❖ PERT was developed in the late 1950 by the US Navy
submarine missile programme and was applied in 1958
❖ PERT shows the time taken by each component of project & the
total time required for its completion.
❖ PERT breaks down theproject into events, activity & lays down
their proper sequence relationship & duration in the form of
network.
1) Identity 2) Determine
the the proper
specific sequence of
activity & the activities
events
3) Construct a
network
5) Determine diagram
the critical
path
4) Estimate the
time require
for each
activity
1. Identity Activities & events :
The activities are tasks require to complete the project. The
events marking the beginning & end of one or more
activities. It is helpful to list the tasks in a table that in later
steps can be expanded to include on sequence is duration .
C) Pessimistic time :
The longest time that an activity might require.
5. Determine the critical path :
The critical path is determine by adding the times for the