Boq - Pani Bhaban
Boq - Pani Bhaban
Boq - Pani Bhaban
The concrete strength must obtain cylinder-crushing strength of 21 MPa (3000 Psi) at 28
days, which shall be determined from the materials at site by trial mix and sample test.
Actual length of service piles shall be determined and finalized after obtaining the Load
test result on test piles and if higher length of piles is required to be executed, no
enhancement of rates shall be entertained. Being the land is undulated and marshy to
some extent all necessary measures for execution of piles such as filling and leveling of
piling area with requisite compaction for moving the winch, machines and rigs and making
the area workable for setting pile layout and execution of pilling work shall have to be
taken at the own cost of Contractor and all the cost that shall be incurred against above
mentioned items shall be; inclusive of the quoted rates. The work will complete as per
direction of Engineer-in-charge. Two hundred
3700 cft 210.00 Ten only 777,000.00
The unit rate of pile is exclusive of cost of steel reinforcement and its fabrication). I he
payment shall be made for the length from TIP to cut-off level in the drawing. No payment
shall be made for extra boring from existing ground level to top level files. completed as
per direction of Engineer-in-charge.
4 EARTHWORK
Earthwork in excavation in all kinds of soil for foundation trenches in/c. layout, providing
center lines, bench-mark pillars, leveling, ramming and preparing the base, fixing
bamboo spikes & giving layout with chalk powder, providing necessary tools and plants,
protecting and maintaining the trench dry etc., stacking the excavated earth at a safe
distance of up to 60 m lead, removing the spools etc. all complete as per direction of
Engineering-in-charge (rate is excluding the cost of bench mark pillars).
If in any way failure occurs, Contractor will be fully held responsible for such failures and 1 L.S 10,000 Taka Ten 10,000.00
the damages to be made good and any compensation arisen out of such failure shall be thousand only
borne by the Contractor.
6 BRICK FLAT SOLING
SL Rate in Figure and Works
NO. Description of Item Quantity Unit (To be Quoted) Quoted Amount
in figure in word in Taka
1 2 3 4 5 6 7
Single brick flat soling including preparation of bed, sand filling (FM>=0.50), 10 leveling, Taka Twenty
dressing and sand blinding in foundation or floor with supply of all materials etc. complete 300 sft 25.00 Five only 7,500.00
as per direction of Engineer-in-charge.
7 CEMENT CONCRETE
Cement concrete work in leanest mix. 1:3:6 with sand of FM>=1.5, in foundation or floor
including breaking, screening, grading and washing aggregates with clear water, mixing, Taka One
laying in position, consolidation to levels, curing, including supply of all materials,
100.00 cft 160.00 hundred Sixty 16,000.00
excluding the cost of formworks etc. complete as per direction of Engineering-in-charge
only
Concrete shall be produced including necessary admixture: plasticizer, retarder etc. in the
Batching Plant and shall be transported to site by Transit Mixture Truck and placing shall
done by Concrete Pumps at site. The minimum cement content shall be 450 kg per cum
of concrete.
Rate is excluding the cost of reinforcement and its fabrication. But shall be inclusive of all
cost of production of concrete including necessary admixture : plasticizer, retarder etc. in
the Batching Plant, and Transportation of Concrete upto site and pouring of Concrete by
Pump at site
10 RCC WORK
Reinforced cement concrete works of specified minimum-compressive strength fc = 21
Mpa (3000 Psi) for concrete at 28 days on standard cylinder, with Portland cement
conforming to BDS 232 & ASTM Standard, best quality coarse sand [Sylhet sand F.M.
2.5 to 2.8], 20 mm down well graded Bholaganj crushed stone chips of proportion which
actually is to be determined by trial mix from approved materials including breaking chips
and screening through proper sieves, making, placing in position the centering shuttering.
M.S. sheet, steel forms. 40 mm M.S. pipes, 50 x 40 mm adjustable pipes (jug pipes) with
150 x 150 x 6 mm base plate having pipe wall thickness 2.5 to 4.5 mm as props, making
water-tight steel shuttering, placing of reinforcement in position; concrete mixing in
Batching Plant. casting in forms. compacting by vibrator machine and curing at least for
28 days, removing centering, shuttering, all complete including cost of water, electricity,
testing of materials and concrete & other charges as per direction of the Engineer-in-
charge.
Concrete shall be produced including necessary admixture: plasticizer, retarder etc. in the
Batching Plant and shall be transported to site by Transit Mixture Truck and placing shall
done by Concrete Pumps at site. The minimum cement content shall be 400 kg per cum
of concrete.
Rate is excluding the cost of reinforcement and its fabrication. But shall be inclusive of all
cost of production of concrete including necessary admixture : plasticizer, retarder etc. in
the Batching Plant, and Transportation of Concrete upto site and pouring of Concrete by
Pump at site
Taka Two hundred
Seventy only
2500 cft 270.00 675,000.00
REINFORCEMENT IN RCC
11 Supplying, fabrication and fixing to details as per design deformed bar reinforcement in
concrete in accordance with BSTI standard in/c straightening and cleaning rust, if any,
bending & binding in position in/c supply of G.I. wires etc. complete in all respects in all
floors. The work complete as per direction of Engineer-in- charge.
Taka Sixty
12 60 Grade deformed bar with minumum fy=415Mpa ultimate strength 620 Mpa 10.00 Ton 60,000.00 thousand only 600,000.00
13 SAND FILLING
Sand filling in foundation trenches and plinth with coarse sand having min. F.M.
SL Rate in Figure and Works
NO. Description of Item Quantity Unit (To be Quoted) Quoted Amount
in figure in word in Taka
1 2 3 4 5 6 7
1.20 in 150mm layers including leveling, watering and consolidating each layer 10000 cft 18.00 Taka Eighteen 180,000.00
up to finished level (to be used when required as per design supplied by the
only
design office only) etc. all complete as per direction of the Engineer-in-Charge.
15 NCF WORK
NCF work in floor including mixing, laying in position, consolidation to levels, curing, 9000 sft 30.00 Taka Thirty only 270,000.00
including supply of all materials etc. complete as per direction of Engineering-in-charge
15 BRICK WORK
250 mm brick work with 1st class bricks in cement sand (F.M.1.2) mortar (1:4) and Taka Fifty Five
making bond with connected walls in/c necessary scaffolding, raking out joints, cleaning 600 cft 220.00 only 132,000.00
and soaking the bricks for at least 24 hours before use and washing of sand curing at
least for 7 days in all floors including cost of water, electricity & other charges etc. all
complete as per. direction of the Engineer-in-charge.
