mm and upto 150mm
Details of cost for 338 TRM ( 1 Person will do Through packing including slewing 9
sleepers of 1540 density in a day)
Labour:
Mate (Skilled) Day 0002 609.00 1.00 609.00
Waterman (Un-skilled) Day 0034 431.00 2.00 862.00
Look Out Man (Un-skilled) Day 0033 431.00 1.00 431.00
Labour Unskilled Day 0020 431.00 58.00 24,998.00
Misc.:
T&P Lumpsum 9901 1.00 116.00 116.00
27,016.00
Add for working under traffic block @ 10% Lumpsum 9992 0.10 2,701.60
29,717.60
Add for Water Charges @ 1% Lumpsum 9902 0.01 297.18
30,014.78
Add for GST @ 12% (multiplying factor 0.1405) Lumpsum 9903 0.14 4,217.08
34,231.85
Add for Contractor’s Overheads and Profit @ 15% Lumpsum 9904 0.15 5,134.78
39,366.63
Add for Cess @ 1% Lumpsum 9905 0.01 393.67
Cost for 338 TRM 39,760.30
Rate per TRM TRM 117.63
134014 Other than PSC Sleeper track - Maximum slew more than 150mm
Details of cost for 312 TRM ( 1 Person will do Through packing including slewing 8
sleepers of 1540 density in a day)
Labour:
Mate (Skilled) Day 0002 609.00 1.00 609.00
Look Out Man (Un-skilled) Day 0033 431.00 1.00 431.00
Waterman (Un-skilled) Day 0034 431.00 2.00 862.00
Labour Unskilled Day 0020 431.00 60.00 25,860.00
Misc.:
T&P Lumpsum 9901 1.00 120.00 120.00
27,882.00
Add for working under traffic block @ 10% Lumpsum 9992 0.10 2,788.20
30,670.20
Add for Water Charges @ 1% Lumpsum 9902 0.01 306.70
30,976.90
Add for GST @ 12% (multiplying factor 0.1405) Lumpsum 9903 0.14 4,352.25
35,329.16
Add for Contractor’s Overheads and Profit @ 15% Lumpsum 9904 0.15 5,299.37
40,628.53
Add for Cess @ 1% Lumpsum 9905 0.01 406.29
Cost for 312 TRM 41,034.82
Rate per TRM TRM 131.52
134016 PSC Sleeper track - Maximum slew more than 50mm and upto 100mm
Details of cost for 286 TRM ( 1 Person will do Through packing including slewing 8
sleepers of 1540 density in a day)
Labour:
Mate (Skilled) Day 0002 609.00 1.00 609.00
Look Out Man (Un-skilled) Day 0033 431.00 1.00 431.00
Waterman (Un-skilled) Day 0034 431.00 2.00 862.00
Labour Unskilled Day 0020 431.00 55.00 23,705.00
Misc.:
T&P Lumpsum 9901 1.00 110.00 110.00
25,717.00
Add for working under traffic block @ 10% Lumpsum 9992 0.10 2,571.70
28,288.70
Add for Water Charges @ 1% Lumpsum 9902 0.01 282.89
28,571.59
Add for GST @ 12% (multiplying factor 0.1405) Lumpsum 9903 0.14 4,014.31
32,585.89
Add for Contractor’s Overheads and Profit @ 15% Lumpsum 9904 0.15 4,887.88
37,473.78
Add for Cess @ 1% Lumpsum 9905 0.01 374.74
Cost for 286 TRM 37,848.52
Rate per TRM TRM 132.34
134017 PSC Sleeper track - Maximum slew more than 100mm and upto 150mm
Details of cost for 260 TRM ( 1 Person will do Through packing including slewing 7
sleepers of 1540 density in a day)
Labour:
Mate (Skilled) Day 0002 609.00 1.00 609.00
Look Out Man (Un-skilled) Day 0033 431.00 1.00 431.00
Waterman (Un-skilled) Day 0034 431.00 2.00 862.00
Labour Unskilled Day 0020 431.00 58.00 24,998.00
Misc.:
T&P Lumpsum 9901 1.00 116.00 116.00
27,016.00
Add for working under traffic block @ 10% Lumpsum 9992 0.10 2,701.60
29,717.60
Add for Water Charges @ 1% Lumpsum 9902 0.01 297.18
30,014.78
Draft IR Unified Standard Analysis of Rates - 2021 Chapter - 13: Maintenance Activities
135020 Providing temporary Buffer Rails of fish plated joints of 3 pairs, measuring 6.5m each,
duly removing rails of the existing track including cutting & drilling of rails as required
for isolating LWR/CWR on all types of track structure. Work will be done under traffic
block condition.
Note:
1.Each set comprises of 3 pairs of rails 6.5 m long only.
2.Only Rails fish plate and fish bolts will be supplied free by Railway within free lead
of 250m.
136020 Providing wooden blocks under rail joints duly transporting Railway’s released
wooden blocks, providing bearing plate with rail screw / dog spikes and doing
packing, as directed under traffic condition.
Note: Wooden blocks, Bearing plates, rail screws/dog spikes will be supplied free at
SSE/P.Way depot
136030 Removing the existing wooden blocks under each joint, duly removing fittings,
transporting and stacking material wise in a countable manner and handing over the
wooden blocks & fittings at PWI's Depot or as directed by Engineer incharge.
136040 Maintenance of track on main line & loops, Points & crossings etc. including special
attention to section for carrying out various maintenance works listed in Indian
Railways P.Way Manual / Bridge Manual for safe running of goods and passenger
trains with contractor's tools / labours etc. complete, as directed by Engineer in-
charge.
Note: Contractor shall arrange one gang at any point of time comprising of minimum
specified labours with sufficient experience in P.Way working.
Draft IR Unified Standard Analysis of Rates - 2021 Chapter - 13: Maintenance Activities
136050 Interchanging gauge face of rails of any section in traffic line block including removal
of fittings and re-fixing the same after changing of gauge face, cutting of rails, joining
the rails with fish plate & drilling holes as directed by engineer in-charge.
136060 Replacing existing glued joint rail with cut rails or with glued joint rail or insertion of
glued joint by cutting existing track under traffic condition by cutting rails, refixing with
all rail sleeper fastenings and providing required gaps for carrying out welding as an
alternative to drilling holes or joining rails with fish plates duly drilling holes as
required and as directed by engineer in-charge.
Note:
(1) Drilling holes & rail cutting will be paid separately.
(2) Transportation of materials to the site of work from supply points, if more than
250m, shall be paid separately.
136070 Fixing of wooden distance pieces for platforms with contractor's labour, tools and
plants of size Wooden Block (size : 1.0m x 0.3m x 0.15m)
136071 With Railway’s wooden block (by cutting Railway’s wooden sleepers into blocks by
sawing to size)
Details of cost for 60 nos.
Labour:
(i) Cutting of wooden blocks from sleepers ( 1 carpenter + 1 helper prepare 20 Blocks
in a day )
Carpenter (Skilled) Day 0006 609.00 3.00 1,827.00
Helper (Semi-skilled) Day 0021 505.00 3.00 1,515.00
(ii) Fixing of wooden blocks
Mate (Skilled) Day 0002 609.00 0.50 304.50
Labour Unskilled Day 0020 431.00 10.00 4,310.00
Misc.:
T&P Lumpsum 9901 1.00 50.00 50.00
8,006.50
Draft IR Unified Standard Analysis of Rates - 2021 Chapter - 13: Maintenance Activities
136080 Drilling holes of 16mm to 22mm dia. on all types of PSC sleepers and fixing the
dowels with adhesive of approved quality for fixing check rails & guard rails, as
directed by engineer in-charge
Details of cost for 60 holes
Material:
Drill twist made of high speed steel for size 18mm dia of Addison / I T make Each 0467 1866.40 1.00 1,866.40
Normal unleaded Petrol Litre 0182 105.00 1.00 105.00
Kerosene Oil Litre 0185 56.00 5.00 280.00
Epoxy for fixing HDPE dowel, Rubber Pads as per RDSO approved specification Kg 0321 500.00 3.00 1,500.00
HDPE Dowels Each 0456 100.00 60.00 6,000.00
Labour:
Blacksmith - 1st Class (Skilled) Day 0008 609.00 1.00 609.00
Helper (Semi-skilled) Day 0021 505.00 1.00 505.00
Look Out Man (Un-skilled) Day 0033 431.00 1.00 431.00
Labour Unskilled Day 0020 431.00 1.00 431.00
Misc.:
T&P Lumpsum 9901 1.00 10.00 10.00
Hire charges of Concrete Sleeper Drilling Machine Day 0140 300.00 1.00 300.00
Hire charges of Generator 5 KVA (without POL) Day 0072 500.00 1.00 500.00
12,537.40
Add for Water Charges @ 1% Lumpsum 9902 0.01 125.37
12,662.77
Add for GST @ 12% (multiplying factor 0.1405) Lumpsum 9903 0.14 1,779.12
14,441.89
Add for Contractor’s Overheads and Profit @ 15% Lumpsum 9904 0.15 2,166.28
16,608.18
Add for Cess @ 1% Lumpsum 9905 0.01 166.08
Draft IR Unified Standard Analysis of Rates - 2021 Chapter - 13: Maintenance Activities
136090 Cleaning of side drains along the track including disposing of muck beyond Railway
boundary as per instructions of Engineer in-charge to keep drains clean and clear in
cuttings etc.
Details of cost for 500 RM ( One group of two persons will clean 50 Running metre
in a day)
Labour:
Mate (Skilled) Day 0002 609.00 1.00 609.00
Waterman (Un-skilled) Day 0034 431.00 1.00 431.00
Look Out Man (Un-skilled) Day 0033 431.00 1.00 431.00
Labour Unskilled Day 0020 431.00 20.00 8,620.00
Misc.:
T&P Lumpsum 9901 1.00 40.00 40.00
10,131.00
Add for Water Charges @ 1% Lumpsum 9902 0.01 101.31
10,232.31
Add for GST @ 12% (multiplying factor 0.1405) Lumpsum 9903 0.14 1,437.64
11,669.95
Add for Contractor’s Overheads and Profit @ 15% Lumpsum 9904 0.15 1,750.49
13,420.44
Add for Cess @ 1% Lumpsum 9905 0.01 134.20
Cost for 500 RM 13,554.65
Rate per RM RM 27.11
136100 Removing weeds & bushes in ballast section and cess upto 3.95m from centre line
of track in mid section & station yard, as specified by Engineer in-charge including
disposal of branches, bushes outside cess/yard.
Details of cost for 1040 TRM ( One persons will Remove weeds & bushes 52
Running metre in a day)
Labour:
Mate (Skilled) Day 0002 609.00 1.00 609.00
Waterman (Un-skilled) Day 0034 431.00 1.00 431.00
Labour Unskilled Day 0020 431.00 20.00 8,620.00
Misc.:
T&P Lumpsum 9901 1.00 40.00 40.00
9,700.00
Add for Water Charges @ 1% Lumpsum 9902 0.01 97.00
9,797.00
Add for GST @ 12% (multiplying factor 0.1405) Lumpsum 9903 0.14 1,376.48
11,173.48
Add for Contractor’s Overheads and Profit @ 15% Lumpsum 9904 0.15 1,676.02
12,849.50
Add for Cess @ 1% Lumpsum 9905 0.01 128.50
Cost for 1040 RM 12,978.00
Rate per TRM TRM 12.48
136110 Trimming of tree branches coming within 4m of centre line of track & those
obstructing views of Curves/LCs / Signal / Indicator at locations in section & station
yard, as specified by Engineer in-charge including disposal of branches, bushes
outside cess/yard.
Note: Girth of more than 30 cm will only be considered as tree branch.
136120 Making kutcha trapezoidal side drain of bottom width as 300mm and depth of 450mm
in cutting section by excavation in all types of soil including utilising excavated muck
for dressing of cess, slopes etc. in Railway land.
Details of cost for 100 RM (One group of two persons will make kutcha traezoidal
side drain of bottom width 300mm and depth of 450mm, 6.25 Running metre in a
day)
Labour:
Mate (Skilled) Day 0002 609.00 1.00 609.00
Waterman (Un-skilled) Day 0034 431.00 1.00 431.00
Labour Unskilled Day 0020 431.00 32.00 13,792.00
Misc.:
T&P Lumpsum 9901 1.00 64.00 64.00
14,896.00
Add for Water Charges @ 1% Lumpsum 9902 0.01 148.96
15,044.96
Add for GST @ 12% (multiplying factor 0.1405) Lumpsum 9903 0.14 2,113.82
17,158.78
Add for Contractor’s Overheads and Profit @ 15% Lumpsum 9904 0.15 2,573.82
19,732.59
Add for Cess @ 1% Lumpsum 9905 0.01 197.33
Cost for 100 RM 19,929.92
Rate per RM RM 199.30
136130 Patrol man for patrolling during cold / hot weather on track for protecting track with all
contractor’s labour, tools, plants etc. complete as directed by Engineer In charge.
Note:
1.The person deployed for patrolling must have the following items:
• Valid certificate of competency issued by Railways.
• Medical certificate issued by Railway fit for A-3 medical category.
2.The following equipment will be supplied by Railways for each patrolman and same
to be handed over back to Railways in good condition:
• Detonators – 10 nos. if used, bursted detonators to be handed over back and report
with reasons for use.
• Tri colour Torch – 1no.
• Equipment list to be supplied by railway to be mentioned.
• Canne –a - boule(if required)
3.The following equipment to be arranged by contractor for each patrol man:
H.S.Flags green-1 No (Std size),H.S Flags -Red-2 Nos(Std size),Torch light 3 cell-1
no, Staff for flags-1no,Whistle Thunder- 1no,Protective clothing to withstand climate,
Gum boots, Haver sack.
1,080.00
Add for Water Charges @ 1% Lumpsum 9902 0.01 10.80
1,090.80
Add for GST @ 12% (multiplying factor 0.1405) Lumpsum 9903 0.14 153.26
Draft IR Unified Standard Analysis of Rates - 2021 Chapter - 13: Maintenance Activities
1,595.00
Add for Water Charges @ 1% Lumpsum 9902 0.01 15.95
1,610.95
Add for GST @ 12% (multiplying factor 0.1405) Lumpsum 9903 0.14 226.34
1,837.29
Add for Contractor’s Overheads and Profit @ 15% Lumpsum 9904 0.15 275.59
2,112.88
Add for Cess @ 1% Lumpsum 9905 0.01 21.13
Cost for 24 Hours for 2 Persons, @ 1 person 12 Hours i.e 2 Persons for 24hrs 2,134.01
Rate per Person Each 1,067.01
136140 Patrol man for monsoon / security patrolling whenever required for protection of track
with all contractor’s labour, tools and plants etc. complete and as directed by
Engineer in-charge and as per IRPWM (for a duration of 12 hours)
Note:
1.The person deployed for patrolling must have the following items:
• Valid certificate of competency issued by Railways.
• Medical certificate issued by Railway fit for A-3 medical category.
2.The following equipment will be supplied by Railways per each patrol man and
required to be handed over back to Railways in good condition:
• Detonators – 10 nos.(in a tin case), if used, bursted detonators to be handed over
back with reasons for use.
• Tri Colour Torch - 1no.
• Patrol chart.
• Patrol book.
540.00
Draft IR Unified Standard Analysis of Rates - 2021 Chapter - 13: Maintenance Activities
1,342.50
Add for Water Charges @ 1% Lumpsum 9902 0.01 13.43
1,355.93
Add for GST @ 12% (multiplying factor 0.1405) Lumpsum 9903 0.14 190.51
1,546.43
Add for Contractor’s Overheads and Profit @ 15% Lumpsum 9904 0.15 231.96
1,778.40
Add for Cess @ 1% Lumpsum 9905 0.01 17.78
Cost for 2 Persons 1,796.18
Rate per Person Each 898.09
Details of cost for 130 RM ( One group of 1 Painter + 1 helper + 1 Labour will paint
65 RM i.e 5 Rails of 13 metre in a day)
Material:
Zinc Chromate red oxide Primer to IS:2074 Litre 0308 130.00 30.00 3,900.00
Cotton Jute Kg 0494 40.00 1.00 40.00
Sand Paper Nos. 0496 5.00 12.00 60.00
Wire Brush - 25cm long Each 0313 15.00 2.00 30.00
Soft Brush for painting - 25cm long Each 0314 33.00 2.00 66.00
Labour:
Painter (Skilled) Day 0012 609.00 1.00 609.00
Helper (Semi-skilled) Day 0021 505.00 1.00 505.00
Labour Unskilled Day 0020 431.00 1.00 431.00
Misc.:
T&P Lumpsum 9901 1.00 12.00 12.00
5,653.00
Add for Water Charges @ 1% Lumpsum 9902 0.01 56.53
5,709.53
Add for GST @ 12% (multiplying factor 0.1405) Lumpsum 9903 0.14 802.19
6,511.72
Add for Contractor’s Overheads and Profit @ 15% Lumpsum 9904 0.15 976.76
7,488.48
Add for Cess @ 1% Lumpsum 9905 0.01 74.88
Cost for 130 RM 7,563.36
Rate per RM RM 58.18
137020 Painting of rail on running track on rail, web, foot including liner contact area
(excluding bottom of foot) and fishing plane as per requirement with one coat of red
oxide / zinc chromate primer to IS : 2074 of reputed make including surface
preparation, i.e. cleaning with wire brush / sand paper as a complete job.
Draft IR Unified Standard Analysis of Rates - 2021 Chapter - 13: Maintenance Activities
137030 Anti-corrosive painting of rail outside track on rail bottom, web, foot and fishing
plane as per requirement with two coats of thickness of 100 microns each by
bituminous black paint confirms to IS-9862 of reputed make including surface
preparation, i.e. cleaning with wire brush / sand paper as a complete job as per
procedure prescribed in latest edition of IRPWM.
137050 Anti-corrosive painting to weld collar for Thermit welded rail joints on track or on cess
for new welded joints to protect against normal corrsion for any rail section with two
coats of ready mixed bitumenous black paint of reputed make confirming to IS:9862-
1981 on welded area upto 10cm on either side including on the underside of rail foot
by brush including surface preparation as per Railway's AT Weld Manual including
lettering / weld numbering with approved enamel paint as directed
Note: Before painting, dust, loose rust and mill scale and dirt shall be removed
thoroughly by wire brushing.Scrubbing welded area with water to make it free from
slag and other water soluble compounds to make it dry.
137060 Anti-corrosive painting to weld collar for Thermit welded rail joints on track for old
painted joints in normal corrosive prone area for any rail section with two coats of
ready mixed bitumenous black paint of reputed make confirming to IS:9862-1981 on
welded area upto 10cm on either side including on the underside of rail foot by brush
including surface preparation as per Railway's AT Weld Manual including lettering /
weld numbering with approved enamel paint as directed
Note:
1.Before painting, dust,dirt and flaked paint from the welded joint shall be removed
thoroughly by scrapping with wire brush. Grease and oil shall be removed by use of
appropriate solvent confirming to IS Specification 1745-1976.
2.Use of detergent followed by water washing should also be done to ensure
removal of oil and grease apart from the greasing compound.
3.The paint should be procured along with the thinner recommoned by the
manufacturer of the paint.
4.No other thinner like kerosine oil should be used.
137070 Anti-corrosive painting to weld collar for Thermit welded rail joints on track or on cess
for new welded joints to protect against severe corrsion for any rail section with one
coat of high build epoxy paint (two pack) of reputed make confirming to RDSO
Specification M&C/PCN-111/99 on welded area upto 10cm on either side including
on the underside of rail foot by brush including surface preparation as per Railway's
AT Weld Manual including lettering / weld numbering with approved enamel paint as
directed
Note:
Befor painting,dust,loose rust and mill scale and dirt shall be removed thoroughly by
wire brushing.Scrubbing welded area with water to make it free from slag and other
water soluble compounds to make it dry.
137080 Anti-corrosive painting to weld collar for Thermit welded rail joints on track for old
painted joints in severe corrosive prone area for any rail section with one coat of high
build epoxy paint (two pack) of reputed make confirming to RDSO Specification
M&C/PCN-111/99 on welded area upto 10cm on either side including on the
underside of rail foot by brush including surface preparation as per Railway's AT
Weld Manual including lettering / weld numbering with approved enamel paint as
directed
Note:
1.Before painting, dust,dirt and flaked paint from the welded joint shall be removed
thoroughly by scrapping with wire brush. Grease and oil shall be removed by use of
appropriate solvent confirming to IS Specification 1745-1976.
2.Use of detergent followed by water washing should also be done to ensure removal
of oil and grease apart from the greasing compound.
3.The paint should be procured along with the thinner recommoned by the
manufacturer of the paint
4.No othe thinner like kerosine oil should be used
137090 Marking, inscribing, painting, writing, bordering etc. on new / old iron surface at
various locations of Points & Crossings with details of turn-in / turn-out reference
station mark on rail web for one set, duly preparing surface with contractor's wire
brush and applying two coats of yellow synthetic enamel paint of approved quality as
background and stenciling the details to suitable size, as described for every curve
reference station mark / switch / crossing details with black enamel paint of approved
quality complete, as directed :
Note: Stenciling of letters is only permitted. No hand written letters are accepted.
137091 1 in 16 Turnout
Details of cost for 2 sets. (Yellow & Black paint)
Material:
Enamel Paint as per RDSO's Spec. no.M&C/PCN/120-2011 Litre 0306 190.00 4.00 760.00
Cotton Jute Kg 0494 40.00 0.50 20.00
Soft Brush for painting - 25cm long Each 0314 33.00 0.50 16.50
Paint Brush (writing) of any size Each 0315 150.00 0.50 75.00
Wire Brush - 25cm long Each 0313 15.00 2.00 30.00
Labour:
Painter (Skilled) Day 0012 609.00 1.00 609.00
Helper (Semi-skilled) Day 0021 505.00 1.00 505.00
Labour Unskilled Day 0020 431.00 1.00 431.00
Misc.:
T&P Lumpsum 9901 1.00 10.00 10.00
2,456.50
Add for Water Charges @ 1% Lumpsum 9902 0.01 24.57
2,481.07
Add for GST @ 12% (multiplying factor 0.1405) Lumpsum 9903 0.14 348.59
2,829.65
Add for Contractor’s Overheads and Profit @ 15% Lumpsum 9904 0.15 424.45
3,254.10
Add for Cess @ 1% Lumpsum 9905 0.01 32.54
Cost for 2 sets. 3,286.64
Rate per set Set 1,643.32
137092 1 in 12 Turnout
Details of cost for 3 sets. (Yellow & Black paint)
Material:
Enamel Paint as per RDSO's Spec. no.M&C/PCN/120-2011 Litre 0306 190.00 4.00 760.00
Cotton Jute Kg 0494 40.00 0.50 20.00
Paint Brush 25 mm Each 0327 20.00 0.50 10.00
Paint Brush (writing) of any size Each 0315 150.00 0.50 75.00
Wire Brush - 25cm long Each 0313 15.00 2.00 30.00
Labour:
Painter (Skilled) Day 0012 609.00 1.00 609.00
Helper (Semi-skilled) Day 0021 505.00 1.00 505.00
Labour Unskilled Day 0020 431.00 1.00 431.00
Misc.:
T&P Lumpsum 9901 1.00 10.00 10.00
2,450.00
Add for Water Charges @ 1% Lumpsum 9902 0.01 24.50
2,474.50
Add for GST @ 12% (multiplying factor 0.1405) Lumpsum 9903 0.14 347.67
2,822.17
Add for Contractor’s Overheads and Profit @ 15% Lumpsum 9904 0.15 423.33
3,245.49
Add for Cess @ 1% Lumpsum 9905 0.01 32.45
Cost for 3 sets. 3,277.95
Rate per set Set 1,092.65
137093 1 in 8½ Turnout
Details of cost for 5 sets. (Yellow & Black paint)
Material:
Draft IR Unified Standard Analysis of Rates - 2021 Chapter - 13: Maintenance Activities
137100 Painting 2 coats to various P.Way Reference Post, Structures etc. with enamel paint
of approved make with 2 coats of different colours & letters, as directed by Engineer
in-charge.
Material:
Enamel Paint as per RDSO's Spec. no.M&C/PCN/120-2011 Litre 0306 190.00 2.50 475.00
Luminous Paint as per RDSO's Spec. no. M&C/PCN/120-2011 Litre 0299 300.00 0.20 60.00
Soft Brush for painting - 25cm long Each 0314 33.00 1.00 33.00
Paint Brush (writing) of any size Each 0315 150.00 0.50 75.00
Labour:
Painter (Skilled) Day 0012 609.00 1.00 609.00
Misc.:
T&P Lumpsum 9901 1.00 10.00 10.00
1,262.00
Draft IR Unified Standard Analysis of Rates - 2021 Chapter - 13: Maintenance Activities
137110 Curve details, SE, Versine, Station Nos. etc. per station.
Details of cost for 75 Stn.(2.0 ltr yellow & 1.0 ltr black paint reqd.)
Material:
Enamel Paint as per RDSO's Spec. no.M&C/PCN/120-2011 Litre 0306 190.00 3.00 570.00
Cotton Jute Kg 0494 40.00 0.50 20.00
Wire Brush - 25cm long Each 0313 15.00 2.00 30.00
Soft Brush for painting - 25cm long Each 0314 33.00 0.50 16.50
Paint Brush (writing) of any size Each 0315 150.00 0.25 37.50
Labour:
Painter (Skilled) Day 0012 609.00 1.00 609.00
Helper (Semi-skilled) Day 0021 505.00 1.00 505.00
Look Out Man (Un-skilled) Day 0033 431.00 1.00 431.00
Labour Unskilled Day 0020 431.00 1.00 431.00
T&P Lumpsum 9901 1.00 10.00 10.00
Draft IR Unified Standard Analysis of Rates - 2021 Chapter - 13: Maintenance Activities
137120 Painting 2 coats to Bridge Reference / Boards, Structures etc. along track with
enamel paint of approved make with different colours & letters, as directed by
Engineer in-charge.
137121 Bridge Board
Details of cost for 10 bridge boards (1.5 ltr White & 0.50 ltr black paint reqd.)
Material:
Enamel Paint as per RDSO's Spec. no.M&C/PCN/120-2011 Litre 0306 190.00 2.00 380.00
Soft Brush for painting - 25cm long Each 0314 33.00 1.00 33.00
Paint Brush (writing) of any size Each 0315 150.00 0.50 75.00
Labour:
Painter (Skilled) Day 0012 609.00 1.00 609.00
Misc.:
T&P Lumpsum 9901 1.00 10.00 10.00
1,107.00
Add for Water Charges @ 1% Lumpsum 9902 0.01 11.07
1,118.07
Add for GST @ 12% (multiplying factor 0.1405) Lumpsum 9903 0.14 157.09
1,275.16
Add for Contractor’s Overheads and Profit @ 15% Lumpsum 9904 0.15 191.27
1,466.43
Add for Cess @ 1% Lumpsum 9905 0.01 14.66
Cost for 10 Boards 1,481.10
Rate per board Each 148.11
Details of cost for 9 Sqm i.e. Considering 6 Boards of size 1.5m x 1.0m each (
required 1.50 ltr white / yellow & 0.50 ltr black paint )
Material:
Enamel Paint as per RDSO's Spec. no.M&C/PCN/120-2011 Litre 0306 190.00 2.00 380.00
Soft Brush for painting - 25cm long Each 0314 33.00 1.00 33.00
Paint Brush (writing) of any size Each 0315 150.00 0.50 75.00
Labour:
Painter (Skilled) Day 0012 609.00 0.25 152.25
Helper (Semi-skilled) Day 0021 505.00 0.25 126.25
T&P Lumpsum 9901 1.00 10.00 10.00
776.50
Add for Water Charges @ 1% Lumpsum 9902 0.01 7.77
784.27
Add for GST @ 12% (multiplying factor 0.1405) Lumpsum 9903 0.14 110.19
894.45
Add for Contractor’s Overheads and Profit @ 15% Lumpsum 9904 0.15 134.17
1,028.62
Add for Cess @ 1% Lumpsum 9905 0.01 10.29
Cost for 9 Sqm 1,038.91
Rate per Sqm Sqm 115.43
Draft IR Unified Standard Analysis of Rates - 2021 Chapter - 13: Maintenance Activities
141020 Carrying out Through USFD testing of running rails & welds (excluding flange testing)
including level crossings, lead portion of points and crossings, hand probing of
machined portion of tongue rail, hand probing of machined portion of SEJ and
scabbed rail testing of all types of rails by NBC (Need Based Concept) method under
traffic conditions as per provisions of IR’s "USFD Manual & Specifications for
Ultrasonic Testing of Rails and Welds" with latest correction slips & related
instructions, duly marking defects, submission of daily reports and storing back-up
data, as specified & directed.
Note:
0
The SRT/DRT machine should have minimum of 9 probes (including 37 forward
/backward probe for detecting bolt hole cracks.
