Icoe2010 G.dalton
Icoe2010 G.dalton
Icoe2010 G.dalton
1
HMRC, UCC,
Pouladuff Rd, Togeher, Cork, Ireland
E-mail: g.dalton@ucc.ie
2
same address
E-mail: r.alcorn@ucc.ie
2
same address
E-mail: t.lewis@ucc.ie
1
http://www.ucc.ie/research/hmrc/
1
3rd International Conference on Ocean Energy, 6 October, Bilbao
Total initial cost (IC) of a project is defined in this create a percentage relation to the total COE per MWh
study as the sum of all projects costs which are (see paragraph below). However, $/MWH is not the
necessary to deploy device(s) ready for operation. The simplest metric and from an economic perspective
costs include: costs of components (WEC, cable, and assumes that the total energy output is already
mooring), cost installation, boats and towing, initial calculated. Its disadvantage is that the O/M result is
permits, management fees and decommissioning). location specific, and will change for the same device
Many of the costs of the project are derived as a used in different locations, which might result in
percentage cost of the WEC, which is abbreviated as confusion.
ICwec (explained more thoroughly in Methodology and The next most popular metric is O/M based as a
inputs). O/M costs in this study are calculated for each percentage of the initial cost (IC). The advantage of this
component (WEC, cable and mooring) rather than O/M method is in its simplicity, and that it is uniform in
for the entire project. Calculation for O/M for a operation in any location, and thus easier to use in cash
component is taken as a percentage of the IC cost of flow sheets. The metric has two main disadvantages:
that component, with the inclusion of its installation % of IC quoted in the literature does not normally
cost (explained more thoroughly in Methodology and specify the capital used i.e. whether it is a percentage of
inputs). An example of the abbreviation for initial costs the device IC or the total project IC.
for cable is as follows: The metric does not reflect costs specific to a
location.
(IC+instal)cable= initial cost of cable + cost of cable The % of IC figure is at present arbitrarily chosen
installation. for economic analysis and not based on actual
evidence.
Results extracted from this study must be taken as The final method compares in % the O/M cost in
indicative and relative, keeping in mind that the main $/MWh to the total COE. It is rarely used in reports and
focus of the paper is an analysis of the impacts of assumes that COE is already analysed and discussed.
OPEX on wave energy project returns. Conclusions drawn from the data presented in Table
1 are as follows:
Average wave energy O/M:
2 Literature review on operational o $30/MWh (exception is the low quote
expenditure (OPEX) from EPRI [5] of $8/MWH).
o O/M percentage of IC range from 1.5-5%
(with a max of 10% from Wang [24]).
2.1 Operation and maintenance Average onshore wind O/M:
This section reviews the literature available on o $8-15/MWh (exception is the EWEA [18]
operation and maintenance (O/M). Operation and report quoting 40/MWh).
maintenance is defined in this case study as all annual o O/M percentage of IC range from 1-3.5%
costs required to maintain optimum mechanical (with a max of 7% from Lemming [19]).
performance of a device/ series of devices/ wave farm. Average offshore wind O/M:
In this report, it will include all planned and unplanned o $8-16/MWh (exception is the UK [23]
maintenance. The logistics of these two sub-categories report quoting 3/MWh).
will not be explored in this paper. o O/M percentage of IC range from 3-4.5%
Metrics relating to O/M expense are described by .
either of 4 following metrics: Of the three metrics reviewed, O/M based on the %
$/MWh (/MWh): This metric provides a cost based IC is the most unambiguous. Sensitivity analysis of
on the relationship between the total initial cost of the O/M can be recommended for both wind and wave
project and the annual energy output. ranging from 1-5%.
% of initial cost (IC2): O/M is calculated as a Conclusions from the $/MWh are not as clear.
straight percentage of capital cost. Onshore and offshore wind appear to have the same
% of the total OPEX. $/MWh, although their % of IC figures differ. It would
% of cost of electricity (COE): The metric provide a be perhaps expected that $/MWh for offshore wind
percentage O/M cost in relation to the total COE for the should be higher than onshore wind due to the higher
project. It requires both the O/M and COE based in IC. This anomaly can be explained by the following
$/MWh. example and explanation: a 5MW rated wind turbine
The most commonly quoted metric is $/MWh. Its will be expected to produce a higher energy output in
main advantage is that it can be used as a performance an offshore location than an onshore location, due to an
indicator, as the result is directly proportional to the expected higher capacity or load factor. Although a
device performance at the location. It can be used to 5MW wind turbine may have similar IC costs for both
onshore and offshore applications, the installation and
2
connection costs for offshore will be higher. Thus, the
IC means the total initial costs of the item in question. Therefore it
can refer to either a component such as cable or the entire project. higher energy output of the offshore turbine will offset
Care therefore needs to exercised in defining what the IC refers to the higher IC costs for that location, producing similar
when used. For example, ICwec used later defines the initial cost of /MWH results as its onshore equivalent. The higher
the WEC alone.