16 PLASTERING WORKS
16.1 PLASTER TO CONCRETE SURFACE
Minimum 6 mm thick cement sand (F.M. 1.2) plaster (1:4) with fresh cement (conforming Taka Twenty
to BDS 232) to ceiling R.C.C. columns, beams, surface of stair case, sunshades, 5,000.00 sft 25.00 Five only 125,000.00
cornices, railings, drop wall, louvers, fins and finishing the corners and edges in/c
washing of sand cleaning the surface, scaffolding and curing at least for 7 days, cost of
water, electricity & other charges etc. all complete in all respect as per drawing and
direction of the Engineer-in-charge.
17 PAINTING WORKS
17.1 Plastic emulsion paint of approved best quality and colour delivered from authorized local
agent of the manufacturer in a sealed container, applying to wall and ceiling in two coats
over a coat of brand specified primer or sealer elapsing specified time for drying/recoating
including cleaning drying, making free from dirt, grease, was, removing all chalked &
sealed materials, fungus, mending good the surface defects, sand papering the surface 5000 sft 9.00 Taka Nine only 45,000.00
and necessary scaffolding, spreading by brush/roller/spray etc. all complete in all floor as
per direction of the Engineer-in-charge
SL Rate in Figure and Works
NO. Description of Item Quantity Unit (To be Quoted) Quoted Amount
in figure in word in Taka
1 2 3 4 5 6 7
17.3 Two costs of weather coat of approved quality colour and origin over a coat of plastron
sealer to exterior plastered surface necessary scaffolding and surface cleaning etc. all
complete in all floors complele as per direction of the Engineer-in-charge.
500.00 sft 11.00 Taka Eleven only 5,500.00
18 STAIR RAILING
900 mm high M.S.pipe railing in stairs including manufacturing and fixing in position as
per drawings, providing 62mm dia MS pipe hand rest and 38 mm verticals @ ± 1'-8" C/C
and 4 nos horizontal of 25mm dia MS pipe joining the verticals. The total railing framing
shall be manufactured by proper welding, the end of all verticals shall be embedded Taka Three
75mm into the concrete. welding and grinding of all joints shall be connected, grinded 60 sft 300.00 Hundred only 18,000.00
properly, polishing the pipes after finishing etc. all works complete as per direction of
Engineer-in-charge payment will be made only for clear height after finishing the stair.
2,629,900.00
Concrete shall be produced including necessary admixture: plasticizer, retarder etc. in the
Batching Plant and shall be transported to site by Transit Mixture Truck and placing shall
done by Concrete Pumps at site. The minimum cement content shall be 400 kg per cum
of concrete.
Rate is excluding the cost of reinforcement and its fabrication. But shall be inclusive of all
cost of production of concrete including necessary admixture : plasticizer, retarder etc. in
the Batching Plant, and Transportation of Concrete upto site and pouring of Concrete by
Pump at site
Taka Two hundred
Seventy only
2600 cft 270.00 702,000.00
REINFORCEMENT IN RCC
11 Supplying, fabrication and fixing to details as per design deformed bar reinforcement in
concrete in accordance with BSTI standard in/c straightening and cleaning rust, if any,
bending & binding in position in/c supply of G.I. wires etc. complete in all respects in all
floors. The work complete as per direction of Engineer-in- charge.
Taka Sixty
thousand only
SL Rate in Figure and Works
NO. Description of Item Quantity Unit (To be Quoted) Quoted Amount
in figure in word in Taka
1 2 3 4 5 Taka6Sixty 7
12 60 Grade deformed bar with minumum fy=415Mpa ultimate strength 620 Mpa 11.00 Ton 60,000.00 thousand only 660,000.00
15 NCF WORK
NCF work in floor including mixing, laying in position, consolidation to levels, curing, 2800 sft 30.00 Taka Thirty only 84,000.00
including supply of all materials etc. complete as per direction of Engineering-in-charge
15 BRICK WORK
250 mm brick work with 1st class bricks in cement sand (F.M.1.2) mortar (1:4) and Taka Fifty Five
making bond with connected walls in/c necessary scaffolding, raking out joints, cleaning 4,000.00 sft 110.00 only 440,000.00
and soaking the bricks for at least 24 hours before use and washing of sand curing at
least for 7 days in all floors including cost of water, electricity & other charges etc. all
complete as per. direction of the Engineer-in-charge.
16 PLASTERING WORKS
16.1 PLASTER TO CONCRETE SURFACE
Minimum 6 mm thick cement sand (F.M. 1.2) plaster (1:4) with fresh cement (conforming Taka Twenty
to BDS 232) to ceiling R.C.C. columns, beams, surface of stair case, sunshades, 5,000.00 sft 25.00 Five only 125,000.00
cornices, railings, drop wall, louvers, fins and finishing the corners and edges in/c
washing of sand cleaning the surface, scaffolding and curing at least for 7 days, cost of
water, electricity & other charges etc. all complete in all respect as per drawing and
direction of the Engineer-in-charge.
17 PAINTING WORKS
17.1 Plastic emulsion paint of approved best quality and colour delivered from authorized local
agent of the manufacturer in a sealed container, applying to wall and ceiling in two coats
over a coat of brand specified primer or sealer elapsing specified time for drying/recoating
including cleaning drying, making free from dirt, grease, was, removing all chalked &
sealed materials, fungus, mending good the surface defects, sand papering the surface 11500 sft 9.00 Taka Nine only 103,500.00
and necessary scaffolding, spreading by brush/roller/spray etc. all complete in all floor as
per direction of the Engineer-in-charge
17.2 Painting to door and window frames and shutters in two coats with approved best quality
SL Rate in Figure and Works
NO. Description of Item Quantity Unit (To be Quoted) Quoted Amount
in figure in word in Taka
1 2
Painting to door and window frames and shutters in two coats with approved best quality 3 4 5 6 7
and colour of synthetic enamel paint delivered from authorized local agent of the
manufacturer in a sealed container, having highly water resistant, high bondibilty, flexible,
using specific brand thinner applied by rass/roller/spray over a coat or priming elapsing
2000 sft 10.00 Taka Ten only 20,000.00
time for drying including surface cleaning from dust, oil or dirt, smoothening, finishing and
polishing with sand paper and necessary tools, scaffolding, testing charges etc. all
complete in all floors. The work complete as per direction of the Engineering-in-charge.
17.3 Two costs of weather coat of approved quality colour and origin over a coat of plastron
sealer to exterior plastered surface necessary scaffolding and surface cleaning etc. all
complete in all floors complele as per direction of the Engineer-in-charge.
