Annex I
Administrative Order No. 2014-0027: National Policy on Water Safety Plan (WSP) for All
Drinking-Water Service Providers
GUIDELINES IN DEVELOPING WATER SAFETY PLAN FOR
WATER REFILLING STATIONS IN THE PHILIPPINES
Annex II
3. The plumbing system, water piping connections, fittings and hoses conveying water
constructed, installed and repaired with in accordance with the NBCP and the NBC (PD
1096).
GUIDELINES IN DEVELOPING WATER SAFETY PLAN FOR
WATER REFILLING STATIONS IN THE PHILIPPINES
4. No booster, pneumatic, pressure or other pumps connected to the main water line.
Initial Subsequent
Parameters
Result Result
1. Plans and specifications of the water purification signed and sealed by a licensed Sanitary
Engineer (RA 1364).
2. Design was environmentally sound, ecologically safe, cost efficient, based on the
characteristic of source water and the available water purification technology.
3. Water processing constructed/installed as per approved design and operation. No by-pass
in any of the operations.
4. Product water No Residual of disinfectant.
5. Parts of the equipment (cartridges, membranes, pumps, etc.) used, replaced as per
manufacturer’s requirements.
6. Appropriate quality monitoring program being implemented in all the critical control points
of the water processing
1. Filter thoroughly cleaned and sanitized in place and/or disassembled for cleaning and
sanitizing before being used.
2. Using DOH approved cleaning solution or process.
3. Using DOH approved sanitizing solution or process.
4. Filter thoroughly rinsed internally and externally with product water every after filling
operation.
5. Rim of container when filling pointed directly to the water dispensing nozzle during filling.
6. Refilled containers immediately capped after filling.
1. All containers and caps from customers and for delivery thoroughly washed and sanitized
by the establishment (RWS) before refilling them with water.
2. No residual of disinfectant, oxidant or sanitizer in all the containers and caps.
3. Only DOH-approved cleaning solution or process used.
4. Only DOH-approved sanitizing solution or process used.
5. Product water used for rinsing.
6. Adequate draining of containers and caps employed.
4. All refilled water containers properly capped, arranged crated or boxed. No other product
or material inside the delivery vehicle.
5. Water in delivery vehicles maintained at 25 °C - 28°C temperature.
1. All refilling stations provided with refilling and selling room, enclosed water purification
room, container washing and sanitizing room, separate storage room for empty and refilled
containers, source water storage facility and toilet room.
2. Room/Facility Area Allocation:
a. Refilling & Selling Room – 9.50 sq. m. (minimum)
b. Water Purification Room – 3.10 sq. m. per person (clear of all equipment).
c. Container washing and sanitizing room – 6.0 sq. m. plus 3.10 sq. m. for every additional
personnel
d. Container Storage Room (separate for empty and filled containers) – sufficient area per
approved plan.
e. Source Water Storage Facility – sufficient place to allow free movement during
inspection.
f. Office Space – 1.77 sq. m. per person (clear of all furniture and equipment).
g. Change Room – 2.80 sq. m. per person (inclusive of lockers or other facilities).
h. Toilet Room – per toilet structural requirement.
i. Parking Area (optional) – 30 sq. m. plus 10 sq. m. for each additional car.
3. Filling, selling, and water purification rooms under positive pressure of purified air.
4. All doors and partitions made of see-through materials.
5. All customer service opening designed to minimize the entrance of contaminants and pests.
1. Floors:
a. Constructed of impervious, non-skid easily cleaned materials.
b. Adequately graded and drained.
c. Floor drain provided in store or selling area.
GUIDELINES IN DEVELOPING WATER SAFETY PLAN FOR
WATER REFILLING STATIONS IN THE PHILIPPINES
2. Walls:
a. Internal surfaces – smooth, even, non – absorbent and easily cleaned materials.
b. Painted or finished light with colored materials.
c. All angles between the floor and walls rounded off to a height of 7.62 cm.
d. All angles between the walls and ceilings are sealed.
e. Walls of toilets and other rooms subject to wetting constructed of impervious materials
to a height not less than 2 m. from the floor.
3. Ceilings: constructed of smooth, non – absorbent materials painted light color
4. Doors: self – closing, tight fitting with smooth and non – absorbent surfaces.
5. Lighting: all rooms provided with 20 foot – candle (215,20 lux) illumination intensity.
6. Ventilation:
a. Each personnel provided with 12 cubic meter room volume and minimum of 3 air
exchanges per hour;
1. Windows and other opening – 10% of floor area
2. Mechanical Ventilation – air conditioner, exhaust fan and blower
b. Selling, Filling and Water Purification Rooms – preferably air – conditioned.
c. All rooms provided with odor absorber or air purifier
7. Change Room:
a. All refilling stations provided with suitable lockers or other facilities for storage of
clothing and personal belongings of employees.
b. Facilities situated and arranged that there is no contamination of refilled water.
c. No clothing, gowns, aprons, etc. placed in other rooms or areas other than the facilities
mentioned.
d. Separate change room for establishment employing more than 5 or more employees of
either sex.
e. Change room cleaned daily and disinfected once a week.
