Schedule Pekerjaan - Cladtek

Download as pdf or txt
Download as pdf or txt
You are on page 1of 2

AGUSTUS SEPTEMBER OKTOBER

Item Description Specifiction DURATION START - FINISH


21 22 23 24 25 26 27 28 29 30 31 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26

I PREPARATION
1 Mobilization of tools and materials Kato for Lifting Material 67 days 21-Aug-24 - 26-Oct-24
2 Survey & Measurement Leveling Land 67 days 21-Aug-24 - 26-Oct-24
3 Electrical and Water for Work (supply by owner) 67 days 21-Aug-24 - 26-Oct-24
4 Scaffolding (supply by owner)
5 Safety Equipment 67 days 21-Aug-24 - 26-Oct-24
6 Detail Design & Endorsement 7 days 21-Aug-24 - 27-Aug-24
7 Site Coordination (Joint Meeting at Site) 7 days 21-Aug-24 - 27-Aug-24
II FOUNDATION WORK
A Bore Pile
1 Drilling Hole (12 Point) D-50, Depth 10 m, Cap.>150T 17 days 25-Aug-24 - 10-Sep-24
2 Concrete K350 11 days 28-Aug-24 - 7-Sep-24
3 Reinforce Bar 10D16 / Spiral D10-150 11 days 28-Aug-24 - 7-Sep-24
B Concrete Pile Cap 1200 x 2000 x 800
1 Cutting Pile (12 point) 10 days 3-Sep-24 - 12-Sep-24
2 Excavation with license 10 days 3-Sep-24 - 12-Sep-24
3 Soil Back Fill 10 days 6-Sep-24 - 15-Sep-24
4 Sand Fill Thick 100 mm 10 days 4-Sep-24 - 13-Sep-24
5 Lean Concrete Thick 100 mm, Site Mix 1Pc : 2Ps : 3Kr 10 days 4-Sep-24 - 13-Sep-24
6 Concrete Casting K350, 1200 x 2000 x 800 10 days 5-Sep-24 - 14-Sep-24
7 Reinforce Bar D19-150, 3D16 10 days 5-Sep-24 - 14-Sep-24
8 Concrete Molds Multiplek & wood 10 days 5-Sep-24 - 14-Sep-24
C Concrete Stump 550 x 1720 x 900
1 Anchor Bolt 20D22 - Length 700 mm 6 days 15-Sep-24 - 20-Sep-24
2 Concrete Casting K350, 550 x 1720 x 900 6 days 15-Sep-24 - 20-Sep-24
3 Reinforce Bar D19-150, 2D19 6 days 15-Sep-24 - 20-Sep-24
4 Concrete Molds Multiplek & wood 6 days 15-Sep-24 - 20-Sep-24
5 Grouting
III CONCRETE WORK
D Concrete Tie Beam/Sloof 300 x 500
1 Excavation with license 10 days 3-Sep-24 - 12-Sep-24
2 Soil Back Fill 10 days 6-Sep-24 - 15-Sep-24
3 Sand Fill Thick 100 mm 10 days 4-Sep-24 - 13-Sep-24
4 Lean Concrete Thick 50 mm, Site Mix 1Pc : 2Ps : 3Kr 10 days 4-Sep-24 - 13-Sep-24
5 Concrete Casting K350, 300x500 10 days 5-Sep-24 - 14-Sep-24
6 Reinforce Bar 8D16, D10-150 10 days 5-Sep-24 - 14-Sep-24
7 Concrete Molds Multiplek & wood 10 days 5-Sep-24 - 14-Sep-24
E Concrete Yard
1 Excavation with license Soil cuting 31 days 13-Sep-24 - 13-Oct-24
2 Compactor with license Compactor soil 31 days 14-Sep-24 - 14-Oct-24
3 Dumptruck Soil trasfer near area 31 days 13-Sep-24 - 13-Oct-24
4 Bauxite Thick 30 cm until 40 cm 31 days 16-Sep-24 - 16-Oct-24
5 Plastic Cast Standard for Casting 31 days 16-Sep-24 - 16-Oct-24
6 Concrete Casting K300, Thick. 300 mm 31 days 16-Sep-24 - 16-Oct-24
7 Reinforce Bar A10, 2 Layer 31 days 16-Sep-24 - 16-Oct-24
2
8 Korset D12 / 1m 31 days 16-Sep-24 - 16-Oct-24
9 Dowel D25 - 600 @ 200 mm & Joint Filler 31 days 16-Sep-24 - 16-Oct-24
10 Tie Bar D12 - 150 31 days 16-Sep-24 - 16-Oct-24
11 Concrete Molds Multiplek & wood 31 days 16-Sep-24 - 16-Oct-24
F Concrete Road (27 x 14)
1 Excavation with license Soil cuting 5 days 14-Oct-24 - 18-Oct-24
2 Compactor with license Compactor soil 5 days 15-Oct-24 - 19-Oct-24
3 Dumptruck Soil trasfer near area 5 days 14-Oct-24 - 18-Oct-24
4 Bauxite Thick 30 cm until 40 cm 3 days 17-Oct-24 - 19-Oct-24
5 Plastic Cast Standard for casting 3 days 22-Oct-24 - 24-Oct-24
6 Concrete Casting K300, Thick. 300 mm 4 days 22-Oct-24 - 25-Oct-24
7 Reinforce Bar A10, 2 Layer 5 days 22-Oct-24 - 26-Oct-24
8 Korset D12 / 1m2 5 days 22-Oct-24 - 26-Oct-24
9 Dowel D25 - 600 @ 200 mm & Joint Filler 5 days 22-Oct-24 - 26-Oct-24
10 Tie Bar D12 - 150 5 days 22-Oct-24 - 26-Oct-24
11 Concrete Molds Multiplek 12mm & wood 5 days 22-Oct-24 - 26-Oct-24
IV CONCRETE WORK (OPTIONAL ADD 2 POINT)
A Demolish
1 Column & Runway 2 days 6-Sep-24 - 7-Sep-24
2 Concrete Foundation 3 days 8-Sep-24 - 10-Sep-24
B BORE PILE
1 Drilling Hole (2 Point) D-50, Depth 10 m, Cap.>150T 2 days 11-Sep-24 - 12-Sep-24
2 Concrete K350 1 days 12-Sep-24 - 12-Sep-24
3 Reinforce Bar 10D16 / Spiral D10-150 1 days 12-Sep-24 - 12-Sep-24
C Concrete Pile Cap 1200 x 2000 x 600
1 Cutting Pile (2 point) 2 days 15-Sep-24 - 16-Sep-24
2 Excavation with license 2 days 15-Sep-24 - 16-Sep-24
3 Soil Back Fill 1 days 19-Sep-24 - 19-Sep-24
4 Sand Fill Thick 100 mm 1 days 17-Sep-24 - 17-Sep-24
AGUSTUS SEPTEMBER OKTOBER
Item Description Specifiction DURATION START - FINISH
21 22 23 24 25 26 27 28 29 30 31 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26