2,500.00 sft 11.00 Taka Eleven only 27,500.00
18 STAIR RAILING
900 mm high M.S.pipe railing in stairs including manufacturing and fixing in position as
per drawings, providing 62mm dia MS pipe hand rest and 38 mm verticals @ ± 1'-8" C/C
and 4 nos horizontal of 25mm dia MS pipe joining the verticals. The total railing framing
shall be manufactured by proper welding, the end of all verticals shall be embedded Taka Three
75mm into the concrete. welding and grinding of all joints shall be connected, grinded 60 sft 300.00 Hundred only 18,000.00
properly, polishing the pipes after finishing etc. all works complete as per direction of
Engineer-in-charge payment will be made only for clear height after finishing the stair.
21 STEEL DOOR
Steel door of any design in Penth House or wherever required made of mild steel
structural sections including 18 SWG M.S. sheet shutter, fabricating, welding, fitting, Taka Two
fixing, painting with 3 coats of synthetic enamel paint over a coat of anti-corrosive primer
110 sft 250.00 hundred Fifty 27,500.00
including supply and carriage of all materials, labour, tools, plants, etc. complete as per
drawing, decision and instruction of the Engineer-in-charge in all floors. only
Concrete shall be produced including necessary admixture: plasticizer, retarder etc. in the
Batching Plant and shall be transported to site by Transit Mixture Truck and placing shall
done by Concrete Pumps at site. The minimum cement content shall be 400 kg per cum
of concrete.
Rate is excluding the cost of reinforcement and its fabrication. But shall be inclusive of all
cost of production of concrete including necessary admixture : plasticizer, retarder etc. in
the Batching Plant, and Transportation of Concrete upto site and pouring of Concrete by
Pump at site
Taka Two hundred
Seventy only
SL Rate in Figure and Works
NO. Description of Item Quantity Unit (To be Quoted) Quoted Amount
in figure in word in Taka
1 2 3 4 5 Taka Two6 hundred 7
Seventy only
2600 cft 270.00 702,000.00
REINFORCEMENT IN RCC
11 Supplying, fabrication and fixing to details as per design deformed bar reinforcement in
concrete in accordance with BSTI standard in/c straightening and cleaning rust, if any,
bending & binding in position in/c supply of G.I. wires etc. complete in all respects in all
floors. The work complete as per direction of Engineer-in- charge.
Taka Sixty
12 60 Grade deformed bar with minumum fy=415Mpa ultimate strength 620 Mpa 11.00 Ton 60,000.00 thousand only 660,000.00
15 NCF WORK
NCF work in floor including mixing, laying in position, consolidation to levels, curing, 2800 sft 30.00 Taka Thirty only 84,000.00
including supply of all materials etc. complete as per direction of Engineering-in-charge
15 BRICK WORK
250 mm brick work with 1st class bricks in cement sand (F.M.1.2) mortar (1:4) and Taka Fifty Five
making bond with connected walls in/c necessary scaffolding, raking out joints, cleaning 4,000.00 sft 110.00 only 440,000.00
and soaking the bricks for at least 24 hours before use and washing of sand curing at
least for 7 days in all floors including cost of water, electricity & other charges etc. all
complete as per. direction of the Engineer-in-charge.
16 PLASTERING WORKS
16.1 PLASTER TO CONCRETE SURFACE
Minimum 6 mm thick cement sand (F.M. 1.2) plaster (1:4) with fresh cement (conforming Taka Twenty
to BDS 232) to ceiling R.C.C. columns, beams, surface of stair case, sunshades, 5,000.00 sft 25.00 Five only 125,000.00
cornices, railings, drop wall, louvers, fins and finishing the corners and edges in/c
washing of sand cleaning the surface, scaffolding and curing at least for 7 days, cost of
water, electricity & other charges etc. all complete in all respect as per drawing and
direction of the Engineer-in-charge.
17 PAINTING WORKS
17.1 Plastic emulsion paint of approved best quality and colour delivered from authorized local
agent of the manufacturer in a sealed container, applying to wall and ceiling in two coats
over a coat of brand specified primer or sealer elapsing specified time for drying/recoating
including cleaning drying, making free from dirt, grease, was, removing all chalked &
SL Rate in Figure and Works
NO. Plastic emulsion paint of approvedDescription of Item
best quality and colour delivered from authorized local Quantity Unit (To be Quoted) Quoted Amount
agent of the manufacturer in a sealed container, applying to wall and ceiling in two coats in figure in word in Taka
over a coat of brand specified primer or sealer elapsing specified time for drying/recoating
1 2
including cleaning drying, making free from dirt, grease, was, removing all chalked &
3 4 5 6 7
sealed materials, fungus, mending good the surface defects, sand papering the surface 11500 sft 9.00 Taka Nine only 103,500.00
and necessary scaffolding, spreading by brush/roller/spray etc. all complete in all floor as
per direction of the Engineer-in-charge
17.2 Painting to door and window frames and shutters in two coats with approved best quality
and colour of synthetic enamel paint delivered from authorized local agent of the
manufacturer in a sealed container, having highly water resistant, high bondibilty, flexible,
using specific brand thinner applied by rass/roller/spray over a coat or priming elapsing
2000 sft 10.00 Taka Ten only 20,000.00
time for drying including surface cleaning from dust, oil or dirt, smoothening, finishing and
polishing with sand paper and necessary tools, scaffolding, testing charges etc. all
complete in all floors. The work complete as per direction of the Engineering-in-charge.
17.3 Two costs of weather coat of approved quality colour and origin over a coat of plastron
sealer to exterior plastered surface necessary scaffolding and surface cleaning etc. all
complete in all floors complele as per direction of the Engineer-in-charge.
2,500.00 sft 11.00 Taka Eleven only 27,500.00
18 STAIR RAILING
900 mm high M.S.pipe railing in stairs including manufacturing and fixing in position as
per drawings, providing 62mm dia MS pipe hand rest and 38 mm verticals @ ± 1'-8" C/C
and 4 nos horizontal of 25mm dia MS pipe joining the verticals. The total railing framing
shall be manufactured by proper welding, the end of all verticals shall be embedded Taka Three
75mm into the concrete. welding and grinding of all joints shall be connected, grinded 60 sft 300.00 Hundred only 18,000.00
properly, polishing the pipes after finishing etc. all works complete as per direction of
Engineer-in-charge payment will be made only for clear height after finishing the stair.