141022 With Railway's USFD machine including related T&P and probes
Detail of cost for 3 TKM
Material:
Enamel Paint as per RDSO's Spec. no.M&C/PCN/120-2011 Litre 0306 190.00 0.15 28.50
Paint Brush 25 mm Each 0327 20.00 0.25 5.00
Cotton Jute Kg 0494 40.00 0.20 8.00
Labour:
USFD Operator (With approved Certificate) Day 0043 1500.00 2.00 3,000.00
Helper (Semi-skilled) Day 0021 505.00 2.00 1,010.00
Look Out Man (Un-skilled) Day 0033 431.00 1.00 431.00
Labour Unskilled Day 0020 431.00 4.00 1,724.00
Allowances for carraiage of equipment and Travel/Stay for the team @ 50% labour 3,082.50
cost
Misc.:
T & P (Training charges at LKO and Transportation of machinery) Lumpsum 9901 1.00 400.00 400.00
9,689.00
Add for Water Charges @ 1% Lumpsum 9902 0.01 96.89
9,785.89
Add for GST @ 12% (multiplying factor 0.1405) Lumpsum 9903 0.14 1,374.92
11,160.81
Add for Contractor’s Overheads and Profit @ 15% Lumpsum 9904 0.15 1,674.12
12,834.93
Add for Cess @ 1% Lumpsum 9905 0.01 128.35
Cost for 3 TKM 12,963.28
Rate per TRM TRM 4.32
142011 Track having upto 3 rail panels - With Contractor’s USFD machine :
Details of cost for 55 welds
Material:
Enamel Paint as per RDSO's Spec. no.M&C/PCN/120-2011 Litre 0306 190.00 0.20 38.00
Sand Paper Nos. 0496 5.00 8.00 40.00
Paint Brush 25 mm Each 0327 20.00 0.25 5.00
Wire Brush - 25cm long Each 0313 15.00 1.00 15.00
Cotton Jute Kg 0494 40.00 1.00 40.00
Draft IR Unified Stadard Analysis of Rates - 2021 Chapter - 14: Testing of Rails and Other Components
142012 Track having more than 3 Rail panels - With Contractor’s USFD machine.
Details of cost for 60 welds
Material:
Enamel Paint as per RDSO's Spec. no.M&C/PCN/120-2011 Litre 0306 190.00 0.20 38.00
Sand Paper Nos. 0496 5.00 8.00 40.00
Paint Brush 25 mm Each 0327 20.00 0.25 5.00
Wire Brush - 25cm long Each 0313 15.00 1.00 15.00
Cotton Jute Kg 0494 40.00 1.00 40.00
Labour:
USFD Operator (With approved Certificate) Day 0043 1500.00 2.00 3,000.00
Helper (Semi-skilled) Day 0021 505.00 2.00 1,010.00
Look Out Man (Un-skilled) Day 0033 431.00 1.00 431.00
Labour Unskilled Day 0020 431.00 3.00 1,293.00
Misc.:
T & P (Training charges at LKO and Transportation of machinery) Lumpsum 9901 1.00 200.00 200.00
Hire charges of USFD testing machine Day 0129 800.00 1.00 800.00
6,872.00
Add for Water Charges @ 1% Lumpsum 9902 0.01 68.72
6,940.72
Add for GST @ 12% (multiplying factor 0.1405) Lumpsum 9903 0.14 975.17
7,915.89
Add for Contractor’s Overheads and Profit @ 15% Lumpsum 9904 0.15 1,187.38
9,103.27
Add for Cess @ 1% Lumpsum 9905 0.01 91.03
Cost for 60 welds 9,194.31
Rate per weld Each 153.24
142013 Track having upto 3 rail panels - With Railways’ USFD machine including related
T&P and probes :
Details of cost for 55 welds
Material:
Enamel Paint as per RDSO's Spec. no.M&C/PCN/120-2011 Litre 0306 190.00 0.20 38.00
Sand Paper Nos. 0496 5.00 8.00 40.00
Paint Brush 25 mm Each 0327 20.00 0.25 5.00
Wire Brush - 25cm long Each 0313 15.00 1.00 15.00
Cotton Jute Kg 0494 40.00 1.00 40.00
Labour:
USFD Operator (With approved Certificate) Day 0043 1500.00 2.00 3,000.00
Helper (Semi-skilled) Day 0021 505.00 2.00 1,010.00
Look Out Man (Un-skilled) Day 0033 431.00 1.00 431.00
Labour Unskilled Day 0020 431.00 3.00 1,293.00
Misc.:
T & P (Training charges at LKO and Transportation of machinery) Lumpsum 9901 1.00 200.00 200.00
6,072.00
Draft IR Unified Stadard Analysis of Rates - 2021 Chapter - 14: Testing of Rails and Other Components
142014 Track having more than 3 rail panels - With Railways’ USFD machine including
related T&P and probes :
Details of cost for 60 welds
Material:
Enamel Paint as per RDSO's Spec. no.M&C/PCN/120-2011 Litre 0306 190.00 0.20 38.00
Sand Paper Nos. 0496 5.00 8.00 40.00
Paint Brush 25 mm Each 0327 20.00 0.25 5.00
Wire Brush - 25cm long Each 0313 15.00 1.00 15.00
Cotton Jute Kg 0494 40.00 1.00 40.00
Labour:
USFD Operator (With approved Certificate) Day 0043 1500.00 2.00 3,000.00
Helper (Semi-skilled) Day 0021 505.00 2.00 1,010.00
Look Out Man (Un-skilled) Day 0033 431.00 1.00 431.00
Labour Unskilled Day 0020 431.00 3.00 1,293.00
Misc.:
T & P (Training charges at LKO and Transportation of machinery) Lumpsum 9901 1.00 100.00 100.00
5,972.00
Add for Water Charges @ 1% Lumpsum 9902 0.01 59.72
6,031.72
Add for GST @ 12% (multiplying factor 0.1405) Lumpsum 9903 0.14 847.46
6,879.18
Add for Contractor’s Overheads and Profit @ 15% Lumpsum 9904 0.15 1,031.88
7,911.05
Add for Cess @ 1% Lumpsum 9905 0.01 79.11
Cost for 60 welds 7,990.16
Rate per weld Each 133.17
143011 Track having upto 3 rail panels - With Contractor’s USFD machine :
Details of cost for 55 welds
Material:
Sand Paper Nos. 0496 5.00 8.00 40.00
Cotton Jute Kg 0494 40.00 1.00 40.00
Enamel Paint as per RDSO's Spec. no.M&C/PCN/120-2011 Litre 0306 190.00 0.20 38.00
Wire Brush - 25cm long Each 0313 15.00 1.00 15.00
Paint Brush 25 mm Each 0327 20.00 0.25 5.00
Labour:
USFD Operator (With approved Certificate) Day 0043 1500.00 2.00 3,000.00
Draft IR Unified Stadard Analysis of Rates - 2021 Chapter - 14: Testing of Rails and Other Components
143012 Track having more than 3 rail panels - With Contractor’s USFD machine :
Details of cost for 60 welds
Material:
Sand Paper Nos. 0496 5.00 8.00 40.00
Cotton Jute Kg 0494 40.00 1.00 40.00
Enamel Paint as per RDSO's Spec. no.M&C/PCN/120-2011 Litre 0306 190.00 0.20 38.00
Wire Brush - 25cm long Each 0313 15.00 1.00 15.00
Paint Brush 25 mm Each 0327 20.00 0.25 5.00
Labour:
USFD Operator (With approved Certificate) Day 0043 1500.00 2.00 3,000.00
Helper (Semi-skilled) Day 0021 505.00 2.00 1,010.00
Look Out Man (Un-skilled) Day 0033 431.00 1.00 431.00
Labour Unskilled Day 0020 431.00 4.00 1,724.00
Misc.:
Training charges at LKO and Transportation of machinery Lumpsum 9901 1.00 200.00 200.00
Hire charges of USFD testing machine Day 0129 800.00 1.00 800.00
7,303.00
Add for Water Charges @ 1% Lumpsum 9902 0.01 73.03
7,376.03
Add for GST @ 12% (multiplying factor 0.1405) Lumpsum 9903 0.14 1,036.33
8,412.36
Add for Contractor’s Overheads and Profit @ 15% Lumpsum 9904 0.15 1,261.85
9,674.22
Add for Cess @ 1% Lumpsum 9905 0.01 96.74
Cost for 60 welds 9,770.96
Rate per weld Each 162.85
143013 Track having upto 3 rail panels -With Railway's USFD machine including related T&P
and probes :
Details of cost for 55 welds
Material:
Sand Paper Nos. 0496 5.00 8.00 40.00
Cotton Jute Kg 0494 40.00 1.00 40.00
Enamel Paint as per RDSO's Spec. no.M&C/PCN/120-2011 Litre 0306 190.00 0.20 38.00
Wire Brush - 25cm long Each 0313 15.00 1.00 15.00
Paint Brush 25 mm Each 0327 20.00 0.25 5.00
Labour:
USFD Operator (With approved Certificate) Day 0043 1500.00 2.00 3,000.00
Helper (Semi-skilled) Day 0021 505.00 2.00 1,010.00
Look Out Man (Un-skilled) Day 0033 431.00 1.00 431.00
Labour Unskilled Day 0020 431.00 4.00 1,724.00
Misc.:
Training charges at LKO and Transportation of machinery Lumpsum 9901 1.00 200.00 200.00
6,503.00
Add for Water Charges @ 1% Lumpsum 9902 0.01 65.03
6,568.03
Draft IR Unified Stadard Analysis of Rates - 2021 Chapter - 14: Testing of Rails and Other Components
143014 Track having more than 3 rail panels - With Railway's USFD machine including
related T&P and probes :
Details of cost for 60 welds
Material:
Sand Paper Nos. 0496 5.00 8.00 40.00
Cotton Jute Kg 0494 40.00 1.00 40.00
Enamel Paint as per RDSO's Spec. no.M&C/PCN/120-2011 Litre 0306 190.00 0.20 38.00
Wire Brush - 25cm long Each 0313 15.00 1.00 15.00
Paint Brush 25 mm Each 0327 20.00 0.25 5.00
Labour:
USFD Operator (With approved Certificate) Day 0043 1500.00 2.00 3,000.00
Helper (Semi-skilled) Day 0021 505.00 2.00 1,010.00
Look Out Man (Un-skilled) Day 0033 431.00 1.00 431.00
Labour Unskilled Day 0020 431.00 4.00 1,724.00
Misc.:
Training charges at LKO and Transportation of machinery Lumpsum 9901 1.00 200.00 200.00
6,503.00
Add for Water Charges @ 1% Lumpsum 9902 0.01 65.03
6,568.03
Add for GST @ 12% (multiplying factor 0.1405) Lumpsum 9903 0.14 922.81
7,490.84
Add for Contractor’s Overheads and Profit @ 15% Lumpsum 9904 0.15 1,123.63
8,614.46
Add for Cess @ 1% Lumpsum 9905 0.01 86.14
Cost for 60 welds 8,700.61
Cost for 1 weld Each 145.01
144012 With Railway's USFD machine including related T&P and probes
Details of cost for 8 set SEJ'S
Material:
Kerosene Oil Litre 0185 56.00 4.00 224.00
Enamel Paint as per RDSO's Spec. no.M&C/PCN/120-2011 Litre 0306 190.00 0.15 28.50
Wire Brush - 25cm long Each 0313 15.00 1.00 15.00
Cotton Jute Kg 0494 40.00 2.00 80.00
Paint Brush 25 mm Each 0327 20.00 0.25 5.00
Labour:
USFD Operator (With approved Certificate) Day 0043 1500.00 2.00 3,000.00
Helper (Semi-skilled) Day 0021 505.00 2.00 1,010.00
Look Out Man (Un-skilled) Day 0033 431.00 1.00 431.00
Labour Unskilled Day 0020 431.00 4.00 1,724.00
Misc.:
T & P (Training charges at LKO and Transportation of machinery) Lumpsum 9901 1.00 200.00 200.00
6,717.50
Add for Water Charges @ 1% Lumpsum 9902 0.01 67.18
6,784.68
Add for GST @ 12% (multiplying factor 0.1405) Lumpsum 9903 0.14 953.25
7,737.92
Add for Contractor’s Overheads and Profit @ 15% Lumpsum 9904 0.15 1,160.69
8,898.61
Add for Cess @ 1% Lumpsum 9905 0.01 88.99
Cost for 8 set SEJ'S 8,987.60
Rate per set Set 1,123.45
144020 Providing an assiting gang comprising of 4 men per day with SSE/P.Way/ USFD for
carrying out ancillary works viz., lookout, watering, paint marking and handling
machine for USFD test with Single Rail Testor (SRT) machine and as directed by
Engineer incharge.
Note:
1. This item shall be operated only when there is no departmental staff available and
only with the prior approval of concerned Sr. DEN/Co-ordination.
2. In case, contractor provides less no. of Labour, payment will be deducted for each
such person @ 50% of the accepted item rate.
151020 Assembling of 13m / 12.6m long track panels in PQRS Depot by spreading PSC
sleepers already unloaded and stacked, to correct spacing as per specified sleeper
density per km, using portal crane, placing service rails on them and fixing rails to
sleepers with standard fastening properly to get correct gauge with all contractor’s
labour, tools, plants etc.
Draft IR Unified Stadard Analysis of Rates - 2021 Chapter - 15: Heavy Track Machines
Labour:
Mate (Skilled) Day 0002 609.00 1.00 609.00
Helper (Semi-skilled) Day 0021 505.00 2.00 1,010.00
Labour Unskilled Day 0020 431.00 26.00 11,206.00
Misc.:
T & P (Beater, Rail tongue, Hammer, Crow bars, Tommy bar etc.) Lumpsum 9901 1.00 36.00 36.00
12,861.00
Add for Water Charges @ 1% Lumpsum 9902 0.01 128.61
12,989.61
Add for GST @ 12% (multiplying factor 0.1405) Lumpsum 9903 0.14 1,825.04
14,814.65
Add for Contractor’s Overheads and Profit @ 15% Lumpsum 9904 0.15 2,222.20
17,036.85
Add for Cess @ 1% Lumpsum 9905 0.01 170.37
Cost for 520 TRM 17,207.22
Rate per TRM TRM 33.09
151030 Loading pre-assembled panels of PSC sleepers in layers on BFR with portal crane in
PQRS Depot, complete in such a manner that it may be dispatched in train formation
to mid section, as directed by engineer in-charge.
151040 PQRS:Pre Block activity:Removing of the existing ballast from crib portion of the full
length of existing PSC sleeper and further up to the bottom of sleepers to
accomadate new sleeper and dumping the ballast so removed on the
shoulders/cess with contractor own labour, tools and plants etc, complete with all
lead and lift and as directed by the Engineer-in-charge at site including crossing of
track wherever necessary.
151050 PQRS:During line block activity: Dismantling existing track, levelling disturbed and
uneven surface of bed up to bottom of sleeper, Loading the released panels in to
BFR with Railway's portal cranes, Placing new panels from BFRs on to track with
Railway's portal crane, Linking of Track with all fittings, placing ballst as required in
crib and shoulders, aligning and surfacing of track, attending track parametres and
initial packing to track to allow traffic at restricted speed of 20 kmph with contractors
own labour, tools etc, complete and lead & lift as directed by the Engineer-in-charge
at site including crossing of track wherever necessary.
Note: The PQRS cranes with fuel and operators will be provided by Railway.
151060 PQRS:Post Block activity, Pulling back the left over ballast from shoulders/cess in to
track and dumping in cribs and shoulders, regulating and boxing with available
ballast to facilitate surfacing of track during lifting.with contractors own labour, tools
etc, complete and lead & lift as directed by the Engineer-in-charge at site including
crossing of track wherever necessary.
151070 Unloading of released track panels consisting of all types of rails & sleepers from
Railway wagon at PQRS Depot, using portal cranes including dismantling of released
panels to rails, sleepers & fastenings and stacking them material-wise and
classification-wise at nominated locations within the yard limits with all leads, lift and
crossing of tracks.
Labour:
Mate (Skilled) Day 0002 609.00 1.00 609.00
Helper (Semi-skilled) Day 0021 505.00 2.00 1,010.00
Labour Unskilled Day 0020 431.00 2.00 862.00
For dismantling panels & stacking in a countable manner
Labour Unskilled Day 0020 431.00 15.00 6,465.00
Misc.:
T & P (Beater, Rail tounge, Hammer, Crow bars, Tami bar etc.) Lumpsum 9901 1.00 48.00 48.00
Hire charges of 12 MT Hydra Day 0090 5000.00 1.00 5,000.00
13,994.00
Add for Water Charges @ 1% Lumpsum 9902 0.01 139.94
14,133.94
Add for GST @ 12% (multiplying factor 0.1405) Lumpsum 9903 0.14 1,985.82
16,119.76
Add for Contractor’s Overheads and Profit @ 15% Lumpsum 9904 0.15 2,417.96
18,537.72
Add for Cess @ 1% Lumpsum 9905 0.01 185.38
Draft IR Unified Stadard Analysis of Rates - 2021 Chapter - 15: Heavy Track Machines
151072 With Railway’s portal crane for other than PSC sleeper track
Details of cost for 520 TRM by 2 portal cranes [ On each portal crane one helper
(semi skilled ) for operation of crane, 1 person for assistance during work ]
Labour:
Mate (Skilled) Day 0002 609.00 1.00 609.00
Helper (Semi-skilled) Day 0021 505.00 2.00 1,010.00
Labour Unskilled Day 0020 431.00 2.00 862.00
For dismantling panels & stacking in a countable manner
Labour Unskilled Day 0020 431.00 20.00 8,620.00
Misc.:
T & P (Beater, Rail tounge, Hammer, Crow bars, Tami bar etc.) Lumpsum 9901 1.00 48.00 48.00
11,149.00
Add for Water Charges @ 1% Lumpsum 9902 0.01 111.49
11,260.49
Add for GST @ 12% (multiplying factor 0.1405) Lumpsum 9903 0.14 1,582.10
12,842.59
Add for Contractor’s Overheads and Profit @ 15% Lumpsum 9904 0.15 1,926.39
14,768.98
Add for Cess @ 1% Lumpsum 9905 0.01 147.69
Details of cost for 520 TRM 14,916.67
Rate per TRM TRM 28.69
Labour:
Mate (Skilled) Day 0002 609.00 1.00 609.00
Helper (Semi-skilled) Day 0021 505.00 2.00 1,010.00
Labour Unskilled Day 0020 431.00 2.00 862.00
For dismantling panels & stacking in a countable manner
Labour Unskilled Day 0020 431.00 30.00 12,930.00
Misc.:
T & P (Beater, Rail tounge, Hammer, Crow bars, Tami bar etc.) Lumpsum 9901 1.00 48.00 48.00
Hire charges of Portal Crane (with Fuel & Driver) Hour 0159 250.00 16.00 4,000.00
19,459.00
Add for Water Charges @ 1% Lumpsum 9902 0.01 194.59
19,653.59
Add for GST @ 12% (multiplying factor 0.1405) Lumpsum 9903 0.14 2,761.33
22,414.92
Add for Contractor’s Overheads and Profit @ 15% Lumpsum 9904 0.15 3,362.24
25,777.16
Add for Cess @ 1% Lumpsum 9905 0.01 257.77
Details of cost for 390 TRM 26,034.93
Rate per TRM TRM 66.76
151074 With contractor’s portal crane for other than PSC sleeper track
Details of cost for 520 TRM by 2 portal cranes [ On each portal crane one helper (
Labour:
Mate (Skilled) Day 0002 609.00 1.00 609.00
Helper (Semi-skilled) Day 0021 505.00 2.00 1,010.00
Labour Unskilled Day 0020 431.00 2.00 862.00
For dismantling panels & stacking in a countable manner
Labour Unskilled Day 0020 431.00 20.00 8,620.00
Misc.:
Draft IR Unified Stadard Analysis of Rates - 2021 Chapter - 15: Heavy Track Machines
151080 Mechanical / Manual loading of all types of rails on BFRs in PQRS Depot, as directed
by engineer in-charge.
151090 Doing various miscellaneous works for Railway's PQRS cranes (one set of 2 portals)
for proper upkeep of crew rest van / rest room, as directed by the machine in-charge
by :
(1) Fuelling the machine, duly bringing diesel / hydraulic oil from the stacked drums;
(2) Bringing water to the staff rest van or staff rest room, cleaning rest van / rest
room, cooking food for Track Machine staff or bringing food from outside (cost of
food shall be borne by the staff concerned).
Details of cost for 1 day for one Machine / Crew rest van
Labour:
Labour Unskilled Day 0020 431.00 1.00 431.00
Waterman (Un-skilled) Day 0034 431.00 1.00 431.00
Misc.:
T&P Lumpsum 9901 1.00 10.00 10.00
872.00
Add for Water Charges @ 1% Lumpsum 9902 0.01 8.72
880.72
Add for GST @ 12% (multiplying factor 0.1405) Lumpsum 9903 0.14 123.74
1,004.46
Add for Contractor’s Overheads and Profit @ 15% Lumpsum 9904 0.15 150.67
1,155.13
Add for Cess @ 1% Lumpsum 9905 0.01 11.55
Cost for per day for one machine / crew rest van 1,166.68
Cost for Per day per machine / crew rest van Day 1,166.68
151100 Guarding and watching the Track machine / group of machines, spare parts, oils,
grease etc. of PQRS cranes (one set of 2 portals) during day and night time in a shift
of 12 hours each, at all locations wherever necessary, as instructed by the machine
in-charge.
Note: One shift comparises of 12 hours.
Details of cost for 1 day for Guarding & watching Track machine / Group of machines
considering 2 chowkidars for 1 day i.e. (12 hr's Shift)
Labour:
Chowkidar (Semi skilled) Day 0039 505.00 2.00 1,010.00
Misc.:
T&P Lumpsum 9901 1.00 10.00 10.00
1,020.00
Add for Water Charges @ 1% Lumpsum 9902 0.01 10.20
1,030.20
Add for GST @ 12% (multiplying factor 0.1405) Lumpsum 9903 0.14 144.74
1,174.94
Add for Contractor’s Overheads and Profit @ 15% Lumpsum 9904 0.15 176.24
1,351.18
Add for Cess @ 1% Lumpsum 9905 0.01 13.51
Cost for per day for one track machine / group of machines 1,364.70
Rate per shift Shift 682.35
Draft IR Unified Stadard Analysis of Rates - 2021 Chapter - 15: Heavy Track Machines
151120 In PQRS work, through rail renewal of BG track on PSC sleepers of any density with
all types of rails / rail panels lying in auxiliary track or on cess for replacement of
service rails including handling of rails by way of dragging, pairing etc. and leading
released service rails to load into BFR / Lorry or to shift to next location including
crossing of track with lead & lift and any other incidental works as required.
151122 For rails of more than 13m and upto 40m length
Details of cost for 390 TRM
Labour:
For removal of existing rail and Re fixing the rails taken from auxiliary track
Mate (Skilled) Day 0002 609.00 1.00 609.00
Blacksmith - 1st Class (Skilled) Day 0008 609.00 2.00 1,218.00
Helper (Semi-skilled) Day 0021 505.00 2.00 1,010.00
Waterman (Un-skilled) Day 0034 431.00 1.00 431.00
Labour Unskilled Day 0020 431.00 27.00 11,637.00
For carting of service rails etc.
Labour Unskilled Day 0020 431.00 27.00 11,637.00
Misc.:
T & P (Rail tounge, Spanner, Hammer, Crow bars, Beater etc.) Lumpsum 9901 1.00 116.00 116.00
26,658.00
Add for Water Charges @ 1% Lumpsum 9902 0.01 266.58
26,924.58
Add for GST @ 12% (multiplying factor 0.1405) Lumpsum 9903 0.14 3,782.90
30,707.48
Add for Contractor’s Overheads and Profit @ 15% Lumpsum 9904 0.15 4,606.12
35,313.61
Add for Cess @ 1% Lumpsum 9905 0.01 353.14
Cost for 390 TRM 35,666.74
Rate per TRM TRM 91.45
151130 Through Rail renewal with free service rails of all types by removing existing running
rails, already cut into free rails / rail panels for making auxiliary track, including
attending alignment, cross level, gauging, packing; wherever required including
crossing of track, as directed.
Labour:
Mate (Skilled) Day 0002 609.00 1.00 609.00
Helper (Semi-skilled) Day 0021 505.00 4.00 2,020.00
For providing dunnage (wooden beddings) between layers
Labour Unskilled Day 0020 431.00 4.00 1,724.00
Waterman (Un-skilled) Day 0034 431.00 1.00 431.00
Misc.:
T & P (Beater, Rail tounge, Hammer, Crow bars, Tami bar etc.) Lumpsum 9901 1.00 20.00 20.00
4,804.00
Add for Water Charges @ 1% Lumpsum 9902 0.01 48.04
4,852.04
Add for GST @ 12% (multiplying factor 0.1405) Lumpsum 9903 0.14 681.71
5,533.75
Add for Contractor’s Overheads and Profit @ 15% Lumpsum 9904 0.15 830.06
6,363.81
Add for Cess @ 1% Lumpsum 9905 0.01 63.64
Cost for 1660 sleepers 6,427.45
Rate per sleeper Each 3.87
Labour:
Mate (Skilled) Day 0002 609.00 1.00 609.00
Helper (Semi-skilled) Day 0021 505.00 4.00 2,020.00
For providing dunnage (wooden beddings) between layers
Labour Unskilled Day 0020 431.00 4.00 1,724.00
Waterman (Un-skilled) Day 0034 431.00 1.00 431.00
Misc.:
T & P (Beater, Rail tounge, Hammer, Crow bars, Tami bar etc.) Lumpsum 9901 1.00 20.00 20.00
Hire charges of Portal Crane (with Fuel & Driver) Hour 0159 250.00 16.00 4,000.00
8,804.00
Add for Water Charges @ 1% Lumpsum 9902 0.01 88.04
8,892.04
Add for GST @ 12% (multiplying factor 0.1405) Lumpsum 9903 0.14 1,249.33
10,141.37
Add for Contractor’s Overheads and Profit @ 15% Lumpsum 9904 0.15 1,521.21
11,662.58
Add for Cess @ 1% Lumpsum 9905 0.01 116.63
Cost for 1660 sleepers 11,779.20
Rate per sleeper Each 7.10
152030 Unloading of released sleepers from BRH (special type modified BFR for TRT
working) in Depot by using contractor’s Gantry (Crane) and stacking them at
nominated locations within the yard limits with all leads & lift.
Details of cost for 1660 sleepers by 2 portal cranes [ On each portal crane 1 crane
operator, 1 Assistant crane operator (semi skilled) & 1 helper for operation of crane
during work ]
Draft IR Unified Stadard Analysis of Rates - 2021 Chapter - 15: Heavy Track Machines
153011 1 in 8½ Turnout
Details of cost for 1 set
Labour:
Mate (Skilled) Day 0002 609.00 2.00 1,218.00
Blacksmith - 1st Class (Skilled) Day 0008 609.00 2.00 1,218.00
Helper (Semi-skilled) Day 0021 505.00 2.00 1,010.00
Waterman (Un-skilled) Day 0034 431.00 1.00 431.00
Look Out Man (Un-skilled) Day 0033 431.00 1.00 431.00
(i) Dismantling of Turnout & stacking of released material
Labour Unskilled Day 0020 431.00 20.00 8,620.00
(ii) Removing ballast & muck (Including levelling)
Labour Unskilled Day 0020 431.00 16.00 6,896.00
(iii) Preparation of formation bed for runing T-28
Labour Unskilled Day 0020 431.00 10.00 4,310.00
(iv) After laying of turn out filling the ballast, packing & Fitting of all components of
Labour Unskilled Day 0020 431.00 14.00 6,034.00
Misc.:
T & P (Rail tounge, Crow bars, Hammer, Beater,spanner, pan iron morter etc.) Lumpsum 9901 1.00 140.00 140.00
30,308.00
Add for working under traffic block @ 10% Lumpsum 9992 0.10 3,030.80
33,338.80
Add for Water Charges @ 1% Lumpsum 9902 0.01 333.39
33,672.19
Add for GST @ 12% (multiplying factor 0.1405) Lumpsum 9903 0.14 4,730.94
38,403.13
Add for Contractor’s Overheads and Profit @ 15% Lumpsum 9904 0.15 5,760.47
44,163.60
Draft IR Unified Stadard Analysis of Rates - 2021 Chapter - 15: Heavy Track Machines
153012 1 in 12 Turnout
Details of cost for 1 set
Draft IR Unified Stadard Analysis of Rates - 2021 Chapter - 15: Heavy Track Machines
153013 1 in 16 Turnout
Details of cost for 1 set
Labour:
Mate (Skilled) Day 0002 609.00 2.00 1,218.00
Blacksmith - 1st Class (Skilled) Day 0008 609.00 4.00 2,436.00
Helper (Semi-skilled) Day 0021 505.00 4.00 2,020.00
Waterman (Un-skilled) Day 0034 431.00 1.00 431.00
Look Out Man (Un-skilled) Day 0033 431.00 1.00 431.00
(i) Dismantling of Turnout & stacking of released material
Labour Unskilled Day 0020 431.00 24.00 10,344.00
(ii) Removing ballast & muck (Including levelling)
Labour Unskilled Day 0020 431.00 20.00 8,620.00
(iii) Preparation of formation bed for runing T-28
Labour Unskilled Day 0020 431.00 14.00 6,034.00
(iv) After laying of turn out filling the ballast, packing &Fitting of all components of
Labour Unskilled Day 0020 431.00 18.00 7,758.00
Misc.:
T & P (Rail tounge, Crow bars, Hammer, Beater,spanner, pan iron morter etc.) Lumpsum 9901 1.00 184.00 184.00
39,476.00
Add for working under traffic block @ 10% Lumpsum 9992 0.10 3,947.60
43,423.60
Add for Water Charges @ 1% Lumpsum 9902 0.01 434.24
43,857.84
Add for GST @ 12% (multiplying factor 0.1405) Lumpsum 9903 0.14 6,162.03
50,019.86
Add for Contractor’s Overheads and Profit @ 15% Lumpsum 9904 0.15 7,502.98
57,522.84
Add for Cess @ 1% Lumpsum 9905 0.01 575.23
Rate per set Each 58,098.07
153014 1 in 20 Turnout
Draft IR Unified Stadard Analysis of Rates - 2021 Chapter - 15: Heavy Track Machines
153021 1 in 8½ Switch
Details of cost for 1 set
Labour:
Mate (Skilled) Day 0002 609.00 1.00 609.00
Blacksmith - 1st Class (Skilled) Day 0008 609.00 1.00 609.00
Helper (Semi-skilled) Day 0021 505.00 1.00 505.00
Waterman (Un-skilled) Day 0034 431.00 1.00 431.00
Look Out Man (Un-skilled) Day 0033 431.00 1.00 431.00
(i) Dismantling of Switch & stacking of released material
Labour Unskilled Day 0020 431.00 8.00 3,448.00
(ii) Removing ballast & muck (Including levelling)
Labour Unskilled Day 0020 431.00 6.00 2,586.00
(iii) Preparation of formation bed for runing T-28
Labour Unskilled Day 0020 431.00 4.00 1,724.00
(iv) After laying of turn out filling the ballast & packing
Labour Unskilled Day 0020 431.00 4.00 1,724.00
(v) Fitting of all components of Switch
Labour Unskilled Day 0020 431.00 2.00 862.00
Draft IR Unified Stadard Analysis of Rates - 2021 Chapter - 15: Heavy Track Machines
153022 1 in 12 Switch
Details of cost for 1 set
Labour:
Mate (Skilled) Day 0002 609.00 1.00 609.00
Blacksmith - 1st Class (Skilled) Day 0008 609.00 1.00 609.00
Helper (Semi-skilled) Day 0021 505.00 1.00 505.00
Waterman (Un-skilled) Day 0034 431.00 1.00 431.00
Look Out Man (Un-skilled) Day 0033 431.00 1.00 431.00
(i) Dismantling of Switch & stacking of released material
Labour Unskilled Day 0020 431.00 8.00 3,448.00
(ii) Removing ballast & muck (Including levelling)
Labour Unskilled Day 0020 431.00 6.00 2,586.00
(iii) Preparation of formation bed for runing T-28
Labour Unskilled Day 0020 431.00 6.00 2,586.00
(iv) After laying of turn out filling the ballast & packing
Labour Unskilled Day 0020 431.00 4.00 1,724.00
(v) Fitting of all components of Switch
Labour Unskilled Day 0020 431.00 4.00 1,724.00
Misc.:
T & P (Rail tounge, Crow bars, Hammer, Beater,spanner, pan iron morter etc.) Lumpsum 9901 1.00 60.00 60.00
14,713.00
Add for working under traffic block @ 10% Lumpsum 9992 0.10 1,471.30
16,184.30
Add for Water Charges @ 1% Lumpsum 9902 0.01 161.84
16,346.14
Add for GST @ 12% (multiplying factor 0.1405) Lumpsum 9903 0.14 2,296.63
18,642.78
Add for Contractor’s Overheads and Profit @ 15% Lumpsum 9904 0.15 2,796.42
21,439.19
Add for Cess @ 1% Lumpsum 9905 0.01 214.39
Rate per set Each 21,653.58
153023 1 in 16 Switch
Details of cost for 1 set
Labour:
Mate (Skilled) Day 0002 609.00 1.00 609.00
Blacksmith - 1st Class (Skilled) Day 0008 609.00 2.00 1,218.00
Helper (Semi-skilled) Day 0021 505.00 2.00 1,010.00
Waterman (Un-skilled) Day 0034 431.00 1.00 431.00
Look Out Man (Un-skilled) Day 0033 431.00 1.00 431.00
(i) Dismantling of Switch & stacking of released material
Labour Unskilled Day 0020 431.00 10.00 4,310.00
(ii) Removing ballast & muck (Including levelling)
Labour Unskilled Day 0020 431.00 6.00 2,586.00
(iii) Preparation of formation bed for runing T-28
Draft IR Unified Stadard Analysis of Rates - 2021 Chapter - 15: Heavy Track Machines
153024 1 in 20 Switch
Details of cost for 1 set
Labour:
Mate (Skilled) Day 0002 609.00 1.00 609.00
Blacksmith - 1st Class (Skilled) Day 0008 609.00 2.00 1,218.00
Helper (Semi-skilled) Day 0021 505.00 2.00 1,010.00
Waterman (Un-skilled) Day 0034 431.00 1.00 431.00
Look Out Man (Un-skilled) Day 0033 431.00 1.00 431.00
(i) Dismantling of Switch & stacking of released material
Labour Unskilled Day 0020 431.00 11.00 4,741.00
(ii) Removing ballast & muck (Including levelling)
Labour Unskilled Day 0020 431.00 7.00 3,017.00
(iii) Preparation of formation bed for runing T-28
Labour Unskilled Day 0020 431.00 7.00 3,017.00
(iv) After laying of turn out filling the ballast & packing
Labour Unskilled Day 0020 431.00 6.00 2,586.00
(v) Fitting of all components of Switch
Labour Unskilled Day 0020 431.00 4.00 1,724.00
Misc.:
T & P (Rail tounge, Crow bars, Hammer, Beater,spanner, pan iron morter etc.) Lumpsum 9901 1.00 75.00 75.00
18,859.00
Add for working under traffic block @ 10% Lumpsum 9992 0.10 1,885.90
20,744.90
Add for Water Charges @ 1% Lumpsum 9902 0.01 207.45
20,952.35
Add for GST @ 12% (multiplying factor 0.1405) Lumpsum 9903 0.14 2,943.81
23,896.15
Add for Contractor’s Overheads and Profit @ 15% Lumpsum 9904 0.15 3,584.42
27,480.58
Add for Cess @ 1% Lumpsum 9905 0.01 274.81
Rate per set Each 27,755.38
154020 Carrying out various works during operation of BCM, like filling up of ballast from
available locations (including adjoining tracks), required packing, adjustment of PSC
Sleepers, provision wooden blocks supplied by department and attending track
parameters etc. complete so as to make track fit for 20 kmph speed.
