ORIGINAL
ORIGINAL
ORIGINAL
T LXWXH S Description T
A. SUB STRUCTURE
1.Excavation and Earthwork 0
1.1 Site clearance 20cm
30.00
13.50 axis 1-5 b/n axis A-S
405
1 10.85
8.00
0.40 axis 1-5 b/n axis A-S
34.72
0 6.32
0.20
0.00
0 13.18
0.20
0.00
1.60
1.50 F1 0
0.00
405.0
0.20 0
81.00 m total area of site cleared.
3
2. CONCRETE WORK
0.00 M2
CONTRACTOR
CONTRACTOR
0 0.4 C1 @ +8.20
0.3 L=0.4 W=0.3 D=3.8
3.80
0.00 M3
1.20 M3
a-2 Ditto but on first floor
5 9.2 RB-2
0.2 L=22 W=0.2 D=0.35
0.2
1.83 M3
2 10.9 RB-2
0.2 L=22 W=0.2 D=0.35
0.2
0.87 M3
4 8.0 RB-2
0.2 L=22 W=0.2 D=0.35
0.2
1.28 M3
________________________
CONTRACTOR
Project Factory Building
T LXWXH S Description T
1.20 Form Work
a) Elevation Column
a-1 on ground floor 1
10 0.8 C1 @ +4.00
3 P=2*(0.4+0.3)=1.4 D=3.6
24.00 M 2
0 1.4 C1 @ +8.20 0
3.8 P=2*(0.4+0.3)=1.4 D=3.8
0.00 M2
0 91.00 IB-1
1.10 P=0.4+0.4+0.3=1.1 L=91
0.00 M2
0 22.00 IB-2
1.10 P=0.4+0.4+0.3=1.1 L=22
0.00 M2
2
________________________
CONTRACTOR
139.5 L=sum=91+91+22+22-(44*0.4)=208.4
3.5 H=3.60m
488.075 m2
Deduction
doors
-165.66 3(4*5)=60m2
322.42 m2
0.0 L=sum=91+91+22+22-(44*0.4)=208.4
3.8 H=3.8m
0 m2
Deduction
doors & windows
0.00 3(1*5)+44(4.6*0.6)=136.44m2
0.00 m2
________________________
CONTRACTOR
Project Factory Building
T LXWXH S Description T
3.0 Roofing
3.1 Decra Roof cover
1 20.00 L=22 W=46.1
9.15
183.00 m2
4.0 Carpentary
a) Eucalyptus truss
a) 200 x 50 mm zigba rafter
b)Diam 120mm eucalyprus upper & lower cord
c)Diam 100mm eucalyprus Vertical & diagonal cord
5x4cm Zigba wood purlin c/c40cm for roof cover
5x4cm Zigba wood purlin c/c40cm for ceiling
5.0 Joinery
Internal wooden doors 40mm thick core covered
D1 size: 90x270cm
D2 " 80x270cm
D3 " 70x270cm
D4 " 150x270cm
________________________
CONTRACTOR
7.1 Apply two coats of plastering in cement sand mortar 1:3 &
one coat gypsum plastering to internal part of HCB wall.
789.29 m2
7.2 Ditto as item 7.1, but to concrete beam, floor slab, lintels,
columns ,staircase and to all concrete elements.
0.00 m2
*Apply two coats of plastering in cement sand mortar 1:3 to
external part of concrete element.
789.29 m2
7.3 Apply two coats of plastering in cement sand mortar 1:3 &
one coat of fine cement plastering to internal part of HCB
wall.
7.7 Supply & lay 2mm thick PVC tile with approved type
adhesive colour and size to be approved by the engineer.
0.00 m2
________________________
CONTRACTOR
0.00 m2
0
________________________
CONTRACTOR
________________________
CONTRACTOR
1 -
1 pcs MDB = GF
43 pcs SDB = GF
11.2 LIGHT POINTS AND SWITCHES
36 -
36 pcs Light point fed through PVC insulated copper
Conductor of 2x2.5 sq. mm in PVC conduit of
16 mm diameter
2 -
2 pcs Single switch 75
-
43 pcs Two-way switch
-
16 pcs 16 Ampere / 1 Phase with switch 1
1
CONTRACTOR
Takeoff Sheet
Page 1
LXWXH S Description
3.00
1.50 F1
0.00
9.15
0.20 axis 1-5 b/n axis A-S
36.60
10.85
8.00
0.20 axis 1-5 b/n axis A-S
17.36
0.00
0.00 m3 total Volume of Back fill.