2
3rd International Conference on Ocean Energy, 6 October, Bilbao
UK Dale [23] 3b ()
Table 1: Literature review of operation and maintenance cost for onshore and offshore wind, and wave energy studies. Three metrics
a
are presented: $/MWh, % of initial cost IC and % of cost of electricity (COE). All costs are in $US unless stated otherwise in brackets.
% quoted are assumed to be a % of the total IC, although not clearly defined in reports. b Result based on $24/kw/yr quoted in the
paper.
the wave energy rental costs will be similar to offshore Ocenica (CEO) which was 77% owned by a
wind rental costs, and were thus used in the modeling subsidiary of Babcock and Brown Limited and 23% by
section for wave energy in this report. Pelamis Wave Power Limited. Since the financial crisis
accelerated in the last quarter of 2008, Babcock and
Brown Limited has had its shares suspended and has
3 Methodology and inputs been in a managed process of selling its assets5. The
E.ON energy group are the second major developer
3.1 Project location and device using the Pelamis. E.ON plans to deploy the latest
Pelamis design, the P2, in the European Marine
The location for the data collection was the M4 buoy Energy Centre (EMEC) in 2010. Future plans for the
off Belmullet, 55 deg N, 10 deg W or approximately 25 EMEC and the Orcadian Wave Farm will consist of
km off the coast of Mayo, water depth approx 150m four Pelamis generators supplied by PWP to
(Figure 1). ScottishPower Renewables supported by 4m funding
from the Scottish Executive providing.
Equation 1 WEI=0.55Hs2Tz
Figure 1: Map of location of the M series buoys around Ireland4. Equation 2 Te = 1.2*Tz
Period (Te)
1 2 3 4 5 6 7 8 9 10 11 12 13
Height (Hs) 0.5 0 0 0 0 0 0 0 0 0 0 0 0 0
1 0 0 0 0 0 29 37 38 35 29 23 0 0
1.5 0 0 32 65 83 86 78 65 53 42 33
2 0 57 115 148 152 138 116 93 74 59
2.5 89 180 231 238 216 181 146 116 92
3 129 260 332 332 292 240 210 167 132
3.5 354 438 424 377 326 260 215 180
4 462 540 530 475 384 339 267 213
4.5 544 642 628 562 473 382 338 266
5 726 707 670 557 472 369 328
5.5 750 750 737 658 530 446 355
6 750 750 750 711 619 512 415
6.5 750 750 750 750 658 579 481
7 750 750 750 750 613 525
7.5 750 750 750 750 686 593
8 750 750 750 750 625
8.5 750 750 750 750
9 750 750 750
9.5 750 750
10 750
10.5
11
11.5
12
5
3rd International Conference on Ocean Energy, 6 October, Bilbao
50MW project at 5000/kW, due to bulk discount rates low risk projects. Low risk projects have their discount
discussed later. The capital costs used in this report are rate calculated in the following Equation 5:
approximately double those quoted for other wave BR + f
energy reports and offshore wind (see paper by Dalton Equation 5 DR =
1 f
et al. [30] for more detail).
The remainder of other costs were calculated as a
Where BR is the borrowing rate given for a loan and
percentage of the IC of the WEC (ICwec) (Table 4),
f is the inflation rate. By defining the discount rate in
and were based on costs derived from a previous paper
this way, inflation is factored out of the economic
by the author, Dalton et al. [30]. This method allowed
analysis during the project lifetime. All costs therefore
for simplified cost and sensitivity analysis.
become real costs, meaning that they are in defined in
terms of constant Euros. The assumption is that the rate
WEC parameter % of ICwec of inflation is the same for all costs. A general inflation
rate of 3% [31] was used for the project.
Mooring 10%
Cabling 10% Farm size Discount rate
Replacement costs 90% 0-5MW 14%
Spare parts 2% 6-10MW 12%
Sitting and permits 2% 11-20MW 10%
GHG investigations 0.05% 21-50MW 8%
Decommissioning fees 10% 50MW 6%
Grid connection 5% >50MW Equation 5
Table 6: Discount rates.
Management fees 10% of total IC
Table 4: Costs of WEC infrastructure, calculated as a percentage
of the ICwec. The majority of Previsic [5] costings were used in
the report. 3.4 Grid Sales Revenue
Feed-in tariff (FIT) refers to the regulatory,
A summary of the project inputs can be viewed in minimum guaranteed price per kWh that an electricity
Table 5. utility has to pay to a private, independent producer of
renewable power fed into the grid [32]. It is defined in
Borrowing or interest 7.5% this report as the full price per kWh received by an
rate independent producer of renewable energy including
Inflation rate 3% the premium above or additional to the market price,
Project years 15a but excluding tax rebates or other production subsidies
paid by the government. Grid sales are a credit, and are
Table 5: Input values for the project. (a The DCENR tariff of
0.22/kWh is available for 15 year duration)
added to other negative cost values for the each year.