Details of cost for 360 TRM ( 1 group of two persons deputed for 40 metre track )
Labour:
Mate (Skilled) Day 0002 609.00 1.00 609.00
Waterman (Un-skilled) Day 0034 431.00 1.00 431.00
Labour Unskilled Day 0020 431.00 18.00 7,758.00
Draft IR Unified Stadard Analysis of Rates - 2021 Chapter - 15: Heavy Track Machines
154030 Removal of screened muck discharged by BCM, where muck disposal on side slope
is restricted due to platform, cutting, OHE mast etc. and disposing it beyond 5m from
edge of cutting upto 3m deep or alternatively carting it upto 50m for disposing off
beyond the end of cutting / platform and making up cess wherever low.
Details of cost for 520 TRM (1 group of two persons deputed for 52 Track metre )
Labour:
Mate (Skilled) Day 0002 609.00 1.00 609.00
Waterman (Un-skilled) Day 0034 431.00 1.00 431.00
Labour Unskilled Day 0020 431.00 20.00 8,620.00
Misc.:
T & P (Rake ballast, Crow bars, Hammer, Beater etc.) Lumpsum 9901 1.00 40.00 40.00
9,700.00
Add for Water Charges @ 1% Lumpsum 9902 0.01 97.00
9,797.00
Add for GST @ 12% (multiplying factor 0.1405) Lumpsum 9903 0.14 1,376.48
11,173.48
Add for Contractor’s Overheads and Profit @ 15% Lumpsum 9904 0.15 1,676.02
12,849.50
Add for Cess @ 1% Lumpsum 9905 0.01 128.50
Cost for 520 TRM 12,978.00
Rate per TRM TRM 24.96
154040 Removal of screened muck discharged by FRM/SBCM where muck disposal on side
slope is restricted due to platform, cutting, OHE mast etc. and disposing it beyond
5m from edge of cutting upto 3m deep or alternatively carting it upto 50m for
disposing off beyond the end of cutting / platform and making up cess wherever low.
Details of cost for 780 TRM (1 group of two persons deputed for 78 Track metre)
Labour:
Mate (Skilled) Day 0002 609.00 1.00 609.00
Waterman (Un-skilled) Day 0034 431.00 1.00 431.00
Labour Unskilled Day 0020 431.00 20.00 8,620.00
Misc.:
T & P (Rake ballast, Crow bars, Hammer, Beater etc.) Lumpsum 9901 1.00 40.00 40.00
9,700.00
Add for Water Charges @ 1% Lumpsum 9902 0.01 97.00
9,797.00
Add for GST @ 12% (multiplying factor 0.1405) Lumpsum 9903 0.14 1,376.48
11,173.48
Add for Contractor’s Overheads and Profit @ 15% Lumpsum 9904 0.15 1,676.02
12,849.50
Add for Cess @ 1% Lumpsum 9905 0.01 128.50
Cost for 780 RM 12,978.00
Rate per TRM TRM 16.64
Draft IR Unified Stadard Analysis of Rates - 2021 Chapter - 15: Heavy Track Machines
Details of cost for 500 Track Metre (Extra labour element required for additional
average lead of 250 metre for dispoal of muck)(@ one man per 25 TRM)
Labour:
Labour Unskilled Day 0020 431.00 10.00 4,310.00
Misc.:
T&P Lumpsum 9901 1.00 20.00 20.00
4,330.00
Add for Water Charges @ 1% Lumpsum 9902 0.01 43.30
4,373.30
Add for GST @ 12% (multiplying factor 0.1405) Lumpsum 9903 0.14 614.45
4,987.75
Add for Contractor’s Overheads and Profit @ 15% Lumpsum 9904 0.15 748.16
5,735.91
Add for Cess @ 1% Lumpsum 9905 0.01 57.36
Cost for 500 TRM / 250 metres lead 5,793.27
Cost for 500 TRM / every 50 metres lead 1,158.65
Rate per TRM / every 50 metres TRM 2.32
154060 Extra to item nos. from 154030 and 54040 for disposal of muck for additional lift of 1
metre or part thereof beyond 3 metre lift in case of disposal of muck from track in
cutting.
Details of cost for 400 TRM (Extra labour element required for additional average lift
of 3 metre for dispoal of muck)(@ one man per 20 TRM)
Labour:
Labour Unskilled Day 0020 431.00 10.00 4,310.00
Misc.:
T&P Lumpsum 9901 1.00 20.00 20.00
4,330.00
Add for Water Charges @ 1% Lumpsum 9902 0.01 43.30
4,373.30
Add for GST @ 12% (multiplying factor 0.1405) Lumpsum 9903 0.14 614.45
4,987.75
Add for Contractor’s Overheads and Profit @ 15% Lumpsum 9904 0.15 748.16
5,735.91
Add for Cess @ 1% Lumpsum 9905 0.01 57.36
Cost for 400 TRM / 3 metre lift 5,793.27
Cost for 400 TRM / every 1 metre lift 1,931.09
Rate per TRM / every 1 metre lift TRM 4.83
154070 Removing the ballast from shoulders, left over after BCM/SBCM working, screening
the same removing the muck and putting back the screened ballast in track profile,
boxing the ballast to profile and using released muck for cess making or throwing
away within 50m lead and 3m lift when not required for cess repairs and as directed
by the Engineer-in-charge.
Note: This item shall be used only when BRM is not available.
154080 Ballast equalisation & ballast profiling after completion of deep screening work by
BCM and/or after unloading of ballast by DMT (Ballast Train), as directed by Site
Engineer as per IRPWM including heaping of ballast in tamping zone keeping rails &
sleeper top free from ballast, spacing and squaring of sleeper, gauging, cleaning of
muck, proper fixing of fastening, attention during each round of sleeper tamping in
relation to pre & post working
Note:
Payment shall be made only once in irrespective of numbers of TTRM packing round
and after restoration of normal speed and restoration of complete ballast profile and
cess profile.
Details of cost for 200 TRM (1group of two persons deputed for 40 Track metre
Labour:
Mate (Skilled) Day 0002 609.00 0.50 304.50
Labour Unskilled Day 0020 431.00 10.00 4,310.00
Misc.:
T & P (Rake ballast, Crow bars, Beater etc.) Lumpsum 9901 1.00 20.00 20.00
4,634.50
Add for Water Charges @ 1% Lumpsum 9902 0.01 46.35
4,680.85
Add for GST @ 12% (multiplying factor 0.1405) Lumpsum 9903 0.14 657.66
5,338.50
Add for Contractor’s Overheads and Profit @ 15% Lumpsum 9904 0.15 800.78
6,139.28
Add for Cess @ 1% Lumpsum 9905 0.01 61.39
Cost for 200 TRM 6,200.67
Rate per TRM TRM 31.00
154090 Making cess in deep screened track by using screened muck discharged by BCM
where cess is low or cutting cess to required depth upto 4m from centre of track,
where cess is high and disposing off extra muck beyond 5m from edge of cutting
which are upto 3m deep or alternatively carting it upto 50m for disposing it off beyond
cutting or platforms, so as to make cess as per standard profile including providing
proper slope.
Details of cost for 260 TRM (1group of two persons deputed for 26 Track metre for
Labour:
Mate (Skilled) Day 0002 609.00 1.00 609.00
Waterman (Un-skilled) Day 0034 431.00 1.00 431.00
Labour Unskilled Day 0020 431.00 20.00 8,620.00
Misc.:
T&P Lumpsum 9901 1.00 40.00 40.00
9,700.00
Add for Water Charges @ 1% Lumpsum 9902 0.01 97.00
9,797.00
Add for GST @ 12% (multiplying factor 0.1405) Lumpsum 9903 0.14 1,376.48
11,173.48
Add for Contractor’s Overheads and Profit @ 15% Lumpsum 9904 0.15 1,676.02
12,849.50
Add for Cess @ 1% Lumpsum 9905 0.01 128.50
Cost for 260 TRM 12,978.00
Draft IR Unified Stadard Analysis of Rates - 2021 Chapter - 15: Heavy Track Machines
154100 Carrying out Through packing of sleepers to make track fit for 30 KM speed as per
procedure stipulated in latest version of IRPWM, behind BCM including filling ballast
when only lifting is carried out by BCM.
Details of cost for 182 TRM ( 1 Person will do packing including filling the ballast 14
Labour:
Mate (Skilled) Day 0002 609.00 1.00 609.00
Waterman (Un-skilled) Day 0034 431.00 1.00 431.00
Labour Unskilled Day 0020 431.00 20.00 8,620.00
Misc.:
T & P (Rake ballast, Crow bars, Hammer, Beater etc.) Lumpsum 9901 1.00 40.00 40.00
9,700.00
Add for Water Charges @ 1% Lumpsum 9902 0.01 97.00
9,797.00
Add for GST @ 12% (multiplying factor 0.1405) Lumpsum 9903 0.14 1,376.48
11,173.48
Add for Contractor’s Overheads and Profit @ 15% Lumpsum 9904 0.15 1,676.02
12,849.50
Add for Cess @ 1% Lumpsum 9905 0.01 128.50
Cost for 182 TRM 12,978.00
Rate per TRM TRM 71.31
154110 Pulling the left over ballast to the shoulders and dumping excess ballast in the cribs
and shoulders including boxing/profiling as per IRPWM of track together with left over
stretches at fixed structures/masts immediately after FRM work, leveling the muck for
making up cess and side slopes including removing and re-fixing of traction bonds
during line block with all contractors labour, tools, plant, all lead, lift, crossing of track
etc. complete and as directed by the Engineer-in-charge.
III . Post BCM Operation : a) Packing switch portion including Motor long sleeper ie.,
SRJ to heel joint to to reset Point for train movement & initial packing of lead portion
to allow train at 20KMPH and lifting the track in two stages (50mm to 75mm in each
lift) wherever required for correcting the longitudinal surfacing b) Dumping of ballast
in the naked crib portion on main line turnout side for initial packing purpose. c)
Boxing / Levelling of muck duly ensuring levelling of muck on cess side and lowering
of cess to the deep screened depth and removing of muck in between the lines and
leading up to 250mts.
Note:
1. For technical reasons, some of the points and crossings cannot be deep screened
either fully or partially by BCM, in which case, the left over length will be deep
screeniend manually.
2. The length of points and crossings assembly for payment of this item should be
taken from SRJ to longest concrete sleeper available just beyond heel of crossing
along main line..
Details of cost for one Points and crossing 1 in 12 points and Crossings for a length
of 45.50m
Man Power
Mate (Skilled) Day 0002 609.00 0.50 304.50
Blacksmith - 1st Class (Skilled) Day 0008 609.00 0.50 304.50
Helper (Semi-skilled) Day 0021 505.00 1.00 505.00
For Pre Block,Post block & during block activities
Labour Unskilled Day 0020 431.00 10.00 4,310.00
Misc
T&P (no rates reqd.) Lumpsum 9901 1.00 60.00 60.00
5,484.00
Add for Water Charges @ 1% Lumpsum 9902 0.01 54.84
5,538.84
Add for GST @ 12% (multiplying factor 0.1405) Lumpsum 9903 0.14 778.21
6,317.05
Add for Contractor’s Overheads and Profit @ 15% Lumpsum 9904 0.15 947.56
7,264.60
Add for Cess @ 1% Lumpsum 9905 0.01 72.65
Cost for one Points and crossing 1 in 12 points and Crossings for a length of 45.50m 7,337.25
Rate per TRM TRM 161.26
Draft IR Unified Stadard Analysis of Rates - 2021 Chapter - 15: Heavy Track Machines
(9) Removing and re-fixing joggled fish plates & wooden blocks, wherever necessary;
(10) Manual consolidation of ballast in crib / shoulders;
(11) Removing and refixing of traction bonds during the block in electrified sections
(12) Dressing of ballast
Note:
1. Contractor to provide minimum 40 men with 1 supervisor and 2 mates for
carrying out above work.
2. Tamping blocks are not identical & it may be given at any time either during day or
night.
3. Stages of payment a) 30% of the rate will be paid on completion of pre tamping
attention, b) Balance 70% of the rate will be paid on completion of post tamping.
4. Recovery at the rate of twice the above applicable rate will be effected in case
contractor fails to carry out pre/during/post operation.
5.Payment shall be made only once in irrespective of numbers of TTRM packing
round and after restoration of normal speed and restoration of complete ballast
profile.
155020 Pre, during & post tamping operations, for tamping of track on level crossing portion
on all types of track structre and density, during traffic block, duly opening the road
surface by digging up to the required width and up to 50mm below bottom of sleeper
to facilitate tamping, removing and refilling ballast, adustment of deficient ballast if
necessary by picking from adjoining track/shoulder/cribs, removing and refixing all
inter locking gears interfering, removing and re-fixing of check rails and painting of
running rail & check rail with coaltar emulsion, completing road surface to smooth
motorable condition after tamping is over, including tightening of loose fittings,
replacement of broken/missing fittings, correction of displaced sleepers to correct
position and as directed by Engineer incharge.
Draft IR Unified Stadard Analysis of Rates - 2021 Chapter - 15: Heavy Track Machines
155030 Removing and refixing of guard Rails over slab bridges during machine packing with
all contractor's men and materials duly removing fittings, leading guard rails to bridge
approaches, lifting, dragging, positioning and crossing of track etc, and as directed
by Engineer In charge.
156020 Extra Over Item Numbers 156011 to 156015 for night block working
156030 Carrying out pre-tamping, during tamping and post-tamping works prescribed in
current version IRTMM/IRPWM for tamping of Turnouts of all types Under
Conditions not requiring Traffic Block.
For newly assembled turnout on compacted and level ballast bed, precisely laid as
per layout drawing (s) with all new sleepers, fittings and other fixtures; many
activities are not required in comparison to that turnouts over under train operation.
Also there is no obstruction of traffic and no restriction of working hours as required
for work under traffic block, the cost is considered as 60% of the cost turnouts under
operation i.e. 60% of corresponding rates of item nos. 156010.
156031 1 in 8½ Turnouts
Rate as per item no. 156011 156011 7844.33 0.60 4,706.60
Rate per set Set 4,706.60
156032 1 in 12 Turnouts
Rate as per item no. 156012 156012 9124.73 0.60 5,474.84
Rate per set Set 5,474.84
156033 1 in 16 Turnouts
Rate as per item no. 156013 156013 11862.16 0.60 7,117.29
Rate per set Set 7,117.29
156034 1 in 20 Turnouts
Rate as per item no. 156014 156014 12511.19 0.60 7,506.71
Rate per set Set 7,506.71
157000 7. Miscellaneous
157010 Carrying out various miscellaneous works, for proper upkeep of crew rest van / rest
room as directed by machine in-charge of Track Machines by providing a team of 2
labours for 12 hours shift, broadly mentioned hereunder:
(1) Bringing water from nearby source and cleaning machine with water jet or any
suitable means;
(2) Fuelling machine duly bringing diesel / hydraulic oil from the stacked drums;
(3) Bringing water to staff rest van or staff rest room, cleaning rest van / rest room,
cooking food for Track Machine staff or bringing food from outside;
(4) Guarding & watching machines, spare parts, oils, grease etc. during day and
night time at all locations, wherever necessary, as instructed by the machine in-
charge;
(5) Cooking food for Track Machine staff or bringing food from outside (cost of food
shall be borne by the staff concerned).
(6) In case, contractor provides less no. of Labour/Mate, payment will be deducted
for each such person @ 75% of the accepted item rate.
157020 Carrying out ancillary works required for UTV working under line block i.e., turning of
rails/ Sleepers and keeping in position for fixing of UTV clamps to rail, keeping
rails/PSC Sleepers in position while loading into BFR, removal of clamps on BFR for
releasing loaded rail/Sleepers, adjusting of rails/Sleepers on BFR etc. by providing
minimum of three men in a shift of 8 hours, with all contractor's tools, all lead, lift,
crossing of tracks etc., complete and as directed by the engineer - in - charge.
Note: In case, contractor provides less no. of Labour, payment will be deducted for
each such person @ 2/3 rd of the accepted item rate.
157030 Providing lighting arrangements with halogen lamps on and around machine during
machine working in night time blocks, with contractors own generator, consumables,
all necessary electrical fittings, operators etc.
Note:
1. Lighting arrangement is to be provided as per advance planning of Night Blocks
and written communication.
2. In case lighting arrangement is made available but not used due to non-availability
of block, payment @ 60% of the item rate shall be made.
157032 CSM / DUO / 3X with or without DGS (7.5 kVA generator and 8x500 W)
Detail of cost for per night
Materials :
Hire Charges of Halogen Lamps 500 Watt Nos. 0488 40.00 8.00 320.00
Labour:
Electrician (Skilled) Day 0013 609.00 1.00 609.00
Helper (Semi-skilled) Day 0021 505.00 1.00 505.00
Misc.:
T&P Lumpsum 9901 1.00 10.00 10.00
Hire charges of 7.5 KVA Generator Day 0073 1000 1.00 1,000.00
2,444.00
Add for Water Charges @ 1% Lumpsum 9902 0.01 24.44
2,468.44
Add for GST @ 12% (multiplying factor 0.1405) Lumpsum 9903 0.14 346.82
2,815.26
Add for Contractor’s Overheads and Profit @ 15% Lumpsum 9904 0.15 422.29
3,237.54
Add for Cess @ 1% Lumpsum 9905 0.01 32.38
Cost for per night 3,269.92
Rate per night Night 3,269.92
Draft IR Unified Stadard Analysis of Rates - 2021 Chapter - 16: Small Track Machines
As per RDSO SpecificaNo. TM/SM/2 Rev. 01 of 2007) number of cut per disk
is 7. Thus for 60 cuts, number of disk required = 60/7 = 8.5 nos. Say 9 nos.
Abrasive rail cutting disc as per RDSO's Spec. no. TM/SM/2 Each 0459 574.00 9.00 5,166.00
Driving belt (abrasive rail cutter) Each 0460 600.00 1.00 600.00
Normal unleaded Petrol Litre 0182 105.00 8.00 840.00
Labour:
Machinist (operator) (Skilled) Day 0040 609.00 0.50 304.50
Helper (Semi-skilled) Day 0021 505.00 0.50 252.50
Labour Unskilled Day 0020 431.00 2.00 862.00
Misc.:
T & P including consumables Lumpsum 9901 1.00 50.00 50.00
Hire charges of Abrasive Rail Cutter (without POL) Day 0143 300.00 1.00 300.00
8,375.00
Add for Water Charges @ 1% Lumpsum 9902 0.01 83.75
8,458.75
Add for GST @ 12% (multiplying factor 0.1405) Lumpsum 9903 0.14 1,188.45
9,647.20
Add for Contractor’s Overheads and Profit @ 15% Lumpsum 9904 0.15 1,447.08
11,094.29
Add for Cess @ 1% Lumpsum 9905 0.01 110.94
Cost for 60 cuts 11,205.23
Draft IR Unified Stadard Analysis of Rates - 2021 Chapter - 16: Small Track Machines
161020 Cutting of rails with Rail Cutting Machine (Saw type) in all types of rail sections with
contractor's tools & plants, equipment, consumable with all lead & lift etc. complete,
as directed by Engineer in-charge. Rail Cutting Machine (Saw type) will be as per
RDSO Specification No. TM/SM/4, dated 24.04.1991.
Note: This item shall only be used in specific circumstances on specific order of
Engineer-in-Charge.
161030 Cutting of rails with electrically operated Rail Cutting Machine in all types of rail
sections, with contractor's tools & plants, equipment, consumable with all lead & lift
etc. complete, as directed by Engineer in-charge as per Specifications. Machine to
be fitted with monorail wheel arrangement and a handle of convenient height to
enable it to be pushed over one rail by one person to take it to the work-site.
161031 Outside track - When Electricity provided by static power supply of Railway :
Details of cost for 14 cuts
Material:
High Speed Hacksaw Blade of size 300mm x 12.5mm x 0.63mm (18TPI) as per as Nos. 0457 160.00 2.00 320.00
Labour:
Machinist (operator) (Skilled) Day 0040 609.00 0.50 304.50
Helper (Semi-skilled) Day 0021 505.00 0.50 252.50
Labour Unskilled Day 0020 431.00 1.00 431.00
Misc.:
T&P Lumpsum 9901 1.00 20.00 20.00
Hire charges of Electrically operated Rail Cutting Machine Day 0141 100.00 1.00 100.00
1,428.00
Add for Water Charges @ 1% Lumpsum 9902 0.01 14.28
1,442.28
Add for GST @ 12% (multiplying factor 0.1405) Lumpsum 9903 0.14 202.64
1,644.92
Add for Contractor’s Overheads and Profit @ 15% Lumpsum 9904 0.15 246.74
1,891.66
Add for Cess @ 1% Lumpsum 9905 0.01 18.92
Cost for 14 cuts 1,910.57
Rate per cut Each 136.47
161032 On Running track - When Electricity provided by static power supply of Railway :
Details of cost for 14 cuts
Draft IR Unified Stadard Analysis of Rates - 2021 Chapter - 16: Small Track Machines
161040 Drilling holes of 16 mm to 32 mm dia. with Rail Drilling machine in all types of rail
section with contractor's tools & plants, equipment, consumable with all lead & lift
etc. complete, as directed by Engineer in-charge. Rail Drilling Machine will be as per
RDSO Specification No. TM/SM/3, dated 24.04.1991.
161050 Drilling holes of specified size for bond holes with 7.2mm dia drill twist to correct
spacing and location on 60kg/52kg rails on cess or under traffic block with
contractor’s tools and plant, equipment, consumable, labour etc complete as
directed by the Engineer in charge at site.
161060 Drilling holes of 16 mm to 32 mm dia. with electrically operated Rail Drilling Machine
in all types of rail sections, with contractor's tools & plants, equipment, consumable
with all lead & lift etc. complete, as directed by Engineer in-charge as per
Specification.
161061 Outside track - When Electricity provided by static power supply of Railway
Details of cost for 60 holes
Material:
Drill twist made of high speed steel for size 26.5mm dia of Addison / I T make Each 0466 2852.30 0.45 1,283.54
Labour:
Machinist (operator) (Skilled) Day 0040 609.00 0.50 304.50
Helper (Semi-skilled) Day 0021 505.00 0.50 252.50
Labour Unskilled Day 0020 431.00 1.00 431.00
Misc.:
T&P Lumpsum 9901 1.00 20.00 20.00
Hire charges of Electrically operated Rail Drilling Machine Day 0139 200.00 1.00 200.00
Draft IR Unified Stadard Analysis of Rates - 2021 Chapter - 16: Small Track Machines
161062 On Running track- When Electricity provided by static power supply of Railway :
Details of cost for 60 holes
Material:
Drill twist made of high speed steel for size 26.5mm dia of Addison / I T make Each 0466 2852.30 0.45 1,283.54
Labour:
Machinist (operator) (Skilled) Day 0040 609.00 0.50 304.50
Helper (Semi-skilled) Day 0021 505.00 0.50 252.50
Look Out Man (Un-skilled) Day 0033 431.00 1.00 431.00
Labour Unskilled Day 0020 431.00 1.00 431.00
Misc.:
T&P Lumpsum 9901 1.00 20.00 20.00
Hire charges of Electrically operated Rail Drilling Machine Day 0139 200.00 1.00 200.00
2,922.54
Add for Water Charges @ 1% Lumpsum 9902 0.01 29.23
2,951.76
Add for GST @ 12% (multiplying factor 0.1405) Lumpsum 9903 0.14 414.72
3,366.48
Add for Contractor’s Overheads and Profit @ 15% Lumpsum 9904 0.15 504.97
3,871.46
Add for Cess @ 1% Lumpsum 9905 0.01 38.71
Cost for 60 holes 3,910.17
Rate per hole Each 65.17
161070 Bending & De-kinking with Hydraulic rail bender (Jim Crow) heavy duty in all types of
rail sections of flat bottom rails maximum upto 40mm with contractor's tools & plants,
equipment, consumable with all lead & lift etc. complete, as directed by Engineer in-
charge. Hydraulic Rail Bender (Jim Crow) Heavy duty will be as per RDSO
Specification No. TM/SM/5, dated 08.05.1991.
161080 Chamfering of drilled fish bolt holes in rails of any section and any UTS with
chamfering kit and with contractor's tools & plants, equipment, consumable with all
lead & lift etc. complete, as directed by Engineer in-charge. Chamfering Kit will be as
per RDSO's Specification No. TM-53 Rev. 01 of 2004.
161090 Pulling of rail in LWR track by hydraulic rail tensor (Non-infringing type) under traffic
block for maintaining specified gap at rail joints for A.T. welding with contractor's
tools & plant, equipment, consumable with all lead & lift etc. complete, as directed by
Engineer in-charge. Hydraulic Rail Tensor (Non-infringing type) will be as per
RDSO's Specification No. TM/SM/32, dated 20.12.1991.
162000 2. Sleepers :
162010 Sleeper Spacing, Re-spacing / Squaring of sleeper by Hydraulic Sleeper Spacer with
contractor's tools & plants, equipment, consumable with all lead & lift etc. complete,
as directed by Engineer in-charge. Hydraulic Sleeper Spacer shall be as per RDSO's
Specification No. TM/SM/17, dated 31.03.1992.
162020 Drilling of holes (vertically) into concrete sleeper in-situ for fixing guard rails and
check rails on concrete sleeper track at specified locations by concrete sleeper
drilling machine with contractor's tools & plants, equipment, consumable with all lead
& lift etc. complete, as directed by Engineer in-charge as per RDSO's Specification.
162030 Loading / unloading of concrete sleepers from cess to BFR / BRH wagons and vice-
versa by jib crane attachable to BFR / BRH for handling concrete sleepers with
contractor's tools & plants, equipment, consumable with all lead & lift etc. complete,
as directed by Engineer in-charge.
162040 Quick removal of damaged concrete sleepers and restoration of railway track in case
of accidents / derailments and other such emergent situations by Concrete Sleeper
Breaker & angle grinder with contractor's tools & plants, equipments, consumable
etc. with all lead & lift complete, as directed by Engineer in-charge.
163000 3. Fittings :
Draft IR Unified Stadard Analysis of Rates - 2021 Chapter - 16: Small Track Machines
163020 Measuring of Toe Load of ERC during service in field by Electronic Toe Load
Measuring Device with contractor's tools & plants, equipment, consumable with all
lead & lift etc. complete, as directed by Engineer in-charge. Electronic Toe Load
Measuring Device will be as per RDSO's Specification No.TM/SM/ETLMD/218 dated
13.9.2012.
163030 Extraction of jammed ERC by Heavy Duty Hydraulic Extractor with contractor's tools
& plants, equipment, consumable with all lead & lift etc. complete, as directed by
Engineer in-charge. Heavy Duty Hydraulic Extractor for jammed ERCs (10 Ton
capacity) shall be used as per RDSO's Specification No. TM/SM/6, dated 8.05.1991.
164000 4. Miscellaneous :
164010 Tamping of track for picking up slacks in concrete sleeper track by Hand Held Off
Track Tamper (Power Pack Version) with contractor's tools & plants, equipment,
consumable with all lead & lift etc. complete, as directed by Engineer in-charge. Off-
track tamper (Power Pack Version) will be as per RDSO Specification No.
TM/SM/OTT/320, dated 28.01.2009.
