E-Typical End Bracket - Typical Zone

Download as pdf or txt
Download as pdf or txt
You are on page 1of 4

Design office: *

Person in charge: *
Construction project: E-TYPICAL END FIX BRACKET - TYPICAL LZONE
Project number:
Position: Date: 8/5/2024

Input data: Page 1 / 4

Concrete: Static / quasi-static


cracked concrete action
strength class: C35/45 Tensile load:
Reinforcement: Nz,Sd = 8.08 kN
normal or no reinforcement Shear load:
without edge reinforcement Vx,Sd = 1.217 kN
with reinforcement to resist splitting according to [1] chapter 5.2.2.6 Vy,Sd = 0.00 kN
Anchor bending:
Moments:
without anchor bending
Mx,Sd = 0.00 kNm
Installation conditions:
My,Sd = 0.121 kNm
Drilling method: see remarks Page 4
Mz,Sd = 0.00 kNm

Eccentric load
e x = 0.0 mm
e y = 20.0 mm

8.08
Anchor plate:
x = 150 mm 0.121
y = 135 mm
lx1 = 35 mm
lx2 = 35 mm 1.217
ly1 = 103 mm cx2 20
ly2 = 32 mm
sx1 z
Distance between anchors:
sx1 = 80 mm cx1 x
y
Edge distances: h
cx1 = 410 mm 2
cx2 = 110 mm 1
Thickness of anchor base:
h = 1000 mm lx2
ly1 sx1
ly2 lx1 x
y

[ kN, kNm ]
Wedge Anchor BZ plus A4 M12 hef 70
Design method A, ETAG 001, Annex C + TR 055
Assessment ETA-99/0010: MKT BZ plus / BZ-IG
The anchorage is verified. Boundary
Tension loads Shear loads Interaction conditions:
bN [%] bV [%] bN,V [%]
Static / quasi-static action 93.4 9.0 85.4 OK

The calculation only applies if the notes on the last page are observed.

Anchor Design Program Version 4.57

MKT Metall-Kunststoff-Technik GmbH & Co.KG | Auf dem Immel 2 | D-67685 Weilerbach | Tel.: +49 (0) 6374 / 9116-0 | support@mkt.de
Design office: *
Person in charge: *
Construction project: E-TYPICAL END FIX BRACKET - TYPICAL LZONE
Project number:
Position: Date: 8/5/2024

Wedge Anchor BZ plus A4 M12 hef 70 Page 2 / 4


Assessment ETA-99/0010: MKT BZ plus / BZ-IG

Required proofs for tension loads

Anchor loads
Anchor 1 2
NSd [kN] 12.45 11.53

Proof steel failure


h
N Sd ≤ NRk,s / gMs = NRd,s Utilisation:
12.45 ≤ 40.00 / 1.50 = 26.67 46.7%

Proof pullout failure


h
N Sd ≤ NRk,p / gMp = NRd,p Utilisation:
12.45 ≤ 21.47 / 1.50 = 14.31 87.0%
NRk,p YC,(C35/45)
16.00 kN 1.34

Proof concrete cone failure


g
N Sd ≤ NRk,c / gMc = NRd,c Utilisation:
23.98 ≤ 38.50 / 1.50 = 25.67 93.4%
o
N Rk,c YA,c,N Ys,N Yre,N Yec,N
28.29 kN 1.38 1.00 1.00 0.99
o
k1 Ac,N A c,N hef fck,cube ccr,N ec1,N ec2,N
2 2 2
7.2 60900 mm 44100 mm 70.0 mm 45 N/mm 105.0 mm 1.5 mm 0.0 mm

Proof splitting failure


No proof required. Existing reinforcement to resist splitting according to [1] chapter 5.2.2.6

Anchor Design Program Version 4.57

MKT Metall-Kunststoff-Technik GmbH & Co.KG | Auf dem Immel 2 | D-67685 Weilerbach | Tel.: +49 (0) 6374 / 9116-0 | support@mkt.de
Design office: *
Person in charge: *
Construction project: E-TYPICAL END FIX BRACKET - TYPICAL LZONE
Project number:
Position: Date: 8/5/2024