SUPERVISOR
Takeoff Sheet
Page 2
LXWXH S Description
Takeoff Sheet
Page 3
LXWXH S Description
0.00 M2
Takeoff Sheet
Page 4
LXWXH S Description
SUPERVISOR
Takeoff Sheet
Page 5
LXWXH S Description
b) In INTERMIDIATE Beams
91 IB-1
0.30 L=91 W=0.3 D=0.4
0.40
0.00 M3
22.0 IB-2
0.30 L=22 W=0.3 D=0.4
0.40
0.00 M3
Takeoff Sheet
Page 6
LXWXH S Description
f) Ditto but in doors lintel
ground floor
5 door lintel
0.2 L=5 W=0.2 D=0.3
0.3
0.00 M3
first floor
second floor
______________________
SUPERVISOR
Takeoff Sheet
Page 7
LXWXH S Description
c) Ditto but in top tie beams
139.45 RB-1
0.60 P=0.35+0.2+0.35=0.9 L=91
83.67 M2
9.15 RB-2
0.60 P=0.35+0.2+0.35=0.9 L=22
0.00 M2
Takeoff Sheet
Page 8
LXWXH S Description
Deduction
doors
-21.20 3(4*5)=60m2
0.00 m2
0.00 m2
______________________
SUPERVISOR
Takeoff Sheet
Page 9
LXWXH S Description
6.0 METAL WORK
a) Door frames
8 D1 size 80 x 280 cm
1 D2 " 120x280cm
DW3 " 120x271cm
0 W1 " 60x460cm
W2 '' 123x130cm
W3 " 110x130cm
W4 " 90x130cm
W5 '' 100x60cm
b) window frames
1 WD1 '' 350X280
WD3 '' 170X268
2 W1 " 80X50
3 W2 100X150
2 W3 180X150
W4 60X125
W4 60x255
W4 60x180
W5 200X120
W9 130x120
TW1 " 120x70
TW2 " 210x70
Takeoff Sheet
Page 10
LXWXH S Description
7.8 Supply & fix 7cm high PVC skirting to wall with
approved type adhesive.
0.00 m2
0.00 m2
0.00 m2
______________________
SUPERVISOR
Takeoff Sheet
Page 10
LXWXH S Description
8.0 Painting
789.29 m2
9.0 Glazing
4 W1 size 60x460cm
0
0.00 m2
______________________
SUPERVISOR
Takeoff Sheet
Page 11
LXWXH S Description
10.3 WASTE, VENT AND RAIN WATER
PIPES AND ACCESSORIES
0.00
0.00 m UPVC pipe for waste water drainage from the
manhole to the septic tank ф-150
44.0 L=2*22=44m
44.00
44.00 m Construct open ditch as per the detail drawing
______________________
SUPERVISOR
Takeoff Sheet
Page 11
LXWXH S Description
11.4 BELL CALL SYSTEM
-
0 pcs Telephone outlet
-
0 pcs Telephone & TV box
-
0 pcs Ceiling Light
-
75 pcs Fluorescent Light
1287.00
1287.00 m 4X10
606.3
606.32
606.32 m 5X6
429.0
429.00
429.00 m pvc 21mm
203.1
203.06
203.06 m pvc 40mm
3
3 pcs Concrete man hole
10
10 pcs CUPPER ROD 50 MM Diam.,2m long
SUPERVISOR
Item Description Unit Qty Rate Amount
\ A. Substructure
1. EXCAVATION AND EATRH WORK
Clearing of the building area and removal of all dirt and M2 405.00 11.00 4,455.00
1.1 expansive soil to an average depth of 20cm.
Bulk excavationof ordinary soil from reduced levevl to M3 107.92 82.00 8,849.44
1.2 a depth not exceeding 40cm.
Trench excavation for masonary workfoundation in M3 97.62 87.00 8,492.51
1.4 ordinary soil to a depth of 100cm.
Fill around masonary foundation, under hard core with M3 53.96 33.00 1,780.68
1.5 non expansive soil and compact by layer to depth 20cm
Cartaway and spread surplus excavated material and M3 386.82 66.00 25,530.27
1.6 deposit to an appropriate tip but away from the site.