171011 In wagons during period of traffic block where handling by mechanical means is not
possible
Details of cost for 89 Metric Tonne (114 nos., 60 kg/m rails of 13 metre)
Labour:
Mate (Skilled) Day 0002 609.00 1.00 609.00
Look Out Man (Un-skilled) Day 0033 431.00 1.00 431.00
Waterman (Un-skilled) Day 0034 431.00 1.00 431.00
Labour Unskilled Day 0020 431.00 30.00 12,930.00
Misc.:
T&P Lumpsum 9901 1.00 60.00 60.00
14,461.00
Add for working under traffic block @ 10% Lumpsum 9992 0.10 1,446.10
15,907.10
Add for Water Charges @ 1% Lumpsum 9902 0.01 159.07
16,066.17
Add for GST @ 12% (multiplying factor 0.1405) Lumpsum 9903 0.14 2,257.30
18,323.47
Add for Contractor’s Overheads and Profit @ 15% Lumpsum 9904 0.15 2,748.52
21,071.99
Add for Cess @ 1% Lumpsum 9905 0.01 210.72
Cost for 89 Metric Tonne 21,282.71
Rate per MT MT 239.13
171012 In wagons not involving traffic block or on lines not opened to traffic but handling by
mechanical means is not possible
Details of cost for 133.38 Metric Tonne (171 nos. 60 kg/m rails of 13 metre)
Labour:
Mate (Skilled) Day 0002 609.00 1.00 609.00
Labour Unskilled Day 0020 431.00 30.00 12,930.00
Misc.:
T&P Lumpsum 9901 1.00 60.00 60.00
13,599.00
Add for Water Charges @ 1% Lumpsum 9902 0.01 135.99
13,734.99
Add for GST @ 12% (multiplying factor 0.1405) Lumpsum 9903 0.14 1,929.77
15,664.76
Add for Contractor’s Overheads and Profit @ 15% Lumpsum 9904 0.15 2,349.71
18,014.47
Add for Cess @ 1% Lumpsum 9905 0.01 180.14
Cost for 133.38 Metric Tonne 18,194.61
Rate per MT MT 136.41
171014 In Wagon where mechanical handling is possible and traffic block is not required or
in Truck/Trailor.
Details of cost for 150 Metric Tonne (192 rails 13 metre 60 Kg)
Labour:
Mate (Skilled) Day 0002 609.00 1.00 609.00
Labour Unskilled Day 0020 431.00 8.00 3,448.00
Misc.:
Lifting beam arrangement for handling of multi rails at a time Lumpsum 9901 1.00 150.00 150.00
Hire charges of 12 MT Hydra Day 0090 5000.00 1.50 7,500.00
11,707.00
Add for Water Charges @ 1% Lumpsum 9902 0.01 117.07
11,824.07
Add for GST @ 12% (multiplying factor 0.1405) Lumpsum 9903 0.14 1,661.28
13,485.35
Add for Contractor’s Overheads and Profit @ 15% Lumpsum 9904 0.15 2,022.80
15,508.15
Add for Cess @ 1% Lumpsum 9905 0.01 155.08
Cost for 150 Metric Tonne 15,663.24
Rate per MT MT 104.42
171020 Loading of tongue rail, stock rail, switch assembly and crossings of any section and
length, SEJ,Glued joint etc. with / without P.way fittings and fastenings, in Wagon /
Truck / Trailor including lead upto 250 metre and lift upto 5 metre.
171021 In wagons during period of traffic block where handling by mechanical means is not
possible
Details of cost for 84 Metric Tonne
Labour:
Mate (Skilled) Day 0002 609.00 1.00 609.00
Waterman (Un-skilled) Day 0034 431.00 1.00 431.00
Look Out Man (Un-skilled) Day 0033 431.00 1.00 431.00
Labour Unskilled Day 0020 431.00 35.00 15,085.00
Misc.:
T&P Lumpsum 9901 1.00 50.00 50.00
16,606.00
Add for working under traffic block @ 10% Lumpsum 9992 0.10 1,660.60
18,266.60
Add for Water Charges @ 1% Lumpsum 9902 0.01 182.67
18,449.27
Add for GST @ 12% (multiplying factor 0.1405) Lumpsum 9903 0.14 2,592.12
21,041.39
Add for Contractor’s Overheads and Profit @ 15% Lumpsum 9904 0.15 3,156.21
24,197.60
Add for Cess @ 1% Lumpsum 9905 0.01 241.98
Cost for 84 Metric Tonne 24,439.57
Rate per MT MT 290.95
171022 In wagons not involving traffic block or on lines, not opened to traffic but handling by
mechanical means is not possible.
171023 In Wagon where mechanical handling is possible and traffic block is required.
171024 In Wagon where mechanical handling is possible and traffic block is not required or
in Truck/Trailor.
Details of cost for 168 Metric Tonne
Labour:
Mate (Skilled) Day 0002 609.00 1.00 609.00
Waterman (Un-skilled) Day 0034 431.00 1.00 431.00
Labour Unskilled Day 0020 431.00 10.00 4,310.00
Misc.:
Sundries Lumpsum 9901 1.00 100.00 100.00
Hire charges of 12 MT Hydra Day 0090 5000.00 1.50 7,500.00
12,950.00
Add for Water Charges @ 1% Lumpsum 9902 0.01 129.50
13,079.50
Add for GST @ 12% (multiplying factor 0.1405) Lumpsum 9903 0.14 1,837.67
14,917.17
Add for Contractor’s Overheads and Profit @ 15% Lumpsum 9904 0.15 2,237.58
17,154.75
Add for Cess @ 1% Lumpsum 9905 0.01 171.55
Cost for 168 Metric Tonne 17,326.29
Rate per MT MT 103.13
Draft IR Unified Stadard Analysis of Rates - 2021 Chapter - 17: Handling of Materials
171033 Extra to Items no. 171032 for lead beyond 1 Km for every subsequent Km or part
thereof and upto 10 Km
Details of cost for 18.72 MT ( Average Lead Considered 5 Km )
Labour:
Labour Unskilled Day 0020 431.00 8.00 3,448.00
Misc.:
T&P Lumpsum 9901 1.00 12.00 12.00
3,460.00
Add for Water Charges @ 1% Lumpsum 9902 0.01 34.60
3,494.60
Add for GST @ 12% (multiplying factor 0.1405) Lumpsum 9903 0.14 490.99
3,985.59
Add for Contractor’s Overheads and Profit @ 15% Lumpsum 9904 0.15 597.84
4,583.43
Add for Cess @ 1% Lumpsum 9905 0.01 45.83
Cost for 18.72 MT for lead upto 5 Km 4,629.26
Cost for 1 MT for 5 Km 247.29
Rate per MT for 1 Km MT 49.46
171034 Extra to Item no. 171031 and 171032 with contractor's Rail Dolly / Dip Lorry
Draft IR Unified Stadard Analysis of Rates - 2021 Chapter - 17: Handling of Materials
171040 Loading, unloading and hauling of 52Kg / 60Kg rail more than 13 metre and upto 39
metre length by Railway's Rail Dolly / Dip Lorry to the nominated location under
traffic in case road carriage is not possible for different leads and lift upto 5 metre.
171043 Extra to Items no. 171042 for lead beyond 1 Km for every subsequent Km or part
thereof and upto 10 Km
Draft IR Unified Stadard Analysis of Rates - 2021 Chapter - 17: Handling of Materials
171044 Extra to Item no. 171041 and 171042 with contractor's Rail Dolly / Dip Lorry
Details of cost for 42.12 MT
Misc.:
T & P ( Rs.5 for Each Rail Dolly ) Lumpsum 9901 1.00 60.00 60.00
Hire charges of Insulated Rail Dolly Day 0160 20.00 14.00 280.00
340.00
Add for Water Charges @ 1% Lumpsum 9902 0.01 3.40
343.40
Add for GST @ 12% (multiplying factor 0.1405) Lumpsum 9903 0.14 48.25
391.65
Add for Contractor’s Overheads and Profit @ 15% Lumpsum 9904 0.15 58.75
450.39
Add for Cess @ 1% Lumpsum 9905 0.01 4.50
Cost for 42.12 MT 454.90
Rate per MT MT 10.80
171050 Unloading of rails of any section and length upto 13 metre, in neat manner for
Railway usage from departmental material train (DMT) or contractor's / Railway's
Truck/Trailor including lead upto 50 metre, lift upto 5 metre and stacking in
prescribed manner.
171051 In wagons during period of traffic block where handling by mechanical means is not
possible
Details of cost for 600 Metric Tonne ( 8 BFR's )
Labour:
Mate (Skilled) Day 0002 609.00 4.00 2,436.00
Look Out Man (Un-skilled) Day 0033 431.00 4.00 1,724.00
Waterman (Un-skilled) Day 0034 431.00 2.00 862.00
Labour Unskilled Day 0020 431.00 128.00 55,168.00
Misc.:
T&P Lumpsum 9901 1.00 64.00 64.00
60,254.00
Add for working under traffic block @ 10% Lumpsum 9992 0.10 6,025.40
66,279.40
Add for Water Charges @ 1% Lumpsum 9902 0.01 662.79
66,942.19
Add for GST @ 12% (multiplying factor 0.1405) Lumpsum 9903 0.14 9,405.38
76,347.57
Add for Contractor’s Overheads and Profit @ 15% Lumpsum 9904 0.15 11,452.14
87,799.71
Add for Cess @ 1% Lumpsum 9905 0.01 878.00
Cost for 600 Metric Tonne 88,677.71
Rate per MT MT 147.80
Draft IR Unified Stadard Analysis of Rates - 2021 Chapter - 17: Handling of Materials
171052 In wagons not involving traffic block or on lines, not opened to traffic but handling by
mechanical means is not possible
Details of cost for 600 Metric Tonne ( 8 BFR's )
Labour:
Mate (Skilled) Day 0002 609.00 2.00 1,218.00
Labour Unskilled Day 0020 431.00 104.00 44,824.00
Misc.:
T&P Lumpsum 9901 1.00 64.00 64.00
46,106.00
Add for Water Charges @ 1% Lumpsum 9902 0.01 461.06
46,567.06
Add for GST @ 12% (multiplying factor 0.1405) Lumpsum 9903 0.14 6,542.67
53,109.73
Add for Contractor’s Overheads and Profit @ 15% Lumpsum 9904 0.15 7,966.46
61,076.19
Add for Cess @ 1% Lumpsum 9905 0.01 610.76
Cost for 600 Metric Tonne 61,686.95
Rate per MT MT 102.81
171053 In Wagon where mechanical handling is possible and traffic block is not required or
in Truck / Trailor
Details of cost for 216 Metric Tonne ( 12 Trailors ) Two Road Crane required in a day
Labour:
Mate (Skilled) Day 0002 609.00 1.00 609.00
Labour Unskilled Day 0020 431.00 10.00 4,310.00
Misc.:
T&P Lumpsum 9901 1.00 50.00 50.00
Hire charges of 12 MT Hydra Day 0090 5000.00 1.50 7,500.00
12,469.00
Add for Water Charges @ 1% Lumpsum 9902 0.01 124.69
12,593.69
Add for GST @ 12% (multiplying factor 0.1405) Lumpsum 9903 0.14 1,769.41
14,363.10
Add for Contractor’s Overheads and Profit @ 15% Lumpsum 9904 0.15 2,154.47
16,517.57
Add for Cess @ 1% Lumpsum 9905 0.01 165.18
Cost for 216 Metric Tonne 16,682.74
Rate per MT MT 77.23
171060 Unloading of rails of any section and length from 13 metre to 39 metre, in neat
manner for Railway usage from departmental material train (DMT) including lead
upto 50 metre and lift upto 5 metre.
171070 Unloading of all type of rails of length 130 metre and beyond from end unloading
rake and keep the panels in head-up position at specified distance from centre of
track clear from any infringement..
Note: Contractor has to keep Oxygen and Acetylene gas with cutter as standby
during the period of work.
172000 2. Sleepers :
172010 Loading of 52kg / 60kg PSC normal line and special sleepers upto 2.75 metre length
including existing fittings and fastenings in Depot / Station / Mid-section between
stations in a neat manner to departmental material train (DMT) or contractor's /
Railway's Truck/Trailer with crane or any other means including crossing of one track
with free lead upto 250 metre and lift upto 5 metre, if required with contractor's
labour, tools & plants, machinery, consumables etc.
172011 In wagons during period of traffic block where handling by mechanical means is not
possible
Details of cost for 84 Metric Tonne
Labour:
Mate (Skilled) Day 0002 609.00 1.00 609.00
Look Out Man (Un-skilled) Day 0033 431.00 1.00 431.00
Waterman (Un-skilled) Day 0034 431.00 1.00 431.00
Labour Unskilled Day 0020 431.00 22.00 9,482.00
Misc.:
T & P (Rail tongue, Crow bar etc.) Lumpsum 9901 1.00 160.00 160.00
11,113.00
Add for working under traffic block @ 10% Lumpsum 9992 0.10 1,111.30
12,224.30
Add for Water Charges @ 1% Lumpsum 9902 0.01 122.24
12,346.54
Add for GST @ 12% (multiplying factor 0.1405) Lumpsum 9903 0.14 1,734.69
14,081.23
Add for Contractor’s Overheads and Profit @ 15% Lumpsum 9904 0.15 2,112.18
16,193.42
Add for Cess @ 1% Lumpsum 9905 0.01 161.93
Cost for 84 Metric Tonne 16,355.35
Rate per MT MT 194.71
172012 In wagons not involving traffic block or on lines, not opened to traffic but handling by
mechanical means is not possible
Details of cost for 168 Metric Tonne
Labour:
Mate (Skilled) Day 0002 609.00 1.00 609.00
Waterman (Un-skilled) Day 0034 431.00 1.00 431.00
Labour Unskilled Day 0020 431.00 30.00 12,930.00
Misc.:
T & P (Rail tongue, Crow bar etc.) Lumpsum 9901 1.00 84.00 84.00
14,054.00
Add for Water Charges @ 1% Lumpsum 9902 0.01 140.54
14,194.54
Add for GST @ 12% (multiplying factor 0.1405) Lumpsum 9903 0.14 1,994.33
16,188.87
Add for Contractor’s Overheads and Profit @ 15% Lumpsum 9904 0.15 2,428.33
18,617.20
Draft IR Unified Stadard Analysis of Rates - 2021 Chapter - 17: Handling of Materials
172013 In Wagon where mechanical handling is possible and traffic block is required.
172014 In Wagon where mechanical handling is possible and traffic block is not required or
in Truck / Trailor
Details of cost for 168 Metric Tonne
Labour:
Labour Unskilled Day 0020 431.00 6.00 2,586.00
Misc.:
T & P (Rail tongue, Crow bar etc.) Lumpsum 9901 1.00 72.00 72.00
Hire charges of 12 MT Hydra Day 0090 5000.00 1.50 7,500.00
10,158.00
Add for Water Charges @ 1% Lumpsum 9902 0.01 101.58
10,259.58
Add for GST @ 12% (multiplying factor 0.1405) Lumpsum 9903 0.14 1,441.47
11,701.05
Add for Contractor’s Overheads and Profit @ 15% Lumpsum 9904 0.15 1,755.16
13,456.21
Add for Cess @ 1% Lumpsum 9905 0.01 134.56
Cost for 168 Metric Tonne 13,590.77
Rate per MT MT 80.90
172020 Loading of 52kg / 60kg PSC line and special sleepers beyond 2.75 metre length
including existing fittings and fastenings in Depot / Station / Mid-section between
stations in a neat manner to departmental material train (DMT) or contractor's /
Railway's Truck/Trailor with crane or any other means including crossing of one track
with free lead upto 250 metre and lift upto 5 metre, if required with contractor's
labour, tools & plants, machinery, consumables etc.
172021 In wagons during period of traffic block where handling by mechanical means is not
possible
Details of cost for 84 Metric Tonne
Labour:
Mate (Skilled) Day 0002 609.00 1.00 609.00
Waterman (Un-skilled) Day 0034 431.00 1.00 431.00
Look Out Man (Un-skilled) Day 0033 431.00 1.00 431.00
Labour Unskilled Day 0020 431.00 30.00 12,930.00
Misc.:
T & P (Rail tongue, Crow bar etc.) Lumpsum 9901 1.00 92.00 92.00
14,493.00
Draft IR Unified Stadard Analysis of Rates - 2021 Chapter - 17: Handling of Materials
172022 In wagons not involving traffic block or on lines, not opened to traffic but handling by
mechanical means is not possible
Details of cost for 168 Metric Tonne
Labour:
Mate (Skilled) Day 0002 609.00 1.00 609.00
Waterman (Un-skilled) Day 0034 431.00 1.00 431.00
Labour Unskilled Day 0020 431.00 50.00 21,550.00
Misc.:
T & P (Rail tongue, Crow bar etc.) Lumpsum 9901 1.00 48.00 48.00
22,638.00
Add for Water Charges @ 1% Lumpsum 9902 0.01 226.38
22,864.38
Add for GST @ 12% (multiplying factor 0.1405) Lumpsum 9903 0.14 3,212.45
26,076.83
Add for Contractor’s Overheads and Profit @ 15% Lumpsum 9904 0.15 3,911.52
29,988.35
Add for Cess @ 1% Lumpsum 9905 0.01 299.88
Cost for 168 Metric Tonne 30,288.23
Rate per MT MT 180.29
172023 In Wagon where mechanical handling is possible and traffic block is required.
172024 In Wagon/Truck / Trailor where mechanical handling is possible and traffic block is
not required.
Details of cost for 168 Metric Tonne
Labour:
Mate (Skilled) Day 0002 609.00 1.00 609.00
Waterman (Un-skilled) Day 0034 431.00 1.00 431.00
Labour Unskilled Day 0020 431.00 10.00 4,310.00
Draft IR Unified Stadard Analysis of Rates - 2021 Chapter - 17: Handling of Materials
172030 Loading, leading and unloading of PSC Sleepers of 52Kg / 60Kg by Railway's Rail
Dolly/ Dip Lorry to the nominated location under traffic in case road carriage is not
possible for different leads and lift upto 5 metres.
172033 Extra to Items no. 172032 for lead beyond 1 Km for every subsequent Km or part
thereof and upto 10 Km
Details of cost for 24 MT ( Average Lead Considered 5 Km )
Labour:
Draft IR Unified Stadard Analysis of Rates - 2021 Chapter - 17: Handling of Materials
172034 Extra to Item no. 172031 and 172032 with contractor's Rail Dolly/Dip Lorry.
Details of cost for 18 MT
Misc.:
T&P Lumpsum 9901 1.00 20.00 20.00
Hire charges of Insulated Rail Dolly Day 0160 20.00 7.00 140.00
160.00
Add for Water Charges @ 1% Lumpsum 9902 0.01 1.60
161.60
Add for GST @ 12% (multiplying factor 0.1405) Lumpsum 9903 0.14 22.70
184.30
Add for Contractor’s Overheads and Profit @ 15% Lumpsum 9904 0.15 27.65
211.95
Add for Cess @ 1% Lumpsum 9905 0.01 2.12
Cost for 18 MT 214.07
Rate per MT MT 11.89
172040 Loading, leading and unloading of all types of P.Way fittings and all other
miscellaneous material except Rails, sleepers, switches, crossings, SEJs and Glued
Joints by road vehicles.
172048 Extra for every Km per MT beyond 150 Km over item no. 172047
Considering only the additional cost of running beyond 150 km for a distance of 240
km with the following yardstick:
(i) Speed = 60 kmph,
Hiring time of truck = 240/60 = 4 hours = 0.5 day
(ii) Fuel consumption = 5 kmpl
Diesel consumption for 240 kms = 240/5 = 48 litres
Hire Charges of Truck - 9 tonne (without POL ) Day 0059 2000.00 0.50 1,000.00
Diesel (HSD) Oil Litre 0181 101.62 48.00 4,877.76
5,877.76
Add for Water Charges @ 1% Lumpsum 9902 0.01 58.78
5,936.54
Draft IR Unified Stadard Analysis of Rates - 2021 Chapter - 17: Handling of Materials
172050 Transportation of Rails, sleepers, switches, crossings, SEJs and Glued Joints by
road vehicles.
Note: Loading and unloading shall be paid extra under relevant items.
172058 Extra for every Km per MT beyond 150 Km over item no. 172057
Considering only the additional cost of running beyond 150 km for a distance of 240
km with the following yardstick:
(i) Speed = 60 kmph,
Hiring time of truck = 240/60 = 4 hours = 0.5 day
(ii) Fuel consumption = 5 kmpl
Diesel consumption for 240 kms = 240/5 = 48 litres
Hire Charges of Truck - 9 tonne (without POL ) Day 0059 2000.00 0.50 1,000.00
Draft IR Unified Stadard Analysis of Rates - 2021 Chapter - 17: Handling of Materials
172060 Unloading of 52kg / 60kg PSC line and special sleepers upto 2.75 metre length in
Depot / Station / Mid-section between stations in neat manner for Railway usage
from departmental material train (DMT) or contractor's / Railway's Truck/Trailer with
crane or any other means including crossing of one track and lead upto 250 metre &
lift upto 5 metre with contractor's labour, tools & plants, machinery, consumables etc.
172070 Unloading of 52kg / 60kg PSC special sleepers beyond 2.75 metre length in Depot /
Station / Mid-section between stations in neat manner for Railway usage from
departmental material train (DMT) or contractor's / Railway's Truck/Trailer with crane
or any other means including crossing of one track and lead upto 50 metre & lift upto
5 metre with contractor's labour, tools & plants, machinery, consumables etc.
172080 Spreading of New / SH PSC normal line sleepers from stack along track on either
side for different leads with all lifts by any means.
172081 For a lead upto 500m
Details of cost for 120 sleepers ( Average lead considered 250 metre )
Labour:
Labour Unskilled Day 0020 431.00 12.00 5,172.00
Misc.:
T & P ( Rail dolly, Rail tongue, Crow bar, etc. ) Lumpsum 9901 1.00 50.00 50.00
5,222.00
Add for Water Charges @ 1% Lumpsum 9902 0.01 52.22
5,274.22
Add for GST @ 12% (multiplying factor 0.1405) Lumpsum 9903 0.14 741.03
6,015.25
Add for Contractor’s Overheads and Profit @ 15% Lumpsum 9904 0.15 902.29
6,917.54
Add for Cess @ 1% Lumpsum 9905 0.01 69.18
Cost for 120 sleepers for upto 500 metre Lead 6,986.71
Rate per sleeper Each 58.22
172082 Extra to Item no. 172081 for additional lead of every 500m or part thereof beyond
500 m
Details of cost for 120 sleepers ( Average Lead considered beyond 250m beyond
500m )
Labour:
Labour Unskilled Day 0020 431.00 8.00 3,448.00
Misc.:
T & P ( Rail dolly, Rail tongue, Crow bar, etc. ) Lumpsum 9901 1.00 50.00 50.00
3,498.00
Add for Water Charges @ 1% Lumpsum 9902 0.01 34.98
3,532.98
Add for GST @ 12% (multiplying factor 0.1405) Lumpsum 9903 0.14 496.38
4,029.36
Add for Contractor’s Overheads and Profit @ 15% Lumpsum 9904 0.15 604.40
Draft IR Unified Stadard Analysis of Rates - 2021 Chapter - 17: Handling of Materials
173010 Unloading of Switches / Crossings / SEJ Rails / Glued Joints of any rail section and
length with or without P.Way fittings & fastenings in neat manner for Railway usage
from departmental material train (DMT) or contractor's / Railway's Truck/Trailer with
lead upto 250 metre & lift upto 5 metre -
173020 Unloading all types of P.Way fittings and fastenings for Railway usage from Truck
and stacking with lead upto 250 metre & lift upto 5 metre.
Details of cost for 20 Metric Tonne
Labour:
Labour Unskilled Day 0020 431.00 4.00 1,724.00
Misc.:
T&P Lumpsum 9901 1.00 20.00 20.00
1,744.00
Add for Water Charges @ 1% Lumpsum 9902 0.01 17.44
1,761.44
Add for GST @ 12% (multiplying factor 0.1405) Lumpsum 9903 0.14 247.48
2,008.92
Add for Contractor’s Overheads and Profit @ 15% Lumpsum 9904 0.15 301.34
2,310.26
Add for Cess @ 1% Lumpsum 9905 0.01 23.10
Cost for 20 Metric Tonne 2,333.36
Rate per MT MT 116.67
173030 Collection and stacking of various P.Way materials at nominated stacking location
with serviceable and un-serviceable ones separately within a lead upto 500 metre
and lift upto 5 metre including crossing of track(s) wherever necessary as directed
by Engineer-in-Charge.
173031 Rails, switches, crossings, SEJ, Glued Joints, Check Rails etc.
173033 P.Way fittings of all types and other similar loose items
Details of cost for 40 Metric Tonne
Labour:
Mate (Skilled) Day 0002 609.00 1.00 609.00
Look Out Man (Un-skilled) Day 0033 431.00 1.00 431.00
Labour Unskilled Day 0020 431.00 20.00 8,620.00
Misc.:
T&P Lumpsum 9901 1.00 40.00 40.00
9,700.00
Add for Water Charges @ 1% Lumpsum 9902 0.01 97.00
9,797.00
Add for GST @ 12% (multiplying factor 0.1405) Lumpsum 9903 0.14 1,376.48
11,173.48
Add for Contractor’s Overheads and Profit @ 15% Lumpsum 9904 0.15 1,676.02
12,849.50
Add for Cess @ 1% Lumpsum 9905 0.01 128.50
Cost for 40 Metric Tonne 12,978.00
Rate per MT MT 324.45
173040 Stacking of glued joints in single layer for electrical testing, in such a manner that
glued joints - (a) shall not touch ground, (b) shall not touch one another, (c) shall not
touch any rail or any metallic body, (d) shall not be water-logged from any side and
(e) end post shall not rest on supports of glued joint
173050 Un Loading of stone boulders weighing not less than 35 kg each from Railway
Wagons and stack at specificed locations with all contractor's tools & plants,
machinary, labour, lead and lift, crossing of track wherever necessary etc., complete
as directed by the Engineer Incharge.
Draft IR Unified Stadard Analysis of Rates - 2021 Chapter - 17: Handling of Materials
Details of cost for 77 Sqm [ For Insertion of PSC Sleeper in LC Area required width for
dismantling of road surface is 3.5 metre from centre line of track ] Taken 11 metre
wide LC. i.e. { 11m x (3.5m + 3.5m) = 77 Sqm }
Labour:
Mate (Skilled) Day 0002 609.00 1.00 609.00
Blacksmith - 1st Class (Skilled) Day 0008 609.00 1.00 609.00
Helper (Semi-skilled) Day 0021 505.00 1.00 505.00
Look Out Man (Un-skilled) Day 0033 431.00 1.00 431.00
Waterman (Un-skilled) Day 0034 431.00 1.00 431.00
Labour Unskilled Day 0020 431.00 35.00 15,085.00
Misc.:
T&P Lumpsum 9901 1.00 74.00 74.00
17,744.00
Add for Water Charges @ 1% Lumpsum 9902 0.01 177.44
17,921.44
Add for GST @ 12% (multiplying factor 0.1405) Lumpsum 9903 0.14 2,517.96
20,439.40
Add for Contractor’s Overheads and Profit @ 15% Lumpsum 9904 0.15 3,065.91
23,505.31
Add for Cess @ 1% Lumpsum 9905 0.01 235.05
Cost for 77 Sqm 23,740.37
Rate per Sqm Sqm 308.32
181020 Dismantling existing check rail of Level Crossing, blocks, bolts & nuts and stacking
these in a countable manner, as directed by Engineer in-charge.
Details of cost for 22 RM Taken 9 Metre wide LC For both side check rails {(9+ 2) x 2
= 22 Metre }
Labour:
For Dismantling and stacking of check rail
Labour Unskilled Day 0020 431.00 4.00 1,724.00
Blacksmith - 1st Class (Skilled) Day 0008 609.00 0.50 304.50
Helper (Semi-skilled) Day 0021 505.00 0.50 252.50
Look Out Man (Un-skilled) Day 0033 431.00 0.50 215.50
Misc.:
T&P Lumpsum 9901 1.00 14.00 14.00
2,510.50
Add for Water Charges @ 1% Lumpsum 9902 0.01 25.11
2,535.61
Add for GST @ 12% (multiplying factor 0.1405) Lumpsum 9903 0.14 356.25
2,891.86
Add for Contractor’s Overheads and Profit @ 15% Lumpsum 9904 0.15 433.78
3,325.64
Add for Cess @ 1% Lumpsum 9905 0.01 33.26
Cost for 22 Running Metre 3,358.89
Rate per RM RM 152.68
181030 Dismantling exiting Rail Height Gauge carefully and stacking the released material in
acountable manner as directed by engineer in-charge including removal of cement
concrete foundation and making surface clean.
Details of cost for 2 No's of one LC
Draft IR Unified Stadard Analysis of Rates - 2021 Chapter - 18: Level Crossings
181040 Dismantling existing lifting barrier alongwith winch assembly and other components
like boom, fringes, locking arrangements, pedestal, boom rest, locking rods/wires,
pulley stakes, turn out wheels, 'A' base and other materials connected with
functioning of lifting barrier, removing engineering indicators on track and level
crossing raod signages without any damage including demolishing concrete base of
existing structures, filling, ramming and levelling the ground disturbed during
demolition, clearing debris and stacking all released material in a neat and countable
manner and clear of infringements, as directed.
Note: Barriers on both sides of level crossing constitute one set.
181050 Dismantling existing lifting barrier and other components except winch assembly, like
boom, fringes, locking arrangements, pedestal, boom rest, locking rods/wires, pulley
stakes, turn out wheels, 'A' base and other materials connected with functioning of
lifting barrier without any damage including demolishing concrete base of existing
structures and clearing debris in a neat and stacking in a countable manner and clear
of infringements, as directed.
Note: Barriers on both sides of level crossing constitute one set.
Draft IR Unified Stadard Analysis of Rates - 2021 Chapter - 18: Level Crossings
181060 Deduction to item no. 181050 for not dismantling ‘A’ base and its foundations
Details of cost 1 set
Labour:
(i) For dismantling of foundation and A base
Labour Unskilled Day 0020 431.00 -4.00 -1,724.00
Misc.:
T&P Lumpsum 9901 1.00 10.00 10.00
-1,714.00
Add for Water Charges @ 1% Lumpsum 9902 0.01 -17.14
-1,731.14
Add for GST @ 12% (multiplying factor 0.1405) Lumpsum 9903 0.14 -243.23
-1,974.37
Add for Contractor’s Overheads and Profit @ 15% Lumpsum 9904 0.15 -296.15
-2,270.52
Add for Cess @ 1% Lumpsum 9905 0.01 -22.71
Deduction for 1 set -2,293.23
Deduction per set Set -2,293.23
181070 Dismantling existing swing gate consisting of two leaves with gate posts, meeting post
and stopper post etc. without causing any damage to material and stacking the same,
as directed by Engineer in-charge.
