HSE Committee Meeting

Minutes of Meeting:
Project : MOB Renovation Project, Nelamangala
Date : 20-07-2023
Time : 11.00AM TO 01.30 PM
Chaired by : Vimal SS, Sundaresh KJ

Name Designation Organization Signature

Members in Attendance:

Page 1 of 2
The discussion continued on following subjects related to Site HSE requirements.

S.No Subject Discussion Points Action By Remark

HSE plan preparation with PM and implementation responsibility at


01 HSE Plan PM With SO
site.

Pre Startup Safety Signature need to be taken from contractor's site- in charge before
02 Soubhagya / Ranjith
Checklist starting of activity

If any new work is planned, it should be informed well in advance


Upcoming New
03 so that all related documents preparation and approval shall be All Vendors
activity
done on time (10 days prior starting the Job).

The work shall only be start after completion of onsite risk


04 Work clearance assessment with PMC and ABB then issuing the PTW at the work All Vendors
location only.
ABRA 3 Level Approval process
First level – (Site HSE for ABRA & PMC for MS)
ABRA 3 Level
Second Level- Division HSE
05 Approval process All Vendors
Third Level- Project Manager
.
.

Every week Friday SOT to be performed by PMC and Contractor


06 Weekly SOT ABB/PMC
Team.

Signage and
Poster for Safety
07
Park and work
area

Safety committee
08 meeting (once in Need to attend with all team member (excluding workmen) All Vendors
month)
1. Prior Information should be given to ABB Site manager/ Safety
Visitor &
officer for conducting safety induction before deploying workmen
09 Workmen All Vendors
at site.
Induction

Page 2 of 2
2. All the personnel including drivers, helpers, operators and
visitors entering the site on behalf of ABB and Contractor to
undergo safety induction.

3. Contractor to submit W.C policy, insurance document, ESI, P.F


etc.

4. The contractor will have to submit the health fitness certificate,


COVID Final dose Vaccination certificate and ID card of the workers
at the time of Induction.

5. Workmen screening report Need to be submitted by Contractor


at the time of Induction.

6. Competency certificate need to be submitted by the contractor


for all the technician and supervisor at the time of Induction.

Training calendar for upcoming 3 month’s need to be prepared by


10 Training Calendars All Vendors
contractor as per ABB LSR.

Extend work permit for beyond 08:00 P.M work, Approval request
e-mail need to be sent to PM before 04:00 P.M. on that day.

11 Dark hour Activity PMC/contractor


Minimum 4-6 emergency light need to be arranged by contactor
team for dark hour activity.

12 Fatigue Fatigue: Work is being carried out only for 12 hours or less than All Vendors
12 Hrs. per day (24 Hrs.) by an individual. If work continues beyond 08
hours, Manpower is planned in shifts.
Power distribution box with locking provision and ELCB/RCCB to be
For temporary NOTE; BOSCH,
13 fixed to Distribution board (Tripping value-30 mA). All Vendors
power connection Hitachi,
Availability of wireman license electrician

All lifting equipment’s Load test certificate needs to be verified &


14 Lifting Equipment All Vendors
submit two day before.

Dark hour No height work and hot work shall proceed in extended/night hours
15 All Vendors
restriction (Except proper/required approval taken for such activity)

Weekly Hazard Site team instructed to record and submitted the hazard report
16 All Vendors
report before Thurs day of every week.

Motivation Every month’s end, one motivational program needs to be


17 All Vendors
program conducted by all Vendor.

Contractor E- Monthly contractor evaluation to be done at site as per the


18 ABB
Valuation standard format every month along with Site HSE.

Any deviation to issued PTW for planned work will be considered as


19 Safety Violation safety violation and action shall be taken as per ABB Way control ABB
standard (Consequence Management Program)