Textbook Reading: 2.4, 6.4: Power System Flow Analysis
Textbook Reading: 2.4, 6.4: Power System Flow Analysis
POWER SYSTEMS 2
– Note the location of all emergency signage, break glass alarms & EXIT’s
– Security Officers are trained in First Aid.
– Note the location and availability of the campus Medical Suite.
– 24 hour Security Escort Service - call 6304 3333 (JO) 9370 3333 (ML) or use
security phone located at various points on campus
– If attending the campus out of hours we encourage you to travel in pairs.
Purpose of this Lecture
circuits
Any questions?
7
Introduction
In the prerequisite unit Power Systems 1 you were introduced to many of the
basic concepts and fundamental elements and components of a power system.
This was a fairly “broad picture” introduction to the area of power engineering.
Other previous units like Electrical Machines and Transformers focused on the
“narrow picture” view of a power system by only looking at components in a
stand alone capacity without looking at the wider issues that arise from the fact
that they are not stand alone components but in fact interconnected with many
other components in the system.
In this unit, Power Systems 2, we will look in particular detail at the planning,
operation, analysis and design of these interconnected power systems. The “big
picture” view taken in this unit allows us to look at the wider system as a whole,
considering all of the elements interconnected within it and the ways in which
they interact.
This unit builds upon the power systems concepts introduced in Power Systems
1. Power systems are analysed from the point of view of power flow.
Symmetrical faults and symmetrical components, and asymmetrical faults are
discussed. Students gain experience in the design of power network protection
circuits and systems. The unit continues with power system controls and
stability, and concludes with communication, SCADA, and substation design
8
fundamentals.
Planning
Its horizon can be medium (5-10 years) to long term (over 20 years).
Bulk power system means all loads connected downstream from the
For this lumped load, both the coincident peak loads and light loads
are of interest.
The peak loads stretch the network and test for low voltages and
system overload.
The light loads test the network for high voltages due to Ferranti
effect.
The light loads are taken as 40% of the peak loads on a busbar.
10
Methodologies
11
A Planning Methodology Example
Powerlink is the sole holder of the
Queensland.
• TNSP must plan and operate its transmission networks to allow the
operating conditions
area under the most critical element out of service, without the necessity of
load shedding.
Powerlink has defined the Credible contingency events that must be taken
into account.
contingency event.
for double line or circuit failures. Voltages and line rating criteria must be
met.
For double line contingency, line rating may be relaxed up to 150% to 200%
• Load forecast;
• Generation assumptions;
18
Load Forecast
maximum ratings.
21
Power, Frequency, and Voltage Requirements
The voltage of supply at a connection point should not vary by more than 10
percent above or below its normal voltage.
As a consequence of a credible contingency event, the voltage of supply at
a connection point must comply with the following figure:
22
Step by Step Planning Procedure
23
Power Flow Problem
studies.
25
Recap: Phasors
Phasor is a trick to ease the understanding of sinusoidal signals.
Voltage and current signals can be defined by their amplitude and
phase angle definition as their frequency is fixed.
26
Recap: Power in Single-Phase Circuits
The average power delivered to the load is called Active Power or Real
Power (P), and its unit is Watt. Ѳ is the load angle, β is the angle of
Reactive Power (Q) accounts for power oscillation into and out of the
27
Recap: Complex and Apparent Power
Complex Power (S) is used to conveniently define P and Q concepts.
consumer.
28
Recap: Complex Power Flow
30
Recap: Single Line Representation of Power Systems
For a balanced circuit, the system can be modelled as an equivalent
single-phase system, termed as Single Line Diagram.
Resistances are negligible in real networks. Thus, system
components can be represented by their equivalent reactances,
called Single Line Reactance Diagram.
31
Single Line Diagram of a Sample Power System
32
Example: The IEEE 30 Bus Test Case
Represents a portion of the American Electric Power System (in the
Midwestern US) as of December, 1961. This network has been widely
used by various analytical and computer-based load flow techniques as
a standard evaluation test case.
33
Recap: Per-Unit Calculations
of transformers.
actual quantity
quantity in per unit
base value of quantity
34
Recap: Per-Unit Conversion Procedure, 1f
2. Pick a voltage base for each different voltage level, VB. Voltages are
line to line.
3. Calculate the impedance base: VB2, LL ( 3 VB ,LN )2 VB2, LN
ZB
S B3 3S 1B S1B
n
Ykk ykj ; k j
j 1
Yij Y ji yij ; i j
38
Example of Nodal Analysis
Write the nodal equations for the following circuit and determine the bus
admittance matrix:
Step 1: select one node (or bus) to be the reference bus, determine the
number of remaining non-reference buses (N) and define the voltages at the
remaining buses with respect to the reference bus. The circuit has 4 buses,
therefore N = 3. Bus 0 is chosen as the reference bus and bus voltages V10,
V20 and V30 are the bus voltages defined with respect to the reference. 39
Example of Nodal Analysis (cont.)