Details of cost for 5 MT
Material:
Acetylene Gas (in cylinder) Kg 0341 65.00 4.00 260.00
Oxygen Gas (in cylinder) Kg 0340 50.00 12.00 600.00
Draft IR Unified Stadard Analysis of Rates - 2021 Chapter - 18: Level Crossings
183030 Cutting foot of rail by gas or any other approved method for check rails with
contractor’s tools & plants. Payment shall be made for length of cutting of foot.
Details of cost for 18.20 RM of Gas Cut (9.10 x 2.0 = 18.20 RM)
Material:
Oxygen Gas (in cylinder) Kg 0340 50.00 9.00 450.00
Acetylene Gas (in cylinder) Kg 0341 65.00 3.00 195.00
Labour:
Welder (Skilled) Day 0029 609.00 1.00 609.00
Helper (Semi-skilled) Day 0021 505.00 1.00 505.00
Misc.:
T & P ( Includes Gas cutting torch ) Lumpsum 9901 1.00 26.00 26.00
1,785.00
Add for Water Charges @ 1% Lumpsum 9902 0.01 17.85
1,802.85
Add for GST @ 12% (multiplying factor 0.1405) Lumpsum 9903 0.14 253.30
2,056.15
Add for Contractor’s Overheads and Profit @ 15% Lumpsum 9904 0.15 308.42
2,364.57
Add for Cess @ 1% Lumpsum 9905 0.01 23.65
Cost for 18.20 RM of Gas Cut 2,388.22
Rate per RM RM 131.22
Draft IR Unified Stadard Analysis of Rates - 2021 Chapter - 18: Level Crossings
Details of cost for each set for 1 LC. Considering average length of chck rail as 7.50m
Labour:
Blacksmith - 1st Class (Skilled) Day 0008 609.00 0.50 304.50
Helper (Semi-skilled) Day 0021 505.00 0.50 252.50
Labour Unskilled Day 0020 431.00 6.00 2,586.00
Misc.:
T&P Lumpsum 9901 1.00 14.00 14.00
3,157.00
Add for Water Charges @ 1% Lumpsum 9902 0.01 31.57
3,188.57
Add for GST @ 12% (multiplying factor 0.1405) Lumpsum 9903 0.14 447.99
3,636.56
Add for Contractor’s Overheads and Profit @ 15% Lumpsum 9904 0.15 545.48
4,182.05
Add for Cess @ 1% Lumpsum 9905 0.01 41.82
Rate oer Set Set 4,223.87
184020 Painting speed breakers with paint of approved quality & colour over the Bituminous
surface near approaches to level crossing.
184021 With enamel paint (two coats)
Details of cost for 34 Sqm
Draft IR Unified Stadard Analysis of Rates - 2021 Chapter - 18: Level Crossings
185040 Manufacture, supply, assembly, erection, commissioning and testing of Lifting Barrier
assembly, having fragmented boom, boom light boxes with suitable gate lamps, bell,
boom supports (stay wires) with adjusters, counter weight, pedestal and lock posts
with foundation of ‘A’ type as required, turn-union wheel with brackets, balance and
auxiliary weights clamps etc. to approved standard drawing nos. SA 7973 to 7980
with all fittings and fastenings complete with contractor's men, equipments and
materials, as per specifications and as directed (this item is excluding fringes).
185060 Manufacture, supply, assembly, erection, commissioning and testing of auto boom
locking arrangement for existing lifting barriers, consisting of interlocking ground
frame near gate lodge, foundation of ‘A’ type, as required and connecting ground
frame to lock posts of gate booms with stipulated rodding on guide rollers, supported
on trestles including required excavation, foundation, providing RCC NP-2 Class
pipes of 100mm dia. for road / rail crossing, as per RDSO’s drawings complete
(Excavation, concrete work and NP-2 pipe will be paid separately).
185080 Manufacture, supply and replacement of Railway's lifting barrier assembly and boom
supports, gate lamps at one side of level crossing including required excavation &
concreting foundation of ‘A’ type, as required for pedestal bases, including painting
iron works with two coats of synthetic enamel paint of approved quality and colour
over one coat of red lead primer of approved quality, setting lifting barrier for smooth
operation complete and as directed.
Note: Excavation & concrete work will be paid separately.
186020 Fixing of Railway’s precast concrete slabs of different sizes in position for level
crossings / trolley path and filling gap between check rail / running rail, slabs,
approaches etc. with asphalt complete and as directed.
Details of cost for 84.36 sqm {7.20 x 1.30 + 2 x(7.50 x 5.0)}
Material:
Coal tar Emulsion Litre 0317 50.00 20.00 1,000.00
Fuel wood Quintal 0345 4000.00 0.20 800.00
Wire Brush - 25cm long Each 0313 15.00 2.00 30.00
Soft Brush for painting - 25cm long Each 0314 33.00 1.00 33.00
Draft IR Unified Stadard Analysis of Rates - 2021 Chapter - 18: Level Crossings
186030 Paving of level crossing road surface with Railway's precast RCC slab / blocks as per
standards / approved drawings for light and heavy vehicles, supplied on bed of sand,
moorum or gravel, duly compacted and joints filled with mixture of sand & tar/bitumen
in proportion of 1:2 by weight.
186040 Removal of RCC slab in existing level crossing portion and in between tracks
alongwith stacking them in countable manner, as directed.
Details of cost for 40 Sqm
Labour:
Labour Unskilled Day 0020 431.00 3.00 1,293.00
Draft IR Unified Stadard Analysis of Rates - 2021 Chapter - 18: Level Crossings
186050 Fixing of speed breaker on approaches of level crossings with pre-cast concrete
blocks (M-25) of parabolic shape for entire road width with 125 mm central rise, 2m
wide in the middle including painting two coats with paint of approved quality and
colour.
186060 Provision of one Asphalt Speed Breaker Rumble Strip on each side of the approaches
of manned level crossings as per approved drawing including painting two coats with
paint of approved quality and colour
Details of cost for 15 Running Metre
Material:
Bitumen Hot sealing compound : Gr. A MT 0319 28000.00 0.06 1,680.00
Stone Aggregate (Single size) : 10 mm nominal size Cum 0208 775.00 0.50 387.50
Fuel wood Quintal 0345 4000.00 0.50 2,000.00
Luminous Paint as per RDSO's Spec. no. M&C/PCN/120-2011 Litre 0299 300.00 4.00 1,200.00
Soft Brush for painting - 25cm long Each 0314 33.00 1.00 33.00
Labour:
Mason 1st class (Skilled) Day 0004 609.00 1.00 609.00
Painter (Skilled) Day 0012 609.00 1.00 609.00
Helper (Semi-skilled) Day 0021 505.00 2.00 1,010.00
Misc.:
T & P including tray for heating asphalt Lumpsum 9901 1.00 50.00 50.00
7,578.50
Add for Water Charges @ 1% Lumpsum 9902 0.01 75.79
7,654.29
Add for GST @ 12% (multiplying factor 0.1405) Lumpsum 9903 0.14 1,075.43
8,729.71
Draft IR Unified Stadard Analysis of Rates - 2021 Chapter - 18: Level Crossings
186070 Manufacture & supply of tested GI wire rope of 6mm dia. and 6 ply to suit lifting barrier
gates at nearby P.Way Stores / Depot / Level Crossing gate, as directed.
186080 Supplying and fixing of Boom Supports (stay wires) for lifting barrier (approx. 8mm
dia.) with suitable adjuster and other specials, as directed
Detail of cost for 4 no's
Material:
Boom Supports (stay wires) for lifting barrier (approx. 8mm dia) Each 0448 1000.00 4.00 4,000.00
Man Power : (For Fixing)
Blacksmith - 1st Class (Skilled) Day 0008 609.00 1.00 609.00
Helper (Semi-skilled) Day 0021 505.00 1.00 505.00
Misc.:
T&P Lumpsum 9901 1.00 10.00 10.00
5,124.00
Add for Water Charges @ 1% Lumpsum 9902 0.01 51.24
5,175.24
Add for GST @ 12% (multiplying factor 0.1405) Lumpsum 9903 0.14 727.12
5,902.36
Add for Contractor’s Overheads and Profit @ 15% Lumpsum 9904 0.15 885.35
6,787.72
Add for Cess @ 1% Lumpsum 9905 0.01 67.88
Cost for 4 no's 6,855.59
Rate for each Each 1,713.90
186090 Manufacture and supply of vertical / horizontal Turnout Wheels and Shafts, mounted
over base plate weighing not be less than 6 Kg with supporting vertical base, made of
MS angle 75mm x 75mm x 10mm as per Railway's approved drawings and
specifications complete and as directed.
186100 Manufacturing and supplying to site of work including installation pulley with pulley
stakes complete, wire rope 6 x 6 x 19 with accessories as per Railway’s approved
drawings for operation of lifting barriers complete, as directed.
186110 Fabrication, supply and fixing of Fringes to the lifting barriers of various length at level
crossing as per approved drawing; made of MS flat of size 30mm x 6mm in 2 rows,
40mm x 6mm in 1 row horizontally and MS flat of size 30mm x 6mm vertically at
500mm centre to centre, painting iron works with two coats of synthetic enamel paint
of approved quality & colour over one coat of red lead primer of approved quality, as
directed.
186120 Supplying and driving into ground 'C' class G.I. pipes of 20mm dia. x 150mm length
for planting red flags and lamp at 5 metre on both sides from the centre of road at
level crossings with all leads & lifts. Payment shall be made for complete work at one
Level Crossing.
Note: Two pipes make one set.
186130 Manufacturing & supplying to site of work and installing Turnout wheel - Horizontal
Rope Wheel - double wire (2-way) including guides with all contractor's materials,
fabrication, labour, T&P, consumables, all leads & lifts etc. complete as per approved
drawing and as directed by Engineer in-charge.
186140 Supplying galvanized Steel Wire Rope for DW signalling 6 x 19 ply as per IRS No.
S.11 amended upto date for lifting barrier at level crossing gates, as directed by
Engineer in-charge
Details of cost 100 Kg
Material:
Galvanized STEEL WIRE ROPE for DW signalling 6 x 19 ply as per IRS No. S.11 Kg 0453 250.00 100.00 25,000.00
Misc.:
25,000.00
Add for Water Charges @ 1% Lumpsum 9902 0.01 250.00
25,250.00
Add for GST @ 12% (multiplying factor 0.1405) Lumpsum 9903 0.14 3,547.63
28,797.63
Add for Contractor’s Overheads and Profit @ 15% Lumpsum 9904 0.15 4,319.64
33,117.27
Add for Cess @ 1% Lumpsum 9905 0.01 331.17
Cost for 100 Kg 33,448.44
Rate per Kg Kg 334.48
186150 Fabrication, supplying and fixing Stop Boards of 600mm dia. to lifting barriers as per
approved drawing, made of 3mm thick plate, using MS clamps, providing 6 nos. of
50mm dia. red reflector on stop board, painting iron works with two coats of synthetic
enamel paint over one coat of red lead primer of approved quality & colour and writing
STOP mark over the board.
186160 Manufacturing, supplying and fixing Wicked Gate of size 1025mm x 1025mm x
1000mm at manned level crossings, as per approved drawing including painting with
2 coats of specified enamel colour paint over 1 coat of primer including earthwork in
excavation etc. complete, as per specifications and as directed.
Details of cost for 1.5 MT {Mild steel plates/sheets/angles required for one wicket gate
is approx 0.15 MT}
Material:
Zinc Chromate red oxide Primer to IS:2074 Litre 0308 130.00 6.00 780.00
Enamel Paint as per RDSO's Spec. no.M&C/PCN/120-2011 Litre 0306 190.00 10.00 1,900.00
Structural Steel Plates conforming to Grade Designation E 250; Quality "A" as per IS Quintal 0223 6300.00 15.00 94,500.00
2062
H3 Electrodes as per RDSO's Spec. no. IRS M:28-2011 Nos. 0427 20.00 300.00 6,000.00
Paint Brush 25 mm Each 0327 20.00 4.00 80.00
Labour:
Welder (Skilled) Day 0029 609.00 3.00 1,827.00
Blacksmith - 1st Class (Skilled) Day 0008 609.00 3.00 1,827.00
Painter (Skilled) Day 0012 609.00 2.00 1,218.00
Helper (Semi-skilled) Day 0021 505.00 8.00 4,040.00
Labour Unskilled Day 0020 431.00 6.00 2,586.00
Misc.:
T&P Lumpsum 9901 1.00 44.00 44.00
Electricity Charges ( 1 Unit ) KWH 0505 7.50 300.00 2,250.00
Hire charges of Arc Welding Machine 500 Amp Day 0132 300.00 2.00 600.00
117,652.00
Add for Water Charges @ 1% Lumpsum 9902 0.01 1,176.52
118,828.52
Add for GST @ 12% (multiplying factor 0.1405) Lumpsum 9903 0.14 16,695.41
135,523.93
Add for Contractor’s Overheads and Profit @ 15% Lumpsum 9904 0.15 20,328.59
155,852.52
Add for Cess @ 1% Lumpsum 9905 0.01 1,558.53
Cost for 1.5 MT 157,411.04
Rate per MT MT 104,940.69
186170 Fixing of wooden blocks of approximate size of 150mm x 300mm x 1200mm on end of
check rails including sizing at level crossings with contractor's labour, tools & plants
and as directed.
186171 With Railway’s wooden block by cutting Railway’s wooden sleepers (supplied free by
Railways) into blocks by sawing to size
Details of cost for 40 nos.
Labour:
Draft IR Unified Stadard Analysis of Rates - 2021 Chapter - 18: Level Crossings
Hard Variety Jungle Wood blocks 10 Cudm 0343 350.00 216.00 75,600.00
Labour:
(i) Fixing of wooden blocks
Mate (Skilled) Day 0002 609.00 1.00 609.00
Carpenter (Skilled) Day 0006 609.00 1.00 609.00
Helper (Semi-skilled) Day 0021 505.00 1.00 505.00
Labour Unskilled Day 0020 431.00 10.00 4,310.00
Misc.:
T&P Lumpsum 9901 1.00 24.00 24.00
81,657.00
Add for Water Charges @ 1% Lumpsum 9902 0.01 816.57
82,473.57
Add for GST @ 12% (multiplying factor 0.1405) Lumpsum 9903 0.14 11,587.54
94,061.11
Add for Contractor’s Overheads and Profit @ 15% Lumpsum 9904 0.15 14,109.17
108,170.27
Add for Cess @ 1% Lumpsum 9905 0.01 1,081.70
Cost for 40 nos 109,251.98
Rate for each Each 2,731.30
186180 Fixing of grip expansion bolts of 18mm / 22mm dia. with nuts and MS clips / washers
on PSC sleepers as per specifications for fixing guard rails / check rails / trolley path
including drilling of required holes in sleepers with all fittings with contractor's tools &
plants, equipment, consumables with all lead, lifts etc. complete, as directed by
Engineer in-charge, excluding cost of bolts, nuts, washers, clips etc.
6,907.20
Add for Water Charges @ 1% Lumpsum 9902 0.01 69.07
6,976.27
Add for GST @ 12% (multiplying factor 0.1405) Lumpsum 9903 0.14 980.17
7,956.44
Add for Contractor’s Overheads and Profit @ 15% Lumpsum 9904 0.15 1,193.47
9,149.90
Add for Cess @ 1% Lumpsum 9905 0.01 91.50
Cost for 80 nos. 9,241.40
Rate for each Each 115.52
186190 Erecting detonator rail posts at required locations as required including cutting the rail
to required length varying from 1.00M to 1.50M , leading the rail pieces from
nominated station / mid section from nearest depot to site of work, erecting the rail
post by making the pit size as required and filling with CC 1:3:6 mix with 40mm metal
and painting the rail post with two coats of synthetic enamel paint of approved colour
and make, with contractor's materials, labour, paint, all lead and lifts,etc., complete as
per specifications and as directed by the Engineer-in-charge.
Note: Excavation and concrete work for foundation will be paid under relavent item
186210 Providing Rail Barricading with rails supplied by Railways with verticals provided at
every 1.5m interval, height of barricade being upto 1.5m above ground / termination
level and one or more row of horizontal rail, duly cutting rails and drilling holes as
required, assembling necessary accessories to required length, including earthwork
excavation for foundation, fixing posts in cement concrete 1:3:6 base of size 0.45m x
0.45m x 0.60m and one coat of red oxide painting of steel work.
Note:
1. Excavation and concrete work will be paid separately.
2. Rail shall be made available within 250 metres
13,029.00
Add for working under traffic block @ 5% Lumpsum 9991 0.05 651.45
13,680.45
Add for Water Charges @ 1% Lumpsum 9902 0.01 136.80
13,817.25
Add for GST @ 12% (multiplying factor 0.1405) Lumpsum 9903 0.14 1,941.32
15,758.58
Add for Contractor’s Overheads and Profit @ 15% Lumpsum 9904 0.15 2,363.79
18,122.37
Add for Cess @ 1% Lumpsum 9905 0.01 181.22
Cost for 50 TRM 18,303.59
Rate per TRM TRM 366.07
11,305.00
Add for Water Charges @ 1% Lumpsum 9902 0.01 113.05
11,418.05
Add for GST @ 12% (multiplying factor 0.1405) Lumpsum 9903 0.14 1,604.24
13,022.29
Draft IR Unified Stadard Analysis of Rates - 2021 Chapter - 19: Bridge Related Activities
191021 RH /Temporary girder of length varying from 12.2m to 16.3m using road crane
capacity of 80 tons
Details of cost for 1 span
Material:
Acetylene Gas (in cylinder) Kg 0341 65.00 4.00 260.00
Oxygen Gas (in cylinder) Kg 0340 50.00 12.00 600.00
Labour:
Mate (Skilled) Day 0002 609.00 1.00 609.00
Blacksmith - 1st Class (Skilled) Day 0008 609.00 1.00 609.00
Welder (Skilled) Day 0029 609.00 1.00 609.00
Carpenter (Skilled) Day 0006 609.00 2.00 1,218.00
Helper (Semi-skilled) Day 0021 505.00 4.00 2,020.00
Look Out Man (Un-skilled) Day 0033 431.00 1.00 431.00
Waterman (Un-skilled) Day 0034 431.00 1.00 431.00
(i) Removing ballast, Slewing track by road crane
Labour Unskilled Day 0020 431.00 4.00 1,724.00
(ii) Excavation formation, installation of crib for insertion of girder
Labour Unskilled Day 0020 431.00 12.00 5,172.00
(iii) Placement of girder by road crane
Labour Unskilled Day 0020 431.00 8.00 3,448.00
Misc.:
T & P (Crow bar, tami bar, beater, hammer, Jacks, Spanner etc.) Lumpsum 9901 1.00 48.00 48.00
Hire charges of Diesel Truck - 9 tonne Day 0060 3940.00 1.00 3,940.00
Hire charges for jack of 40 MT lifting capacity Day 0105 800.00 2.00 1,600.00
Hire Charges of JCB of 0.92 cum bucket Capacity Hour 0058 800.00 4.00 3,200.00
Hiring charges of 80MT capacity crane Day 0095 35000.00 1.00 35,000.00
60,919.00
Add for working under traffic block @ 5% Lumpsum 9991 0.05 3,045.95
63,964.95
Add for Water Charges @ 1% Lumpsum 9902 0.01 639.65
64,604.60
Add for GST @ 12% (multiplying factor 0.1405) Lumpsum 9903 0.14 9,076.95
73,681.55
Add for Contractor’s Overheads and Profit @ 15% Lumpsum 9904 0.15 11,052.23
84,733.78
Add for Cess @ 1% Lumpsum 9905 0.01 847.34
Rate per Span Each 85,581.12
Draft IR Unified Stadard Analysis of Rates - 2021 Chapter - 19: Bridge Related Activities
191030 Manufacturing and using wooden sleepers/blocks required for matting and bearing as
per approved design for use below and above CC Crib for insertion of Temporary
Girder.
Note: The item is for one time use and released wooden sleepers/blocks shall be the
property of the Contractor.
Wooden Blocks required for matting and bearing at both ends on top and bottom
considering size of 3.6m x 3 m = 4 x 3.6 x 3.0 x 0.30 = 12.96 cum = 12960 cudm.
Assuming these wooden block can be used 50 times, quantity to be taken for one
time use = 12960/50 = 259.20 cudm
Hard Variety Jungle Wood blocks 10 Cudm 0343 350.00 25.92 9,072.00
Add for Water Charges @ 1% Lumpsum 9902 0.01 90.72
9,162.72
Add for GST @ 12% (multiplying factor 0.1405) Lumpsum 9903 0.14 1,287.36
10,450.08
Add for Contractor’s Overheads and Profit @ 15% Lumpsum 9904 0.15 1,567.51
12,017.59
Add for Cess @ 1% Lumpsum 9905 0.01 120.18
Cost for 12960 Cudm 12,137.77
Rate per Cum Cum 936.56
Draft IR Unified Stadard Analysis of Rates - 2021 Chapter - 19: Bridge Related Activities
191041 RH /Temporary girder of length varying from 12.2m to 16.3m using road crane
capacity of 80 tons
Details of cost for 1 set of RH girder
Material:
Acetylene Gas (in cylinder) Kg 0341 65.00 4.00 260.00
Oxygen Gas (in cylinder) Kg 0340 50.00 12.00 600.00
Labour:
Mate (Skilled) Day 0002 609.00 1.00 609.00
Blacksmith - 1st Class (Skilled) Day 0008 609.00 1.00 609.00
Welder (Skilled) Day 0029 609.00 1.00 609.00
Helper (Semi-skilled) Day 0021 505.00 4.00 2,020.00
Look Out Man (Un-skilled) Day 0033 431.00 1.00 431.00
Waterman (Un-skilled) Day 0034 431.00 1.00 431.00
(i) Removal/Slewing of girder including crib & placing on crib/cess away from track by
road crane
Labour Unskilled Day 0020 431.00 8.00 3,448.00
(ii) Filling earth,ramming,laying & linking of track
Labour Unskilled Day 0020 431.00 14.00 6,034.00
(iii) Filling ballast,packing,levelling,aligning,boxing & dressing of track
Labour Unskilled Day 0020 431.00 14.00 6,034.00
Misc.:
T & P (Crow bar, tami bar, beater, hammer, Jacks, Spanner etc.) Lumpsum 9901 1.00 40.00 40.00
Hire charges of Diesel Truck - 9 tonne Day 0060 3940.00 1.00 3,940.00
Hire charges for jack of 40 MT lifting capacity Day 0105 800.00 2.00 1,600.00
Hire Charges of JCB of 0.92 cum bucket Capacity Hour 0058 800.00 4.00 3,200.00
Hiring charges of 80MT capacity crane Day 0095 35000.00 1.00 35,000.00
64,865.00
Add for working under traffic block @ 5% Lumpsum 9991 0.05 3,243.25
68,108.25
Add for Water Charges @ 1% Lumpsum 9902 0.01 681.08
68,789.33
Add for GST @ 12% (multiplying factor 0.1405) Lumpsum 9903 0.14 9,664.90
78,454.23
Add for Contractor’s Overheads and Profit @ 15% Lumpsum 9904 0.15 11,768.14
90,222.37
Add for Cess @ 1% Lumpsum 9905 0.01 902.22
Rate per Span Each 91,124.59
191042 RH /Temporary girder of length above 16.3m and up to 26.00 using Road crane
capacity of 100Tons
Details of cost for 1 set of RH girder
Material:
Acetylene Gas (in cylinder) Kg 0341 65.00 5.00 325.00
Oxygen Gas (in cylinder) Kg 0340 50.00 15.00 750.00
Labour:
Mate (Skilled) Day 0002 609.00 2.00 1,218.00
Blacksmith - 1st Class (Skilled) Day 0008 609.00 2.00 1,218.00
Welder (Skilled) Day 0029 609.00 1.00 609.00
Helper (Semi-skilled) Day 0021 505.00 5.00 2,525.00
Look Out Man (Un-skilled) Day 0033 431.00 1.00 431.00
Waterman (Un-skilled) Day 0034 431.00 1.00 431.00
Draft IR Unified Stadard Analysis of Rates - 2021 Chapter - 19: Bridge Related Activities
192020 Extra to item no. 192010 for Track Circuited area including handling of released PVC
washers on bolts and extra rubber pads on sleepers
Detail of cost for 80 sleepers
Work involves handling of released PVC washers on bolts and extra rubber pads on
sleepers
Draft IR Unified Stadard Analysis of Rates - 2021 Chapter - 19: Bridge Related Activities
192030 Inserting in track Steel Channel/H-beam sleepers with all Railway supplied fittings
complete for TBTR work to specified gauge under traffic block with contractor’s tools
including aligning, levelling to make track fit for 20 kmph speed and as directed by
Engineer in-charge.
Note: Transportation of track material if supplied beyond 250m of bridge appraches,
shall be paid seperately under relevant item.
Details of cost for 84 sleepers (For carting & inserting Steel Channel Sleepers one
group of 4 persons will insert 12 sleepers in a day)
Labour:
Mate (Skilled) Day 0002 609.00 1.00 609.00
Look Out Man (Un-skilled) Day 0033 431.00 1.00 431.00
Waterman (Un-skilled) Day 0034 431.00 1.00 431.00
(i) For inserting sleeper with fixing fittings etc.
Labour Unskilled Day 0020 431.00 28.00 12,068.00
(ii) For guaging, aligning, levelling etc.
Blacksmith - 1st Class (Skilled) Day 0008 609.00 1.00 609.00
Helper (Semi-skilled) Day 0021 505.00 1.00 505.00
Labour Unskilled Day 0020 431.00 2.00 862.00
Misc.:
T&P Lumpsum 9901 1.00 64.00 64.00
15,579.00
Add for working under traffic block @ 10% Lumpsum 9992 0.10 1,557.90
17,136.90
Add for Water Charges @ 1% Lumpsum 9902 0.01 171.37
17,308.27
Add for GST @ 12% (multiplying factor 0.1405) Lumpsum 9903 0.14 2,431.81
19,740.08
Add for Contractor’s Overheads and Profit @ 15% Lumpsum 9904 0.15 2,961.01
22,701.09
Add for Cess @ 1% Lumpsum 9905 0.01 227.01
Cost for 84 sleepers 22,928.10
Rate per sleeper Each 272.95
192040 Extra to item no. 192030 for Track Circuited area including handling of released PVC
washers on bolts and extra rubber pads on sleepers.
Detail of cost for 84 sleepers
Work involves providing PVC washers on bolts and extra rubber pads on sleepers
Labour:
Labour Unskilled Day 0020 431.00 4.00 1,724.00
Misc.:
T&P Lumpsum 9901 1.00 14.00 14.00
1,738.00
Add for Water Charges @ 1% Lumpsum 9902 0.01 17.38
1,755.38
Draft IR Unified Stadard Analysis of Rates - 2021 Chapter - 19: Bridge Related Activities
192050 Complete Track Renewal on Bridge with Steel Channel/H-beam sleepers as per
approved drawings including leading of running and guard rails, sleepers and fittings,
bending of guard rails, drilling of holes, cutting of rails etc. and leading the released
rails, slepeers & fittings near bridge approaches under traffic block as directed and
making track structure fit for normal speed.
Note:
1) Rails, Steel Channel/H-beam sleeper and all fittings will be supplied by Railways.
2)Transportation of track material if supplied beyond 250m of bridge appraches, shall
be paid seperately under relevant item.
193020 Renewal of existing running rail and guard rails of all sections on bridge portion over
Steel Channel sleepers/PSC sleepers under traffic block including leading of new
rails,fittings, refixing all the fastenings as per approved drawings including cutting of
rails, drilling of holes to running and guard rails,as required as per drawing and
leading back the released rails and fittings and stacking at nominated place clear of
infringements with all leads & lifts tools and consumables complete and as directed.
Details of cost for 50 TRM
Material:
Drill twist made of high speed steel for size 18mm dia of Addison / I T make Each 0467 1866.40 1.00 1,866.40
Kerosene Oil Litre 0185 56.00 8.00 448.00
Normal unleaded Petrol Litre 0182 105.00 1.00 105.00
Labour:
(i) Leading new running Rails & Guard Rails and fittings on to bridge and carting back
released materials and stacking
Labour Unskilled Day 0020 431.00 16.00 6,896.00
(ii) Fixing rail with Fitting Clip
Labour Unskilled Day 0020 431.00 8.00 3,448.00
(iii) Fixing Guard rail
Mate (Skilled) Day 0002 609.00 2.00 1,218.00
Blacksmith - 1st Class (Skilled) Day 0008 609.00 2.00 1,218.00
Helper (Semi-skilled) Day 0021 505.00 2.00 1,010.00
Look Out Man (Un-skilled) Day 0033 431.00 1.00 431.00
Waterman (Un-skilled) Day 0034 431.00 1.00 431.00
Labour Unskilled Day 0020 431.00 8.00 3,448.00
Misc.:
T & P (Crow bar, Rake ballast, Auger, Beater, Spanner, Hammer etc.) Lumpsum 9901 1.00 72.00 72.00
Hire charges of Rail Cutting Machine Day 0142 300.00 0.50 150.00
Hire charges of Rail Drill Machine Day 0137 300.00 0.50 150.00
Hire charges for pillar drilling machine Day 0138 1000.00 0.50 500.00
21,391.40
Add for working under traffic block @ 10% Lumpsum 9992 0.10 2,139.14
23,530.54
Add for Water Charges @ 1% Lumpsum 9902 0.01 235.31
23,765.85
Add for GST @ 12% (multiplying factor 0.1405) Lumpsum 9903 0.14 3,339.10
27,104.95
Add for Contractor’s Overheads and Profit @ 15% Lumpsum 9904 0.15 4,065.74
31,170.69
Add for Cess @ 1% Lumpsum 9905 0.01 311.71
Cost for 50 TRM 31,482.40
Rate of TRM TRM 629.65
2,038.50
Add for Water Charges @ 1% Lumpsum 9902 0.01 20.39
2,058.89
Add for GST @ 12% (multiplying factor 0.1405) Lumpsum 9903 0.14 289.27
2,348.16
Add for Contractor’s Overheads and Profit @ 15% Lumpsum 9904 0.15 352.22
2,700.38
Add for Cess @ 1% Lumpsum 9905 0.01 27.00
Cost for 100 nos.sleeper 2,727.39
Rate per sleeper Each 27.27
194030 Drilling holes 25mm to 40mm dia. with drill twist in the foot of guard rails for fixing
guard rails on bridge as directed.
Details cost for 80 nos.