Wedge Anchor BZ plus A4 M12 hef 70 Page 3 / 4


Assessment ETA-99/0010: MKT BZ plus / BZ-IG

Required proofs for shear loads

Anchor loads
Anchor 1 2
VSd [kN] 1.04 1.04
Vx,Sd [kN] 0.61 0.61
Vy,Sd [kN] 0.84 -0.84

Proof steel failure without lever arm


h
V Sd ≤ VRk,s / gMs = VRd,s Utilisation:
1.04 ≤ 30.00 / 1.25 = 24.00 4.3%

Proof concrete pryout failure


1
V Sd ≤ VRk,cp / gMc = VRd,cp Utilisation:
1.04 ≤ 38.17 / 1.50 = 25.45 4.1%
o
N Rk,c YA,c,N Ys,N Yre,N Yec,N k
28.29 kN 0.69 0.81 1.00 1.00 2.40
o
k1 Ac,N A c,N hef fck,cube ccr,N ec1,N ec2,N
2 2 2
7.2 30450 mm 44100 mm 70.0 mm 45 N/mm 105.0 mm 0.0 mm 0.0 mm

Proof concrete edge failure (most unfavourable edge) Edge cx2


g
V Sd ≤ VRk,c / gMc = VRd,c Utilisation:
1 1.48 ≤ 24.71 / 1.50 = 16.47 9.0%
2 1.77 ≤ 46.22 / 1.50 = 30.81 5.7%
o
V Rk,c YA,c,V Ys , V Yh,V Ya, V Yec,V Yre,V
1 21.07 kN 1.00 1.00 1.00 1.17 1.00 1.00
2 44.35 kN 1.00 1.00 1.00 1.11 0.94 1.00
o
Anchor c1 Ac , V A c,V aV eV
2 2
1 2 110.0 mm 54450 m m 54450 m m 34.75 0.00 mm
2 2
2 1,2 190.0 mm 1625 cm 1625 cm 28.5 19.09 mm
k1 dnom lf fck,cube
2
1.7 12 mm 70 mm 45 N/mm

Interaction, combined load in most unfavourable case


bN + bV ≤ 1.2 Utilisation:
0.93 + 0.09 = 1.02 ≤ 1.2 85.4%

Anchor Design Program Version 4.57

MKT Metall-Kunststoff-Technik GmbH & Co.KG | Auf dem Immel 2 | D-67685 Weilerbach | Tel.: +49 (0) 6374 / 9116-0 | support@mkt.de
Design office: *
Person in charge: *
Construction project: E-TYPICAL END FIX BRACKET - TYPICAL LZONE
Project number:
Position: Date: 8/5/2024

Wedge Anchor BZ plus A4 M12 hef 70 Page 4 / 4


Assessment ETA-99/0010: MKT BZ plus / BZ-IG

Installation parameters

Thread M12
Diameter of drill hole d0 = 12 mm
Depth of drill hole h1 = 90 mm
Effective anchorage depth hef = 70 mm
Installation torque Tinst = 50 Nm
Width across nut SW = 19 mm
Minimum thickness
of anchor base hmin = 140 mm
Diameter of clearance hole
in the fixture df ≤ 14 mm

Remarks
The anchors are without influence of edge distance, if: c ≥ max ( 10 h ef ; 60 d )
If the diameter df of the clearance hole does not correspond with the specifications in the assessment,
or with the design of slotted holes, follow the notes in [1], chapter 1.1.
The calculation regards data for standard thickness of concrete slab.
The design is based on the assumption that the anchor plate remains flat under the acting forces.
The proof of the capacity of the anchor base component shall be shown according to chapter 7 in [1].
The temperature ranges are specified in [2].
For the proof of concrete edge failure not all load cases (e.g. torsion with shear load parallel to the edge)
are clearly described in the above guidelines.
For these cases the calculation method is applied with current engineering judgement.
The selected anchor can be installed deeper to reduce the fixture thickness. Therfore the borehole shall
be drilled correspondingly deeper and the minimum thickness of anchor base must be checked.
The minimum thickness of the concrete member hmin increases by this deeper drilled length.
The calculation is valid for the following drilling method
- Vacuum drilling without cleaning
- Drilling followed by cleaning (with hammer drill, compressed air drill or vacuum drill)
The installation instruction shall be observed.

[1] ETAG 001, Annex C


[2] ETAG 001-1

Anchor Design Program Version 4.57