25cm thick basaltic or equivalent stone hardcore well M2 269.80 165.00 44,517.00
1.7 rolled consolidated and blinded with crushed stone.
Total carried to summary 93,624.89
2. Masonry work
Stone masonry wall below ground level 70cm according M3 48.81 1,025.00 50,027.69
2.1 to the drawing bedded in cement sand mortar mix ration
(1:3)
Stone masonry wall above ground level 50cm according M3 28.86 1,151.00 33,220.74
2.2 to the drawing bedded in cement sand mortar mix ration
(1:3) both sides left for pointing.
Total carried to summary 83,248.43
3.Concrete Work
5cm lean concrete quality C-5 with minimum cement
3.1 content of 150Kg/m3 of concrete
a/ under masonary wall M2 24.00 71.00 1,704.00
Reinforced concrete in class C-25 with minimum
cement content of 382Kg/m3 filled in to formwork and
vibrated around rod reinforcement.(steel and formwork
measuered separately)
3.2 In grade beams M3 5.58 2,327.00 12,980.01
3.3 In 10 cm thick ground floor slab M2 269.80 725.00 195,605.00
Total carried to summary 210,289.01
4. Form work
Provide, cut and fix in position sawn zigba wood form
work
4.1 To grade beams M2 55.78 181.00 10,096.18
Total carried to summary 10,096.18
5.Steel Reinforcement
Steel reinforcement according to structural drawing
price shall include cutting, bending placing in position
and tying wires
Door -
a/90X300 Pcs 3,100.00 -
c/70X300 Pcs 3,000.00 -
Total carried to summary 7,494.00
7. Metal work
Window and doors made of aluminium profiles as per
the detail drawing and architect’s approval,. Cut and
assemble to size and shape shown on the drawing. Price
shall include all the necessary iron mongary and
accessories including approved type of lock
7.1 Door
D1 size 80 x 280 cm Pcs 8.00 3,420.00 27,360.00
D2 " 120x280cm Pcs 1.00 3,633.75 3,633.75
c/90X285 Pcs - 3,847.50 -
d/95X285 Pcs - 4,061.25 -
e/70X285 Pcs - 2,992.50 -
f/87X285 Pcs - 2,610.00 -
7.2 Window
WD1 '' 350X280 Pcs 1.00 12,825.00 12,825.00
WD3 '' 170X268 Pcs - 1,912.50 -
W1 " 80X50 Pcs 2.00 450.00 900.00
W2 100X150 Pcs 3.00 1,800.00 5,400.00
W3 180X150 Pcs 2.00 2,700.00 5,400.00
g/90X150 Pcs - 2,340.00 -
Total carried to summary 24,525.00
8. Finishing
Finishing work shall include all surfaces cleaning
preparation, chiseling, application of finishing,
polishing and cleaning at the end of finishing work.
Apply three coats of plaster in cement mortar (1:3) to M2 628.08 150.00 94,212.75
8.1 internal wall surface
8.2 Ditto but to external wall surface M2 418.72 150.00 62,808.50
ceramic tile flooring bedded in 3 cm thick cement sand M 2
269.80 280.00 75,544.00
8.3 screed
M2 269.80 120.00 32,376.00
8.4
gypsum ceiling
Total carried to summary 264,941.25
9. Glazing
M2 21.20 350.00 7,420.00
9.1 Supply and fix 4 mm thick clearing glazing as per the
detail drawing. Price shall include putty
Total carried to summary 7,420.00
10. Painting
Apply three coats of approved type plastic emulsion M2 628.08 45.00 28,263.82
10.1
paint to internal wall beams and columns.
10.2 Ditto but to external wall, beams and columns M2 418.72 45.00 18,842.55
10.3 Ditto but to gypsum ceiling M 2
269.80 45.00 12,141.00
Total carried to summary 59,247.38
11. Sanitary Installation
Supply and fix hand wash basin made of white vitreous No. 2.00 4,500.00 9,000.00
china equipped with concealed bracket mad of grey
11.1 malleable cast iron white painted compete with plug.
Chains and traps. Size 500x405
Supply and fix wash down water closet made of white No. 2.00 6,000.00 12,000.00
vitreous china with plastic seat and cover including low
flush cistern and stop cock on the water supply line
11.2 complete with all accessories. Supply and fix toilet
paper holder with metal roller 150x150x25mm
complete with fastening screws.
construct septic tank for toilet.price shall include all No. 2.00 1,600.00 3,200.00
necessary things according to the detail drawing.