Material:
Drill twist made of high speed steel for size 26.5mm dia of Addison / I T make Each 0466 2852.30 0.50 1,426.15
Kerosene Oil Litre 0185 56.00 5.00 280.00
Normal unleaded Petrol Litre 0182 105.00 0.50 52.50
Labour:
Machinist (operator) (Skilled) Day 0040 609 1.00 609.00
Helper (Semi-skilled) Day 0021 505 1.00 505.00
Labour Unskilled Day 0020 431.00 1.00 431.00
Misc.:
T & P (Crow bar, tami bar, beater, hammer, Rail dolly, Spanner etc.) Lumpsum 9901 1.00 10.00 10.00
Hire charges for pillar drilling machine Day 0138 1000.00 0.50 500.00
3,813.65
Add for Water Charges @ 1% Lumpsum 9902 0.01 38.14
3,851.79
Add for GST @ 12% (multiplying factor 0.1405) Lumpsum 9903 0.14 541.18
4,392.96
Add for Contractor’s Overheads and Profit @ 15% Lumpsum 9904 0.15 658.94
5,051.91
Add for Cess @ 1% Lumpsum 9905 0.01 50.52
Cost for 80 nos. 5,102.43
Rate for each Each 63.78
194040 Drilling of 25mm to 40mm dia. holes in PSC sleepers with suitable rotary hammer /
drilling machine at indicated location for fixing of guard rails on bridges & its
approaches as per approved drawing and fixing of HDPE dowels with adhesive of
approved quality to Drawing no. RDSO/T-3002, procured from RDSO's approved
sources with contractor’s materials and consumable.
Draft IR Unified Stadard Analysis of Rates - 2021 Chapter - 19: Bridge Related Activities
194050 Renewal of existing guard rails of all rail sections on bridge portion over
wooden/PSC/steel channel sleepers excluding flared ends duly leading new guard
rails including cutting of rails,drilling holes to the guard rails as required and as per
drawings,refixing with all fastenings,and leading back the released rail, stacking at
nominated place clear of infringements with all leads & lifts complete and as directed.
194060 Dismantling of existing flared portion of guard rails of any rail section over PSC
sleepers duly removing rails & fastenings and leading and stacking released
materials at nominated place within free lead, clear of infringements, complete and as
directed.
Note: One set consists of LH & RH side rails of one end.
2,595.50
Add for Water Charges @ 1% Lumpsum 9902 0.01 25.96
2,621.46
Add for GST @ 12% (multiplying factor 0.1405) Lumpsum 9903 0.14 368.31
2,989.77
Add for Contractor’s Overheads and Profit @ 15% Lumpsum 9904 0.15 448.47
3,438.23
Add for Cess @ 1% Lumpsum 9905 0.01 34.38
Cost for 2 Sets 3,472.62
Rate per Set Set 1,736.31
195020 Fabrication & supply of Galvanized H-beam Sleepers made out of the materials
confirming to IS 2062 of standard Rolled sections as per approved drawing Nos
RDSO/B/1636/4/R,5&9 complete and as directed by Engineer-incharge.
Note: Cost of steel fittings and GRSP shall be paid separately.
195030 Supply of 25mm thick new rubber pads of RDSO drawing no B/1636/I/R2 from
approved sources of RDSO and replacement with old crushed rubber pads of 10mm
thickness and fixing by approved adhesive on steel channel sleepers on bridges
complete, as directed by Engineer In-charge.
Details of cost for 100 Channel sleepers ( Each sleeper having 2 Rubber pads ) i.e.
Material:
Supply of 25/30 mm thick Elastomeric Pad as per RDSO drawing No. B/1636/I/R2 Each 0432 152.00 200.00 30,400.00
Poly chloroprene rubber based solvent (toluene free) to prevent working out of rubber Kg 0492 2000.00 1.00 2,000.00
pads
Labour:
Mate (Skilled) Day 0002 609.00 1.00 609.00
Blacksmith - 1st Class (Skilled) Day 0008 609.00 1.00 609.00
Helper (Semi-skilled) Day 0021 505.00 1.00 505.00
Look Out Man (Un-skilled) Day 0033 431.00 1.00 431.00
Waterman (Un-skilled) Day 0034 431.00 1.00 431.00
Labour Unskilled Day 0020 431.00 10.00 4,310.00
Misc.:
T&P Lumpsum 9901 1.00 24.00 24.00
39,319.00
Add for Water Charges @ 1% Lumpsum 9902 0.01 393.19
39,712.19
Add for GST @ 12% (multiplying factor 0.1405) Lumpsum 9903 0.14 5,579.56
45,291.75
Add for Contractor’s Overheads and Profit @ 15% Lumpsum 9904 0.15 6,793.76
52,085.52
Add for Cess @ 1% Lumpsum 9905 0.01 520.86
Cost for 200 nos. 52,606.37
Draft IR Unified Stadard Analysis of Rates - 2021 Chapter - 19: Bridge Related Activities
195040 Supplying & fixing MS chequered plates 6 to 8mm thick between guard rails on un-
ballasted deck bridge for gang pathway, overlapping at regular intervals of 2m to
2.5m with rail screws or bolts duly drilling holes in chequered plate, as directed
Note: Overlapping of chequered plates shall not fall in between sleepers.
195050 Providing staging during traffic block to 3.6 m x 3.0 m x 3.0 m approx. size using
steel cribs and/or wooden sleepers as per RDSO’s approved drawing, duly
excavating earth in pit and driving rails / sleepers vertically to form shoring and filling
gap with sand bags etc. complete, as directed.
Note:
(1) Steel CC cribs, rails and wooden sleepers will be supplied by Railway.
(2) Dismantling and linking of track will be paid separately.
195070 Clearing waterway of major & minor bridges by removing weeds / shrubs / bushes,
removing silt deposit, filling scours, if any upto 10 metre from centre of bridge on
either side including disposing waste and silt away from waterway.
Note: Rate is for a single line and per metre of bridge span.
195080 Fabrication, supplying and fixing 600mm x 450mm Bridge Board made from 16 SWG
MS Sheet duly welded or rivited to back support of two 600mm long horizontal angles
of size 25mm x 25mm x 3mm & two 2.5 metre long vertical support of MS Angle of
size 50mm x 50mm x 5mm, welded / rivited to board. Vertical supports shall have split
ends for proper fixing in ground. Vertical supports of board shall be embedded in
ground in M 20 Cement Concrete blocks of size 300mm x 300mm x 300mm,
complete job including painting & writing of subject matter on bridge board, as
directed by Engineer - Incharge
Note: Excavation & concrete work will be paid separately.
Draft IR Unified Stadard Analysis of Rates - 2021 Chapter - 19: Bridge Related Activities
Material:
Structural Steel Plates conforming to Grade Designation E 250; Quality "A" as per IS Quintal 0223 6300.00 2.46 15,498.00
2062
H3 Electrodes as per RDSO's Spec. no. IRS M:28-2011 Nos. 0427 20.00 50.00 1,000.00
Zinc Chromate red oxide Primer to IS:2074 Litre 0308 130.00 3.00 390.00
Enamel Paint as per RDSO's Spec. no.M&C/PCN/120-2011 Litre 0306 190.00 2.00 380.00
Soft Brush for painting - 25cm long Each 0314 33.00 1.00 33.00
Paint Brush (writing) of any size Each 0315 150.00 1.00 150.00
Man Power (for fabricating) :
Blacksmith - 1st Class (Skilled) Day 0008 609.00 1.00 609.00
Welder (Skilled) Day 0029 609.00 1.00 609.00
Painter (Skilled) Day 0012 609.00 1.00 609.00
Helper (Semi-skilled) Day 0021 505.00 3.00 1,515.00
Man Power (for fixing) :
Labour Unskilled Day 0020 431.00 4.00 1,724.00
Misc.:
T&P Lumpsum 9901 1.00 18.00 18.00
Electricity Charges ( 1 Unit ) KWH 0505 7.50 50.00 375.00
Hire charges of Arc Welding Machine 500 Amp Day 0132 300.00 1.00 300.00
23,210.00
Add for Water Charges @ 1% Lumpsum 9902 0.01 232.10
23,442.10
Add for GST @ 12% (multiplying factor 0.1405) Lumpsum 9903 0.14 3,293.62
26,735.72
Add for Contractor’s Overheads and Profit @ 15% Lumpsum 9904 0.15 4,010.36
30,746.07
Add for Cess @ 1% Lumpsum 9905 0.01 307.46
Cost for 10 Boards 31,053.53
Rate per Board Each 3,105.35
195090 Shallow screening of track on ballasted deck slab bridge i.e. screening of crib ballast
and shoulder ballast in between sleeper ends and ballast retaining walls on both
sides of the track without disturbing core under the sleeper under traffic following all
safety precautions and othe instructions prescribed by Engineer in-charge. Muck
should be disposed of away from bridge upto a maximum distance of 350 m and lift
upto 10m.
Details of cost for 50 TRM (One group of 4 persons deputed for 5 track metre length)
Labour:
Mate (Skilled) Day 0002 609.00 0.50 304.50
Waterman (Un-skilled) Day 0034 431.00 1.00 431.00
Look Out Man (Un-skilled) Day 0033 431.00 1.00 431.00
Labour Unskilled Day 0020 431.00 40.00 17,240.00
Misc.:
T & P (Rake ballast, Crow bars, Hammer, Beater etc.) Lumpsum 9901 1.00 40.00 40.00
18,446.50
Add for Water Charges @ 1% Lumpsum 9902 0.01 184.47
18,630.97
Add for GST @ 12% (multiplying factor 0.1405) Lumpsum 9903 0.14 2,617.65
21,248.62
Add for Contractor’s Overheads and Profit @ 15% Lumpsum 9904 0.15 3,187.29
24,435.91
Draft IR Unified Stadard Analysis of Rates - 2021 Chapter - 19: Bridge Related Activities
195100 Bending the inner and outer 52 Kg/60Kg/90R rails availble at site suitable for V
portion along bulb of rerailing ramp as per RDSO Drg No T-8259 drilling of holes and
cutting to the required length and shape all lead, lifts, labour, tools and plants
machinery and all other required materials for bending etc, and as directed by
Engineer Incharge at site.
195110 Supplying providing and fixing country kali wood/hard wood (Non teak) sleepers of
various thickness and length as per the RDSO re railing ramp Drg No T-8259 for
fixing bent rails and MS plates including cutting the wood in saw mills, transporting to
site of work with all leads and lifts, labour, tools and plant etc. as directed by Engineer
In-charge.
195130 Tightening of steel channel sleeper fittings i.e. hook bolts, running rails bolts, guard
rail bolts on girder bridges with contractor labour tools, plants etc., including oiling,
greasing of fittings complete and as directed by engineer in charge.
Note: Before execution of work specific approval of ADEN to be obtained by duly
indicating the locations with speciic reasons along with date of last tightening done.
Details of cost for 100 sleepers. Each sleeper requires 35 gms of grease
Material:
Grease Graphite Grade 'O' (IS:408) Kg 0184 240.00 3.50 840.00
Black Oil (used lubricating oil) Litre 0475 15.00 2.00 30.00
Cotton Jute Kg 0494 40.00 2.00 80.00
Labour:
Blacksmith - 1st Class (Skilled) Day 0008 609.00 1.00 609.00
Helper (Semi-skilled) Day 0021 505.00 2.00 1,010.00
Look Out Man (Un-skilled) Day 0033 431.00 1.00 431.00
Misc.:
T&P Lumpsum 9901 1.00 10.00 10.00
3,010.00
Add for Water Charges @ 1% Lumpsum 9902 0.01 30.10
3,040.10
Add for GST @ 12% (multiplying factor 0.1405) Lumpsum 9903 0.14 427.13
3,467.23
Add for Contractor’s Overheads and Profit @ 15% Lumpsum 9904 0.15 520.09
3,987.32
Add for Cess @ 1% Lumpsum 9905 0.01 39.87
Cost for 100 sleepers 4,027.19
Rate per sleeper Sleeper 40.27
Draft IR Unified Stadard Analysis of Rates - 2021 Chapter - 20: Supply of P.Way Materials
201020 Manufacture & supply of 10mm thick Grooved Rubber Pads as per drg. No. RDSO/T-
5199 & RDSO's Spec. no. IRS-T-47-2006 (Prov.) from RDSO approved sources to
IRS specification with all contractor's lead, lift, labour, tools, plant and transportation
etc. complete as instructed by Engineer in-charge.
Note: One set constitutes two nos.
201030 Manufacture & supply of Elastomeric Pads 25mm / 30mm thick as per RDSO drawing
No. B/1636/I/R2 to suit Insulated steel channel sleepers from RDSO approved
sources with all contractor's material, lead, lift, labour, tools, plant and transportation
etc. complete as per approved drawings and as instructed by Engineer in-charge.
Note: One set constitutes two Nos.
304.00
Add for GST @ 12% (multiplying factor 0.1405) Lumpsum 9903 0.14 42.71
346.71
Add for Contractor’s Overheads and Profit @ 15% Lumpsum 9904 0.15 52.01
398.72
Add for Cess @ 1% Lumpsum 9905 0.01 3.99
Rate per Set Set 402.71
201040 Manufacture & supply of a set of 2 Nos of Elastomeric Pads 25mm / 30mm thick and
4 nos of Grooved rubber pads as per RDSO drawing No. B/1636/5 alt 2 to suit
Insulated H Beam sleepers from RDSO approved sources with all contractor's
material, lead, lift, labour, tools, plant and transportation etc. complete as per
approved drawings and as instructed by Engineer in-charge.
Note:
One Set consists of 2 nos. Elastomeric Pad 25mm/30mm and 4 nos. Grooved Rubber
Pad
201050 Manufacturing and supplying Galvanised MS Inner and Outer Clips for Steel Channel
Sleeper (RDSO Drg. No. T-6150 & T-6151) from RDSO approved sources{One set
constitutes two inner & two outer clips}
Detail cost for 1 set
Material:
Galvanised MS liner and Outer Clip for steel channel sleeper (RDSO Drg. No. T- Set 0434 434.00 1.00 434.00
6150 & T-6151)
434.00
Add for GST @ 12% (multiplying factor 0.1405) Lumpsum 9903 0.14 60.98
494.98
Add for Contractor’s Overheads and Profit @ 15% Lumpsum 9904 0.15 74.25
569.22
Add for Cess @ 1% Lumpsum 9905 0.01 5.69
Rate per set Set 574.92
201060 Manufacture, supply & fixing of galvanised steel fittings of insulated galvanised steel
channel sleeper for 60 Kg running rails & 52 Kg Guard Rail as per RDSO drawing no.
RDSO/T-5155 to 5164 with up-to-date correction slips and specifications from RDSO
approved sources with all contractor's lead, lift, labour, tools, plant, transportation etc.
complete as per approved drawings and instructions of Engineer in-charge.
201070 Manufacture, supply & fixing of galvanised steel fittings of insulated galvanised steel
channel sleeper for 52Kg running rails & 52 Kg/90R Guard Rail as per RDSO drawing
no. RDSO/T-5197 to 5200 with up-to-date correction slips and specifications from
RDSO approved sources with all contractor's lead, lift, labour, tools, plant,
transportation etc. complete as per approved drawings and instructions of Engineer in-
charge.
201080 Supplying of Zero toe load fixtures for each H Beam sleepers of 52/60Kg Rails
procured from RDSO approved firms as per RDSO approved drawing with up-to-
date correction slips and specifications with all contractor's lead, lift, labour, tools,
plant, transportation etc. complete as per approved drawings and instructions of
Engineer in-charge.
Note: Complete fixture for 1 sleeper shall constitute 1 set.
3,000.00
Add for GST @ 12% (multiplying factor 0.1405) Lumpsum 9903 0.14 421.50
3,421.50
Add for Contractor’s Overheads and Profit @ 15% Lumpsum 9904 0.15 513.23
3,934.73
Add for Cess @ 1% Lumpsum 9905 0.01 39.35
Rate per sleeper Set 3,974.07
202020 Manufacturing & supplying linked chain made of 8mm dia. rods with joints welded
with links of length not exceeding 40mm with ring & bolt at one end and hook &
locking arrangement at other end, painted with two coats of PO red paint of various
length of 5.5 m to 11 m of approved quality, as directed.
Details of cost for 140 Metre chain {8mm dia rods per metre weight = 0.39 kg/metre}
For 140 metre long chain required double length i.e.280 x 0.39 = 109.20 Kg or 1.10
Quintal + 0.20 quiantal for hooks & locking arrengements.
Material:
MS round bar for reinforcement- average rate for various dia Quintal 0220 3600.00 1.30 4,680.00
H3 Electrodes as per RDSO's Spec. no. IRS M:28-2011 Nos. 0427 20.00 120.00 2,400.00
MS Bolts & Nuts below 10mm dia Kg 0251 60.00 2.00 120.00
Zinc Chromate red oxide Primer to IS:2074 Litre 0308 130.00 1.00 130.00
Enamel Paint as per RDSO's Spec. no.M&C/PCN/120-2011 Litre 0306 190.00 1.00 190.00
Paint Brush 25 mm Each 0327 20.00 1.00 20.00
Man Power :
Blacksmith - 1st Class (Skilled) Day 0008 609.00 2.00 1,218.00
Painter (Skilled) Day 0012 609.00 1.00 609.00
Helper (Semi-skilled) Day 0021 505.00 3.00 1,515.00
Misc.:
T&P Lumpsum 9901 1.00 20.00 20.00
Electricity Charges ( 1 Unit ) KWH 0505 7.50 120.00 900.00
Hire charges of Arc Welding Machine 500 Amp Day 0132 300.00 1.00 300.00
12,102.00
Add for GST @ 12% (multiplying factor 0.1405) Lumpsum 9903 0.14 1,700.33
13,802.33
Draft IR Unified Stadard Analysis of Rates - 2021 Chapter - 20: Supply of P.Way Materials
203000 3. Level Crossing Indicator Boards, Engineering Indicators, Curve Boards etc :
Aluminum Sheet / Strips of various sizes & thickness Kg 0245 200.00 3.00 600.00
Aluminum sheet @ 6.23 kg/sqm
High intensity retro-reflective sheet Sqm 0476 1625 0.49 796.25
Considering 5% wastage i.e 0.47 + 0.024 = 0.49 Sqm
Structural Steel Plates conforming to Grade Designation E 250; Quality "A" as per IS Quintal 0223 6300.00 0.22 1,386.00
Draft IR Unified Stadard Analysis of Rates - 2021 Chapter - 20: Supply of P.Way Materials
Detail of cost for one board of size (675mm x 525mm) with support length of
3650mm. So Area of board = 0.354sqm
Material:
Aluminum Sheet / Strips of various sizes & thickness Kg 0245 200.00 2.21 442.00
Aluminum sheet @ 6.23 kg/sqm
High intensity retro-reflective sheet Sqm 0476 1625 0.37 601.25
Considering 5% wastage i.e 0.354 + 0.024 = 0.37 Sqm
Structural Steel Plates conforming to Grade Designation E 250; Quality "A" as per IS Quintal 0223 6300.00 0.20 1,260.00
Rivets (different sizes) for miscellaneous works. Kg 0233 54.50 0.20 10.90
Zinc Chromate red oxide Primer to IS:2074 Litre 0308 130.00 0.60 78.00
Enamel Paint as per RDSO's Spec. no.M&C/PCN/120-2011 Litre 0306 190.00 0.50 95.00
Paint Brush 25 mm Each 0327 20.00 0.40 8.00
Man Power:
Blacksmith - 1st Class (Skilled) Day 0008 609.00 0.40 243.60
Painter (Skilled) Day 0012 609.00 0.20 121.80
Helper (Semi-skilled) Day 0021 505.00 0.60 303.00
T & P (Including cost of materials for drilling holes nuts bolts etc.) Lumpsum 9901 1.00 40.00 40.00
3,203.55
Add for GST @ 12% (multiplying factor 0.1405) Lumpsum 9903 0.14 450.10
3,653.65
Add for Contractor’s Overheads and Profit @ 15% Lumpsum 9904 0.15 548.05
4,201.70
Add for Cess @ 1% Lumpsum 9905 0.01 42.02
Cost for 1 board set 4,243.71
Rate per set Set 4,243.71
Material:
Aluminum Sheet / Strips of various sizes & thickness Kg 0245 200.00 3.90 780.00
Aluminum sheet @ 6.23 kg/sqm
High intensity retro-reflective sheet Sqm 0476 1625 0.65 1,056.25
Considering 5% wastage i.e 0.62 + 0.031 = 0.65 Sqm
Structural Steel Plates conforming to Grade Designation E 250; Quality "A" as per IS Quintal 0223 6300.00 0.22 1,386.00
2062
Rivets (different sizes) for miscellaneous works. Kg 0233 54.50 0.25 13.63
Zinc Chromate red oxide Primer to IS:2074 Litre 0308 130.00 1.00 130.00
Enamel Paint as per RDSO's Spec. no.M&C/PCN/120-2011 Litre 0306 190.00 0.75 142.50
Paint Brush 25 mm Each 0327 20.00 0.50 10.00
Draft IR Unified Stadard Analysis of Rates - 2021 Chapter - 20: Supply of P.Way Materials
203015 Single Strip / Double Strip Level Crossing Road Warning Board
Detail of cost for one board of size ( 675 x 525mm) with support length of 3650mm.
Material:
Aluminum Sheet / Strips of various sizes & thickness Kg 0245 200.00 2.21 442.00
Aluminum sheet @ 6.23 kg/sqm
High intensity retro-reflective sheet Sqm 0476 1625 0.37 601.25
Considering 5% wastage i.e 0.47 + 0.024 = 0.49 Sqm
Structural Steel Plates conforming to Grade Designation E 250; Quality "A" as per IS Quintal 0223 6300.00 0.20 1,260.00
Rivets (different sizes) for miscellaneous works. Kg 0233 54.50 0.20 10.90
Zinc Chromate red oxide Primer to IS:2074 Litre 0308 130.00 0.60 78.00
Enamel Paint as per RDSO's Spec. no.M&C/PCN/120-2011 Litre 0306 190.00 0.50 95.00
Paint Brush 25 mm Each 0327 20.00 0.40 8.00
Man Power:
Blacksmith - 1st Class (Skilled) Day 0008 609.00 0.40 243.60
Painter (Skilled) Day 0012 609.00 0.20 121.80
Helper (Semi-skilled) Day 0021 505.00 0.60 303.00
Misc:
T & P (Including cost of materials for drilling holes nuts bolts etc.) Lumpsum 9901 1.00 40.00 40.00
3,203.55
Add for GST @ 12% (multiplying factor 0.1405) Lumpsum 9903 0.14 450.10
3,653.65
Add for Contractor’s Overheads and Profit @ 15% Lumpsum 9904 0.15 548.05
4,201.70
Add for Cess @ 1% Lumpsum 9905 0.01 42.02
Rate per set Set 4,243.71
203016 Manufacturing and supply of circular STOP Disc of 600mm dia for fixing on
emergency chains at level crossings as given in IRPWM including providing Retro
reflective sheet fully covered over board confirming to type-IV of ASTM-D4956 in red
back ground colour and text "STOP" of white colour over back ground.The circular
board shall consists of 2mm thick Aluminium sheet fixed to 1.5mm thick MS Sheet of
600mm dia with suitable sized aluminium alloy rivets @ 20 cm c/c to back-support
.Retro reflective sheet is to be pasted on substrate by an adhesive backing which
shall be activated by applying heat and pressure conforming to class-2 of ASTM-D-
4956-01.A vertical holding stand of 1000 mm length x15mm thick to be jointed to back
side of board along with a hook for fixing emergency chain as directed by Engineer
Incharge.
Detail of cost for one Stop Disc of Circular shape having diameter of 600mm with
support length of 1000mm. So Area of board is = 0.283sqm + wastage 25% for
circular shape = 0.36 Sqm
Material:
Aluminum Sheet / Strips of various sizes & thickness Kg 0245 200.00 2.25 450.00
Aluminum sheet @ 6.23 kg/sqm
High intensity retro-reflective sheet Sqm 0476 1625.00 0.38 617.50
Considering 5% wastage i.e 0.36 + 0.018 = 0.38 Sqm
Structural Steel Plates conforming to Grade Designation E 250; Quality "A" as per IS Quintal 0223 6300.00 0.06 378.00
2062
Draft IR Unified Stadard Analysis of Rates - 2021 Chapter - 20: Supply of P.Way Materials
Rivets (different sizes) for miscellaneous works. Kg 0233 54.50 0.20 10.90
Zinc Chromate red oxide Primer to IS:2074 Litre 0308 130.00 0.60 78.00
Enamel Paint as per RDSO's Spec. no.M&C/PCN/120-2011 Litre 0306 190.00 0.50 95.00
Paint Brush 25 mm Each 0327 20.00 0.40 8.00
Man Power:
Blacksmith - 1st Class (Skilled) Day 0008 609.00 0.50 304.50
Painter (Skilled) Day 0012 609.00 0.20 121.80
Helper (Semi-skilled) Day 0021 505.00 1.00 505.00
Misc:
T & P (Including cost of materials for drilling holes nuts bolts etc.) Lumpsum 9901 1.00 50.00 50.00
2,618.70
Add for GST @ 12% (multiplying factor 0.1405) Lumpsum 9903 0.14 367.93
2,986.63
Add for Contractor’s Overheads and Profit @ 15% Lumpsum 9904 0.15 447.99
3,434.62
Add for Cess @ 1% Lumpsum 9905 0.01 34.35
Rate per Board Each 3,468.97
Rivets (different sizes) for miscellaneous works. Kg 0233 54.50 0.25 13.63
Zinc Chromate red oxide Primer to IS:2074 Litre 0308 130.00 0.85 110.50
Enamel Paint as per RDSO's Spec. no.M&C/PCN/120-2011 Litre 0306 190.00 0.75 142.50
Paint Brush 25 mm Each 0327 20.00 0.50 10.00
Man Power:
Blacksmith - 1st Class (Skilled) Day 0008 609.00 0.50 304.50
Painter (Skilled) Day 0012 609.00 0.25 152.25
Helper (Semi-skilled) Day 0021 505.00 0.75 378.75
T & P (Including cost of materials for drilling holes nuts bolts etc.) Lumpsum 9901 1.00 50.00 50.00
4,458.88
Add for GST @ 12% (multiplying factor 0.1405) Lumpsum 9903 0.14 626.47
5,085.35
Add for Contractor’s Overheads and Profit @ 15% Lumpsum 9904 0.15 762.80
5,848.15
Add for Cess @ 1% Lumpsum 9905 0.01 58.48
Rate per board Each 5,906.63
Draft IR Unified Stadard Analysis of Rates - 2021 Chapter - 20: Supply of P.Way Materials
203030 Manufacturing and supplying Trolley Refuge Indicator Boards / Level Crossing No.
Boards, made of MS sheet of 2mm thick of size 240mm dia. and 50mm x 50mm x
6mm angle, welded to MS sheet, duly painting with 2 coats of ready mixed yellow
enamel paint over one coat of red oxide with all lead & lift as per specification and as
directed by Engineer in-charge
Material:
H3 Electrodes as per RDSO's Spec. no. IRS M:28-2011 Nos. 0427 20.00 4.00 80.00
Zinc Chromate red oxide Primer to IS:2074 Litre 0308 130.00 1.00 130.00
Enamel Paint as per RDSO's Spec. no.M&C/PCN/120-2011 Litre 0306 190.00 2.50 475.00
Structural Steel Plates conforming to Grade Designation E 250; Quality "A" as per IS Quintal 0223 6300.00 0.52 3,276.00
2062
Paint Brush 25 mm Each 0327 20.00 1.00 20.00
Man Power:
Blacksmith - 1st Class (Skilled) Day 0008 609.00 2.00 1,218.00
Welder (Skilled) Day 0029 609 1.00 609.00
Painter (Skilled) Day 0012 609.00 1.00 609.00
Helper (Semi-skilled) Day 0021 505.00 3.00 1,515.00
T&P Lumpsum 9901 1.00 50.00 50.00
7,982.00
Add for GST @ 12% (multiplying factor 0.1405) Lumpsum 9903 0.14 1,121.47
9,103.47
Add for Contractor’s Overheads and Profit @ 15% Lumpsum 9904 0.15 1,365.52
10,468.99
Add for Cess @ 1% Lumpsum 9905 0.01 104.69
Cost for 10 no. 10,573.68
Rate per unit Each 1,057.37
203040 Manufacturing, supplying and fixing Curve Indicator / Point Indicator / SEJ Boards to
be provided at various locations on formation, made out of MS sheet 2mm thick of
size 450mm x 300mm duly fixed with MS frame of 25mm x 25mm x 3mm angle
welded to 50mm x 50mm x 3mm MS angle, 1000mm long post split and bent 100mm
at bottom end with all lead & lift as per specification and including painting of details
with enamel paint, as directed by Engineer in-charge (Earthwork & concreting will be
paid separately)
Draft IR Unified Stadard Analysis of Rates - 2021 Chapter - 20: Supply of P.Way Materials
Material:
H3 Electrodes as per RDSO's Spec. no. IRS M:28-2011 Nos. 0427 20.00 8.00 160.00
Zinc Chromate red oxide Primer to IS:2074 Litre 0308 130.00 2.00 260.00
Enamel Paint as per RDSO's Spec. no.M&C/PCN/120-2011 Litre 0306 190.00 4.00 760.00
Holding down HTS bolts with plates, nuts etc. Quintal 0235 7500 4.00 30,000.00
Structural Steel Plates conforming to Grade Designation E 250; Quality "A" as per IS Quintal 0223 6300.00 1.40 8,820.00
2062
Paint Brush 25 mm Each 0327 20.00 1.00 20.00
Man Power:
Blacksmith - 1st Class (Skilled) Day 0008 609.00 2.00 1,218.00
Painter (Skilled) Day 0012 609.00 1.00 609.00
Welder (Skilled) Day 0029 609.00 1.00 609.00
Helper (Semi-skilled) Day 0021 505.00 3.00 1,515.00
Labour Unskilled Day 0020 431.00 2.00 862.00
T&P Lumpsum 9901 1.00 50.00 50.00
44,883.00
Add for GST @ 12% (multiplying factor 0.1405) Lumpsum 9903 0.14 6,306.06
51,189.06
Add for Contractor’s Overheads and Profit @ 15% Lumpsum 9904 0.15 7,678.36
58,867.42
Add for Cess @ 1% Lumpsum 9905 0.01 588.67
Cost for 20 nos. 59,456.09
Rate per unit Each 2,972.80
204012 16 mm dia.
Detail cost for each.
Material:
Drill twist made of high speed of size 16 mm dia of Addison / I.T. make Each 0464 1631.50 1.00 1,631.50
1,631.50
Add for GST @ 12% (multiplying factor 0.1405) Lumpsum 9903 0.14 229.23
1,860.73
Draft IR Unified Stadard Analysis of Rates - 2021 Chapter - 20: Supply of P.Way Materials
204013 18 mm dia.
