11kV SWITCH GEARS & 11kV DISTRIBUTION BOQ

REV.00 DT: 3.11.24


S. No DESCRIPTION UNIT QTY RATE AMOUNT
I 11kV DISTRIBUTION
1 11kV RCC Type Single Pole Structure
Supply installation testing and commissioning of RCC
type Single pole structure with 11mtr long Including
supply and fixing of 11KV 400A AB Switch, HG fuse,
3nos 9KV 5KA Lightning arrestors set and all necessary
hardware including pedestal / coping for the pole. as
required complete set. as per TSCPDCL specifications.
Supply Nos 1
Installation Testing & Commissioning Nos 1

3 DISTRIBUTION TRANSFORMERS
Supply,Installation,Testing and commissioning of
3Phase, 50Hz outdoor, copper wound, plinth mounted,
Dyn11 connected, oil immersed, core type, ONAN
Copper wound Distribution Transformer with no load
voltage ratio of 11000/433 Volts, with Off-Load Tap
Changer, on existing plinth as per APCPDCL
specifications.(Make: as per APCPDCL list)
2.1 100kVA, 11kV/433V ONAN with OCTC
supply Nos 1
Installation Testing & Commissioning Nos 1

3 Earthing
3.1 Providing Cast Iron Pipe Earth station, with 100mm
dia. 2500mm long Cast iron pipe including construction
of brick pedestal, providing meshed funnel,CI cover and
other civil Engineering works, spreading a
homogeneous mixture of salt, charcoal around the pipe
e tc, completely as per IS 3043, 1987 or latest
revision..(TR-2nos & 11kV pole -2no.) Supply Nos 4
Installation Nos 4

3.2 Providing Copper Plate Earth station, with 600 X 600 X


3.15mm thick copper plate including construction of
brick pedestal, providing meshed funnel, CI cover and
other civil Engineering works, spreading a homogenous
mixture of salt and charcoal around the plate etc,
completely as per IS 3043, 1987 or latest revision. as
per detail shown std.dwg. (2Nos Earth station for each
Transformer). Supply Nos 2
Installation Nos 2
4 GI /Copper strip
Supply and laying of following size strips including
excavation and refilling of earth when laid in ground
and with all fixing accessories when laid inside the
building including all necessary interconnections with
earth station and equipments.
4.1 40X6mm GI strip from earth station
Supply Mtrs 12
Installation Mtrs 12
4.2 40X6mm Hot dip GI strip
Supply Mtrs 20
Installation Mtrs 20
4.3 25X6mm Electrolytic Copper strip
Supply Mtrs 10
Installation Mtrs 10

5 Providing Galvanised Iron Chain mesh fencing around


HT Yard upto a height of 1.8m including providing 2nos
3m wide double leaf gates as per standards and with
MS supports. Job includes painting of structural
supports with two coats of primer and two coats of
enamel paint
Supply Mtrs 10
Installation Mtrs 10

6 Spreading of two layers of 40mm stone metal inside the


Transformer yard with 200mm depth.

Supply Cu.Mtr 10
Spreading Cu.Mtr 10

7 Supply and installation of Cable Route Markers made


out of Cast iron, with engraving' H.T CABLES' including
bottom concrete pedestal and painted red. (at every 15
meters interval)
Supply Nos 4
Installation Nos 4

8 HT Cables
laying and commissioning of following size
11KVgrade(E) XLPE insulated armored Aluminum
conductor cable in existing cable trench / Hume pipe /
Cable tray.(To be confirmed by site surveyor)
8.1 3C X 95 sq.mm,11KV (E) Supply Mtrs 80
Laying in ground Mtrs 80
12 HT End Terminations
Supply,installation,testing and commissioning of
Outdoor Heat shrinkable end terminations for the cables
specified below with all materials such as single/double
compression glands, Bimetallic lugs, HT Insulation
Tapes, Identification tags etc., including end connection
and Earthing of Gland.
12.1 3C X 95 sq.mm,11KV (E)
Outdoor type Supply & installation Nos 2

Grand Total for II Rs. 0.00

VII STATUTORY APPROVALS


S. No DESCRIPTION UNIT QTY RATE AMOUNT
1.0 Liasoning charges for the approval of electrical Lum 0.00
inspector for the HT substation and including the
submission of required drawing and obtaining final
approval for commissioning of substation and approval
of the entire electrical installation
2.0 Liasoning charges for load sanction & HT installation Lum 0.00
from AP Transco
Note: Contractors will work understanding & liaise with
APCPDCL / CEIG for installation approvals &
commissioning / permission for energization

Grand Total for V Rs. 0.00