11.3
2.LIGHT POINT
Supply and install light point fed through PVC No. 14.00 300.00 4,200.00
insulated conductor of2x2.5mm2 in PVC conduits
12.2 including , junction boxes, with screw, cups and
complete all accessories
3.SOCKET OUTLET
Supply and install socket point fed through PVC No. 20.00 250.00 5,000.00
insulated conductor 3x2.5mm2 in PVC hard conduit
12.3 including junction boxes with screw caps and complete
accessories
4.TELEPHONE,
Supply telephone point only conduit diam21 mm No. 1.00 450.00 450.00
12.4 including Supply telephone point only conduit diam21
mm including
5.TV
Flush mounted through wiring TV-FM_SAT socket No. 1.00 450.00 450.00
outlet point with conduit diam21 mm including junction
12.5 box with cover , pooling wireand TV outlet including
all accessories for complet installation.
6.FITTING
12.6 Best fittings on market No. 1.00 35.00 35.00
Supply flush switch type legrand or equivalent
Single switch No. 1.00 100.00 100.00
Double switch No. 26.00 120.00 3,120.00
Telephon terminal box No. 1.00 200.00 200.00
T.v terminal socket outlet No. 1.00 300.00 300.00
7.POWER CABLE
12.7 Best and modern cables now on market M 112.00 75.00 8,400.00
8.Conduits and Pipes
12.8 PVC pipes of 75mm in diameter M 65.00 50.00 3,250.00
Total carried to summary 28,005.00
PROJECT :RESIDENCE BUILDING
OWNER-GALANE BIRU
A. Substructure BIRR
1 Excavation and earth work 93,624.89
2 Masonry work 83,248.43
3 Concrete Work 210,289.01
4 Form Work 10,096.18
5 Steel Reinforcement 12,283.94
TOTAL A 409,542.45
B. Superstructure
1 Concrete Work 15,772.41
2 Form Work 19,488.27
3 Steel Reinforcement 27,264.00
4 Block Work 234,866.66
5 Roofing 62,482.20
6 Carpentry and joinery 7,494.00
7 Metal Work 24,525.00
8 Finishing 264,941.25
9 Glazing 7,420.00
10 Painting 59,247.38
11 Sanitary Installation 24,200.00
12 Electrical installation 28,005.00
TOTAL B 775,706.16
GRAND TOTAL A+B 1,185,248.61
VAT(15%) 177,787.29
GRAND TOTAL WITH VAT 1,363,035.90
GRAND SUMMARY
PROJECT :RESIDENCE BUILDING
OWNER-DUGO TULEMA
Type of Material
+ Transport Unit Qty U.Price* T.Cost Trade No UF
Selected
material m3 1.00 100.000 100.00 DL 5.00 100%
0.00 E/Forman 1.00 50%
0.00 Con. Engine 1.00 0%
0.00 Surveyor 1.00 0%
Type of Material
+ Transport Unit Qty U.Price* T.Cost Trade No UF
Selected
material m3 1.00 100.000 100.00 DL 5.00 100%
Water m4 0.20 12.000 2.40 E/Forman 1.00 50%
0.00 Con. Engine 1.00 0%
0.00 Surveyor 1.00 25%
Orator-III 1.00 90%
Orator-I 2.00 65%
Total (1.01) 102.40 Total (1.02)
Total of (1.02) 3.99375
Hourly Out Put
Type of Material
+ Transport Unit Qty U.Price* T.Cost Trade No UF
0.00 Helper I 3.00 100%
0.00 E/Forman 1.00 50%
0.00 Con. Engine 1.00 0%
Opretor-I 3.00 65%
Total (1.01) 0.00 Total (1.02)
Total of (1.02) 5.96875
Hourly Out Put
Type of Material
+ Transport Unit Qty U.Price* T.Cost Trade No UF
0.00 DL 1.00 100%
0.00 E/Forman 1.00 0%
0.00 Helper-III 1.00 100%
Opretor-III 1.00 100%