21 STEEL DOOR
Steel door of any design in Penth House or wherever required made of mild steel
structural sections including 18 SWG M.S. sheet shutter, fabricating, welding, fitting, Taka Two
fixing, painting with 3 coats of synthetic enamel paint over a coat of anti-corrosive primer
SL Rate in Figure and Works
NO. Description of Item Quantity Unit (To be Quoted) Quoted Amount
Steel door of any design in Penth House or wherever required made of mild steel in figure in word in Taka
1 structural sections including 18 SWG M.S. sheet
2 shutter, fabricating, welding, fitting, 3 4 5 Taka6 Two 7
fixing, painting with 3 coats of synthetic enamel paint over a coat of anti-corrosive primer
including supply and carriage of all materials, labour, tools, plants, etc. complete as per
110 sft 250.00 hundred Fifty 27,500.00
drawing, decision and instruction of the Engineer-in-charge in all floors. only
Concrete shall be produced including necessary admixture: plasticizer, retarder etc. in the
Batching Plant and shall be transported to site by Transit Mixture Truck and placing shall
done by Concrete Pumps at site. The minimum cement content shall be 400 kg per cum
SL Rate in Figure and Works
NO. Description of Item Quantity Unit (To be Quoted) Quoted Amount
in figure in word in Taka
1 2 3 4 5 6 7
done by Concrete Pumps at site. The minimum cement content shall be 400 kg per cum
of concrete.
Rate is excluding the cost of reinforcement and its fabrication. But shall be inclusive of all
cost of production of concrete including necessary admixture : plasticizer, retarder etc. in
the Batching Plant, and Transportation of Concrete upto site and pouring of Concrete by
Pump at site
Taka Two hundred
Seventy only
500.00 cft 270.00 135,000.00
REINFORCEMENT IN RCC
11 Supplying, fabrication and fixing to details as per design deformed bar reinforcement in
concrete in accordance with BSTI standard in/c straightening and cleaning rust, if any,
bending & binding in position in/c supply of G.I. wires etc. complete in all respects in all
floors. The work complete as per direction of Engineer-in- charge.
Taka Sixty
12 60 Grade deformed bar with minumum fy=415Mpa ultimate strength 620 Mpa 2.00 Ton 60,000.00 thousand only 120,000.00
15 LCC WORK
LCC work in floor including mixing, laying in position, consolidation to levels, curing, 2500 sft 40.00 Taka Forty only 100,000.00
including supply of all materials etc. complete as per direction of Engineering-in-charge
15 BRICK WORK
125 mm brick work with 1st class bricks in cement sand (F.M.1.2) mortar (1:4) and Taka Fifty Five
making bond with connected walls in/c necessary scaffolding, raking out joints, cleaning 600 sft 110.00 only 66,000.00
and soaking the bricks for at least 24 hours before use and washing of sand curing at
least for 7 days in all floors including cost of water, electricity & other charges etc. all
complete as per. direction of the Engineer-in-charge.
16 PLASTERING WORKS
16.1 PLASTER TO CONCRETE SURFACE
Minimum 6 mm thick cement sand (F.M. 1.2) plaster (1:4) with fresh cement (conforming Taka Twenty
to BDS 232) to ceiling R.C.C. columns, beams, surface of stair case, sunshades, 5000 sft 25.00 Five only 125,000.00
cornices, railings, drop wall, louvers, fins and finishing the corners and edges in/c
washing of sand cleaning the surface, scaffolding and curing at least for 7 days, cost of
water, electricity & other charges etc. all complete in all respect as per drawing and
direction of the Engineer-in-charge.
17 PAINTING WORKS
17.1 Plastic emulsion paint of approved best quality and colour delivered from authorized local
agent of the manufacturer in a sealed container, applying to wall and ceiling in two coats
over a coat of brand specified primer or sealer elapsing specified time for drying/recoating
SL Rate in Figure and Works
NO. Description of Item Quantity Unit (To be Quoted) Quoted Amount
Plastic emulsion paint of approved best quality and colour delivered from authorized local in figure in word in Taka
1 agent of the manufacturer in a sealed container,
2 applying to wall and ceiling in two coats 3 4 5 6 7
over a coat of brand specified primer or sealer elapsing specified time for drying/recoating
including cleaning drying, making free from dirt, grease, was, removing all chalked &
sealed materials, fungus, mending good the surface defects, sand papering the surface 7000 sft 9.00 Taka Nine only 63,000.00
and necessary scaffolding, spreading by brush/roller/spray etc. all complete in all floor as
per direction of the Engineer-in-charge
17.2 Painting to door and window frames and shutters in two coats with approved best quality
and colour of synthetic enamel paint delivered from authorized local agent of the
manufacturer in a sealed container, having highly water resistant, high bondibilty, flexible,
using specific brand thinner applied by rass/roller/spray over a coat or priming elapsing
800 sft 10.00 Taka Ten only 8,000.00
time for drying including surface cleaning from dust, oil or dirt, smoothening, finishing and
polishing with sand paper and necessary tools, scaffolding, testing charges etc. all
complete in all floors. The work complete as per direction of the Engineering-in-charge.
17.3 Two costs of weather coat of approved quality colour and origin over a coat of plastron
sealer to exterior plastered surface necessary scaffolding and surface cleaning etc. all
complete in all floors complele as per direction of the Engineer-in-charge.
500.00 sft 11.00 Taka Eleven only 5,500.00
21 STEEL DOOR
Steel door of any design in Penth House or wherever required made of mild steel
structural sections including 18 SWG M.S. sheet shutter, fabricating, welding, fitting, Taka Two
fixing, painting with 3 coats of synthetic enamel paint over a coat of anti-corrosive primer
50 sft 250.00 hundred Fifty 12,500.00
including supply and carriage of all materials, labour, tools, plants, etc. complete as per
drawing, decision and instruction of the Engineer-in-charge in all floors. only
667,400.00
25 SITE CLEANING
Cleaning the work site after completion of works and demobilization of contractor's men,
materials, equivalent etc. including washing and clearing of floors, sote and touch up work Taka Fifty
required before work handover of the building/project complete as per direction of the
1 L.S 50,000 thousand only 50,000.00
Engineer-in-charge.
2500+2600+2600+500
10+11+11+2
8800
16000
24000
28000
12000
150
SECTIOPN - 6 : BILL OF QUANTITIES
PART- B2 : SANITARY, WATER SUPPLY & PLUMBING WORKS
SL Rate in Figure and Works
NO. Description of Item Quantity Unit (To be Quoted) Quoted Amount
in figure in word in Taka
1 2 3 4 5 6 7
1.0 UPVC PIPE AND PIPE FITTINGS
Supply, fitting and fixing of Extra heavy uPVC pipe shall be made uPVC as per
BS4514/18044221 88213 standard. Pipe shall be bell end socket type. Approved type
of solvent cement/sealant shall be used to install pipe and jointing the pipe with pipe
fittings. Joint shall be watertight. In brick wall pipe shall be surrounded by concrete in 1:
3.5: 5.5 and shall be clamped to wall properly at an interval of not more than 1200 mm.
