Minutes of Meeting:
Project : MOB Renovation Project, Nelamangala
Date : 20-07-2023
Time : 11.00AM TO 01.30 PM
Chaired by : Vimal SS, Sundaresh KJ
Members in Attendance:
Page 1 of 2
The discussion continued on following subjects related to Site HSE requirements.
Pre Startup Safety Signature need to be taken from contractor's site- in charge before
02 Soubhagya / Ranjith
Checklist starting of activity
Signage and
Poster for Safety
07
Park and work
area
Safety committee
08 meeting (once in Need to attend with all team member (excluding workmen) All Vendors
month)
1. Prior Information should be given to ABB Site manager/ Safety
Visitor &
officer for conducting safety induction before deploying workmen
09 Workmen All Vendors
at site.
Induction
Page 2 of 2
2. All the personnel including drivers, helpers, operators and
visitors entering the site on behalf of ABB and Contractor to
undergo safety induction.
Extend work permit for beyond 08:00 P.M work, Approval request
e-mail need to be sent to PM before 04:00 P.M. on that day.
12 Fatigue Fatigue: Work is being carried out only for 12 hours or less than All Vendors
12 Hrs. per day (24 Hrs.) by an individual. If work continues beyond 08
hours, Manpower is planned in shifts.
Power distribution box with locking provision and ELCB/RCCB to be
For temporary NOTE; BOSCH,
13 fixed to Distribution board (Tripping value-30 mA). All Vendors
power connection Hitachi,
Availability of wireman license electrician
Dark hour No height work and hot work shall proceed in extended/night hours
15 All Vendors
restriction (Except proper/required approval taken for such activity)
Weekly Hazard Site team instructed to record and submitted the hazard report
16 All Vendors
report before Thurs day of every week.
Page 3 of 2