Total (1.01) 0.00 Total (1.02)
Total of (1.02) 13.28125
Hourly Out Put
Type of Material
+ transport Unit Qty U.Price* T.Cost Trade No UF
Stone masonry m3 1.20 430.000 516.00DL 8.00 100%
Sand m3 0.24 481.250 115.50Forman 1.00 50%
Cement Qnt 0.62 235.000 145.70Masson 4.00 80%
Water m3 0.10 12.000 1.20Helper-I 1.00 90%
Orator-I 1.00 65%
Total (1.01) 778.40 Total (1.02)
Total of (1.02) 79.32143
Hourly Out Put
Type of Material
+ transport Unit Qty U.Price* T.Cost Trade No UF
Stone masonry m3 1.00 430.000 430.00 DL 8.00 100%
Sand m3 0.24 481.250 115.50 Forman 1.00 50%
Cement Qnt 0.52 235.000 122.20 Masson 4.00 80%
Water m3 0.10 12.000 1.20 Helper-I 1.00 90%
Orator-I 1.00 65%
Total (1.01) 668.90 Total (1.02)
Total of (1.02) 79.32143
Hourly Out Put
Type of Material
+ transport Unit Qty U.Price* T.Cost Trade No UF
Agregate m3 0.80 450.000 360.00 DL 12.00 100%
Sand m3 0.40 481.250 192.50 Forman 1.00 50%
Cement Qnt 2.00 235.000 470.00 Masson 2.00 80%
Water m3 0.10 12.000 1.20 M/oprt. 1.00 80%
1.00
Total (1.01) 1023.70 Total (1.02)
Total of (1.02) 8.704044
Hourly Out Put
Type of Material
+ transport Unit Qty U.Price* T.Cost Trade No UF
Aggregate m3 0.80 450.000 360.00 DL 8.00 100%
Sand m3 0.40 481.250 192.50 Forman 1.00 50%
Cement Qnt 2.00 235.000 470.00 Masson 1.00 80%
Water m3 0.10 12.000 1.20 M/oprt. 1.00 80%
Type of Material
+ transport Unit Qty U.Price* T.Cost Trade No UF
Aggregate m3 0.80 450.000 360.00 DL 15.00 100%
Sand m3 0.46 481.250 221.38 Forman 1.00 100%
Cement Qnt 3.80 235.000 893.00 Masson 2.00 100%
Water m3 0.10 12.000 1.20 M/oprt. 1.00 100%
Type of Material
+ transport Unit Qty U.Price* T.Cost Trade No UF
Aggregate m3 0.75 450.000 337.50 DL 25.00 100%
Sand m3 0.50 481.250 240.63 Forman 1.00 100%
Cement Qnt 4.10 235.000 963.50 Masson 2.00 100%
Water m3 0.10 12.000 1.20 M/oprt. 2.00 100%
Type of Material
+ transport Unit Qty U.Price* T.Cost Trade No UF
Aggregate m3 0.82 450.000 369.00 DL 15.00 100%
Sand m3 0.41 481.250 197.31 Forman 1.00 100%
Cement Qnt 4.80 235.000 1128.00 Masson 2.00 100%
Water m3 0.10 12.000 1.20 M/oprt. 1.00 100%
Type of Material
+ transport Unit Qty U.Price* T.Cost Trade No UF
Aggregate m3 0.75 450.000 337.50 DL 25.00 100%
Sand m3 0.45 481.250 216.56 Forman 1.00 100%
Cement Qnt 5.00 235.000 1175.00 Masson 2.00 100%
Water m3 0.10 12.000 1.20 M/oprt. 2.00 100%
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
Type of Material
+ transport Unit Qty U.Price* T.Cost Trade No UF
Sand m3 0.60 481.250 288.75 DL 2.00 100%
Cement Qnt 3.00 235.000 705.00 Forman 1.00 25%
Water m3 0.10 12.000 1.20 Masson 1.00 80%
Type of Material
+ transport Unit Qty U.Price* T.Cost Trade No UF
Sand m3 0.36 481.250 173.25 DL 2.00 100%
Cement Qnt 1.50 235.000 352.50 Forman 1.00 25%
Water m3 0.10 12.000 1.20 Masson 1.00 80%
ance
ance
spective of distance
nd ratio of mortar
nd ratio of mortar
- -
- -
- -
- -
- -
- -
- -
12.50 10.00
31.25 25.00
- -
spective of distance