The sales are the product of the following two
variables:
The discount factor (DF) translates expected The total energy produced each year, referred to as
financial benefits or costs in any given future year into the annual energy output (AEO).
present value terms. The total nominal profit is The electricity tariff rate from the utility company.
adjusted for cash depreciation by multiplying the total In this report, FIT of 0.22/kWh was assessed.
nominal profit by a discount factor. The rate of 0.22/kWh is the rate presently proposed
DF is calculated using the discount rate, and is by the Irish government [7]. The tariff spans a 15 year
calculated by Equation 4. project and is available until 20157.
1
Equation 4 DF =
(1 + DR) n 3.5 Cost reduction for multiple devices
The cost of purchasing multiple devices are cheaper
The discount rate (DR) is an interest rate than buying a singular device, due to discounts
commensurate with perceived risk used to convert provided any manufacturer to encourage multiple
future payments or receipts (within a project lifetime) purchases. The discount is based on a cumulative
to present value. The discount rates for various project factorial reduction in price. The cumulative total of n
sizes are listed in Table 6. Small WEC projects are number of devices is the sum of the discounted costs,
deemed high risk, as they are at the beginning of their derived in Equation 6.
commercialisation phase, and thus have high discount
rates. For this project, wave farms greater than 50MW
are deemed fully commercial and thus categorised as
7
Personal communication from Richard Browne (DCENR).
6
3rd International Conference on Ocean Energy, 6 October, Bilbao
7
3rd International Conference on Ocean Energy, 6 October, Bilbao
Costs for Utility O/M and capacity charges were Capacity charges taken from [33, 34] for the west of
taken from Eirgrid and ESBI Network reports [33, 34]. Ireland was 8000/MW.
Line works and cable costs related to the kV and
MW of the project are multiplied by the overhead cable
lengths which in this study was 30km (Table 8).
Subtotal of off-shore
cabling 5%
Mooring 5%
Spare parts 1%
Table 7: Schedule of overhaul every 4 years and replacement every 10 years, for WEC, cable and moorings, for 50 MW project at
0.22/kWh. (for simplicity, overhaul still takes place in year 12 despite the fact that replacement occurred in year 10).
8
3rd International Conference on Ocean Energy, 6 October, Bilbao
2007. The values in this table vary form from those lies within the periods of 5-7 seconds and wave
reported in an earlier paper by the author [30], as a heights of between 1- 3.5m. The average power of
different method was used to bin the hours. In the the waves for the M4 location in 2007 was 58kW/m.
first paper, the median value for Hs and Tz was used. Figure 3 presents the monthly average energy output
of the wave, showing a large variation between
The revised method used in this paper floors the winter and summer outputs.
Hs and Tz values. The highest frequency of hours
Tz (s)
1 2 3 4 5 6 7 8 9 10 11 12 13
0.5 52 130 25
1 8 41 164 387 151 59 11
1.5 5 44 82 488 360 236 75 12
2 26 65 293 503 258 142 31 4
2.5 76 107 354 386 129 26 5 3 1
3 30 45 226 496 201 41 1 2
3.5 1 26 44 352 227 82 9
Hs (m) 4 23 19 181 252 99 19 3 1
4.5 9 9 71 210 99 19 4
5 2 6 6 158 123 30 3 1
5.5 3 81 144 29 10 3
6 4 21 100 44 7 4
6.5 4 6 47 42 11 4
7 4 27 57 16 3
7.5 3 14 33 19
8 3 29 21 5
8.5 1 21 17 2
9 4 15 2 2
9.5 1 9 1
10 2 3 1
10.5 2 1
11 2
11.5 1
Table 9: Scatter plot of hours for M4 buoy off the west coast of Ireland, 2007.
Overhaul 11% 20
Replacement 34% 61
a
Insurance 26% (19%) 47 (31)
Utility charges 2% 4
Rent 3% 6
Total 100% 177
Table 10: Results for the break down on expenditure costs for a
50MW wave farm, using O/M at 3% of IC and insurance at 3%
of IC. aresults for insurance modelled at 2% of IC are in
brackets.
