Metal Clad SWGR
Metal Clad SWGR
Metal Clad SWGR
sibilities
SITE TEST REPORT Date :
Legend
Contractor’s name: Customer:
CSD Hadi Haider Company NG-EOA
Contract No. :
Name of substation: Contruction of Mardumah 115/13.8kV 20BD 564-C31
Page 1 of 24
METAL CLAD SWITCHGEAR
Panel/Bay No: Equip. No.: Dwg. Ref.: Record No.:
Have all relevant safety instructions been followed?
..\WorkInstructions\29.pdf
For Mechanical Check/Visual Inspection and Electrical Tests Use C.L. of W.I.29
Make :
Type :
Auxiliary Volts
Close - DC :
Trip - DC :
Serial No. :
Date of Manufacturer :
Testing Instrument :
Procedure : The bus continuity and the phase of the buses are checked at all the CB feeders.
Result :
Make : S. No. :
Range :
Calibration Certificate :
Connections : Both current & voltage leads are connected across a Bus
tapping point and outgoing cable termination points.
Wiring Correctness
Testing Instrument
Procedure
All Panels wiring correctness will be checked by continuity method as per approved drawing.
Panel Designation :
Breaker Reference :
Instrument :
Make :
Calibration Certificate :
Panel Reference :
Earth Switch Designation :
Instrument :
Make :
Calibration Certificate :
Instrument :
Make :
Applied points : Between Auxiliary Control circuits connected together as a whole and
frame of the switchgear.
Result :
Note: Auxiliary control circuits shall include complete Switchgear control wiring.
FEEDER DESIGNATION:
1. The breaker was closed and the control switch was held in CLOSE position. It was ensured that the
breaker closes.
a) Manually b) Electrically
3. It will be noted from the results below that the breaker does not attempt to re-close if a permanent closing
TEST DATE: TEST EQUIPMENT CALIB.DATE & DETAIL
2. Breaker control switch held YES Breaker trips and Breaker remains
in “CLOSE” position. Electrically does not attempt to OPEN
RECLOSE
5. Breaker control switch held YES Breaker trips and Breaker remains
in “CLOSE” position. mechanically does not attempt to OPEN
RECLOSE
Measured IR value
Applied points between Criteria Mega Remarks
( Mega. Ohms )
Ohms
CURRENT TRANSFORMER
TEST
TEST DESCRIPTION REMARKS
NO
2. ELECTRICAL TESTS:
TEST
TEST DESCRIPTION REMARKS
NO
Criteria
CORE-1 1S1-1S2
B CORE-1 1S1-1S3
CORE-2 2S1-2S2
CORE-1 1S1-1S2
C CORE-1 1S1-1S3
CORE-2 2S1-2S2
3. Polarity Test
4. Ratio Test
Ratio Test
Secondry
TERMINAL Primary Test
PHASE CT REF RATIO C.T %Error
No Current (A)
Meas.
Core-2 2S1-2S2
A
Core-2 2S1-2S2
B
Core-2 2S1-2S2
C
Instruments:
Criteria : The % error for magnetizing Current shall be within + 5% of the factory test report
.
Note: All CT cores shall be demagnetized after the tests are carried out.
TEST DATE: TEST EQUIPMENT CALIB.DATE & DETAIL
Measured Values
Phase Description
1 2 3 4 5 6 7 8
Ratio:
A Current (mA)
Terminal Nos.
Current from
magnetizing
Curve (mA)
CORE-2
Voltage (V)
Ratio:
Current (mA)
Current (mA)
Measured Values
Phase Description
1 2 3 4 5 6 7 8
Current from
Terminal Nos.
magnetizing
Curve (mA)
Current from
Terminal Nos.
magnetizing
Curve (mA)
Ratio:
Current (mA)
Current from
Terminal Nos. magnetizing
Curve (mA)
CORE-2
Ratio: Voltage (V)
Current (mA)
Measured Values
Phase Description
1 2 3 4 5 6 7 8
Voltage (V)
CORE-1
Ratio:
Current (mA)
Current from
Terminal Nos.
magnetizing
Curve (mA)
Voltage (V)
CORE-1
Current from
Terminal Nos.
magnetizing
Curve (mA)
Ratio:
Current (mA)
Current from
Terminal Nos. magnetizing
Curve (mA)
CORE-2
Ratio: Voltage (V)
Current (mA)
Current from
Terminal magnetizing
Nos. Curve (mA)
6. Burden Test
Instrument:
Make :
A
CORE-1
CORE-2
B
CORE-1
CORE-2
C
CORE-1
Core No.
Injected Measured Secondary Current (mA)
Current (A) R Y B N
Phase Identification Check (by shorting secondary terminal during primary injection) :
Note: All CT cores shall be demagnetized after the tests are carried out.
VOLTAGE TRANSFORMER
TEST
TEST DESCRIPTION REMARKS
NO
2. ELECTRICAL TESTS:
TEST
TEST DESCRIPTION REMARKS
NO
NOTE: 1.
Rc = Calculated value at 75 C
Rm = Measurement value which contained a measurement cable.
NOTE: 2
Calculated 75 C Rc = (Rm-Rx) x (234.5+75)
(234.5+Ta)
NOTE: 3
Make :
1 Primary - Ground
Secondary-1 - Ground
Primary - Secondary-2
2 Secondary-2 - Ground
3 Secondary-1 – Secondary –2
3.Ratio test.
1S1-1S3
1S1-1S3
1S1-1S2
1S1-1S2
B 1S1-1S2
1S1-1S2
1S1-1S3
1S1-1S3
1S1-1S3
1S1-1S3
1S1-1S2
1S1-1S2
Core-2 2S1-2S2
A
Core-2 2S1-2S2
B
Core-2 2S1-2S2
C
Result:
4. Polarity Test
Instrument 1. Multimeter
2. Battery
Tick here if found okay
Polarity checked
Phase Core & found okay
A 1
5. Burden Test
Instrument:
Multimeter
Make :
Model / Sl. No. :
Calibration
Certificate ref. :
B 1
C 1
Instruments:
Make :
3. Procedure
a) Remove the 13.8kV side HRC fuses of the potential transformers in all the three phases to
ensure that the primary induced voltage is not fed to the switchgear bus or the other equipments.
No Breakdown
A
No Breakdown
B
No Breakdown
C
Functional Checks:
Trip Coil # 2 :
Functional Test
2. Thermostat Operation
Heater Circuit ON 55 ± 5 º F
Heater Circuit OFF 70 ± 5 º F
3. Heater Current ( A )
( Single Phase )