Detail cost for each.
Material:
Drill twist made of high speed steel for size 18mm dia of Addison / I T make Each 0467 1866.40 1.00 1,866.40
1,866.40
Add for GST @ 12% (multiplying factor 0.1405) Lumpsum 9903 0.14 262.23
2,128.63
Add for Contractor’s Overheads and Profit @ 15% Lumpsum 9904 0.15 319.29
2,447.92
Add for Cess @ 1% Lumpsum 9905 0.01 24.48
Rate per unit Each 2,472.40
205030 Manufacture & supply of wire brush 25mm long, as directed by Engineer in-charge
Draft IR Unified Stadard Analysis of Rates - 2021 Chapter - 20: Supply of P.Way Materials
211020 Erection or removal of temporary Engineering Indicator Board or any other board at
specified locations without causing infringement to track etc. complete and as
directed.
Draft IR Unified Stadard Analysis of Rates - 2021 Chapter - 21: Miscellaneous Items
Item no. Description Unit Rate Rate (Rs) Quantity Amount (Rs.)
Code
211021 For erection
Details of cost for 10 boards
Labour:
Mate (Skilled) Day 0002 609.00 0.50 304.50
Labour Unskilled Day 0020 431.00 3.00 1,293.00
Misc.:
T&P Lumpsum 9901 1.00 10.00 10.00
1,607.50
Add for Water Charges @ 1% Lumpsum 9902 0.01 16.08
1,623.58
Add for GST @ 12% (multiplying factor 0.1405) Lumpsum 9903 0.14 228.11
1,851.69
Add for Contractor’s Overheads and Profit @ 15% Lumpsum 9904 0.15 277.75
2,129.44
Add for Cess @ 1% Lumpsum 9905 0.01 21.29
Cost for 10 boards 2,150.73
Rate per board Each 215.07
211030 Fabricating of check rails of 52Kg and 90R sections for providing to curves by
cutting web of rail horizontally by gas, grinding for smoothening the cut edge and
drilling of parabolic shaped holes to the web of check rails as per drawing and
specification and as per directions of engineer in-charge with all contractor’s labour,
tools and materials complete.
Note:
1. Rails shall be supplied by Railways
2.The both ends of head of check rails are to bent/cut as per drawing.
3. The released rail scrap shall be stacked neatly with in a lead of 500m.
4.Drilling of holes shall be paid under relavant item.
Item no. Description Unit Rate Rate (Rs) Quantity Amount (Rs.)
Code
12,536.12
Add for GST @ 12% (multiplying factor 0.1405) Lumpsum 9903 0.14 1,761.32
14,297.44
Add for Contractor’s Overheads and Profit @ 15% Lumpsum 9904 0.15 2,144.62
16,442.06
Add for Cess @ 1% Lumpsum 9905 0.01 164.42
Cost for 100 RM 16,606.48
Rate per RM RM 166.06
211040 Dismantling Check Rail on curves on track of all rail sections, duly removing fish
plates and bolts including removing chairs from sleepers, leading and stacking
released materials away from track clear of infringements, complete and as directed.
211050 Fixing of check rails on curves on track of all rail sections as per drawing and to
correct alignment and level with Railways fastenings including leading of rails and
fittings,crossing of tracks, greasing of plate screws with approved grease etc., as per
drawing and directions of Engineer incharge with all contractors labour, tools, plants,
machinery, consumables etc., complete.
Note: Required P.Way fittings will be supplied at SSE/P.Way stores.
Item no. Description Unit Rate Rate (Rs) Quantity Amount (Rs.)
Code
Misc.:
T & P (Crow bars,Rail tongs,spanners etc ) Lumpsum 9901 1.00 30.00 30.00
4,528.50
Add for Water Charges @ 1% Lumpsum 9902 0.01 45.29
4,573.79
Add for GST @ 12% (multiplying factor 0.1405) Lumpsum 9903 0.14 642.62
5,216.40
Add for Contractor’s Overheads and Profit @ 15% Lumpsum 9904 0.15 782.46
5,998.86
Add for Cess @ 1% Lumpsum 9905 0.01 59.99
Cost for 96 RM 6,058.85
Rate per RM RM 63.11
211060 Supply and fixing in position pre-cast cement concrete Fouling Mark as per approved
drawing at station yard, duly painting letters of Fouling Mark, complete in all respects
with all labour, materials including cement, tools and plants etc.
211070 Providing and erecting water proof Gypsy Tent of size 3m x 3m for a specific period of
time and removal of the same after completion of work or as directed by Engineer in-
charge.
Item no. Description Unit Rate Rate (Rs) Quantity Amount (Rs.)
Code
211080 Provision of furniture temporarily for site work in good condition at different locations
as per direction of Engineer In-charge, for a specific period of time & removing the
same after completion of work.
211100 Removing /Re-erecting existing Gradient Post / Kilometre Post, duly demolishing
concrete foundation, fixing the post in cement concrete foundation as per drawing
with 1:3:6 mix using 20mm hard aggregate, as directed (Cost of concrete work will be
paid under relevant item separately).
Item no. Description Unit Rate Rate (Rs) Quantity Amount (Rs.)
Code
211102 For Fixing / Re-erecting
Details of cost for 6 post
Labour:
Labour Unskilled Day 0020 431.00 2.00 862.00
T & P (Crow bar, Chisel, Hammer, Phawra etc.) Lumpsum 9901 1.00 10.00 10.00
872.00
Add for Water Charges @ 1% Lumpsum 9902 0.01 8.72
880.72
Add for GST @ 12% (multiplying factor 0.1405) Lumpsum 9903 0.14 123.74
1,004.46
Add for Contractor’s Overheads and Profit @ 15% Lumpsum 9904 0.15 150.67
1,155.13
Add for Cess @ 1% Lumpsum 9905 0.01 11.55
Cost for 6 post 1,166.68
Rate per post Each 194.45
211110 Breaking the damaged PSC sleepers including dragging, if required duly removing
inserts safely and handing over inserts to Railways at Stores or Depot of SSE/P.Way,
including disposing the broken concrete pieces, as directed by Engineer in-charge.
Released HTS wire shall be the property of Contractor.
211120 Fixing vertically the unserviceable PSC sleepers at locations of tress-passing, railway
boundary or to make temporary store by excavating trench, fixing PSC sleeper in
trench and filling back open trench.
Item no. Description Unit Rate Rate (Rs) Quantity Amount (Rs.)
Code
211130 Providing and fixing Trolley Refuge of size 3.0m x3.0m on cess, placing with
released unserviceable PSC sleepers and keepeing them at all four sides of refuge
and also placing as matting inside the refuge by keeping them in upside down
position with a minmum of 10 sleepers including levelling with earth, excavation, all
lead and lift, crossing of tracks,leading the sleepers with in a free lead and lift,
handling etc., with all contractor's men material complete and as directed by the
Engineer-in-charge.
Note: Earth-work will to be paid separately under relavent item.
Details of cost for 6 no's Trolley refuge { For one trolly refuge required 84 no's U/s
Labour:
Mate (Skilled) Day 0002 609.00 1.00 609.00
Waterman (Un-skilled) Day 0034 431.00 1.00 431.00
Labour Unskilled Day 0020 431.00 30.00 12,930.00
Misc.:
T&P Lumpsum 9901 1.00 10.00 10.00
Hire charges for tractor with trolley Day 0081 1200.00 1.00 1,200.00
15,180.00
Add for Water Charges @ 1% Lumpsum 9902 0.01 151.80
15,331.80
Add for GST @ 12% (multiplying factor 0.1405) Lumpsum 9903 0.14 2,154.12
17,485.92
Add for Contractor’s Overheads and Profit @ 15% Lumpsum 9904 0.15 2,622.89
20,108.81
Add for Cess @ 1% Lumpsum 9905 0.01 201.09
Cost for 6 no's Trolley refuge 20,309.89
Rate for each Each 3,384.98
211140 Supplying and spraying in specified proportion Weedicide Chemical, capable to kill
entire weed on track / cess / embankment with all labour, material, tools & plants etc.
complete job in all respect. Scientific name of the chemical is Isopropylamine Salt of
Glyphosate, in which active ingredient is Glyphosate (41%), colour is light amber to
brownish, very low in toxicity and has favourable enviremental characteristics. It will
be ensured that no weed growth occurs upto six months period, otherwise respraying
shall be done by the contractor free of cost.
211150 Supplying & applying single liquid solution in 250ml pack, having break loose torque
of 400Nm to 540Nm, as per ISO:10123 norms with shear strength of liquid solutions
as 25 to 35 N/mm2, viscosity 1500 to 3000 (Centipoise) & specific gravity of 1.1 ±
0.05. for tightening of nuts & bolts at important locations, such as Bridges, SEJs,
Turnouts, Fish Plates, Steel Channel Sleepers etc. Work includes opening of bolts,
cleaning of bolts with suitable cleaner and tightening of bolts after applying liquid
solution as directed by Engineer in-charge.
Draft IR Unified Stadard Analysis of Rates - 2021 Chapter - 21: Miscellaneous Items
Item no. Description Unit Rate Rate (Rs) Quantity Amount (Rs.)
Code
211151 Bolts dia. 20mm to 25mm
Details of cost for 100 nos Nut & Bolts
Material:
Liquid solution in 250ml pack, having break loose torque of 400Nm to 540Nm, as per Each 0491 2500.00 0.30 750.00
Kerosene Oil Litre 0185 56.00 1.00 56.00
Wire Brush - 25cm long Each 0313 15.00 1.00 15.00
Soft Brush for painting - 25cm long Each 0314 33.00 1.00 33.00
Labour:
Mate (Skilled) Day 0002 609.00 0.25 152.25
Labour Unskilled Day 0020 431.00 2.00 862.00
T&P Lumpsum 9901 1.00 10.00 10.00
1,878.25
Add for Water Charges @ 1% Lumpsum 9902 0.01 18.78
1,897.03
Add for GST @ 12% (multiplying factor 0.1405) Lumpsum 9903 0.14 266.53
2,163.57
Add for Contractor’s Overheads and Profit @ 15% Lumpsum 9904 0.15 324.53
2,488.10
Add for Cess @ 1% Lumpsum 9905 0.01 24.88
Cost for 100 nos 2,512.98
Rate per unit Each 25.13
Item no. Description Unit Rate Rate (Rs) Quantity Amount (Rs.)
Code
2,656.25
Add for Water Charges @ 1% Lumpsum 9902 0.01 26.56
2,682.81
Add for GST @ 12% (multiplying factor 0.1405) Lumpsum 9903 0.14 376.94
3,059.75
Add for Contractor’s Overheads and Profit @ 15% Lumpsum 9904 0.15 458.96
3,518.71
Add for Cess @ 1% Lumpsum 9905 0.01 35.19
Cost for 100 nos 3,553.90
Rate per unit Each 35.54
211160 Supplying & applying of Poly Chloroprene rubber-based Solvent (toulene free, i.e. not
harmful to human body) to prevent working out of rubber pads, having density
0.85±0.01 gm/cm3, viscosity of solvent as 1500 to 1900 (centipoise) at 30 degree
centigrade & shear strength 8 to 12 Kg/Sq.In. for bonding rubber pads / GR Sole
Plates on PSC sleepers complete job, as directed by Engineer in-charge.
Item no. Description Unit Rate Rate (Rs) Quantity Amount (Rs.)
Code
211163 1 in 12 Turnout Set
Detail of cost for 1 set ( 315 Rubber Pads in each set )
Material:
Poly chloroprene rubber based solvent (toluene free) to prevent working out of rubber Kg 0492 2000.00 2.25 4,500.00
pads
Paint Brush 25 mm Each 0327 20.00 1.00 20.00
Labour:
Helper (Semi-skilled) Day 0021 505.00 1.00 505.00
Labour Unskilled Day 0020 431.00 2.00 862.00
T&P Lumpsum 9901 1.00 10.00 10.00
5,897.00
Add for Water Charges @ 1% Lumpsum 9902 0.01 58.97
5,955.97
Add for GST @ 12% (multiplying factor 0.1405) Lumpsum 9903 0.14 836.81
6,792.78
Add for Contractor’s Overheads and Profit @ 15% Lumpsum 9904 0.15 1,018.92
7,811.70
Add for Cess @ 1% Lumpsum 9905 0.01 78.12
Cost for 1 Set 7,889.82
Rate per set Set 7,889.82
Item no. Description Unit Rate Rate (Rs) Quantity Amount (Rs.)
Code
211166 1 in 8½ Crossing Assembly
Detail of cost for 4 set ( 18 Rubber Pads in each set )
Material:
Poly chloroprene rubber based solvent (toluene free) to prevent working out of rubber Kg 0492 2000.00 0.65 1,300.00
pads
Paint Brush 25 mm Each 0327 20.00 1.00 20.00
Labour:
Helper (Semi-skilled) Day 0021 505.00 1.00 505.00
Labour Unskilled Day 0020 431.00 1.00 431.00
T&P Lumpsum 9901 1.00 10.00 10.00
2,266.00
Add for Water Charges @ 1% Lumpsum 9902 0.01 22.66
2,288.66
Add for GST @ 12% (multiplying factor 0.1405) Lumpsum 9903 0.14 321.56
2,610.22
Add for Contractor’s Overheads and Profit @ 15% Lumpsum 9904 0.15 391.53
3,001.75
Add for Cess @ 1% Lumpsum 9905 0.01 30.02
Cost for 4 Set 3,031.77
Cost for Each Set Set 757.94
Item no. Description Unit Rate Rate (Rs) Quantity Amount (Rs.)
Code
Add for Water Charges @ 1% Lumpsum 9902 0.01 868.82
87,750.82
Add for GST @ 12% (multiplying factor 0.1405) Lumpsum 9903 0.14 12,328.99
100,079.81
Add for Contractor’s Overheads and Profit @ 15% Lumpsum 9904 0.15 15,011.97
115,091.78
Add for Cess @ 1% Lumpsum 9905 0.01 1,150.92
Cost for 5 MT 116,242.70
Rate per MT MT 23,248.54
211200 Hiring of JCB upto 1 cum bucket capacity or other similar machinery for levelling and
dressing ground/dismantling structures, Removal of jungle, clearing of earth, lowering
high cess etc., along side the track between up and down lines obstructing drainages
of rain water, clearing of bushes obstructing visibility at curves and Level Crossings
with all lead and lift etc. complete and as directed by the Engineer-in-charge. All
labour, tools and plants consumables stores including supply of earth mover with
crew to be provided by the contractor at his own cost. The contractor shall arrange
road permit for vehicle for all the States of operation, as per instructions of engineer in-
charge and vehicle shall not be more than three years old. Payment shall be made for
actual working hours at site.
211210 Arranging labour as and when required by the Engineer incharge, for various works
under SSE/P.Way, with contractor's T&P, equipments, hand signal flags, etc. as per
specifications, special conditions and detailed scope of work as furnished in the
tender and as directed by the Engineer incharge.
Note: Item shall be operated with prior approval of concerned Sr. DEN / DEN
incharge.
Labour:
Labour Unskilled Day 0020 431.00 1.00 431.00
Misc.:
T & P (Crow bar, Hammer,spanner, mortar pan etc.) Lumpsum 9901 1.00 10.00 10.00
441.00
Add for Water Charges @ 1% Lumpsum 9902 0.01 4.41
Draft IR Unified Stadard Analysis of Rates - 2021 Chapter - 21: Miscellaneous Items
Item no. Description Unit Rate Rate (Rs) Quantity Amount (Rs.)
Code
445.41
Add for GST @ 12% (multiplying factor 0.1405) Lumpsum 9903 0.14 62.58
507.99
Add for Contractor’s Overheads and Profit @ 15% Lumpsum 9904 0.15 76.20
584.19
Add for Cess @ 1% Lumpsum 9905 0.01 5.84
Rate per labour per day Day 590.03
211220 Supplying and filling 50 kg size empty cement polythene bags with Rly.
Ballast/moorum/earth/Sand/quarry dust etc. placing the filled bags on the high banks
/bridge approaches/nominated place etc. dumping and spreading at the nominated
locations to profile under block period with all contractor's labour, tools, plants. ,
loading, unloading, filling, spreading including all lead/lift etc. complete and as
directed by the Engineer in charge at site including crossing of track where
necessary.
Details of Cost for 400 bags
Material
Empty cement bag polythene 50 Kgs capacity Each 0495 5.00 400.00 2,000.00
Labour:
Filling and carrying then to high banks.bridge approaches/nominated place including
Mate (Skilled) Day 0002 609.00 0.50 304.50
Labour Unskilled Day 0020 431.00 4.00 1,724.00
Misc.:
T&P Lumpsum 9901 1.00 10.00 10.00
4,038.50
Add for Water Charges @ 1% Lumpsum 9902 0.01 40.39
4,078.89
Add for GST @ 12% (multiplying factor 0.1405) Lumpsum 9903 0.14 573.08
4,651.97
Add for Contractor’s Overheads and Profit @ 15% Lumpsum 9904 0.15 697.80
5,349.76
Add for Cess @ 1% Lumpsum 9905 0.01 53.50
Cost of 400 bags 5,403.26
Rate per bag Each 13.51
211230 Filling and stacking of sand bags layer by layer filled with Railway Sand/railway quarry
dust in Contractor's empty polythene cement bags of 50 kg bags with all contractors
labour, tools, plants, lead, lift etc., including stiching the same with machine using
polythene thread complete as directed by Engineer-incharge at site.
211240 Loading of sand/quarry dust filled bags from Railway stacks in to Railway Wagons
with all contractor's tools & plants, machinary, labour, lead and lift, crossing of track
wherever necessary etc., complete as directed by the Engineer Incharge.
Details of Cost for 780 bags
Material:
Draft IR Unified Stadard Analysis of Rates - 2021 Chapter - 21: Miscellaneous Items
Item no. Description Unit Rate Rate (Rs) Quantity Amount (Rs.)
Code
Empty cement bag polythene 50 Kgs capacity Each 0495 5.00 780.00 3,900.00
Labour:
For loading of bags in to vehicles
Mate (Skilled) Day 0002 609.00 0.50 304.50
Labour Unskilled Day 0020 431.00 6.00 2,586.00
Sundries Lumpsum 9901 1.00 10.00 10.00
6,800.50
Add for Water Charges @ 1% Lumpsum 9902 0.01 68.01
6,868.51
Add for GST @ 12% (multiplying factor 0.1405) Lumpsum 9903 0.14 965.02
7,833.53
Add for Contractor’s Overheads and Profit @ 15% Lumpsum 9904 0.15 1,175.03
9,008.56
Add for Cess @ 1% Lumpsum 9905 0.01 90.09
Cost of 780 Bags 9,098.65
Rate per bag Each 11.66
211250 Manufacturing and fixing buffer stop with Railway supplied rails, cutting, including
bending of rails as per plan ,with all contractor’s labour,materials, tools, plants etc.
and all lead and lift including crossing of track where necessary and as directed by
Engineer in charge at site.
Note: Excavation, fixing rails in cement concrete, drilling of holes will be paid
seperately.
211260 Manufacture and supply of Precast Kilometer Posts of size 1.15x0.50m and 75mm
thick in RCC 1:2:4 mix, engraving letters and leading to work spot, fixing in position
with CC 1:3:6 concrete duly making pits of size as required, painting the post, writing
the letters on both sides of the post with 2 coats of enamel paint of approved quality
to the Railways drawings/IRPWM with contractor's materials, cement, steel, labour,
tools, plant, with all lead and lifts etc., complete as per specifications and as directed
by the Engineer-in-charge.
Note: Excavation, Concrete and steel work will be paid under relavent items.
Item no. Description Unit Rate Rate (Rs) Quantity Amount (Rs.)
Code
T&P ( crow bars,shovels etc) Lumpsum 9901 1.00 20.00 20.00
Hire charges for tractor with trolley Day 0081 1200.00 1.00 1,200.00
8,317.00
Add for Water Charges @ 1% Lumpsum 9902 0.01 83.17
8,400.17
Add for GST @ 12% (multiplying factor 0.1405) Lumpsum 9903 0.14 1,180.22
9,580.39
Add for Contractor’s Overheads and Profit @ 15% Lumpsum 9904 0.15 1,437.06
11,017.45
Add for Cess @ 1% Lumpsum 9905 0.01 110.17
Cost of 30 Boards 11,127.63
Rate per Board Each 370.92
211270 Manufacture and supply of Precast gradient Posts of size 1.65 x 0.60 m and 75mm
thick in RCC 1:2:4 mix, engraving letters and leading to work spot, fixing in position
with CC 1:3:6 concrete duly making pits of size as required, painting the post, writing
the letters on both sides of posts in 2 coats with enamel paint of approved quality to
the Railways drawings/IRPWM with contractor's materials, cement, steel, labour,
tools, plant, with all lead and lifts etc., complete as per specifications and as directed
by the Engineer-in-charge.
Note: Excavation,Concrete and steel work will be paid under relavent items.
Item no. Description Unit Rate Rate (Rs) Quantity Amount (Rs.)
Code
T&P ( crow bars,shovels etc) Lumpsum 9901 1.00 30.00 30.00
Hire charges for tractor with trolley Day 0081 1200.00 1.00 1,200.00
12,774.00
Add for Water Charges @ 1% Lumpsum 9902 0.01 127.74
12,901.74
Add for GST @ 12% (multiplying factor 0.1405) Lumpsum 9903 0.14 1,812.69
14,714.43
Add for Contractor’s Overheads and Profit @ 15% Lumpsum 9904 0.15 2,207.17
16,921.60
Add for Cess @ 1% Lumpsum 9905 0.01 169.22
Cost of 100 Boards 17,090.82
Rate per Board Each 170.91
Analysis of Rates for transportation P. Way Material other than PSC sleeper, Rails, Switches, Glued Joints, & Crossings
Rate Linked
Name Unit Rate Code to Basic
Sheet
Hire Day 0059 2000.00
Charges of
Truck - 9
Diesel Litre 0181 101.62
Beldar (Un Day 0025 431.00
Diesel kmpl 5.00
Mobile oil kmpl 140.00
Time of hour 1.00
Distance kmpl 6.00
from
Lead in Average Nos. of Nos. of km Litres of Cost of Hire Total Cost = Cost per Trip Cost per Rate per
km (L) Speed IN Trips Done in Diesel Diesel Charges of col. 6+7 = Col.10/Col.3 tonne tonne per
KMPH (S) N=8/(2L/S) one day consumed Truck km
+0.5 (2NL+6) (0084)
1 2 3 4 5 6 7 8 9 10 11
1 16.00 7.11 20.22 4.04 411.00 2,000.00 2,411.00 339.05 37.67 37.67
2 17.00 6.48 31.90 6.38 648.43 2,000.00 2,648.43 408.95 45.44 22.72
2.50 17.25 6.20 37.01 7.40 752.22 2,000.00 2,752.22 443.75 49.31 19.72
3 17.50 5.96 41.74 8.35 848.42 2,000.00 2,848.42 478.13 53.13 17.71
4 18.00 5.54 50.31 10.06 1,022.45 2,000.00 3,022.45 545.72 60.64 15.16
5 18.50 5.19 57.93 11.59 1,177.37 2,000.00 3,177.37 611.86 67.98 13.60
6 19.00 4.90 64.84 12.97 1,317.78 2,000.00 3,317.78 676.65 75.18 12.53
7 19.50 4.66 71.19 14.24 1,446.95 2,000.00 3,446.95 740.21 82.25 11.75
7.50 19.75 4.55 74.20 14.84 1,508.07 2,000.00 3,508.07 771.55 85.73 11.43
8 20.00 4.44 77.11 15.42 1,567.21 2,000.00 3,567.21 802.62 89.18 11.15
9 20.50 4.26 82.68 16.54 1,680.29 2,000.00 3,680.29 863.97 96.00 10.67
10 21.00 4.10 87.95 17.59 1,787.52 2,000.00 3,787.52 924.34 102.70 10.27
11 21.50 3.95 92.99 18.60 1,889.90 2,000.00 3,889.90 983.78 109.31 9.94
12 22.00 3.83 97.83 19.57 1,988.22 2,000.00 3,988.22 1,042.38 115.82 9.65
13 22.50 3.71 102.49 20.50 2,083.11 2,000.00 4,083.11 1,100.17 122.24 9.40
14 23.00 3.61 107.02 21.40 2,175.07 2,000.00 4,175.07 1,157.22 128.58 9.18
15 23.50 3.51 111.42 22.28 2,264.51 2,000.00 4,264.51 1,213.57 134.84 8.99
16 24.00 3.43 115.71 23.14 2,351.78 2,000.00 4,351.78 1,269.27 141.03 8.81
17 24.50 3.35 119.91 23.98 2,437.14 2,000.00 4,437.14 1,324.35 147.15 8.66
18 25.00 3.28 124.03 24.81 2,520.84 2,000.00 4,520.84 1,378.86 153.21 8.51
19 25.50 3.21 128.08 25.62 2,603.07 2,000.00 4,603.07 1,432.82 159.20 8.38
20 26.00 3.15 132.06 26.41 2,684.00 2,000.00 4,684.00 1,486.27 165.14 8.26
21 26.50 3.09 135.99 27.20 2,763.77 2,000.00 4,763.77 1,539.24 171.03 8.14
22 27.00 3.04 139.86 27.97 2,842.50 2,000.00 4,842.50 1,591.75 176.86 8.04
23 27.50 2.99 143.69 28.74 2,920.30 2,000.00 4,920.30 1,643.83 182.65 7.94
24 28.00 2.95 147.47 29.49 2,997.26 2,000.00 4,997.26 1,695.50 188.39 7.85
25 28.50 2.90 151.22 30.24 3,073.45 2,000.00 5,073.45 1,746.78 194.09 7.76
26 29.00 2.86 154.94 30.99 3,148.97 2,000.00 5,148.97 1,797.70 199.74 7.68
27 29.50 2.83 158.62 31.72 3,223.85 2,000.00 5,223.85 1,848.27 205.36 7.61
28 30.00 2.79 162.28 32.46 3,298.16 2,000.00 5,298.16 1,898.51 210.95 7.53
29 30.50 2.76 165.91 33.18 3,371.95 2,000.00 5,371.95 1,948.43 216.49 7.47
30 31.00 2.73 169.52 33.90 3,445.25 2,000.00 5,445.25 1,998.06 222.01 7.40
31 31.50 2.70 173.10 34.62 3,518.12 2,000.00 5,518.12 2,047.40 227.49 7.34
32 32.00 2.67 176.67 35.33 3,590.57 2,000.00 5,590.57 2,096.47 232.94 7.28
33 32.50 2.64 180.21 36.04 3,662.65 2,000.00 5,662.65 2,145.27 238.36 7.22
34 33.00 2.61 183.74 36.75 3,734.38 2,000.00 5,734.38 2,193.84 243.76 7.17
35 33.50 2.59 187.26 37.45 3,805.79 2,000.00 5,805.79 2,242.16 249.13 7.12
36 34.00 2.57 190.75 38.15 3,876.90 2,000.00 5,876.90 2,290.26 254.47 7.07
37 34.50 2.54 194.24 38.85 3,947.73 2,000.00 5,947.73 2,338.15 259.79 7.02
38 35.00 2.52 197.71 39.54 4,018.29 2,000.00 6,018.29 2,385.82 265.09 6.98
39 35.50 2.50 201.17 40.23 4,088.62 2,000.00 6,088.62 2,433.30 270.37 6.93
40 36.00 2.48 204.62 40.92 4,158.71 2,000.00 6,158.71 2,480.59 275.62 6.89
41 36.50 2.46 208.06 41.61 4,228.59 2,000.00 6,228.59 2,527.70 280.86 6.85
42 37.00 2.45 211.49 42.30 4,298.27 2,000.00 6,298.27 2,574.63 286.07 6.81
43 37.50 2.43 214.91 42.98 4,367.77 2,000.00 6,367.77 2,621.40 291.27 6.77
44 38.00 2.41 218.32 43.66 4,437.08 2,000.00 6,437.08 2,668.00 296.44 6.74
45 38.50 2.40 221.72 44.34 4,506.23 2,000.00 6,506.23 2,714.45 301.61 6.70
46 39.00 2.38 225.11 45.02 4,575.23 2,000.00 6,575.23 2,760.75 306.75 6.67
47 39.50 2.37 228.50 45.70 4,644.07 2,000.00 6,644.07 2,806.91 311.88 6.64
48 40.00 2.35 231.88 46.38 4,712.78 2,000.00 6,712.78 2,852.93 316.99 6.60
49 40.50 2.34 235.26 47.05 4,781.35 2,000.00 6,781.35 2,898.82 322.09 6.57
50 41.00 2.33 238.62 47.72 4,849.80 2,000.00 6,849.80 2,944.58 327.18 6.54
60 46.00 2.22 272.02 54.40 5,528.62 2,000.00 7,528.62 3,396.06 377.34 6.29
62.5 48.00 2.22 283.46 56.69 5,760.97 2,000.00 7,760.97 3,496.48 388.50 6.22
70 51.00 2.14 305.06 61.01 6,199.99 2,000.00 8,199.99 3,838.72 426.52 6.09
75 53.00 2.09 319.30 63.86 6,489.46 2,000.00 8,489.46 4,064.53 451.61 6.02
80 56.00 2.07 337.85 67.57 6,866.50 2,000.00 8,866.50 4,274.92 474.99 5.94
87.5 59.00 2.02 358.99 71.80 7,296.14 2,000.00 9,296.14 4,608.68 512.08 5.85
90 60.00 2.00 366.00 73.20 7,438.58 2,000.00 9,438.58 4,719.29 524.37 5.83
100 60.00 1.85 375.23 75.05 7,626.19 2,000.00 9,626.19 5,214.19 579.35 5.79
125 60.00 1.55 393.10 78.62 7,989.30 2,000.00 9,989.30 6,451.42 716.82 5.73
150 60.00 1.33 406.00 81.20 8,251.54 2,000.00 10,251.54 7,688.66 854.30 5.70
200 60.00 1.04 423.39 84.68 8,605.00 2,000.00 10,605.00 10,163.13 1,129.24 5.65
300 60.00 0.73 442.36 88.47 8,990.60 2,000.00 10,990.60 15,112.07 1,679.12 5.60
400 60.00 0.56 452.51 90.50 9,196.85 2,000.00 11,196.85 20,061.02 2,229.00 5.57
500 60.00 0.45 458.83 91.77 9,325.26 2,000.00 11,325.26 25,009.96 2,778.88 5.56
1000 60.00 0.23 472.02 94.40 9,593.32 2,000.00 11,593.32 49,754.68 5,528.30 5.53
5000 60.00 0.05 483.14 96.63 9819.28 2,000.00 11,819.28 247,712.41 27,523.60 5.50
Number of trip in working day of 8 hours N = 8/((2L/S)+1), Where L = Lead in Km, S = Speed in Km per hour, 1/2 hour is
ll d f l ofdimobile
Consumption / oill taken
di at 140 Km per litre.