Pipe laying shall have the following gradient unless otherwise specified. Nominal dia of
pipe with thickness shall be as follows. The pipes shall be Hf (HAN f ING) National
Polymer industries from Bangladesh and pipe fitting shall be imported from Singapore.
b) 150 mm x 150 mm x 150 mm dia 20 Each 1,590.00 Taka One thousand 31,800.00
five hundred ninety
only
c) 150 mm x 150 mm x 100 mm dia 60 Each 1,750.00 Taka One thousand 105,000.00
seven hundred fifty
only
d) 100 mm x 100 mm x 100 mm dia 150 Each 550.00 Taka Five 82,500.00
hundred fifty only
e) 100 mm x 100 mm x 100 mm x 100 mm dia 10 Each 950.00 Taka nine 9,500.00
hundred fifty only
a) 150 mm x 150 mm x 150 mm dia 10 each 1,870.00 Taka One thousand 18,700.00
eight hundred
seventy only
b) 150 mm x 150 mm x 100 mm dia 50 Each 1,370.00 Taka One thousand 68,500.00
three hundred
seventy only
c) 100 mm x 100 mm x 100 mm dia 10 Each 1,000.00 Taka One thousand 10,000.00
only
SL Rate in Figure and Works
NO. Description of Item Quantity Unit (To be Quoted) Quoted Amount
in figure in word in Taka
1 2 3 4 5 6 7
d) 100 mm x 100 mm x 100 mm x 100 mm dia 2 Each 1,200.00 Taka One thousand 2,400.00
two hundred only
Supply, fitting, fixing of 100 mm dia UPVC trap Syphon trap of P-trap including making Taka seven
holes in wall of floor and mending good the damage upto the satisfaction. 142 Each 700 hundred only 99,400.00
b) S - TRAP
Supply, fitting, fixing of 100 mm dia UPVC trap Syphon trap of S-trap including making
holes in wall of floor and mending good the damage upto the satisfaction. 5 Each 660 Taka six hundred 3,300.00
1.5 UPVC BEND sixty only
Supply, fitting, fixing of 100 mm dia UPVC Deep Bend / Normal Bend including making
holes in wall of floor and mending good the damage upto the satisfaction.
a) Product shall be Model No. basin TF-956 with Pedestal Model-900P American Taka Two thousand
Standard, Thailand or equivalent model of COTTO, Thailand. 85 Each 2500 five hundred only 212,500.00
b) Product shall be Model No. Basin TF-0409 / 0076 of American standard, Taka Three thousand
Thailand or equivalent model of COTTO, Thailand 28 Each 3000 only 84,000.00
Taka nine
a) Commode with seat cover including all internal fittings. The product shall be thousand eight
Model no. TF-2177 of American Standard, Thailand of equivalent model of 55 Set 9800 hundred only 539,000.00
COTTO, Thailand
b) Commode with seat cover include all internal fittings. The product shall be Taka Eleven
Model no. TF-2175 of American Standard, Thailand or equivalent of COTTO 28 Set 11,200.00 thousand two 313,600.00
Thailand.
hundred only
4.14 URINAL
Supply, fitting and fixing of supper vitreous porcelain standing urinal with heavy type CI
wall bracket 32 mm dia CP waste pipe wherever required in/c making hole in wall and
SL Rate in Figure and Works
NO. Description of Item Quantity Unit (To be Quoted) Quoted Amount
in figure in word in Taka
1 2 3 4 5 6 7
wall bracket 32 mm dia CP waste pipe wherever required in/c making hole in wall and
fitting with CI wall bracket and mending good the damages etc. all complete as per
drawing and direction of the Engineer-in-charge.
a) Standing Urinal Model No- TF 6789 tanding Urinal of American Standard, Thailand or Taka one
equivalent model of COTTO. thousand nine
33 set 1,950.00 hundred fifty only 64,350.00
b) Sqyating Urinal Locally made best quality Taka one
thousand five
10 set 1,560.00 hundred sixty only 15,600.00
4.15 AUTOMATIC URINAL FLASH
Supply, fitting and fixing of infrared sensored Automatic Urinal Flash with 2-step system Taka Two
of pre-flashing and main flushing and capable of automatically activating hen the user 33 Set 2,800.00 Thousand eight 92,400.00
comes and leaves the sensing range: Model no.108 (AC) of Solomon, Taiwan or
equivalent model from manufacturers of Thailand/Singapore/Japan.
hundred only
a) Size: 610 mm x 25 mm Model No. TF-9485 Towel bar of American standard, Taka Four
Thailand or equivalent model of COTTO, Thailand. hundred thirty
60 set 435.00 five only 26,100.00
b) Round Ring, Model No. TF-9332 Towel Ring of American standard, Thailand Taka Three
Ir equivalent model of COTTO, Thailand. hundred thirty
30 set 335.00 Five only 10,050.00
b) Construction of masonry Inspection pits, inside measurement (760 mm x 900 mm x Taka seven
1000 mm) with 250 mm thick brick work in cement mortar (4:1) and 100 mm thick R.C.C 35 Each 7,500.00 thousand five 262,500.00
top (4:2: 1) with necessary reinforcement as per drawing and direction Engineer-in-
charge.
hundred only
a) 3 Nos. vertical in line pumps complete in respect with heavy duty cast iron
conforming to BS 1452, closed coupled centrifugal, Impeller shall be manufactured in
gun-metal.
Taka Three
Pump Capacity : 500 GPM 2 Set 350,000.00 hundred fifty 700,000.00
Head required : 90 Meter thousand only
RMP : 2900
b) Accessories like isolating gate valve, on-return valves, and Interconnecting pipe work
complete in all respect.
Electrical Control Panel with logic controller relays. Pressure switch, pressure Gauge,
Hand/Off/Auto switch, pump starter's duty selector switch, wiring cabling from panel to
pumps, level controller, Power on light, run & trip, main isolator switch, terminal blocks
suitable for field services interlocks complete with all
accessories as per manufacturer specification.
SL Rate in Figure and Works
NO. Description of Item Quantity Unit (To be Quoted) Quoted Amount
in figure in word in Taka
1 2 3 4 5 6 7
c) 1 No x 500 litre vessel with inner changeable butyl rubber membrane. Base
frame: All components mild steel 7 hollow section frame & shall be primed & painted
with protective undercoat & gloss finish.
b. 65 mm dia
23.4 VALVES
Supplying welding fitting & fixing of the different sizes valve Tee/Service Tee to connect
the pipe lines with the Titas Gas Main pipe line etc all complete in all respects as per
specification of Titas Gas(T&D) Go Ltd. & as per direction of the Engineer-in-charge.