Rent
6%
Utility charges
4%
Annual O/M
42%
Insurance
48% Overhaul
0%
Replacement
A 0%
Rent
Utility charges 3%
Annual O/M
2%
22%
Insurance
27%
Overhaul
11%
Replacement
35%
B
10
3rd International Conference on Ocean Energy, 6 October, Bilbao
200
NPC (M)
IRR (%)
50
O/M at 1% and 3% result in lengthy payback times of
12-14 years. (No overhaul or replacement costs were 0
1%
2%
3%
5%
10%
1%
2%
3%
5%
10%
1%
2%
3%
5%
10%
1%
2%
3%
5%
10%
0.0%
0
0 2 4 6 8 10 12 14
subcomponents or WEC and cable (for the sake of
-50
simplicity in the graph, mooring was left out). It is
O/M 1% evident from the results that O/M for the WEC
-100
O/M 3%
O/M 5%
component has the most impact, where an increase of
O/M 10% O/M from 1% to 5% for WEC alone pushes the cash
-150
flow projection completely in the negative. A similar
increase in cable costs has a much lesser effect.
-200
The impact of annual insurance costs is assessed in
-250 Figure 9, at FIT of 0.22/kWh. It is evident that even a
modest 1% insurance cost pushes the cash flow for the
-300 15 years into the negative.
The ramifications of a 3% insurance costs at an FIT
Figure 5: Cumulative cash flows for 50MW project at 0.22/kWh
of 0.22/kWh on NPV and IRR are examined in Figure
no overhaul and replacement expenses.
10 and is compared to the results described for 0%
insurance displayed in Figure 6. The insurance
premium eliminates almost all possibility of positive
NPV except for low O/M costs for the largest 100MW
project. IRR fails to reach the 10% threshold in any
scenario, unlike IRR results in Figure 6.
As discussed in the introduction, insurance costs of
5% to 10% are common in the maritime industry and
results from these simulations indicate that severe
consequences on cash flow projections will eventuate,
with current FIT at 0.22/kWh.
11
3rd International Conference on Ocean Energy, 6 October, Bilbao
50
100
0
0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15
-50
0
0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 -100
-50 No Utility O/M Charges
1% WEC, 1% Cable Utility O/M charges
5% cable, 1% WEC -150
-100
5% WEC, 1% cable
5% WEC, 5%cable -200
-150
-200 -250
-250 -300
-300
Figure 11: Cumulative cash flows inspecting impact of ESB O/M
charges (O/M kept ay 3% of IC, 0.22/kWh FIT).
Figure 8: Cumulative cash flows at varying levels of O/M for
either WEC and or cable.
0
0 2 4 6 8 10 12 14
6 Conclusions
-50
Navitas simulations results for /MWh were
Cumulative cash flows (M)
-150
Insurance 3% insurance). The total cost for all OPEX was 87/MWh
Insurance 5%
Insurance 10%
(177/MWh including overhaul and replacement).
-200
These results reflect the high initial costs used in the
case study, and remained high despite the high energy
-250
output from the devices at the chosen case study
location. The results were twice as high as offshore
-300
wind. The author has reservations about the widespread
use of the /MWh metric, as the metric is location
Figure 9: Cumulative cash flows for various levels of insurance specific. It is suggested the metric is best used when
(O/M kept ay 3% of IC, 0.22/kWh FIT). assessing devices of similar MW rating in the same
location. The metric has similar limitations as the cost
of electricity (COE) metric, which was discussed in a
The analysis of utility O/M expenses is often
published paper by Dalton et al [30]. O/M of 3% IC
forgotten about in cash flow analysis. The, the impact
produces /MWh results around the average quoted I
on cash flows in this case study is minimal, as is
the literature.
evident in Figure 11.
The results from the simulations indicate that NPV
100 10.0%
of a project is very sensitive to changes in O/M cost,
8.0%
50
with a limit of 3% before NPV goes negative. Larger
6.0%
0 wave farms of 100MW or more will make projects
1%
2%
3%
5%
10%
1%
2%
3%
5%
10%
1%
2%
3%
5%
10%
1%
2%
3%
5%
10%
4.0%
-50
more profitable from an IRR perspective due to cost
2.0%
NPC (M)
0.0%
-100
costs.
-150
-2.0%
The O/M of the WEC is the most significant
-200
-4.0%
contributor to overall O/M (in comparison to cable and
-6.0%
mooring) as expected due to the higher IC of that
-250
-8.0% component.
-300 -10.0% Variation in insurance costs is the other major factor
NPC IRR
which has significant impact on NPV. Case study
Figure 10: NPC and IRR for 3% insurance, at varying O/M simulations indicate that the current FIT of 0.22/kWh
expenses and different size wave farms, 0.22/kWh and no may not be sufficient if insurance rates of 1% and over
overhaul and replacement. are levied.
Replacement cost is the other OPEX cost which is
not often considered in assessments. In the present case
study modelling, over 1/3 of the total OPEX cost for
the entire project was due to device replacement in the
10th year.
In conclusion, project profits are very sensitive to
annual OPEX, especially if overhaul and replacement
costs are accounted for. Results indicate that device
designers will need to choose whether to opt for longer
12
3rd International Conference on Ocean Energy, 6 October, Bilbao
13
3rd International Conference on Ocean Energy, 6 October, Bilbao
14