In column 4 of 'Km done' an allowance of 6.0 Km has been made for movement of truck from parking place to duty and back
Cost of labour, hire charges of truck, diesel and mobile has been taken from the basic rate sheet. Loading is to be done Track
Analysis of Rates for transportation stone Track Ballast
Rate
Linked to
Name Unit Rate Code
Basic
Sheet
Hire and running charges of Day 0049 2500.00
Tipper 12 Cum Capacity (without
POL)
Diesel (HSD Oil) Litre 0181 101.62
Mobile Oil Litre 0186 250.00
Diesel consumption rate kmpl 6.00
Mobile oil consumption rate kmpl 140.00
Time of Loading/Unloading hour 0.50
Distance from Parking Place to kmpl 6.00
Duty & Back to Parking Place
Lead in Average Nos. of Nos. of km Litres of Cost of Litres of Cost of Hire Total Cost = Cost per Cost per Rate per
km (L) Speed IN Trips Done in Diesel Diesel Mobil oil Mobile Charges of col. 6+8+9 Trip = cum cum per km
KMPH (S) N=8/(2L/S) one day consumed consumed oil Truck Col.10/Co
+0.5 (2NL+6) @ 140 km (0084) l.3
per Litre
1 2 3 4 5 6 7 8 9 10 11
1 16.00 12.80 31.60 5.27 535.20 0.23 56.43 2,500.00 3,091.63 241.53 20.13 20.13
2 17.00 10.88 49.52 8.25 838.70 0.35 88.43 2,500.00 3,427.13 314.99 26.25 13.12
3 17.50 9.49 62.95 10.49 1,066.15 0.45 112.41 2,500.00 3,678.56 387.56 32.30 10.77
4 18.00 8.47 73.76 12.29 1,249.33 0.53 131.72 2,500.00 3,881.05 458.18 38.18 9.55
5 18.50 7.69 82.88 13.81 1,403.76 0.59 148.01 2,500.00 4,051.77 527.00 43.92 8.78
6 19.00 7.07 90.84 15.14 1,538.48 0.65 162.21 2,500.00 4,200.69 594.18 49.51 8.25
7 19.50 6.57 97.96 16.33 1,659.08 0.70 174.92 2,500.00 4,334.01 659.82 54.99 7.86
8 20.00 6.15 104.46 17.41 1,769.23 0.75 186.54 2,500.00 4,455.77 724.06 60.34 7.54
9 20.50 5.81 110.50 18.42 1,871.43 0.79 197.31 2,500.00 4,568.74 786.99 65.58 7.29
10 21.00 5.51 116.16 19.36 1,967.43 0.83 207.44 2,500.00 4,674.87 848.71 70.73 7.07
11 21.50 5.25 121.54 20.26 2,058.52 0.87 217.04 2,500.00 4,775.56 909.30 75.77 6.89
12 22.00 5.03 126.69 21.11 2,145.63 0.90 226.22 2,500.00 4,871.86 968.84 80.74 6.73
13 22.50 4.83 131.64 21.94 2,229.50 0.94 235.07 2,500.00 4,964.57 1,027.39 85.62 6.59
14 23.00 4.66 136.43 22.74 2,310.68 0.97 243.63 2,500.00 5,054.30 1,085.03 90.42 6.46
15 23.50 4.50 141.09 23.51 2,389.59 1.01 251.95 2,500.00 5,141.54 1,141.80 95.15 6.34
16 24.00 4.36 145.64 24.27 2,466.59 1.04 260.06 2,500.00 5,226.66 1,197.78 99.81 6.24
17 24.50 4.24 150.09 25.01 2,541.96 1.07 268.01 2,500.00 5,309.98 1,252.99 104.42 6.14
18 25.00 4.12 154.45 25.74 2,615.93 1.10 275.81 2,500.00 5,391.74 1,307.50 108.96 6.05
19 25.50 4.02 158.75 26.46 2,688.67 1.13 283.48 2,500.00 5,472.15 1,361.33 113.44 5.97
20 26.00 3.92 162.98 27.16 2,760.36 1.16 291.04 2,500.00 5,551.39 1,414.54 117.88 5.89
21 26.50 3.84 167.16 27.86 2,831.11 1.19 298.50 2,500.00 5,629.60 1,467.15 122.26 5.82
22 27.00 3.76 171.29 28.55 2,901.03 1.22 305.87 2,500.00 5,706.90 1,519.20 126.60 5.75
23 27.50 3.68 175.37 29.23 2,970.22 1.25 313.16 2,500.00 5,783.39 1,570.72 130.89 5.69
24 28.00 3.61 179.42 29.90 3,038.77 1.28 320.39 2,500.00 5,859.16 1,621.73 135.14 5.63
25 28.50 3.55 183.43 30.57 3,106.73 1.31 327.56 2,500.00 5,934.28 1,672.27 139.36 5.57
26 29.00 3.49 187.41 31.24 3,174.16 1.34 334.67 2,500.00 6,008.83 1,722.36 143.53 5.52
27 29.50 3.43 191.37 31.89 3,241.12 1.37 341.73 2,500.00 6,082.85 1,772.02 147.67 5.47
28 30.00 3.38 195.30 32.55 3,307.66 1.39 348.74 2,500.00 6,156.40 1,821.27 151.77 5.42
29 30.50 3.33 199.20 33.20 3,373.81 1.42 355.72 2,500.00 6,229.52 1,870.13 155.84 5.37
30 31.00 3.28 203.09 33.85 3,439.60 1.45 362.65 2,500.00 6,302.26 1,918.63 159.89 5.33
31 31.50 3.24 206.95 34.49 3,505.07 1.48 369.56 2,500.00 6,374.63 1,966.78 163.90 5.29
32 32.00 3.20 210.80 35.13 3,570.25 1.51 376.43 2,500.00 6,446.68 2,014.59 167.88 5.25
33 32.50 3.16 214.63 35.77 3,635.15 1.53 383.27 2,500.00 6,518.43 2,062.08 171.84 5.21
34 33.00 3.12 218.45 36.41 3,699.81 1.56 390.09 2,500.00 6,589.90 2,109.27 175.77 5.17
35 33.50 3.09 222.25 37.04 3,764.24 1.59 396.88 2,500.00 6,661.12 2,156.16 179.68 5.13
36 34.00 3.06 226.04 37.67 3,828.45 1.61 403.65 2,500.00 6,732.10 2,202.78 183.57 5.10
37 34.50 3.02 229.82 38.30 3,892.46 1.64 410.40 2,500.00 6,802.86 2,249.14 187.43 5.07
38 35.00 2.99 233.59 38.93 3,956.30 1.67 417.13 2,500.00 6,873.43 2,295.23 191.27 5.03
39 35.50 2.97 237.35 39.56 4,019.96 1.70 423.84 2,500.00 6,943.80 2,341.09 195.09 5.00
40 36.00 2.94 241.10 40.18 4,083.46 1.72 430.54 2,500.00 7,014.00 2,386.71 198.89 4.97
41 36.50 2.91 244.84 40.81 4,146.82 1.75 437.22 2,500.00 7,084.04 2,432.11 202.68 4.94
42 37.00 2.89 248.58 41.43 4,210.04 1.78 443.89 2,500.00 7,153.93 2,477.29 206.44 4.92
43 37.50 2.86 252.30 42.05 4,273.13 1.80 450.54 2,500.00 7,223.67 2,522.26 210.19 4.89
44 38.00 2.84 256.02 42.67 4,336.10 1.83 457.18 2,500.00 7,293.28 2,567.04 213.92 4.86
45 38.50 2.82 259.73 43.29 4,398.96 1.86 463.80 2,500.00 7,362.76 2,611.63 217.64 4.84
46 39.00 2.80 263.43 43.91 4,461.71 1.88 470.42 2,500.00 7,432.13 2,656.03 221.34 4.81
47 39.50 2.78 267.13 44.52 4,524.36 1.91 477.03 2,500.00 7,501.39 2,700.26 225.02 4.79
48 40.00 2.76 270.83 45.14 4,586.92 1.93 483.62 2,500.00 7,570.54 2,744.32 228.69 4.76
49 40.50 2.74 274.52 45.75 4,649.38 1.96 490.21 2,500.00 7,639.59 2,788.21 232.35 4.74
50 41.00 2.72 278.20 46.37 4,711.77 1.99 496.78 2,500.00 7,708.55 2,831.95 236.00 4.72
60 46.00 2.57 314.81 52.47 5,331.85 2.25 562.16 2,500.00 8,394.02 3,261.80 271.82 4.53
70 51.00 2.47 351.14 58.52 5,947.07 2.51 627.03 2,500.00 9,074.10 3,680.79 306.73 4.38
75 53.00 2.40 366.34 61.06 6,204.58 2.62 654.18 2,500.00 9,358.76 3,895.80 324.65 4.33
80 56.00 2.38 387.28 64.55 6,559.17 2.77 691.57 2,500.00 9,750.74 4,091.83 340.99 4.26
90 60.00 2.29 417.43 69.57 7,069.85 2.98 745.41 2,500.00 10,315.26 4,512.92 376.08 4.18
100 60.00 2.09 423.39 70.57 7,170.84 3.02 756.06 2,500.00 10,426.89 4,996.22 416.35 4.16
125 60.00 1.71 434.57 72.43 7,360.19 3.10 776.02 2,500.00 10,636.21 6,204.46 517.04 4.14
175 60.00 1.26 448.11 74.68 7,589.41 3.20 800.19 2,500.00 10,889.60 8,620.93 718.41 4.11
225 60.00 1.00 456.00 76.00 7,723.12 3.26 814.29 2,500.00 11,037.41 11,037.41 919.78 4.09
500 60.00 0.47 472.02 78.67 7,994.44 3.37 842.89 2,500.00 11,337.33 24,328.01 2,027.33 4.05
1000 60.00 0.24 478.91 79.82 8,111.08 3.42 855.19 2,500.00 11,466.27 48,492.76 4,041.06 4.04
Number of trip in working day of 8 hours N = 8/((2L/S)+1), Where L = Lead in Km, S = Speed in Km per hour, 1/2 hour is allowed for loading /
l di
Consumption of mobile oil taken at 140 Km per litre.
In column 4 of 'Km done' an allowance of 6.0 Km has been made for movement of truck from parking place to duty and back
Cost of labour, hire charges of truck, diesel and mobile has been taken from the basic rate sheet. Loading is to be done Track Ballast Manufacturer.
Analysis of Rates for transportation Precast Girders/Slab
By Mechanical Transport including unloading and stacking
Name Unit Rate Code Rate Linked
to Basic
Sheet
Hire Charges of 20T truck with long Trailors (without Day 0103 5000.00
POL)
Hiring charges of Crane 50 MT capacity Day 0094 20000.00
Lead in Average Nos. of Nos. of km Litres of Cost of Litres of Cost of Cost of 2 Hire Total Cost = Cost per Cost of Total Cost Cost per Rate Rate per ton
km (L) Speed IN Trips Done in Diesel Diesel Mobil oil Mobile Beldar at site Charges of col. 6+8+9+10 Trip = Crane per trip i.e. tone including per km
KMPH (S) N=8/(2L/S) one day consumed consumed oil for unloading Truck Col.11/Col. Charges cost for 20
+0.5
GST, CPOH
(2NL+6) @ 140 km with crane (0084) 3 except for
t & Cess
per Litre except hire Crane Loading &
charges of charges unloading
crane per trip
considerin
g 1/4 hrs
of crane
time each
1 2 3 4 5 6 7 8 9 10 11 12 13 14
1 16.00 12.80 31.60 11.92 1,211.77 0.23 56.43 862.00 5,000.00 7,130.20 557.05 1,250.00 1,807.05 90.35 119.69 119.69
2 17.00 10.88 49.52 18.69 1,898.95 0.35 88.43 862.00 5,000.00 7,849.38 721.45 1,250.00 1,971.45 98.57 130.58 65.29
3 17.50 9.49 62.95 23.75 2,413.92 0.45 112.41 862.00 5,000.00 8,388.33 883.77 1,250.00 2,133.77 106.69 141.33 47.11
4 18.00 8.47 73.76 27.84 2,828.67 0.53 131.72 862.00 5,000.00 8,822.39 1,041.53 1,250.00 2,291.53 114.58 151.78 37.94
5 18.50 7.69 82.88 31.28 3,178.33 0.59 148.01 862.00 5,000.00 9,188.34 1,195.10 1,250.00 2,445.10 122.26 161.95 32.39
6 19.00 7.07 90.84 34.28 3,483.35 0.65 162.21 862.00 5,000.00 9,507.56 1,344.82 1,250.00 2,594.82 129.74 171.87 28.64
7 19.50 6.57 97.96 36.97 3,756.41 0.70 174.92 862.00 5,000.00 9,793.33 1,490.97 1,250.00 2,740.97 137.05 181.55 25.94
8 20.00 6.15 104.46 39.42 4,005.80 0.75 186.54 862.00 5,000.00 10,054.34 1,633.83 1,250.00 2,883.83 144.19 191.01 23.88
9 20.50 5.81 110.50 41.70 4,237.19 0.79 197.31 862.00 5,000.00 10,296.51 1,773.64 1,250.00 3,023.64 151.18 200.27 22.25
10 21.00 5.51 116.16 43.84 4,454.56 0.83 207.44 862.00 5,000.00 10,523.99 1,910.61 1,250.00 3,160.61 158.03 209.34 20.93
11 21.50 5.25 121.54 45.86 4,660.79 0.87 217.04 862.00 5,000.00 10,739.83 2,044.94 1,250.00 3,294.94 164.75 218.24 19.84
12 22.00 5.03 126.69 47.81 4,858.04 0.90 226.22 862.00 5,000.00 10,946.26 2,176.81 1,250.00 3,426.81 171.34 226.97 18.91
13 22.50 4.83 131.64 49.67 5,047.93 0.94 235.07 862.00 5,000.00 11,145.00 2,306.39 1,250.00 3,556.39 177.82 235.56 18.12
14 23.00 4.66 136.43 51.48 5,231.72 0.97 243.63 862.00 5,000.00 11,337.34 2,433.83 1,250.00 3,683.83 184.19 244.00 17.43
15 23.50 4.50 141.09 53.24 5,410.40 1.01 251.95 862.00 5,000.00 11,524.34 2,559.26 1,250.00 3,809.26 190.46 252.30 16.82
16 24.00 4.36 145.64 54.96 5,584.74 1.04 260.06 862.00 5,000.00 11,706.81 2,682.81 1,250.00 3,932.81 196.64 260.49 16.28
17 24.50 4.24 150.09 56.64 5,755.39 1.07 268.01 862.00 5,000.00 11,885.40 2,804.59 1,250.00 4,054.59 202.73 268.55 15.80
18 25.00 4.12 154.45 58.28 5,922.86 1.10 275.81 862.00 5,000.00 12,060.67 2,924.71 1,250.00 4,174.71 208.74 276.51 15.36
19 25.50 4.02 158.75 59.91 6,087.57 1.13 283.48 862.00 5,000.00 12,233.05 3,043.27 1,250.00 4,293.27 214.66 284.36 14.97
20 26.00 3.92 162.98 61.50 6,249.87 1.16 291.04 862.00 5,000.00 12,402.90 3,160.36 1,250.00 4,410.36 220.52 292.12 14.61
21 26.50 3.84 167.16 63.08 6,410.05 1.19 298.50 862.00 5,000.00 12,570.55 3,276.05 1,250.00 4,526.05 226.30 299.78 14.28
22 27.00 3.76 171.29 64.64 6,568.37 1.22 305.87 862.00 5,000.00 12,736.24 3,390.43 1,250.00 4,640.43 232.02 307.36 13.97
23 27.50 3.68 175.37 66.18 6,725.03 1.25 313.16 862.00 5,000.00 12,900.20 3,503.58 1,250.00 4,753.58 237.68 314.85 13.69
24 28.00 3.61 179.42 67.71 6,880.22 1.28 320.39 862.00 5,000.00 13,062.62 3,615.55 1,250.00 4,865.55 243.28 322.27 13.43
25 28.50 3.55 183.43 69.22 7,034.09 1.31 327.56 862.00 5,000.00 13,223.65 3,726.40 1,250.00 4,976.40 248.82 329.61 13.18
26 29.00 3.49 187.41 70.72 7,186.78 1.34 334.67 862.00 5,000.00 13,383.45 3,836.20 1,250.00 5,086.20 254.31 336.88 12.96
27 29.50 3.43 191.37 72.21 7,338.39 1.37 341.73 862.00 5,000.00 13,542.12 3,945.00 1,250.00 5,195.00 259.75 344.09 12.74
28 30.00 3.38 195.30 73.70 7,489.04 1.39 348.74 862.00 5,000.00 13,699.78 4,052.85 1,250.00 5,302.85 265.14 351.23 12.54
29 30.50 3.33 199.20 75.17 7,638.81 1.42 355.72 862.00 5,000.00 13,856.53 4,159.80 1,250.00 5,409.80 270.49 358.32 12.36
30 31.00 3.28 203.09 76.64 7,787.78 1.45 362.65 862.00 5,000.00 14,012.43 4,265.88 1,250.00 5,515.88 275.79 365.34 12.18
31 31.50 3.24 206.95 78.10 7,936.01 1.48 369.56 862.00 5,000.00 14,167.57 4,371.15 1,250.00 5,621.15 281.06 372.31 12.01
32 32.00 3.20 210.80 79.55 8,083.58 1.51 376.43 862.00 5,000.00 14,322.01 4,475.63 1,250.00 5,725.63 286.28 379.23 11.85
33 32.50 3.16 214.63 80.99 8,230.54 1.53 383.27 862.00 5,000.00 14,475.81 4,579.37 1,250.00 5,829.37 291.47 386.11 11.70
34 33.00 3.12 218.45 82.43 8,376.93 1.56 390.09 862.00 5,000.00 14,629.02 4,682.39 1,250.00 5,932.39 296.62 392.93 11.56
35 33.50 3.09 222.25 83.87 8,522.80 1.59 396.88 862.00 5,000.00 14,781.68 4,784.74 1,250.00 6,034.74 301.74 399.71 11.42
36 34.00 3.06 226.04 85.30 8,668.18 1.61 403.65 862.00 5,000.00 14,933.84 4,886.44 1,250.00 6,136.44 306.82 406.44 11.29
37 34.50 3.02 229.82 86.73 8,813.13 1.64 410.40 862.00 5,000.00 15,085.53 4,987.52 1,250.00 6,237.52 311.88 413.14 11.17
38 35.00 2.99 233.59 88.15 8,957.65 1.67 417.13 862.00 5,000.00 15,236.78 5,088.00 1,250.00 6,338.00 316.90 419.79 11.05
39 35.50 2.97 237.35 89.57 9,101.80 1.70 423.84 862.00 5,000.00 15,387.64 5,187.91 1,250.00 6,437.91 321.90 426.41 10.93
40 36.00 2.94 241.10 90.98 9,245.58 1.72 430.54 862.00 5,000.00 15,538.12 5,287.28 1,250.00 6,537.28 326.86 432.99 10.82
41 36.50 2.91 244.84 92.39 9,389.03 1.75 437.22 862.00 5,000.00 15,688.25 5,386.12 1,250.00 6,636.12 331.81 439.54 10.72
42 37.00 2.89 248.58 93.80 9,532.17 1.78 443.89 862.00 5,000.00 15,838.06 5,484.46 1,250.00 6,734.46 336.72 446.05 10.62
43 37.50 2.86 252.30 95.21 9,675.02 1.80 450.54 862.00 5,000.00 15,987.56 5,582.32 1,250.00 6,832.32 341.62 452.54 10.52
44 38.00 2.84 256.02 96.61 9,817.59 1.83 457.18 862.00 5,000.00 16,136.77 5,679.72 1,250.00 6,929.72 346.49 458.99 10.43
45 38.50 2.82 259.73 98.01 9,959.91 1.86 463.80 862.00 5,000.00 16,285.71 5,776.67 1,250.00 7,026.67 351.33 465.41 10.34
46 39.00 2.80 263.43 99.41 10,101.99 1.88 470.42 862.00 5,000.00 16,434.41 5,873.19 1,250.00 7,123.19 356.16 471.80 10.26
47 39.50 2.78 267.13 100.81 10,243.84 1.91 477.03 862.00 5,000.00 16,582.86 5,969.31 1,250.00 7,219.31 360.97 478.17 10.17
48 40.00 2.76 270.83 102.20 10,385.47 1.93 483.62 862.00 5,000.00 16,731.09 6,065.02 1,250.00 7,315.02 365.75 484.51 10.09
49 40.50 2.74 274.52 103.59 10,526.91 1.96 490.21 862.00 5,000.00 16,879.11 6,160.36 1,250.00 7,410.36 370.52 490.82 10.02
50 41.00 2.72 278.20 104.98 10,668.15 1.99 496.78 862.00 5,000.00 17,026.94 6,255.32 1,250.00 7,505.32 375.27 497.11 9.94
51 41.50 2.70 281.88 106.37 10,809.22 2.01 503.35 862.00 5,000.00 17,174.57 6,349.93 1,250.00 7,599.93 380.00 503.38 9.87
52 42.00 2.69 285.55 107.76 10,950.11 2.04 509.91 862.00 5,000.00 17,322.03 6,444.21 1,250.00 7,694.21 384.71 509.62 9.80
53 42.50 2.67 289.22 109.14 11,090.85 2.07 516.47 862.00 5,000.00 17,469.31 6,538.15 1,250.00 7,788.15 389.41 515.84 9.73
54 43.00 2.66 292.89 110.52 11,231.43 2.09 523.01 862.00 5,000.00 17,616.44 6,631.77 1,250.00 7,881.77 394.09 522.05 9.67
55 43.50 2.64 296.55 111.91 11,371.86 2.12 529.55 862.00 5,000.00 17,763.42 6,725.09 1,250.00 7,975.09 398.75 528.23 9.60
56 44.00 2.63 300.21 113.29 11,512.16 2.14 536.09 862.00 5,000.00 17,910.25 6,818.11 1,250.00 8,068.11 403.41 534.39 9.54
57 44.50 2.61 303.86 114.67 11,652.33 2.17 542.61 862.00 5,000.00 18,056.95 6,910.84 1,250.00 8,160.84 408.04 540.53 9.48
58 45.00 2.60 307.52 116.04 11,792.38 2.20 549.14 862.00 5,000.00 18,203.51 7,003.30 1,250.00 8,253.30 412.66 546.65 9.43
59 45.50 2.59 311.17 117.42 11,932.30 2.22 555.65 862.00 5,000.00 18,349.96 7,095.48 1,250.00 8,345.48 417.27 552.76 9.37
60 46.00 2.57 314.81 118.80 12,072.12 2.25 562.16 862.00 5,000.00 18,496.28 7,187.41 1,250.00 8,437.41 421.87 558.85 9.31
61 46.50 2.56 318.45 120.17 12,211.82 2.27 568.67 862.00 5,000.00 18,642.49 7,279.09 1,250.00 8,529.09 426.45 564.92 9.26
62 47.00 2.55 322.09 121.55 12,351.43 2.30 575.17 862.00 5,000.00 18,788.60 7,370.53 1,250.00 8,620.53 431.03 570.98 9.21
63 47.50 2.54 325.73 122.92 12,490.93 2.33 581.67 862.00 5,000.00 18,934.60 7,461.73 1,250.00 8,711.73 435.59 577.02 9.16
64 48.00 2.53 329.37 124.29 12,630.35 2.35 588.16 862.00 5,000.00 19,080.50 7,552.70 1,250.00 8,802.70 440.13 583.04 9.11
65 48.50 2.52 333.00 125.66 12,769.67 2.38 594.65 862.00 5,000.00 19,226.32 7,643.45 1,250.00 8,893.45 444.67 589.05 9.06
66 49.00 2.50 336.63 127.03 12,908.91 2.40 601.13 862.00 5,000.00 19,372.04 7,733.99 1,250.00 8,983.99 449.20 595.05 9.02
67 49.50 2.49 340.26 128.40 13,048.06 2.43 607.61 862.00 5,000.00 19,517.67 7,824.32 1,250.00 9,074.32 453.72 601.03 8.97
68 50.00 2.48 343.89 129.77 13,187.14 2.46 614.09 862.00 5,000.00 19,663.23 7,914.45 1,250.00 9,164.45 458.22 607.00 8.93
69 50.50 2.47 347.51 131.14 13,326.14 2.48 620.56 862.00 5,000.00 19,808.70 8,004.38 1,250.00 9,254.38 462.72 612.96 8.88
70 51.00 2.47 351.14 132.50 13,465.07 2.51 627.03 862.00 5,000.00 19,954.10 8,094.13 1,250.00 9,344.13 467.21 618.90 8.84
71 51.50 2.46 354.76 133.87 13,603.93 2.53 633.49 862.00 5,000.00 20,099.42 8,183.69 1,250.00 9,433.69 471.68 624.84 8.80
72 52.00 2.45 358.38 135.24 13,742.72 2.56 639.96 862.00 5,000.00 20,244.68 8,273.07 1,250.00 9,523.07 476.15 630.76 8.76
73 52.50 2.44 361.99 136.60 13,881.45 2.59 646.42 862.00 5,000.00 20,389.87 8,362.27 1,250.00 9,612.27 480.61 636.66 8.72
74 53.00 2.43 365.61 137.97 14,020.12 2.61 652.88 862.00 5,000.00 20,535.00 8,451.31 1,250.00 9,701.31 485.07 642.56 8.68
75 53.50 2.42 369.22 139.33 14,158.73 2.64 659.33 862.00 5,000.00 20,680.06 8,540.19 1,250.00 9,790.19 489.51 648.45 8.65
76 54.00 2.41 372.84 140.69 14,297.28 2.66 665.78 862.00 5,000.00 20,825.06 8,628.90 1,250.00 9,878.90 493.95 654.32 8.61
77 54.50 2.41 376.45 142.06 14,435.78 2.69 672.23 862.00 5,000.00 20,970.01 8,717.46 1,250.00 9,967.46 498.37 660.19 8.57
78 55.00 2.40 380.06 143.42 14,574.22 2.71 678.68 862.00 5,000.00 21,114.90 8,805.87 1,250.00 10,055.87 502.79 666.05 8.54
79 55.50 2.39 383.67 144.78 14,712.62 2.74 685.12 862.00 5,000.00 21,259.74 8,894.14 1,250.00 10,144.14 507.21 671.89 8.50
80 56.00 2.38 387.28 146.14 14,850.96 2.77 691.57 862.00 5,000.00 21,404.53 8,982.26 1,250.00 10,232.26 511.61 677.73 8.47
90 60.00 2.29 417.43 157.52 16,007.20 2.98 745.41 862.00 5,000.00 22,614.61 9,893.89 1,250.00 11,143.89 557.19 738.11 8.20
100 61.00 2.12 429.43 162.05 16,467.32 3.07 766.83 862.00 5,000.00 23,096.16 10,909.15 1,250.00 12,159.15 607.96 805.36 8.05
200 62.00 1.15 466.32 175.97 17,882.24 3.33 832.72 862.00 5,000.00 24,576.96 21,356.19 1,250.00 22,606.19 1,130.31 1497.31 7.49
500 63.00 0.49 494.61 186.64 18,966.85 3.53 883.23 862.00 5,000.00 25,712.08 52,623.03 1,250.00 53,873.03 2,693.65 3568.26 7.14
Number of trip in working day of 8 hours N = 8/((2L/S)+1), Where L = Lead in Km, S = Speed in Km per hour, 1/2 hour is allowed for loading / unloading.
Consumption of diesel taken at 3 Km per litre.
Consumption of mobile oil taken at 140 Km per litre.
In column 4 of 'Km done' an allowance of 6.0 Km has been made for movement of truck from parking place to duty and back
Cost of labour, hire charges of truck, diesel and mobile has been taken from the basic rate sheet. Loading is to be done by Precast Factory by his own crane.
Average Rate
per tonne per
km
9.95
8.84
IR Unified Standard Schedule of Rates 2019
The accessories, meeting applicable RDSO Specification No IRST/19-2020 with latest amendm
integral part of AT welding portions of respective Rail section and shall be supplied free of cos
yardstick.
Sl.No Description of Item Qty to be Supplied
**110 Units complete with every 100
1 Pre-fabricated 3 piece moulds with cake piece
Portions
2 Dry Luting Sand 3.5 Kg per portion in individual packets
3 Single Shot crucible charge 1 No for each portion
4 Auto tapping thimble 1 No for each portion
**105 Units complete with every 100
5 Ignition Matches
Portions
6 Mould shoe 1 Set per 50 Nos of Portions
7 Mould pressure clamp 1 Set per 500 Nos of Portions
8 Torch burner complete 1 Set per 200 Nos of Portions
9 Torch burner Keys 1 per 500 Nos of Portions
10 Goose neck arrangement for vaporization 1 per 500 Nos of Portions
11 Connecting Hose pipe 1 per 1000 Nos of Portions
12 Torch burner stand 1 per 1000 Nos of Portions
13 Aluminium / Steel rod for thermal plugging 1 per 800 Nos of Portions
14 Stop Watch 1 per 800 Nos of Portions
15 Adjustment spanner 1 per 800 Nos of Portions
16 Hot sets Chisels for emergency use 1 per 500 Nos of Portions
17 Pliers 1 per 800 Nos of Portions
18 Steel Wire brush 1 per 400 Nos of Portions
19 Slag Container Bowl 1 per 500 Nos of Portions
Weld Grinding Stone (Top Flexible High speed)
20 1 per 10 Nos of Portions
(150x120x50/22.23) mm)
Trimmer cutter hydraulic pressure pipe with
21 1 pipe per 300 Portions
connecting arrangement
22 Trimmer Cutter Blade (Fixing arrangement) 1 Set per 300 portions
23 Rail cover 1 Set per 100 portions
24 Hammer 1016 2 Nos per 800 portions
25 Thermal Chalks 1 per 800 Portions
26 10 cm Long Gauge 1 per 800 Portions
27 1 m long Gauge 1 per 800 Portions
28 Filler Gauge shims 1 per 800 Portions
29 Pressure Gauge 2 Nos per 800 portions
30 Weld Cover 1 Nos per 800 portions
IR Unified Standard Schedule of Rates 2019
Annexure I
ent, are considered
st as per following
Remarks
1. The quantity to be
supplied shall be in
whole Nos in the
specified ratio or
part thereof.
2.**Extra quantity
towards
damages/breakages
etc., and the rates
quoted are inclusive
of this extra quantity
and no extra
payment will be
there