Digsilent GMBH: P1843 - Optimization of The Protection Settings For The 115 KV Electrical Power System of PEA in Thailand
Digsilent GMBH: P1843 - Optimization of The Protection Settings For The 115 KV Electrical Power System of PEA in Thailand
Key Data:
2
Review of the network model
3
Network Model
4
Network Model - Enhancement
nodes.
5
Review of Network Model
2. Element data: Operational data of the equipment, e.g. load and generators operation points, star
point connection and/or position of tap changer for transformers, length of the line, etc
3. Operational data: Data that can be managed by the object “Operation Scenario” in PowerFactory.
This include controller settings for external grids, tap changers and generators, as well as
6
Review of Network Model – Types Data
Rtd. rat.
Cable / R'(AC,20°C) X' R0'(AC) X0' C' C0' Max. End.
Name Voltage Current
OHL [Ohm/km] [Ohm/km] [Ohm/km] [Ohm/km] [uF/km] [uF/km] Temp. [degC]
[kV] [kA]
7
Review of Network Model – Types Data
8
Review of Network Model – Types Data
Name HV- MV- LV- HV- MV- LV- Name HV-MV HV-MV No Load Los.
rtd.Pow. rtd.Pow. rtd.Pow. rtd.Volt. rtd.Volt. rtd.Volt. Cop.Los. uk0 kW
MVA MVA MVA kV kV kV kW %
3-Winding 100 88 66 115 11,5 11,5 YN0d1d1 0 8 0
Transformer
Type
TR 110 MVA- 110 88 66 115 11,5 11,5 YN0d1d1 0 8 0
RJN1
9
Review of Network Model – Elements Data
10
Review of Network Model – Operational Data
11
Verification of Technical Ratings of the Equipment
Verification based on the results of load flow and short circuit calculations
Considerations for evaluation based on Load Flow Calculation:
- Two study cases with max. load (100%) and min. load (assumed to 60% of max. load),
- Equipment loading over 80%,
- Voltage deviations over 5% from the nominal voltage,
- Branch element losses.
Considerations for evaluation based on Short Circuit Calculation:
- Two study cases with max. Sk” (100%) and min. Sk” (assumed to 60% of max. Sk” – Definition
of a variation in PowerFactory model),
- 3 phase faults with zero fault impedance,
- Initial (Ik”), peak (ip) and thermal equivalent (Ith) short-circuit currents on all energised busbars.
12
Verification of Technical Ratings of the Equipment
Verification based on the results of load flow and short circuit calculations
Considerations for evaluation based on Load Flow Calculation:
- Two study cases with max. load (100%) and min. load (assumed to 60% of max. load),
- Equipment loading over 80%,
- Voltage deviations over 5% from the nominal voltage,
- Branch element losses.
Considerations for evaluation based on Short Circuit Calculation:
- Two study cases with max. Sk” (100%) and min. Sk” (assumed to 60% of max. Sk” – Definition
of a variation in PowerFactory model),
- 3 phase faults with zero fault impedance,
- Initial (Ik”), peak (ip) and thermal equivalent (Ith) short-circuit currents on all energised busbars.
13
Verification of Technical Ratings of the Equipment
- For the reduction of the load values in the study case “Min. Load” scaling factors were
used
14
Verification of Technical Ratings of the Equipment
- For the reduction of the load values in the study case “Min. Load” scaling factors were
used
15
Verification of Technical Ratings of the Equipment
16
Verification of Technical Ratings of the Equipment
17
Verification of Technical Ratings of the Equipment
- For generators with Sn < 100 MVA and Un > 1 kV: R/X = 0,07
- Ik“max = 50,2 kA at Stations SUWINTHAWONG (MEA) and NONG KHAE 2 (islanded zone
„SR5“)
18
Verification of Technical Ratings of the Equipment
- In order to evaluate the thermal and mechanical stress of the busbars and line systems is
necessary the rated short circuit capability of those equiments (Type Data)
- Ik“max = 50,2 kA at Stations SUWINTHAWONG (MEA) and NONG KHAE 2 (islanded zone
„SR5“)
- The short circuit current contributions of the generators cannot be neglected for Ik“max.
- The minimum 3-phase short circuit current is at substation WANG NAM YEN with 1,415 kA
(min. 2-phase short circuit = 1,23 kA)
19
Tie-Open Point Optimisation
Due to the mostly radial operated zones in the 115 kV network, there is optimization potential
regarding the reduction of network losses by changing the position of the open breakers.
Tie-Open Point Optimisation (TOPO) Tool evaluates the switching status with an iterative
optimisation method. The objective function minimizes the network losses only by changing
the position of the opened breakers.
- Since the TOPO-Tool does not work with closed loops, the internal loops in the zones were
opened without any criteria. This leads to an increment of the losses from 41,67 MW to
44,73 MW, but after the optimization of the position of the opened breakers the losses are
reduced to 28,03 MW
- In order to compare the results a new operation scenario has been defined.
20
Tie-Open Point Optimisation
- Losses: 44,73 MW
21
Tie-Open Point Optimisation
- Losses: 28,03 MW
22