High-Profile Customers Demand No-Outage System: Customer Challenge
High-Profile Customers Demand No-Outage System: Customer Challenge
High-Profile Customers Demand No-Outage System: Customer Challenge
GRID CONTROL
Customer Challenge
A large southeastern utility was experiencing outages
on their vintage distribution system that was serving
500 high-profile commercial customers at a popular
vacation spot along International Drive. Accounting
for a peak load of 45 MW, these highly competitive
customers expected a much higher level of electrical
service reliability than what they were currently
experiencing.
At one point, they experienced as many as 16 outages
within a one year period due to main-line cable
faults. Many of the affected customers, at great risk
economically, considered a reasonable level of service
to be one outage every three to four years!
Significant improvement was needed, quickly, to
improve the satisfaction levels of these customers
and to prevent their defection to a nearby utility.
The utilitys goal was to find and implement a solution
that would yield significantly higher levels of reliability
than most customers were experiencingand to
actually exceed their expectations. A fast-track
schedule was developed, requiring that the system be
in service within a year.
Multiple approaches were considered, and of those
many were discarded since they would not produce
significant reliability improvements. The remaining
concepts formed the basis of a request for an
engineering study to review intelligent switching and
primary network alternatives.
S&C Solution
S&C Electric Companys proposal to provide not
only engineering and design services, but also the
equipment to implement the solution on a turnkey
basis was chosen.
www.sandc.com/services
180-1015
www.sandc.com/services
180-1015
Valued Outcome
The result of the entire teams effort was the delivery
of a revolutionary distribution automation system that
has and will provide reliability into the future.
The system was engineered, designed, procured,
configured, delivered, installed, tested, and put in
service in approximately one year to meet the utilitys
aggressive schedule.
Most importantly, the 45 MW load represented by the
affected customers remains on the serving utilitys
system. Bottom line: Business was retained and the
business development opportunities for this utility were
enhanced because they can now offer a level of service
unmatched in the industry.
Communications design
System configuration and commissioning
Programming
Factory acceptance testing
Site acceptance testing
Documentation
Training
In an effort to reduce field setup time and verify the
fault-clearing time and SCADA scan rate, all electronic
components were sent to S&Cs testing facility in
Chicago, IL. There, representatives from both S&C and
the utility worked for a week to check timing and adjust
settings. Loss of voltage tests were conducted to test
the systems intelligent switching portion by bypassing
each overhead switch to ensure they were closing
and reclosing in the correct sequence and within the
allowed-time criteria. These tests played an extremely
important role in building confidence, and training and
adapting the automated system.
www.sandc.com/services
180-1015