29 ROAD CUTTING
Cutting & permanent re installment of the pucca (Rigid I flexible) road & mending good Taka Ten
the damages etc all complete in all respects as per specification Titas Gas(T& D)Co 50 Sqm 10,000.00 thousand only 500,000.00
Ltd. and as per direction of the Engineer-in-charge.
a) Bituminous Road
69,558,385.00
SECTIOPN - 6 : BILL OF QUANTITIES
PART- C2 : INTERNAL ELECTRIFICATION WORKS
SL Rate in Figure and Works
NO. Description of Item Quantity Unit (To be Quoted) Quoted Amount
in figure in word in Taka
1 2 3 4 5 6 7
1.0 CONDUIT WORK
Supply & Installation of PVC pipe and accessories of reputed manufacturers as per
routing shown in the drawing, concealed/ surface mounted in columns, ceiling, walls
and other various places as required, complete with bend/elbow, PVC circular boxes,
shaddles, rowel plugs, sockets, lock-nuts, male/female bushes, 18SWG G.I.pull/wire,
necessary thermo-cool, minimum 4-times taping of joints with plastic of thickness
O.2mm, width 19mm, S-lon solvent cement, fish wire, tying with the reinforcement steel
bar at the rate of 600mm spacing using 2X20 SWG G.I wire including tracing out the
outlets after the shuttering are removed and clearing the outlets & mending good all
damages as per drawings, specifications & direction of the Engineer-in-charge. This is
an average rate with necessary number of 16SWG sheet steel make junction/pull boxes
of appropriate sizes with 3mm approved colour (matching with all colour). all above
mentioned materiall accessories of this item. The cost shall include the necessary
cleaning and necessary civil works like cutting/ breaking of walls/columns/ceiling and
mending the plastering /painting (approved colour)
as per instruction of the Engineer-in-charge. All materials of this item will be of approved
quality
1.1.1 150 mm dia ( C - Class) 200 Rm 450.00 Taka Four hundred 90,000.00
fifty only
1.1.2 100 mm dia ( C - Class) 200 Rm 275.00 Taka Two hundred 55,000.00
Seventy five only
1.1.3 50 mm dia ( C - Class) 370 Rm 125.00 Taka One hundred 46,250.00
twenty five only
1.1.4 38 mm dia ( D - Class) 2800 Rm 88.00 Taka Eighty 246,400.00
eight only
1.1.5 25 mm dia water grade 56600 Rm 35.00 Taka Thirty 1,981,000.00
five only
1.1.6 25 mm dia Flexible pipe 8000 Rm 45.00 Taka Forty 360,000.00
Five only
1.1.7 38 mm dia Flexible pipe 280 Rm 50.00 Taka Fifty 14,000.00
Only
1.1.8 50 mm dia Flexible pipe 350 Rm 55.00 Taka fifty 19,250.00
Five only
SL Rate in Figure and Works
NO. Description of Item Quantity Unit (To be Quoted) Quoted Amount
in figure in word in Taka
1 2 3 4 5 6 7
The rate should be quoted inclusive of locally available best/approved quality PIB
insulating tape, ceiling rose(if necessary), cable sockets, solder less connector, cutting/
cleaning the prelaid PVC pipe, connection etc. This is an average rate and all material
of this item will be of approved quality.
3.1.1 IC-1.5 MM2 re BYA (Green) 38900 Rm 25.00 Taka twenty 972,500.00
five only
3.1.2 IC-2.5 MM2 re BYA (Green) 24000 Rm 40.00 Taka forty 960,000.00
only
3.1.3 IC-4.0 MM2 re BYA (Green) 500 Rm 65.00 Taka Sixty 32,500.00
five only
3.1.4 IC-6.0 MM2 BYA (Green) 960 Rm 90.00 Taka ninety 86,400.00
only
3.1.5 IC-10 MM2 BYA (Green) 300 Rm 150.00 Taka one 45,000.00
hundred
fifty only
3.1.6 IC-16 MM2 BYA (Green) 1300 Rm 250.00 Taka two 325,000.00
hundred
SL Rate in Figure and Works
NO. Description of Item Quantity Unit (To be Quoted) Quoted Amount
in figure in word in Taka
1 2 3 4 5 6 7
fifty only
3.1.7 IC-25 MM2 BYA (Green) 200 Rm 375.00 Taka three 75,000.00
hundred
seventy five only
3.1.8 IC-35 MM2 BYA (Green) 25 Rm 500.00 Taka Five 12,500.00
hundred only
3.1.9 IC-50 MM2 BYA (Green) 200 Rm 750.00 Taka Seven 150,000.00
hundred fifty
only
3.1.10 IC-70 MM2 BYA (Green) 50 Rm 950.00 Taka NIne 47,500.00
hundred fifty
only
4.2 Supply & installation of imported 2x36W ceiling surface mounted fluorescent light
fixture similar to Torando PX.ABS/Classic ASTB of OMS, Slovakia or F&G, Taka Two
Germany/Philips, Netherlands complete with 2x36W fluorescent lamps, T foreign
ballasts, starters, capacitors and all other necessary materials as per ,
thousand one
drawing, specifications and direction of the Engineer-in-charge. 720 Set 2,130.00 hundred thirty 1,533,600.00
only
4.3 Supply & installation of imported 2x36W ceiling recessed mounted fluorescent light 2
fixture similar to Relax PV Par Mat of OMS, Slovakia or F&G, Germany/Philips, Taka Two
Netherlands complete with mirror reflector, 2x36W fluorescent lamps, foreign ballasts,
starters, capacitors and all other necessary materials as per drawing, specifications and
thousand three
direction of the Engineer-in-charge. 20 Set 2,300.00 hundred only 46,000.00
4.4 Supply & installation of imported 4x18W ceiling recessed mounted fluorescent light
fixture similar Relax PV/LA of OMS, Slovakia or F&G, Germany/Philips, Netherlands Taka Two
complete with mirror reflector, 4x18W fluorescent lamps, foreign ballasts, starters,
capacitors and all other necessary materials as per drawing, specifications and direction
thousand four
of the Engineer-in-charge. 690 Set 2,450.00 hundred fifty 1,690,500.00
only
4.5 Supply & installation of imported ceiling recessed mounted double height light fixture Taka one
similar to Down light 212 BR of OMS, Slovakia or F&G, Germany/Philips, Netherlands thousand two
complete with 2x26W energy saving lamp and all other necessary materials as per
drawing, specifications and direction of the Engineer-in-charge.