2. No alteration, addition, deletion or any change in the water purification process without an
approved plan from the LHO.
3. Repairs of structural, plumbing and drainage carried out without delay.
4. Defective or damaged receptacles, appliances, furniture or equipment discarded and
replaced or repaired as required.
5. Rooms and premises maintained in tidy condition and free from accumulation of refuse
and/or wet flooring.
6. Premises, equipment, furniture, etc. maintained in clean and sanitary condition.
1. Refilling station provided with 2 receptacles in all rooms and premises, one for
biodegradable (green color lining bag) and one for non-biodegradable (black color lining
bag).
2. All refuse materials handled in such a manner as to avoid contamination of water.
3. Receptacle for sanitary napkin provided in women’s toilet room.
4. All refuse segregated at source in a sanitary and approved procedure.
1. Absence of mice, rats, flies, mosquitos, roached, and other vermin in the rooms and
premises.
2. Vermin abatement program approved by LHO and maintained by operator.
1. Refilling station being managed by plant manager/supervisor passed the 40-hour basic
certification course for water operators
2. All other personnel completed the 20-hour training conducted by the LHO for water
sanitation.
3. All personnel of the establishment possess up-to-date health certificates.
GUIDELINES IN DEVELOPING WATER SAFETY PLAN FOR
WATER REFILLING STATIONS IN THE PHILIPPINES
Annex III
Process Verification
Critical Limit Monitoring Procedure Corrective Action(s) Records
Step Procedure
Reverse TDS 9 mg/L Assigned staff to check If TDS & pH are above Test water in a TDS Monitoring
Osmosis (ppm) level of TDS in product acceptable levels, laboratory for Physical Sheet
water at least once a day temporarily stop / Chemical parameters
using TDS meter operation, check once every 6 months
condition of pre- or as needed (e.g. TDS Water Test Result
treatment equipment. level is above limit (Physical /
good condition)
If pre-treatment
equipment is
functioning & in good Calibration of
condition, clean / monitoring equipment
rehabilitate membrane (TDS)
GUIDELINES IN DEVELOPING WATER SAFETY PLAN FOR
WATER REFILLING STATIONS IN THE PHILIPPINES
Process Verification
Critical Limit Monitoring Procedure Corrective Action(s) Records
Step Procedure
If condition of pre-
treatment is not
acceptable, clean,
backwash or replace
equipment
UV light 9,000 lamp Operator to monitor If lamp hours has Double check lamp Preventive
sterilization hours lamp hours at least once reached or exceeded hours and review maintenance Record
a year 9,000 hours, replace Preventive
(refer to
bulb immediately Maintenance Records
manufacturer’s
recommendation
on lamp hours)
GUIDELINES IN DEVELOPING WATER SAFETY PLAN FOR
WATER REFILLING STATIONS IN THE PHILIPPINES
Process Verification
Critical Limit Monitoring Procedure Corrective Action(s) Records
Step Procedure
Indicator light is Assigned staff to If indicator light is off / Review Preventive Preventive
on monitor indicator light check if plugged. If Maintenance Records maintenance Record
is on before start of plugged and indicator
operation light is still off, replace
bulb or ballast.
Container, 50 ppm chlorine Assigned staff to check Adjust chlorine Validate procedure of Chlorine Level
caps solution chlorine concentration at concentration to meet chlorine preparation Monitoring Sheet
Washing least once a day using required dose
and chlorine test strips with
sanitizing color chart
Safe Drinking Water (commonly known as Mineral Water) (Source: All types of raw water but passed microbiological test)
Process Verification
Critical Limit Monitoring Procedure Corrective Action Records
Step Procedure
Activated Presence of Assigned staff to check If chlorine is present in Validate procedure of Chlorine Monitoring
Carbon chlorine for presence of chlorine product water, replace staff ‘s chlorine Sheet
Filtration in product water as activated carbon filter monitoring
indication of failed AC
filtration at least once a
GUIDELINES IN DEVELOPING WATER SAFETY PLAN FOR
WATER REFILLING STATIONS IN THE PHILIPPINES
Process Verification
Critical Limit Monitoring Procedure Corrective Action Records
Step Procedure
5lbs pressure Assigned staff to check If pressure drop has Review gauge Gauge monitoring
drop for drop in pressure in reach 5 lbs, backwash monitoring sheet sheet
the pressure gauge once filter
a day
U.V. Light 9,000 lamp Operator to monitor If lamp hours has Double check lamp Preventive
Sterilization hours lamp hours at least once reached or exceeded hours and review maintenance Record
a year 9,000 hours, replace Preventive
(refer to
bulb immediately Maintenance Records
manufacturer’s
recommendatio
n on lamp
hours)
Indicator light is Assigned staff to If indicator light is off / Review Preventive Preventive
on monitor indicator light is check if plugged. If Maintenance Records maintenance Record
plugged and indicator
GUIDELINES IN DEVELOPING WATER SAFETY PLAN FOR
WATER REFILLING STATIONS IN THE PHILIPPINES
Process Verification
Critical Limit Monitoring Procedure Corrective Action Records
Step Procedure
Container 50 ppm chlorine Assigned staff to check Adjust chlorine Validate procedure of Chlorine Monitoring
Washing solution chlorine concentration at concentration to meet chlorine preparation Sheet
least once a day (for required dose
automatic chlorine
injection) using chlorine
test strip
Safe Drinking Water (commonly known as Mineral Water) (Raw Water Source: Failed in Microbiological Test)
Process Monitoring Verification
Critical Limit Corrective Action(s) Records
Step Procedure Procedure
Chlorination Presence of Assigned staff to check If chlorine is not Validate procedure of Chlorine Monitoring
chlorine for presence of chlorine present in the water as staff ‘s chlorine Sheet
in raw water sample indicated by absence of monitoring
30 minutes
using Chlorine test kit color change from the
contact time Review chlorine
(e.g. Othotolidine) test kit, add chlorine in
monitoring sheet to
every preparation the chlorinator
check presence of
GUIDELINES IN DEVELOPING WATER SAFETY PLAN FOR
WATER REFILLING STATIONS IN THE PHILIPPINES
Activated Presence of Assigned staff to check If chlorine is present in Validate procedure of Chlorine Monitoring
Carbon chlorine for presence of chlorine product water, replace staff ‘s chlorine Sheet
Filtration in product water as activated carbon filter monitoring
Water Test Result
indication of failed AC
Test water in a (Physical /
filtration at least once a
laboratory for Physical Chemical)
month using chlorine
/ Chemical parameters
test solution
once every 6 months
(othotolidine)
5lbs pressure Assigned staff to check If pressure drop has Review gauge Gauge monitoring
drop for drop in pressure in reach 5 lbs, backwash monitoring sheet sheet
the pressure gauge filter
once a day
GUIDELINES IN DEVELOPING WATER SAFETY PLAN FOR
WATER REFILLING STATIONS IN THE PHILIPPINES
U.V. Light 9,000 lamp hours Operator to monitor If lamp hours has Double check lamp Preventive
Sterilization lamp hours at least reached or exceeded hours and review maintenance Record
(refer to
once a year 9,000 hours, replace Preventive
manufacturer’s
bulb immediately Maintenance Records
recommendation
on lamp hours)
Indicator light is Assigned staff to If indicator light is off / Review Preventive Preventive
on monitor indicator light check if plugged. If Maintenance Records maintenance Record
is on before start of plugged and indicator
operation light is still off, replace
bulb or ballast.
Container 50 ppm chlorine Assigned staff to check Adjust chlorine Validate procedure of Chlorine Monitoring
Washing solution chlorine concentration concentration to meet chlorine preparation Sheet
at least once a day (for required dose
automatic chlorine
injection) using
chlorine test strip
GUIDELINES IN DEVELOPING WATER SAFETY PLAN FOR
WATER REFILLING STATIONS IN THE PHILIPPINES
Annex IV
Blueprint Sample
C
B
GUIDELINES IN DEVELOPING WATER SAFETY PLAN FOR
WATER REFILLING STATIONS IN THE PHILIPPINES
GUIDELINES IN DEVELOPING WATER SAFETY PLAN FOR
WATER REFILLING STATIONS IN THE PHILIPPINES
Blueprint Notes
C Pump A
Final Filter Polish
Ultrafiltration System
First Filtration System
GUIDELINES IN DEVELOPING WATER SAFETY PLAN FOR
WATER REFILLING STATIONS IN THE PHILIPPINES
Annex V
Monitoring Parameters
Total Dissolved Solids (TDS) Chlorine pH (optional)
Date Time Result Who Date Time Result Who Date Time Result Who
GUIDELINES IN DEVELOPING WATER SAFETY PLAN FOR
WATER REFILLING STATIONS IN THE PHILIPPINES
Gauges Date Time Result Who Date Time Result Who Date Time Result Who
Gauge 1
Gauge 2
Gauge 3
Gauge 4
Gauge 5
Gauge 6
Gauge 7
Gauge 8
Gauge 9
Gauge 10
GUIDELINES IN DEVELOPING WATER SAFETY PLAN FOR
WATER REFILLING STATIONS IN THE PHILIPPINES
Gauges Date Time Result Who Date Time Result Who Date Time Result Who
Gauge 1
Gauge 2
Gauge 3
Gauge 4
Gauge 5
GUIDELINES IN DEVELOPING WATER SAFETY PLAN FOR
WATER REFILLING STATIONS IN THE PHILIPPINES
Annex VI
Template on How to formulate a WSP for WRS