EQUIPMENT COST (1.03)
5
5.75
0
9.84
12.8
0.6 270
0.4 192.5
1
10
5 1175
1,637.50
1,889.53
2,267.44
zigba wood formwork
2.64 26.4
0.12 0.5
0.0390 0.16
three coats of cement mortar plaster mix ratio 1:3
bishoftu city Municipality
SURVEY OF Material price list
Imported
material
cost=Orgi
nal
costxcurre
Item No Description Unit Orginal cost nt
exchange
Rate x
FOB
Index
Factor
Materials
1 Selected Material M3 100.00
2 Pozzolana portland cement Qnt 235.00
3 Oridinary portland cement Qnt 335.00
4 Sand M3 481.25
5 Aggregate M3 450.00
6 water m3 12.00
7 Stone for hardcore M3 250.00
8 stone for masnory M3 430.00
9 Pumice m3
10 Red ash M3 120.00
11 Reinforcement bar
12 Size:- ø6mm Kg 36.00
13 Size:- ø8mm Kg 35.00
14 Size:- ø10mm Kg 34.00
15 Size:- ø12mm Kg 32.00
16 Size:- ø14mm Kg 30.60
17 Size:- ø16mm Kg 30.00
18 Size:- ø20mm Kg 30.00
19 Size:- ø24mm Kg 30.78
20 Size:- ø26mm Kg 29.00
21 Size:- ø30mm Kg 29.00
22 Tying wire kg 50.00
23 Tension wire for shoring kg
24 Nail
25 Size:- ø4mm Kg 60.00
26 Size:- ø6mm Kg 45.00
27 Size:- ø7mm Kg 45.00
28 Size:- ø8mm Kg 45.00
29 Size:- ø9mm Kg 45.00
30 Size:- ø10mm Kg 45.00
31 Size:- ø12mm Kg 45.00
32 Size:- ø15mm Kg 45.00
33 Roofing nail Kg 45.00
34 Block Work
35 HCB 20 cm width Class C pcs 12.00
36 HCB 15 cm width Class C pcs 10.00
37 HCB 10 cm width Class C pcs 9.75
38 Ribbed Block pcs 13.00
39 Brick (6x12x24) pcs 7.00
40 Roofing Materials
41 Aluminium Door & Window ISO
m2 3400.00
standard
42 LTZ Door & Window m2 1000.00
43 Ceiling Work
44 Boards M3
45 Batten M3
46 Ecalyptus dia 12cm ml 20.00
47 Ecalyptus dia 10cm ml 20.00
48 Ecalyptus dia 8cm ml 13.00
49 5X7 cm Zigba purlin ml 20.00
50 Nail kg
51 Purlin ml
52 Fascia board ml 53.00
53 Plywood m2 105.00
54 Chipwood m2 122.00
styrfoam ml 12.20
Timber (2.5X10X400) (Australia) m2 325.00
Timber (2.5X10X400) (Ethiopia) m2 250.00
Timber (2.5X15X400) (Australia) m2 366.67
Timber (2.5X15X400) (Ethiopia) m2 316.67
Timber (2.5X25X400) (Australia) m2 310.00 77.50
Timber (2.5X25X400) (Ethiopia) m2 250.00
Timber (2.5X30X400) (Australia) m2 266.67
Timber (2.5X30X400) (Ethiopia) m2 241.67 60.42
55 PVC plastic cieling m2
56 Faccia ml
57 corner list ml 8.00
58 Boards(X0.5) m 3
Total
Source Transport loading price
Place cost Unloading (with out
vat)
21.73913
170
0 110
0.00 14.95652
Nardeli 117.61 31.06895
47.44
Ethiopian
plywood
Ethiopian
plywood
0.72 43.47826
60.38647
1027.826
57.14286
57.14286
127.1605
#DIV/0!
#DIV/0!
1.952
1.525
1.5
91.8
5.4
19440
0
0
50000
13.88889
BISHOFTU CITY CONSTRUCTION OFFICE Tools rental COST SURVEY
SHEET
Types of
Machine
No. ries and Unit Hourly Rent Remark Location
Equipm
ent
Excavator Chain
With JackHamer
1 185 Horse Power Hour 1,500.00
Excavator Chain
With JackHamer
2 185 Horse Power Hour 1,250.00
Shower Truck
3000-5000l Hour 500.00
TRUCTION OFFICE LABOUR COST SURVEY SHEET
Remark
Location
Finfinne
Finfinne
Finfinne
Finfinne
Finfinne
Finfinne
Finfinne
Finfinne
Finfinne