230 Set 1,270.00 hundred seventy 292,100.00
only
SL Rate in Figure and Works
NO. Description of Item Quantity Unit (To be Quoted) Quoted Amount
in figure in word in Taka
1 2 3 4 5 6 7
4.6 Supply & installation of imported 2x9W surface mounted energy saving light fixture
similar to 31 OPAL of OMS, Slovakia or F&G, Germany/Philips, Netherlands complete Taka six
with 2x9W energy saving lamps and all other necessary materials as per drawing,
specifications and direction of the Engineer-in-charge
30 Set 635.00 hundred thirty 19,050.00
five only
4.7 Supply & installation of imported ceiling recessed mounted light fixture similar to Down
light 201 of OMS, Slovakia or F&G, Germany/Philips, Netherlands complete with 2x13W Taka Six
energy saving lamp and all other necessary materials as per drawing, specifications
and direction of the Engineer-in-charge.
1655 Set 600.00 hundred only 993,000.00
4.8 Supply & installation of imported 1 x18W wall mounted mirror light fixture of similar to
PLAST of OMS, Slovakia or F&G,Germany/Philip5, Netherlands complete with 1 X 18W Taka Nine
fluorescent lamp, ballast, capacitor, holder, etc. and all other necessary accessories as
per drawing, specifications and direction of the Engineer-in-charge.
95 Set 950.00 hundred fifty 90,250.00
only
4.9 Supply & installation of imported 2x9W surface mounted energy saving light fixture Taka Eight
similar to Forwall 11 OMS, Slovakia or F&G, Germany/Philips, Netherlands complete hundred forty
with 2x9W energy saving lamps and all other necessary materials as per : drawing,
specifications and direction of the Engineer-in-charge.
14 Set 840.00 only 11,760.00
4.10 Supply & installation of imported 2x9W surface mounted energy saving light fixture
similar to Forwall 21 OMS, Slovakia or F&G, Germany/Philips, Netherlands complete Taka Eight
with 2x9W energy saving lamps and all other necessary materials as per : drawing,
specifications and direction of the Engineer-in-charge.
20 Set 870.00 hundred seventy 17,400.00
only
4.11 Supply & installation of impor1ed wall mounted building illumination light fixture
similar to cat. no.20431 of Lanzini, Italy, or OMS, Slovakial F&G, Germany/Philips,
Netherlands complete with 1X400W metal halide lamp, base plate, nuts, screws
etc. and all other necessary accessories as per drawing, specifications and
Taka Ten
direction of the Engineer-in-charge. 10 Set 10,000.00 thousand only 100,000.00
4.12 Supply & installation of imported Aviation Light similar to PS14 with GLS-60W, Taka Three
822 lamp of Philips having blinking circuit arrangement complete with 8'-0" long Thousand six
1.5" dia G.I pipe, nuts, bolts, screws, holder and all other necessary accessories
as per specification & direction of Engineer-in-charge.
2 Set 3,600.00 hundred only 7,200.00
4.13 Supply & installation of imported LED Exit sign light similar to Exit light 2841 of OMS,
Slovakia or F&G, Germany/Philips, Netherlands complete with all respect to provide 4- Taka Five
hours backup time and all other necessary accessories as per drawing, : specifications
SL Rate in Figure and Works
NO. Description of Item Quantity Unit (To be Quoted) Quoted Amount
in figure in word in Taka
1 2 3 4 5 6 7
hours backup time and all other necessary accessories as per drawing, : specifications
and direction of the Engineer-in-charge.
20 Set 5,000.00 thousand only 100,000.00
5.2 Supply & installation of concealed/surface type special switches in totally insulated
made switch board from Moeller/Siemens of appropriate dimension with sufficient
spacing suitable for mounting the required nos. of switches, contactors, impulse relay,
push button, earthing block, etc. from reputed manufactures like as per following ratings
with cover and all other accessories & connections as per specifications, drawing &
comprising of .
6.2 Supply and installation of imported 15A, 3-pin, 250V, combined switched socket Quiet
from Legrand (France UK) IM.K(UK)I Crabtree(UK) Nolex(UK) suitable for 3-pin plug Taka
including the box, cover plate with necessary galvanized machine screws, earthing
block complete with necessary connections as per drawings.
20 Set 500.00 Five hundred 10,000.00
specifications and direction of the Engineer-in-charge. The box may be locally only
made of 16SWG galvanized steel sheet conforming to BS4662.
6.3 Supply and installation of imported 15A, 3-pin, 250V, combined switched socket outlet
from Legrand (France/UK) IM.K(UK)I Crabtree(UK) Nolex(UK) (outdoor type) & 3 pin
plug of approved model including the box, cover plate with necessary galvanized
machine screws, earthing block complete with necessary connections as per drawings,
Taka Six
specifications and direction of the Engineer-in-charge. The box may be locally made of 4 Set 650.00 hundred fifty 2,600.00
16SWG galvanized steel sheet conforming to 8S4662. only
6.4 Supply & installation of imported 16A/20A/25A 132A TP Motor protective circuit breaker Taka three
from Moeller(Germany)/ Siemens(Germany) with auxiliary contacts, indicating lamps, thousand two
etc. in flush/surface mounted totally insulated box as per drawing, specifications and
direction of the Engineer-in-charge.
4 Each 3,220.00 hundred twenty 12,880.00
only
7.0 TELEPHONE SYSTEM
7.1 Supply & installation of imported surface /concealed type totally insulated telephone
junction box made of polystrol/ polycarbonate board from Moeller
(Germany)/Siemens(Germany) of following sizes with connecting strip and all required
accessories such as insulator, screw, rubber bushing, rowel plug etc. as per drawing,
specification and instruction of the Engineer-in-charge.
The rate should be quoted inclusive of all required inclusive of all required material for
this item & the cost shall include the necessary clearing and necessary civil works like
cutting and breaking of walls/columns/ceiling /floors and mending the same including
the plastering & painting as per instruction of the Engineer-in-charge.
9.1.41 SDB-LIFT
Incoming : 1 x 160A TP MCCB / DS 1 Set 110,000.00 Taka One hundred 110,000.00
Outgoing : 2 x 100A TP MCCB Ten
3 x 16A/20A SP MCB Thousand only
250A TP +N+E Bushbar
10.1 Supply and installation of imported traffic signal light system from reputed manufacture's Taka Thirteen
complete with red, yellow and green colour lights, push button, impulse relay, contactor, 9 Set 13,000.00 Thousand only 117,000.00
timer (if necessary) and other accessories as per drawing specifications and instruction
of the Engineer-in-charge.
11.1 Supply and installation of 450mm long 12mm dia single point copper air-terminal Taka One
including necessary bolts, nuts, clamps & all other accessories as shown in the 28 Set 1,100.00 thousand one 30,800.00
drawing.
hundred only
11.2 Supply and installation of roof and intermediate conductor made of 2SWG copper Taka Three
wire complete with necessary hole making, connecting the brass plate of air- 182 Rm 320.00 hundred twenty 58,240.00
terminals, down conductors, etc. complete as per drawing.