5 Lean Concrete Thick 100 mm, Site Mix 1Pc : 2Ps : 3Kr 1 days 17-Sep-24 - 17-Sep-24
6 Concrete Casting K350, 1200 x 2000 x 800 1 days 18-Sep-24 - 18-Sep-24
7 Reinforce Bar D19-150, 3D16 1 days 18-Sep-24 - 18-Sep-24
8 Concrete Molds Multiplek & wood 1 days 18-Sep-24 - 18-Sep-24
D Concrete Stump 550 x 1720 x 900
1 Anchor Bolt 20D22 - Length 700 mm 1 days 20-Sep-24 - 20-Sep-24
2 Concrete Casting K350, 550 x 1720 x 900 1 days 20-Sep-24 - 20-Sep-24
3 Reinforce Bar D19-150, 2D19 1 days 20-Sep-24 - 20-Sep-24
4 Concrete Molds Multiplek & wood 1 days 20-Sep-24 - 20-Sep-24
5 Grouting
V DRAINAGE WORK
1 Excavation with license 19 days 13-Sep-24 - 1-Oct-24
2 Sand Fill Thick 100 mm 18 days 14-Sep-24 - 1-Oct-24
3 Open Drainage U 60 U 60 - with Reinforced Bar 18 days 14-Sep-24 - 1-Oct-24
4 Reinforced Concrete Pipe (RCP) - D60 D60 - with Reinforced Bar 18 days 14-Sep-24 - 1-Oct-24
5 Control Box with manhole (1000 x 1000) K300, Thick. 100 mm, Reinforced Bar D10-150 7 days 25-Sep-24 - 1-Oct-24
6 Lean Concrete for slope cover (65m) Thick 50 mm, Site Mix 1Pc : 2Ps : 3Kr 3 days 2-Oct-24 - 4-Oct-24
7 Bauxite for slope cover (48m) 3 days 2-Oct-24 - 4-Oct-24
VI STEEL STRUCTURE
1 Column
2 Beam
3 Rafter
4 Runway
VII METAL ROOF
1 Spandek Roof Spandek Blue Color AZ 50 Thick. 0.52 mm
2 Caping Spandek Blue Color AZ 50 Thick. 0.52 mm
3 Spandek Wall (cover Jackroof existing) Spandek Blue Color AZ 50 Thick. 0.52 mm
4 Flashing Spandek Blue Color AZ 50 Thick. 0.52 mm