40
Example of Nodal Analysis (cont.)
Step 3: Write nodal equations in matrix format. The elements of the bus
admittance matrix are formed as follows:
( j 3 j10) ( j 3) 0 V10 I1
( j 3) ( j 3 j1 j1 j 2 ) ( j1 j 2) V I
20 2
0 ( j1 j 2) ( j1 j 4 j 2) V30 I 3
j 7 j 3 0 V10 I1
j3 j1 j1 V I
20 2
0 j1 j 5 V30 I 3
44
Example 6.9: Bus Data
45
Example 6.9: Bus Data (cont.)
Bus 1 is the slack bus. This bus is the reference bus for the
system and voltage magnitude and phase variables are defined
for this bus. The power flow program computes real and reactive
power.
Bus 3 is a PV bus. Per-unit real power, bus voltage per-unit
magnitude, and per – unit reactive power limits are the input data
variables defined for this bus. The power flow program
calculates reactive power and voltage phase.
Buses 2, 4 and 5 are PQ buses. Per-unit real and reactive power
values are the input data variables defined. The power flow
program calculates voltage magnitude and phase variables.
46
Y11 Y12 Y13 Y14 Y15
Example 6.9: Bus Admittance Matrix Y
21 Y22 Y23 Y24 Y25
Ybus Y31 Y32 Y33 Y34 Y35
n
Ykk ykj ; k j Yij Y ji yij ; i j Y41 Y42 Y43 Y44 Y45
j 1 Y51 Y52 Y53 Y54 Y55
1st row: buses 2, 3 and 4 do not directly connect to bus 1 Y12 Y13 Y14 0
1 1
Y11 3.729 j 49.7203 49.8599 85.7108 per unit
R15 jX 15 0.0015 j 0.02
1 1
Y15 3.729 j 49.7203 49.859994.289 per unit
R15 jX 15 0.0015 j 0.02
47
Example 6.9: Bus Admittance Matrix (cont.)
2nd row: buses 1 and 3 do not directly connect to bus 2 Y21 Y23 0
′ ′
1 1 𝐵 𝐵 124 25 1
𝑌 =
22 ′
+ ′
+𝑗 +𝑗 =
′ ′
+ +¿
𝑅 + 𝑗𝑋 𝑅 +𝑗 𝑋
24 24 25
2 2 0.0099+ 𝑗0.1 0.0045+ 𝑗0.05
25
1 1
Y24 0.89276 j 9.91964 9.9597295.143 p.u.
R24 jX 24 0.009 j 0.1
' '
1 1
Y25 1.78552 j19.83932 19.919595.143
p.u.
R25 jX 25 0.0045 j 0.05
' '
48
Example 6.9:
Simulation
49
Special Case: “Off-Nominal”, Tap Changing Transformers
Load Tap
Changing
transformers
have tap ratios
that can be
varied to
regulate bus
voltages.
The typical
range of
variation is Y11 Y12 V1 I1
Y Y V I
10% from the 21 22 2 2
nominal values,
usually in 33 Yeq cYeq V1 I1
*
c Yeq V2 I 2
2
discrete steps. c Yeq 50
Example: “Off-Nominal”, Tap Changing Transformers
In the previous example the off-nominal tap ratio for the transformer
between buses 3 and 4 was set at 1.0, which effectively means that the
transformer was not considered an off-nominal transformer. In this example
the off-nominal turns ratio is altered to 0.9 and Ybus is recalculated. In this
case the non-tapped side is bus 4 and the tapped side is bus 3.
1 1
Yeq 7.46 j 99.44
R34 jX 34 0.00075 j 0.01
Y33 c 2Yeq 0.9 2 7.46 j 99.44 6.16 j82.18
Y34 Y43 cYeq 0.9 7.46 j 99.44 6.78 j 90.40
' '
1 1 B24 B45
Y44 Yeq j j
'
R24 jX 24
' '
R45 jX 45
'
2 2
1 1
7.46 j 99.44
0.009 j 0.1 0.00225 j 0.025
1.72 0.44
j j 11 .92 j147.96
2 2
1
Yeq
Z eq
Yeq cYeq V1 I1
*
c Yeq V2 I 2
2
c Yeq 51
Summary
In this lecture you have learned/reviewed:
Methodologies for transmission system planning;
How to interpret a single line diagram of a three phase system;
How to normalise them using per unit conversion;
Concepts of real and reactive power;
Effect of voltage and angle and system parameters on real and reactive
power flow: real power is mostly affected by changes in power angles and
reactive power is mostly affected by changes in voltage magnitudes;
How to define a node “k” in a power system that is connected to other nodes
in the system;
How to compute the bus admittance matrix;
How to formulate the power flow problem. 52
What You Need To Do For Next Week