Assignment Transformer Sizes
Assignment Transformer Sizes
3 kVA
6 kVA
9 kVA
15 kVA
30 kVA
37.5 kVA
45 kVA
75 kVA
112.5 kVA
150 kVA
225 kVA
300 kVA
500 kVA
750 kVA
1,000 kVA
https://elscotransformers.com/blog/guide-to-transformer-kva-ratings-how-to-determine-
what-size-transformer-you-need/
2. Transformer – Working Principle
Transformers convert energy from the source to the power required by the load. To use
their transformers effectively, businesses need to know how much power their particular
transformers can give them. A transformer’s rating provides that information. The transformer
typically consists of two windings, a primary and secondary winding. Input power flows through
the primary winding. The secondary winding then converts the power and sends it to the load
through its input leads. A transformer’s rating, or size, is its power level in kilovolt-amperes.
The main principle of operation of a transformer is mutual inductance between two circuits
which is linked by a common magnetic flux. A basic transformer consists of two coils that are
electrically separate and inductive, but are magnetically linked through a path of reluctance. The
working principle of the transformer can be understood from the figure below.
As shown above the electrical transformer has primary and secondary windings. The core
laminations are joined in the form of strips in between the strips you can see that there are some
narrow gaps right through the cross-section of the core. These staggered joints are said to be
‘imbricated’. Both the coils have high mutual inductance. A mutual electro-motive force is
induced in the transformer from the alternating flux that is set up in the laminated core, due to
the coil that is connected to a source of alternating voltage. Most of the alternating flux
developed by this coil is linked with the other coil and thus produces the mutual induced electro-
motive force. The so produced electro-motive force can be explained with the help of Faraday’s
laws of Electromagnetic Induction as
e=M*dI/dt
If the second coil circuit is closed, a current flows in it and thus electrical energy is transferred
magnetically from the first to the second coil.
The alternating current supply is given to the first coil and hence it can be called as the primary
winding. The energy is drawn out from the second coil and thus can be called as the secondary
winding.
Step 1 – Disconnect the all line and neutral terminals of the transformer.
Step 2 – The megger leads are to be connected between the LV and HV bushing studs to
measure the insulation resistance between the LV and HV windings.
Step 3 – The megger leads are to be connected between the HV bushing stud and earth
terminal of the transformer (body of the transformer) to measure the insulation resistance
between the HV winding and the earth.
Step 4 – The megger leads are to be connected between the LV bushing stud and the
body of the transformer (earth terminal) to measure the insulation resistance between the
LV winding and the earth.
All the readings taken above should be tending to infinity for a healthy transformer.
Open and Short Circuit Test of Transformer
Open and short circuit tests are performed on a transformer to determine the:
The ammeter reading gives the no load current I e. As no load current Ie is quite small compared
to rated current of the transformer, the voltage drops due to this current that can be taken as
negligible.
Since voltmeter reading V1 can be considered equal to the secondary induced voltage of the
transformer, wattmeter reading indicates the input power during the test. As the transformer is
open circuited, there is no output, hence the input power here consists of core losses in
transformer and copper loss in transformer during no load condition. But as said earlier, the no-
load current in the transformer is quite small compared to the full load current so, we can neglect
the copper loss due to the no-load current. Hence, can take the wattmeter reading as equal to the
core losses in the transformer.
Let us consider wattmeter reading is Po.
These values are referred to the LV side of the transformer due to the tests being conducted on
the LV side of transformer. These values could easily be referred to HV side by multiplying
these values with square of transformation ratio.
Therefore it is seen that the open circuit test on transformer is used to determine core losses in
transformer and parameters of the shunt branch of the equivalent circuit of the transformer.
Therefore it is seen that the open circuit test on transformer is used to determine core losses in
transformer and parameters of the shunt branch of the equivalent circuit of the transformer.
Let’s say, voltmeter reading is V sc. The watt-meter reading indicates the input power during the
test. As we have short-circuited the transformer, there is no output; hence the input power here
consists of copper losses in the transformer. Since the applied voltage V sc is short circuit voltage
in the transformer and hence it is quite small compared to the rated voltage, so, we can neglect
the core loss due to the small applied voltage. Hence the wattmeter reading can be taken as equal
to copper losses in the transformer. Let us consider wattmeter reading is Psc.
These values are referred to the HV side of the transformer as the test is conducted on the HV
side of the transformer. These values could easily be converted to the LV side by dividing these
values with the square of transformation ratio.
Hence the short-circuit test of a transformer is used to determine copper losses in the
transformer at full load. It is also used to obtain the parameters to approximate the equivalent
circuit of a transformer.
https://www.electrical4u.com/open-and-short-circuit-test-on-transformer/
PROBLEM SOLVING:
1. A 50kVA, 2300/230 volts, 60 Hz transformer was tested with the following result.
Short circuit test: 115V, 21.7, 570W and open circuit test: 230V, 6.5A,
187W .Determine the efficiency of the transformer at three quarter load at unity pf.
2. A 50kVA, 2300/230 volts, 60 Hz transformer was tested with the following result.
Short circuit test: 115V, 21.7, 570W and open circuit test: 230V, 6.5A,
187W .Determine the efficiency of the transformer at half load at 0.85 pf lag.
3. A 100kVa transformer has maximum efficiency of 98% at 10% underload and unity pf.
Evaluate the efficiency at quarter load at 0.8 pf lag.
4. The hysteresis loss in a 6,600 volts, 50 Hz transformer is 480 watts. What will be the loss
when the transformer is connected to a 6,900 volts, 40 Hz source?
5. What is the efficiency at full load and 85% pf lagging of a single phase 50kVA
11000/480V 50Hz transformer with a copper loss at full load of 1.2 times the rated core
loss and is 95% efficient when running at 0.8pf at three quarter load?
6. A 2400/240 V single phase transformer takes 0.5A at 0.3 pf on open circuit test. What is
the amount of core loss?
7. A 50kVA single phase 2400/240 V distribution transformer has primary resistance of 1.6
ohms and secondary resistance of 0.08 ohm. What is the total copper loss at full load and
0.85 pf lagging?
9. A single-phase 37.5kVA 2300/230V 50Hz distribution transformer has a rated core loss
of 300W and full-load copper loss of 500W. What is the efficiency of the transformer at
full load and 80% pf lagging?
10. A single-phase 25kVA 2300/230V 50Hz distribution transformer has a rated core loss of
300W and full-load copper loss of 500W. What is the efficiency of the transformer at half
load and 85% pf lagging?
SOLUTION: