Chapter 3 Gas Turbine
Chapter 3 Gas Turbine
Chapter 3 Gas Turbine
GAS TURBINE
SECTION 1. GAS TURBINE PROPER
Selective positioning of the wheels is made during assembly to reduce the rotor balance correction. The
compressor rotor is dynamically balanced after assembly and again after the compressor and turbine rotors
are mated. They are precision balanced prior to assembly into the stator.
Stator blades utilize square bases for mounting in the casing slots. Blade stages zero through four are
mounted by axial dovetails into blade ring segments. The blade ring segments are inserted into
circumferential grooves in the casing and are secured with locking rings. Stages 5 through 16 are mounted on
individual rectangular bases that are inserted directly into circumferential grooves in the casings. Stage 17
and the exit guide vanes are cast segments.
The casing bore is maintained to close tolerances with respect to the rotor blade tips for maximum
aerodynamic efficiency. Borescope ports are located throughout the machine for component inspection. In
addition all casings are horizontally split for ease of handling and maintenance.
A Inlet Casing
The primary function of the inlet casing, located at the forward end of the gas turbine, is to direct the air
uniformly from the inlet plenum into the compressor. The inlet casing also supports the number 1 thrust
bearing assembly and the variable inlet guide vanes, located at the aft end.
B Compressor Casing
The compressor casing contains compressor stages zero through 12. Extraction ports in the casing allow
bleeds to the exhaust diffuser during startup and extraction of air to cool the second and third stage nozzles.
C Compressor Discharge Casing
The compressor discharge casing contains 13th- through 17th- stage compressor stators and one row of
exit guide vanes. It also provides an inner support for the first-stage turbine nozzle assembly and supports
the combustion components. Air is extracted from the compressor discharge plenum to cool the stage one
nozzle vane, retaining ring, and shrouds.
Similarly, air extracted from the compressor discharge plenum is used to provide the following:
The compressor discharge casing consists of 2 cylinders connected by radial struts. The outer cylinder is a
continuation of the compressor casing and the inner cylinder surrounds the compressor aft stub shaft. A
diffuser is formed by the tapered annulus between the outer and inner cylinders. The compressor discharge
casing is joined to the turbine shell at the flange on its outermost diameter.
Selective positioning of rotor members is performed during assembly to minimize balance corrections of the
assembled rotor. Concentricity control is achieved with mating rabbets on the turbine wheels, spacers, and
shafts. Turbine rotor components are held in compression by bolts. Rotor torque is accomplished by friction
force on the wheel faces due to bolt compression.
The turbine rotor is cooled by air extracted from compressor stage 17. This air is also used to cool the turbine
first- and second-stage buckets plus the rotor wheels and spacers.
Second- and third-stage buckets have integral tip shrouds that interlock buckets to provide vibration damping
and seal teeth that reduce leakage flow. Turbine buckets are attached to the wheel with fir tree dovetails that
fit into matching cutouts at the rim of the turbine wheel. Bucket vanes are connected to the dovetails by
shanks, which separate the wheel from the hot gases and thereby reduce the temperature at the dovetail.
The turbine rotor assembly is arranged to allow buckets to be replaced without having to unstack the wheels,
spacers and stub shaft assemblies. Similarly, buckets are selectively positioned such that they can be replaced
individually or in sets without having to rebalance the wheel assembly.
All turbine nozzles consist of multi-vane segments. First-stage turbine nozzle segments are contained by a
retaining ring, which remains centered in the turbine shell. The second- and third-stage nozzle segments are
held in position by radial pins from the shell into axial slots in the nozzle outer sidewall.
1.5 BEARINGS
1.5.1 The MS7001(FA) gas turbine contains two journal bearings to support the turbine rotor and one dual
direction thrust bearing to maintain the rotor-to-stator axial position. The bearings are located in two (2)
housings: one (1) at the inlet and one (1) at the center of the exhaust frame. All bearings are pressure
lubricated by oil supplied from the main lubrication oil system. The number 1 bearing (journal and thrust) is
accessed by removing the top half of the compressor inlet casing. The number 2 bearing is readily accessible
through the tunnel along the centerline of the exhaust diffuser. (Removal of the turbine casing is not required
for bearing maintenance.) Bearing protection includes vibration sensors and drain oil temperature
thermocouples.
1.6 COMBUSTION
1.6.1 Combustion System
The combustion system uses a reverse flow, multi-chamber (can annular) design in which combustion
chambers are arranged around the periphery of the compressor discharge casing. Combustion chambers are
connected to adjacent chambers by crossfire tubes as illustrated below.
Each chamber contains fuel nozzles and a combustion liner. Specific chambers may also contain spark plugs
or flame detectors. Transition pieces connect the combustion liners to the turbine nozzles. Each combustion
liner, fuel nozzle, and transition piece may be individually replaced if needed for maintenance.
1.6.6 Fuel flow to the six (6) fuel nozzles and quaternary pegs is controlled by independent control valves, each
controlling flow split and unit load. The gas fuel system consists of the gas fuel stop/ratio valve, gas control
valve one (PM1), gas control valve two (PM2), gas control valve three (PM3), and gas control valve four
(Quat).
The stop/ratio valve (SVR) is designed to maintain a predetermined pressure at the inlet of the gas control
valves. Gas control valves one through four regulate the desired gas fuel flow delivered to the turbine in
response to the command signal fuel stoke reference (FSR) from the gas turbine control panel. The DLN 2.6
control system is designed to ratio FSR into a Flow Control Reference. The flow control philosophy is
performed in a cascading routine, scheduling a percentage flow reference for a particular valve, and driving
the remainder of the percentage to the next valve reference parenthetically downstream in the control
software.
As the gas turbine progresses through the starting and loading sequences, the combustion system passes
through several combustion modes while operating on natural gas. Not all fuel nozzles in a combustion
chamber are used for every mode. For example, combustion mode 1 has gas flowing through only the PM 1
nozzle, while combustion mode 3 has gas flowing through the PM 1 and PM 2 nozzles.
The gas turbine, operating on gas fuel, achieves emissions compliance operation only while in combustion
mode 6.
Inlet bleed heating (IBH), through the use of recirculated compressor discharge airflow, is necessary when
operating with reduced IGV angles. Inlet heating protects the compressor from stall by relieving the
discharge pressure and by increasing the inlet air stream temperature. Other benefits include protection from
icing conditions resulting from the increased pressure drop across the IGVs when near the closing position.
The inlet bleed heat system regulates compressor discharge bleed flow through a control valve and into a
manifold located in the compressor inlet air stream. The control valve varies the inlet heating air flow as a
function of IGV angle. At minimum IGV angles the inlet bleed flow is controlled to a maximum of 5% of the
total compressor discharge flow. As the IGVs are opened at higher loads, the inlet bleed flow will
proportionally decrease until shut off.
The IBH control valve is monitored for its ability to track the command setpoint. If the valve command
setpoint differs from the actual valve position by a prescribed amount for a period of time, an alarm will
annunciate to warn the operator. If the condition persists for an additional amount of time, the inlet bleed heat
system will be tripped and the IGVs minimum reference will be raised to the default value.
The IBH system monitors the temperature rise in the compressor inlet airflow which serves as an indication
of bleed flow. Failure to detect a sufficient temperature rise in a set amount of time will cause the inlet bleed
heat system to be tripped and an alarm annunciated.
SECTION 2. AUXILIARY SYSTEM
1.6.13
2 AUXILIARY SYSTEM
2.1.1 General
The lubricating and hydraulic oil requirements for the 7FA gas turbine power plant are furnished by a
separate, enclosed, forced-feed lubrication module. This lubrication module, complete with tank, pumps,
coolers, filters, valves and various control and protection devices, furnishes oil to the gas turbine bearings,
generator bearings (absorbing the heat rejection load), starting means and load gear. This module is also
used to supply oil for the lift oil system, trip oil system and the hydrogen seals on the generator. Additionally,
a portion of the pressurized fluid is diverted and filtered again for use by hydraulic control devices as control
fluid.
The lubrication system is designed to supply filtered lubricant at the proper temperature and pressure for
operation of the turbine and its associated equipment. Refer to the Lube Oil Schematic Piping
Diagram(143E2201). Major system components include:
A Lubricant oil reservoir which serves as a base for the accessory module.
B Two centrifugal pumps (PQ1-1 and PQ1-2) each driven by an AC electrical motor (88QA-1 and 88QA-2).
Each AC motor includes a motor space heater (23QA-1 and -2) to prevent condensation in the motor.
D Seal oil pump (PQ3-1) driven by a “piggy- back” AC motor (88QS-1)/DC motor (88ES-1) driving one
pump. AC motor includes motor space heater (23QS-1).
F Two full flow lubricating oil filters in parallel (LF3-1 and LF3-2).
J Tank temperature thermocouples (LT-OT-3, LT-OT-4) for pump start permissive and immersion heater
control.
The oil is first pumped through one of the two parallel heat exchangers (LOHX-1 and LOHX-2). Each is
designed to maintain the oil at the proper bearing header temperature. The maximum allowable bearing
header temperature under normal operating conditions is 160°F (71.1°C). The oil then flows through one
of the two full flow parallel filters (LF3-1 and LF3-2). A three-way transfer valve controls selection of
which set of heat exchanger/filter is in use. The lubricant oil filters have removable filter elements. A
differential pressure gauge provides visual indication of the dP over the filter. Pressure switches (63QQ-21,
-22) provide a high differential pressure alarm signal across each filter. Filter elements should be
replaced near or at the alarm set point.
Taps (OL-11), (OH-1) and (OLT-1), which are located downstream of the filters, supply lube oil to the
generator bearing seals, hydraulic/lift oil system and trip oil system respectively. Pressure regulating valve
(VPR2-1) then controls the oil pressure to the turbine and generator bearings and the turning gear.
The system is ventilated through a mist eliminator mounted on top of the lube oil reservoir. A slight
negative pressure is maintained in the system by redundant motor driven fans (88QV-1A; FB1-1 and
88QV- 1B; FB2-1) pulling air through the mist eliminator. This negative pressure draws sealing air through
the gas turbine bearing seals. Each AC motor includes a motor space heater (23QV-2A and 23QV-2B) to
prevent condensation in the motor. The motor driven fans have no DC backup motors and are not required
to run in the emergency situation, when the DC pumps has taken over. The fans are set up to run in a
lead/lag configuration and are designed to run one at a time. The selection of lead and lag fans is made by
the operator through the turbine control system prior to startup. The lag fan takes over whenever the lead
fan has failed to run, has been overloaded or if there is insufficient vacuum in the lube oil reservoir. If the
lag fan is started automatically by the control system due to insufficient tank vacuum level, the lead fan
will be automatically shut off. Pressure switch (63QV-1) provides a low differential pressure alarm signal
when there is insufficient vacuum in the lube oil reservoir. A regulating valve is downstream of each fan,
and is adjusted to regulate tank vacuum level.
A level alarm device (float operated) is mounted on the top or side of the lube reservoir. The float
mechanism operates level switches (71QH-1, 71QL-1 and 71QL-2). The switches are connected into the
alarm circuit of the turbine control panel to initiate an alarm if the liquid level rises above, or falls below
the levels. The oil level is visually indicated by a gauge (QH-1) mounted on the top or side of the tank. An
oil drain connection is located on the side of the accessory module to drain the reservoir.
63QA-1A and 63QA-1B, trip the unit and start the emergency DC motor-driven pump (88QE-1) when they
sense low pressure. This will occur if AC power is lost. For a trip, one of the two 63QT switches and one
of the two 63QA switches must signal. This voting logic prevents a trip due to a false signal. The DC
Emergency Pump is designed to provide adequate lube oil circulation for coast down following a trip.
Once the unit is at rest, the DC pump should only operate a few minutes per hour, in order to remove heat,
but conserve battery life. If the bearing metal temperature is above 250ºF, the DC pump is run continuously.
The emergency pump is sized to clear the trip pressure switches (63QT-2A, - 2B), but will not clear the
alarm pressure level (63QA-1A, -1B). On dual fuel units with a single atomizing air compressor a pressure
switch (63QA-3) is provided at the oil supply to the air compressor gearbox. Two pressure switches
(63QA-3 and 4) are provided on dual fuel units with two atomizing air compressors. These pressure
switches will alarm if low pressure is sensed at those points but they will not start the lag pump.
The operation of the 63QA and 63QT switches can be verified by shutting off the normally open valve
between the switch and the oil system. When the normally closed valve to the oil drain is opened, the oil in
the switch lines will drain, the proper warning signal should annunciate and proper lag/emergency pump
start-up should occur.
Filter housings and heat exchangers are self-venting. A sight glass is located in the vent line from the filter
and heat exchanger. When the heat exchanger and filter housing are full, oil will be visible in this sight
glass.
By means of the manually-operated three-way transfer valve, one filter can be put into service as the
second is taken out, without interrupting the oil flow to the main lube oil header. The transfer of operation
from one filter to the other should be accomplished as follows:
1) Open the filler valve and fill the standby filter until a solid oil flow can be seen in the flow sight in the
filter vent pipe. This will indicate a “filled” condition.
2) Operate the transfer valve to bring the standby filter into service.
This procedure simultaneously brings the reserve heat exchanger into service.
NOTE
Only one heat exchanger is intended to be in service at one time. After transfer, the
operator must verify that the cooling water isolation butterfly valves to/from the heat
exchanger not in service are closed. Do not leave all four cooling water isolation valves
open.
E Seal Oil
The seal oil to the generator bearings is normally supplied by the lubricating system through a separate line
(tap OL-11) directly to the generator. In the event of low lube system pressure or lube system shut- down
for service, A seal oil pump supplies the oil required to seal in the generator hydrogen. Under normal
circumstances the AC motor driven pump (PQ3-1, 88QS-1) would serve this function; however, if this AC
motor should fail or if AC power is lost, the emergency DC motor (88ES-1) is activated and drives the seal
oil pump. The AC motor (88QS-1) includes a heater (23QS-1) to prevent condensation in the motor. The
seal oil pump circulates oil through filter (LF3-5). Differential pressure switch (63QQ-25) provides a high
differential pressure alarm signal across the filter. The filter element should be replaced near or at the
alarm set point
1) Pressure transmitter 96QH-1, which provides remote monitoring capability of bearing header pressure.
2) Pressure transmitter 96QL-1, which provides remote monitoring capability of tank oil level.
3) These transmitters are indication-only devices. They do not alarm or trip the machine in case of a
failure, low pressure, level etc.
2.2 STARTING SYSTEM
2) Isolation Transformer
4) Turning Gear
The turning gear provides the power necessary to breakaway and rotate the turbine prior to turbine start
and also to rotate the shafting after turbine shutdown to avoid deformation of its shafting.
The turning gear system consists of an induction motor, reduction gears, SSS clutch, electrical isolation,
and flexible coupling.
The turning gear will breakaway the turbine and slow roll at 5 to 7 rpm. In the event of power failure the
turning gear is equipped with a feature for manual turning of the rotor system.
Lubricating oil for the reduction gears is self–contained. Lubrication of the SSS clutch and output shaft
bearings requires continuous oil supply from the main lube oil system.
The SSS clutch is a positive tooth type overrunning clutch which is self-engaging in the breakaway or
turning mode and overruns whenever the turbine/generator shafting exceeds the turning gear drive speed.
The insulated flexible coupling allows for angular and parallel misalignment as well as allowing for
generator shaft axial expansion.
B Operation
On a start signal, the lube oil pump and hydraulic oil pumps are started to lift the stationary rotor off of the
bearing surfaces. The bearing pressure lift system must be operating prior to energizing the turning gear.
This significantly reduces the amount of starting and break–away torque required for the machines and
minimizes bearing damage during startup. Breakaway of the rotor system is accomplished by energizing
the turning gear induction motor. A double reduction worm gear reducer is furnished with a hollow shaft in
which the SSS clutch is mounted. Automatic engagement of the SSS clutch provides direct power
transmission to the rotor system. The turning gear will rotate the rotor system to 5 to 7 rpm. As the static
starter begins the starting sequence and accelerates the rotor the SSS clutch will automatically disengage
the turning gear from the turbine rotor.
The static starter will begin operation in the “pulsed” mode, changing to the “load commutated” mode as
soon as possible. The static starter will supply the variable frequency stator (armature) current required by
the generator to operate as a synchronous motor and drive the gas turbine. The static starter will control the
excitation system during static starting to regulate the field (rotor) current as required to maintain the
required flux and generator voltage. The static start system operates to accelerate the turbine to 25 to 30
percent of rated speed to purge the system for several minutes. At the end of the purge period the LCI
removes power from the generator allowing the unit to coast down to approximately 15% speed and the
turbine is fired and then accelerated to a self sustaining speed of about 90%. The static starter currents
will be reduced as required until the starting means is no longer required. After self sustaining speed is
accomplished the control system will load and synchronize the gas turbine generator. Operation of the
neutral ground and stator disconnect switches is automatically controlled during the starting process.
Upon turbine shutdown, as the turbine decelerates to below turning gear speed (5 to 7 rpm), the SSS clutch
engages if the turning motor is energized to provide slow roll rotor cool down. This cool down continues
until proper gas turbine wheel space temperatures drop to ambient.
In the event of a power outage when rotor turning is required, a manual turning assembly is provided to
turn the rotor. This manual turning feature can also be used for borescope inspection of the gas turbine.
The turning gear system is sized to provide breakaway of the shafting system with the bearing pressure lift
system operating on both the gas turbine and generator for manual and motor turning of the rotor train.
C Operating Precautions
* * * WARNING * * *
This equipment contains a potential hazard of electric shock or burn. Only personnel who
are adequately trained and thoroughly familiar with the equipment and the instructions
should install, operate, or maintain this equipment.
Isolation of test equipment from the equipment under test presents potential electrical
hazards. If the test equipment cannot be grounded to the equipment under test, the test
equipment’s case must be shielded to prevent contact by personnel.
2.3 HYDRAULIC AND LIFT OIL SYSTEM
2.3.1 General
The Gas Turbine Combined Hydraulic and Lift Oil system functions to provide fluid power required for
operating control components and to provide lift at the Gas Turbine and Generator bearings. The control
components include the Gas Valves (hydraulically actuated servo valves) and the Inlet Guide Vanes-IGV’s
(positioned by a hydraulic cylinder located on the turbine base).
The major components of the system include the pumps and motors, accumulator, filters, and valves
contained in the manifold assembly. This document will describe how the system normally operates.
2.3.2 CAUTION
Pressure relief valves should be periodically checked for proper operation
2.3.3
2.3.4 Lube Oil Supply
Bearing lift oil is used to raise the turbine-generator rotor onto a thin, static oil film at each journal bearing to
minimize rotation friction losses the gas turbine starting means or turning gear must overcome. Lift Oil
Supply Isolation Valve (20QB-1) is a solenoid-operated valve. When energized, high-pressure oil is allowed
to flow to each of the turbine-generator bearings. Each bearing is equipped with a flow-regulating valve to
keep lift oil supply flow rate constant. In addition, the lift oil supply lines at the bearings contain check valves
to prevent bearing feed oil from back flowing into lift oil supply lines. 20QB-1 has a manual override to be
used if the solenoid fails. There is also a sensing line connected from downstream of the solenoid to the
compensator block. When the solenoid is open, the sensing line is pressurized, thus selecting the high-pressure
setting. Bearing Lift Oil Supply Pressure Switch (63QB-1) provides an alarm in the turbine control
system if lift oil supply pressure is low, and will prevent the turning gear motor from starting should, there be
insufficient pressure.
2.3.5 Hydraulic Oil Supply
Hydraulic Supply pressure is required to actuate the gas valves and IGV’s,. Each pump circuit contains a
Hydraulic Oil Supply Pressure Regulating Valve (VPR4-3, VPR4-4). These pressure-regulating valves
maintain hydraulic pressure to hydraulic actuated components during normal operation, regardless of whether
the pump is operating at lift pressure or hydraulic pressure.
Hydraulic Discharge Oil Supply Pressure Switches (63HQ-1A, 63HQ-1B) are used to indicate if the lead
pump is not supplying enough pressure to the system. Should this be the case, the lag pump will be activated.
Hydraulic Supply Low Pressure Relief Valve (VR23-2) is provided to prevent over-pressurization of
hydraulic supply components in the event pressure regulating valves fail or are set incorrectly. Off of the
hydraulic oil supply header is a single Accumulator (AH1-1) that stores hydraulic fluid for use in transient
conditions (e.g. valve actuation). The accumulator is in service regardless of which pump is in operation. The
accumulator contains an isolation valve and flow control valve to control recharge rate. A Manual By pass
Valve allows the operator to quickly depressurize and drain hydraulic oil supply header. This is useful when
resetting pump compensators, relief valves, or pressure regulators. The bypass valve also serves as an
accumulator drain valve.
Pump is Fluid cleanliness issue Resolve fluid cleanliness issue via filter
contaminated element replacement or oil
conditioning.
Shoe slamming into Exceeding 10 psid case to Verify that suction line is sized
swashblock Rounded inlet differential pressure properly. Do not use suction strainers.
shoe edges Shoes
loose on balls Seal
retainer bent
Case not remaining Fluid being siphoned from case Use loop seal above top of pump
full of oil due to improper case drain line casing to keep case full.
routing
2.3.7
2.3.8
2.4 CONTROL AND TRIP OIL SYSTEM
2.4.1 General
The Gas Turbine Control and Protection Systems are operated by the SPEEDTRONIC control through
electro-hydraulic devices. This is done to provide the necessary actuation forces to operate the various
control and protection equipment located on the Gas Turbine and its associated accessory modules.
This equipment consists of the various fuel valves and the compressor’s variable inlet guide vanes. The
electro-hydraulic devices consist of servovalves, which act to modulate the final controlling element in
response to the operational requirements of the unit, and hydro-mechanical relays and solenoid operated
tripping valves, which act to interrupt the controlling action of the servovalves and trip the controlling
element in the event of a trip. Other components include pressure switches, hydraulic accumulators, check
valves, flow metering orifices, a manually operated trip valve and the hydraulic cylinders which position the
final elements.
This section will describe how this system operates the inlet guide vanes and the Gas Fuel System. A
schematic diagram of the Hydraulic Control and Trip System may be found in the Reference Drawings
section of this manual.
The five valves are operated by identical hydraulic systems although the control function of each is unique.
Each valve is operated by an electro-hydraulic servovalve, which acts to position the valve in response to the
position command from the SPEEDTRONIC control system. Each valve has position transducers to
provide a position feedback signal. These are shown on the gas fuel schematic diagram. High-pressure oil
passes through the filters to each of the servovalves. Between the stop and control servovalves and the
hydraulic cylinders is a hydro-mechanical trip relay - VH5-1 through VH5-5. When these relays are in the
run position, the servovalves are able to modulate the position of the valves. When these relays are in the
tripped position, one end of the cylinder is opened to drain, allowing the spring to quickly close the valve to
shut off gas fuel flow. The relays are operated by low-pressure trip oil and a trip solenoid valve (20FG-1),
which when energized, closes and allows the trip oil to build up pressure to move the relays to the run
position. In the event of a trip, 20FG-1 is de-energized, the relays move to the trip position, and the stop and
control valves are closed by their springs. The orifice in the trip oil supply is used to limit the flow into this
branch from the low pressure trip system when 20FG-1 is open. The pressure switches (63HG) are used to
signal the SPEEDTRONIC control system that the Gas Fuel hydraulic trip system branch has been tripped.
This is used in logic as a check to ensure reliability of the tripping system.
2.5 COOLING & SEALING AIR SYSTEM
2.5.1 General
The cooling and sealing air system provides the necessary air flow from the gas turbine compressor to other
parts of the gas turbine rotor and stator. These flows prevent excessive temperature buildup during normal
operation and prevent compressor pulsation. The system also has a Case Temperature Management (CTM)
Clearance Control System, which utilizes impingement air cooling to reduce and control the temperature of
the turbine casing at and around the area of the first turbine stage. The result of this cooling process is a
reduction in the nominal clearances between the tips of the turbine stage 1 blades (buckets) and their
associated casing shrouds. This reduction in clearance decreases the leakage past the blade tips, resulting in
improved turbine performance. In addition to reducing clearances, the impingement cooling process
decreases ovality of the turbine casing, which also improves performance. Activation and operation of the
system is limited to gas turbine loads above 60% of baseload operation.
The 7FA turbines have a vacuum-operated lubrication system. Therefore, the bearing sealing function of the
Cooling & Sealing Air System is not utilized. When the gas turbine is operating, air is extracted from the 9th
and 13th stages of the axial flow compressor as well as from the compressor discharge.
Atmospheric air from off-base, centrifugal-type, blowers is used to cool the turbine exhaust frame and No.2
bearing area.
The cooling and sealing air system consists of specially designed air passages in the turbine casing, turbine
nozzles, rotating wheels, and piping for the compressor extraction air and associated components.
Components used in the system include:
- Pressure switches for Turbine Exhaust Frame Cooling Blowers (63TK-1, -2)
- Limit switches for each VA2 valve 33CB-1, -2, -3, -4,-5,-6,-7,-8.
- Solenoid Valves 20CB-1, -2 (for actuation of air extraction valves)
- Case Temp. Management Blower Motor and Blower Motor Space Heater (88CM-1 & 23CM-1)
Refer to the cooling and sealing air schematic diagram MLI 0417 for further details.
- Exhaust frame and No. 2 bearing area cooling fan module subsystem
The 7FA is fitted with four pneumatically closing butterfly valves (VA2-1, -2, -3, -4) to bleed 9th and 13th
stage compressor air to the exhaust. These valves utilize a spring to open, so a failure in the actuation air
system will cause the valve to move to the open position, placing the compressor in a safe mode for
shutdown.
Customer supplied instrument air (controlled by solenoid valves 20CB-1,-2) is used to close the
compressor bleed valves. From each solenoid valve, the air is piped to the piston housings of 2 bleed
valves.
The 20CB solenoids are fitted with a breather vent which should be inspected as well to ensure that air can
freely flow from the “C” port of the solenoid to the atmosphere. If this breather is clogged, the valves will
not open in a timely manner, and the turbine may experience a trip.
During turbine startup, 20CB-1, -2, are not energized and the 9th and 13th stage bleed valves are open,
allowing air to be discharged into the exhaust plenum, thereby eliminating the possibility of compressor
pulsation. Limit switches, 33CB-1, -2, -3, -4, on the valves provide permissive logic in the starting
sequence and ensure that the bleed valves are fully opened before the turbine is fired. The switches also
provide an alarm if either valve opens when it is supposed to be closed. When the turbine accelerates to
full speed, the 20CB-1, -2, solenoid valves energize to close the bleed valves and allow normal running
operation of the turbine. Limit switches 33CB-5, -6, -7, and -8 are used to detect that the valves are
closed. When a turbine shutdown signal is initiated, the 20CB-1, -2 valves are de-energized, and
compressor air is again discharged into the exhaust plenum to prevent compressor pulsation during the
turbine deceleration period.
CAUTION
Under no circumstances should attempts be made to start the turbine if all bleed valves
are not fully opened. Serious damage to the gas turbine may occur if valves are not opened
during the accelerating and decelerating cycle of the turbine.
Although the bleed valves appear to be in a parallel redundant arrangement, they are not redundant.
Both valves are required to function to provide adequate pulsation protection.
The internal circuit is supplied by 17th stage and compressor discharge air, and the external circuit by 9th
and 13th-stage extraction air. The first stage nozzle and shroud cooling air is supplied from the compressor
discharge plenum housing the combustion transition pieces. The bucket cooling is supplied by air flowing
inward at the 17th-stage compressor wheel, then through holes drilled axially through the distance piece,
and then over the forward face of the first stage turbine wheel. The bucket cooling air then flows through
the bore of the first stage turbine wheel into the chamber between the first and second stage buckets.
This circuit also provides air to heat the bores of the second- and third stage wheels and to purge the wheel
spaces.
The external circuit consists of piping between the 9th and 13th-stage bleed piping and the turbine shell. A
two branch piping system is used to pipe the cooling air from the compressor 13th-stage to the stage 2
turbine shell. 9th stage compressor extraction is used to cool turbine stage 3.
This subsystem piping is shared with the compressor bleed subsystem to minimize piping quantity. In each
piping run to the second-stage nozzle, a witch-hat strainer is placed in the pipe to protect the small
impingement cooling holes within the vanes from clogging with dirt and scale. These witch-hat strainers
are removed after an initial break-in period. The orifice plates in the pipe runs to each nozzle control the
airflow throughout the piping system.
C Exhaust Frame and No. 2 Bearing Area Cooling Fan Module Subsystem
A cooling fan module consisting of four centrifugal blower-driven motors 88TK-1, -2 and 88BN-1, 2
provides airflow to the exhaust frame cooling manifold and the No. 2 bearing area. Each blower is sized to
provide 100 percent of the required flow for its respective cooling requirement. The motors are controlled
to operate in a lead-lag arrangement so that only one of each blower is operating when the gas turbine is
running. Each motor is equipped with a space heater, 23TK -1, -2 or 23BN-1, -2, for humidity control
during periods of shutdown.
Two of the blowers supply air for cooling of the exhaust frame and third aft wheel space. An inlet screen
is provided with each blower and the discharge of each passes through a diverter type check valve VCK7-1
before entering openings in the exhaust frame. The cooling air enters the exhaust frame through eight
radial nozzles on the outer annulus of the frame. The air cools the outer diameter of the outer exhaust gas
path insulation pack. Some of the cooling air exits the frame at the forward joint with the third stage
bucket shroud. The remainder flows aft, then turns, flowing through and cooling the radial support struts.
The air cools the inner diameter of the inner exhaust gas path insulation pack and exits the exhaust frame
through the third stage bucket aft wheel space. The cooling air also prevents exhaust gas from being
aspirated into the No. 2 bearing sump.
A similar arrangement of two blowers is used to provide cooling air to the No. 2 bearing area. These arc
equipped with inlet filters to remove dirt particles that could harm the bearing journal. Also, the discharge
of each passes through a diverter type check valve VCK7-3 before entering the main supply pipe to the No.
2 bearing area. This valve is required because of the lead-lag operation; otherwise the air from the
operating blower would escape through the non-operating blower, thereby bypassing the cooling circuit.
Pressure switches 63TK-l and -2 on the exhaust frame blowers, and 63BN-l and 63BN-2 on the No.2
bearing area blowers are used to sense each of the blower’s discharge pressure. If either blower or motor in
the operating set should fail, the loss of discharge pressure will cause contacts of the respective 63TK or
63BN pressure switch to close, sending a signal to start the idle set. If a second failure should occur, the
turbine will shut down in a normal shutdown sequence.
NOTE
Any failed blower or motor should be repaired or replaced as soon as possible to preclude
the possibility of shutting down the turbine as a result of a second failure.
The firing temperature is calculated from three inputs: the average thermocouple measured exhaust
temperature, the actual pressure ratio across the compressor, and mechanical parameters of the turbine.
If the 96CD compressor discharge pressure transducers and their associated electronics should fail, the
control system also permits the calculation of firing temperature based on exhaust temperature and the
actual fuel consumption.
The Blower Unit is furnished with a Filtration System at the inlet to the suction stack.
This min- imizes the erosion wear on the blower wheel, and prevents large particulate
from entering and potentially “plugging” the impingement cooling holes of CTM
manifolds. The Filters require periodic monitoring for cleaning or replacement. The
frequency is dependent on the cleanliness of the environment. In addition to the
filtration system, the blower suction stack also houses inlet Silencing Panels. This
silencing is provided to maintain the Blower’s acoustic levels be- low site specific limits.
The centrifugal blower is driven by a single speed 3-phase TEFC Motor (88CM-1).
Starting and stopping of the Blower is through the turbine control system. For 7F frames
a 120V Space Heater (23CM-1) is provided for the prevention of condensate in the motor
when the system is not in operation. Similarly on the 9F frames, a 220V, 50Hz space
heater is provided.
A backdraft damper/check valve is provided at the outlet of the skid. This remains closed
at all times when the Gas Turbine is not in operation and the turbine compartment
ventilation system is turned off. The function of the damper/check valve is to maintain
isolation of the turbine compartment during the release of CO2 following a fire detection
event.
5) System Operation
1. CTM System Start-Up
All control and operation of the Case Temperature Management (CTM) Clearance Control
Sys- tem is performed through the gas turbine control system. Initiation and operation of
the CTM system is limited to GT loads at or above approximately 60% of rated baseload.
Activation of the system can occur only when casing thermals (temperatures) achieve a
“steady state” condition. Internal casing temperatures are monitored by the sixteen
embedded thermocouples (TT-TC-1 to16), which are located directly below the CTM
manifolds. In general, steady state temperatures are achieved following 10 minutes of
constant load operation.
Once all permissives are cleared, an enable to START indication is provided on the
turbine con- trol system HMI screen. Starting of the system is a manual operation
performed by the control room operator. Casing temperatures and cooling air supply
pressure and temperatures should be monitored during system start-up.
During steady state gas turbine operation, the CTM system utilizes closed loop control to
maintain target stage 1 clearances. As cycle conditions change due to minor load or
ambient temperature variations, impingement cooling airflow is regulated by automatic
modulation of the case tem- perature management flow control valve/damper.
If, during CTM operation, there is a significant change in gas turbine load (step or ramp),
the CTM system will become disabled. Following this transient event, the Flow Control
Valve/Damper (20CM-1) is commanded to the minimum flow stroke position and is
maintained in “standby” mode. Once the load and casing temperatures are stabilized, as
sensed by the Embedded Casing Thermocouples (TT-TC-1 to 16), the system is re-
enabled. At this time the Operator is required to manually activate the system to achieve
clearance control operation.
The CTM system can be manually shut down at any time during normal steady state
operation, or while in “standby” mode following gas turbine transient/CTM disable event.
It is recommended, but not a requirement, to turn off the CTM system prior to unloading
the turbine in preparation for a gas turbine shut down.
The CTM controls includes the following Lockouts and Faults that will a automatically
disable or prevent activation of the system:
• Blower Fault
6) Technical Data
1. Maintaining System Performance Following GT Maintenance
Many CTM components will need to be removed during standard gas turbine maintenance.
These include the CTM Manifolds, On-Base Piping System and Embedded Casing
Thermocouples and associated conduit and wiring. It is critical that the following areas
are addressed when re-assembling the CTM system components following their removal:
a. CTM manifolds properly secured on the turbine casing with ¾” gaps maintained. All
integrated support/thermowell mounts shall be fully (thread engaged) in the casing and
leveling support nuts “snug” against the casing surface.
b. Embedded casing TC’s shall be inspected for damage prior to reinstallation. When
inserted, it shall be confirmed that the fittings are fully engaged in the support/thermowell
mount. Loop checks shall be performed on any TC’s removed and/or replaced.
c. The flexible metal ducting shall be inspected for damage that could impact airflow. If
dam- aged, the ducting section shall be replaced with new part. All T-bolt clamps used to
connect
The compressed air then reaches the pressure-regulating valve (VPR67-1), which automatically regulates the
flow for the set outlet pressure. This reduction in pressure also calls for a water drain mechanism downstream
either separate or integral with the dryer system. The two heatless dryers (34AD-1) are 2 X 100%. While one
is in operation the other will be on regenerative mode. This regenerative mode uses 15% of the total airflow.
The outcome of the process is air with pressure and temperature as required for the pulse cleaning of the Gas
Turbine inlet air filters. The outlet air exits the APU at purchaser connection AP-2. The two drain lines from
the APU exit the skid at purchaser connections AP-3 and AP-4.
2.6.8
2.6.9 System Level Maintenance Instruction
Refer Vendor document submittal, DIS 201 Operation & Maintenance manual<386A8401> for details.
2.6.10 System Level Trouble Shooting Instruction
Refer Vendor document submittal, DIS 201 Operation & Maintenance manual<386A8401> for details.
2.6.11 Additional Requirements
If the equipment is used in a manner not specified by the manufacturer the protection of the equipment may
be impaired.