11.3 Supply and installation of solid copper wire 2X1/0 SWG in 40mm dia PVC pipe as down Taka Six
conductor as per drawing & specifications. 630 Rm 635.00 hundred thirty 400,050.00
five only
11.4 Supply and installation of test point of size 225X125X100mm made of 16SWG-- Take nine
sheet steel having a copper bar of 1 OOX38X 19mm as per drawing & specifications. 7 Set 950.00 hundred fifty 6,650.00
only
11.5 Supply & installation of solid copper wire earthing lead 2X2/0 SWG in 38mm dia G.I. Take one
pipe and termination of connections at both ends as per drawing & specifications. 75 Rm 1,035.00 thousand thirty 77,625.00
five only
11.6 Supply and installation of 38mm dia, 12m long G.I. pipe earth electrode sunk up to a Taka fourteen
depth of 12m below ground level to be used as earth electrode as per drawing and 10 Set 14,000.00 thousand only 140,000.00
specifications
SL Rate in Figure and Works
NO. Description of Item Quantity Unit (To be Quoted) Quoted Amount
in figure in word in Taka
1 2 3 4 5 6 7
specifications
11.7 Construction of 300X300X300mm earth inspection pit with R.C.C cover as per Taka One
drawing & instruction of the Engineer-in-charge. thousand six
10 Set 1,600.00 hundred only 16,000.00
12.0 CABLE TRAY/LADDER
12.1 Supply and installation of cable tray/ladder made of 18SWG galvanized sheet
steel/angle bar, flat bar of Approved quality of following sizes complete with necessary
hangers, supports, cover junction box, angers, clamps, bends, nuts, bolts, washer & all
other accessories as per drawing, specifications & direction of the Engineer-in-charge.
Take one
12.1.1 100mm width, 75mm -depth thousand five
450 Rm 1,500.00 hundred only 675,000.00
28,007,565.00
SECTIOPN - 6 : BILL OF QUANTITIES
PART- D2 : SUPPLY, INSTALLATION, TESTING AND COMMISSIONING OF DEEP TUBEWELL
SL Rate in Figure and Works
NO. Description of Item Quantity Unit (To be Quoted) Quoted Amount
in figure in word in Taka
1 2 3 4 5 6 7
1 Transpor1ation of Complete boring Equipment's, Labours, Carrying of all Materials to Take Fifty
site, Removing the surplus materials after Completion of work, installation of 1 L.S 50,000.00 Thousand only 50,000.00
equipment's, making necessary arrangements of electricity, water, labour shed, site
office and store, digging mud pit etc. all complete.
2 Execution of Tube well boring specification location water jet or other approved method,
the boring is 400 mm dia ver1ical hole up to designed depth and collection of soil
sample at every 10 m interval and at every charge of formation of soil including sinking
of necessary casing pipe (Measurement will be allowed from G.L to bottom of blank
pipe and the rate is inclusive of the cost of extra depth of boring for caving and siltation).
Length of boring necessary depending on the test result of test boring and
recommendation of BUET (stat size and length of strainer will however be confirmed by
BUET depending on the test result of test boring)
a) 100mm dia bail plug 3m long 1 Each 7,000.00 Taka Seven 7,000.00
thousand only
b) 100mm dia blind G.P Pipe 52 Rm 800.00 Taka Eight 41,600.00
hundred only
c) 100mm dia S.S Strainer 60 Rm 8,600.00 Taka eight thousand 516,000.00
six hundred only
d) 200mm x 100 mm Reducer 1 Each 10,000.00 Taka Ten 10,000.00
SL Rate in Figure and Works
NO. Description of Item Quantity Unit (To be Quoted) Quoted Amount
in figure in word in Taka
1 2 3 4 5 6 7
thousand only
e) 200mm dia M.S Housing Pipe 60 Rm 6,500.00 Taka Six thousand 390,000.00
five hundred only
f) Gravel Packing around the tube well upto 15'-0 above the filter 10 Cum 1,600.00 Taka one thousand 16,000.00
six hundred only
g) Centralizer made 12 BWG MS rod at an interval of 5M 40 Each 500.00 Taka Five 20,000.00
hundred only
h) 40mm dia M.S casing upto min 2M below the raft foundation of building 8 Rm 5,000.00 Taka five 40,000.00
thousand only
4 Development of tube well by alternate surging and pumping by compressor upto Taka forty
satisfactory cleaning of water. 1 L.S 40,000.00 thousand only 40,000.00
5 Testing of the well by required Capacity of water which will be Continued upto 72 Taka forty
hrs or steady state Condition is attained 1 L.S 40,000.00 thousand only 40,000.00
6 Filling the bore hole around the tubewell top of shrouding upto the bottom of sanitary Taka one
seal by selected soil or local clay as pe standard specification 100 Rm 120.00 hundred twenty only 12,000.00
7 Making sanitary seal upto a minimum depth of 6M from GL with 12mm down graded Taka Eight
brick chips in the ration ( 1:1.5:3) 2 Cum 8,000.00 Thousand only 16,000.00
8 Water analysis to be carried out from BUET as detailed in specification of tender Taka Fifteen
document. 1 L.S 15,000.00 thousand only 15,000.00
9 Supply, Installation,Testing and commissioning of submersible pump of any reputed
brad of 80 USGMP capacity against a total head of 60M The pump shall complete with
all necessary under water cable, control/ starter penel made of 20 BWG steel sheet,
circuit breaker, starter, overload relay, time delay relay, voltmeter, ammeter, 100mm dia
Taka Four
pressure gauge. The work include supply and installation of necessary check valve, 1 L.S 400,000.00 hundred thousand 400,000.00
gate valve and column pipe of required diameter. only
10 Obtaining requisite permission from Dhaka WASA or any other Govt. agency for sinking Taka Three
of Tubewell (The Contractor shall be responsible for obtaining permission from WASA hundred thiusand
or other Govt agency )
1 L.S 300,000.00 only 300,000.00
11 38mm dia test boring including supply of all materials required to complete test boring
at site to selected place upto a depth of 300 m or upto satisfactory layer of water Taka Seventy
obtained as per specifications including testing of water and collecting sample of soil at
an internal of 10m and as per direction of Engineer-in-Charge.
1 Item 75,000.00 five thousand 75,000.00
only
2,358,600.00
CIVIL #REF!
PLUMBING 69,558,385.00
ELECTRICAL 28,007,565.00
DEEP TUBEWELL 2,358,600.00
#REF!
Seven
hundred
forty two
thousand
nine
hundred
seventeen
only