2.7 COOLING WATER SYSTEM
2.7.1 General
The cooling water system is designed to accommodate the heat dissipation requirements of the lubricating oil
system, flame detector mounts, generator gas coolers, and the dual tower hydrogen gas dryer and the LCI
cooler. The components of the cooling water system are located on the accessory module, the gas turbine
base, the generator base, and where applicable, the LCI base and gas dryer module. Components include heat
exchangers (Plate and Frame/Shell and Tube), butterfly valves, orifices, ball valves, needle valves and
temperature regulating valves. Refer to the cooling water schematic (MLI 0420) for further details.
All devices are set to give proper temperature, pressure, and flow. The settings for these devices can be found
in the device summary for the corresponding system.
Customer supplied pipe and flow control means must be provided for interconnection of the subsystems.
Refer to GEI 41004 (Latest Revision) for cooling water recommendations for closed cooling systems and
GEK 28170 (Latest Revision) for open cooling systems.
2.7.2
2.7.3 Functional Description
A Accessory Module
1) Lubricating Oil System
The lubricating oil cooling system components consist of two heat exchangers (LOHX1 &
LOHX2), a temperature regulating valve (VA32-1) and butterfly valves. Two heat
exchangers are provided so that one is in operation cooling the lubricating oil while the
other one is being maintained. Only one of the heat exchangers is to be in service during
operation. The exchanger not in service must have the coolant return isolation butterfly
valve closed. Both supply and return isolation valves should not be closed for an extended
period of time on the inactive heat exchanger as this will then be an enclosed volume. In
an enclosed volume, any thermal fluid expansion could result in an external leak. A high
point vent and a low point drain are located on the pipeline.
To change from one heat exchanger to the other while the gas turbine is operating the
following steps are to be followed: 1) Open the lubricating oil fill valve and allow the heat
exchanger to fill with oil until flow is observed in the sight glass. 2) Open the closed
coolant isolation valve on the exchanger currently not in service. Coolant is now being
circulated through both heat exchangers. 3) Operate the oil transfer valve to direct the
total oil flow to the heat exchanger that will now be in service. 4) Close the coolant return
isolation valve on the exchanger with no oil flow.
exchanger and thus reducing the oil temperature. If the oil temperature out of the heat
exchanger is less than the setpoint, then the signal out of 90LT-1 will open the VA32-1
valve further in the B-R position, reducing the flow of coolant to the heat exchanger and
thus reducing the oiltemperature. On start up of the gas turbine, the valve is usually closed
to the heat exchanger and will open as the oil temperature reaches the control temperature
range. The Cooling Water Control Valve arrangement also includes a Pneumatic Pressure
Regulator (VPR64-2). An override crank is also provided on the valve to allow manual
control.
NOTE
At high ambient temperatures, valve VA32-1 may open to full flow to the heat
exchanger. At this point the maximum coolant flow rate exists and the oil
temperature may rise above the temperature control range of the valve. This is
acceptable as the heat exchangers and the system are designed to keep the oil
temperature from exceeding the high oil temperature limit under any site ambient
condition.
Due to the potential for hardware damage and fire, the turbine base (flame detector)
cooling water system components should be given the same importance as the fuel system
components. Regular walk-downs of the system will allow maintenance issues to be
identified and addressed early. Damage and/or leaks which compromise system operation
can be identified and repaired, which will help protect the unit from potential performance
reduction and hardware damage. When installing, replacing, and/or maintaining flame
detector cooling coils, ensure the edge of the Sheet Metal Band is not in contact with the
cooling tubes. This will ensure that no rubbing or fretting of the cooling tubes by the
band’s edge will occur during turbine operation. The torque value for the cooling coil
retainer must be 50 to 60 in. lbs (5.6 to 6.8 Nm).
3) Generator
The generator has five simplex hydrogen gas coolers mounted in the horizontal position.
Heat from the closed circuit gas stream is transferred to the coolant through them.
Isolation butterfly valves are provided on the coolant inlet and outlet of each gas cooler to
allow servicing of the coolers without draining the entire cooling water system. Under
normal operation, all five coolers must be valved into the cooling water system. Refer to
the generator operating instructions for cooler servicing during unit operation.
4) LCI
If the LCI cooler requires water for cooling during unit start up, then the cooling water is
also supplied to the LCI cooler (Load Commutated Inverter). The recommended piping
arrangement is for the cooling water to the LCI cooler to be piped in parallel with the
Generator coolers. If the LCIs are cross-connected the piping arrangement shall be in such
a way that the LCI that starts the unit gets the water for cooling.
NOTE
The gas module has lockable isolation valves in the instrument air and hydraulic oil
supply lines to facilitate Lock-out/Tag-out of these systems.
WARNING
***DANGER***
DO NOT ATTEMPT TO REMOVE THE ACTUATOR OF A VALVE UNLESS
THE VALVE IS IN THE FAIL SAFE POSITION AND THE SPRING IS
UNLOADED.
WARNING
WARNING
The sections to follow are based on normal operation and assumes that the instrument air, the
hydraulic oil, and the gas fuel are in accordance with their applicable GEIs and/or GEKs. If
contamination of these systems is suspected or a known issue exist, increased maintenance and
inspections may be required.
This Section Covers the major Gas Fuel System equipment. It is assumed that industry standards for
annual calibration and verification of pressure, temperature, and flow instrumentation will be
performed.
It is recommended that all seat and seal lapping be preformed by the orginal equipment supplier or a
facility approved by the orginal equipment supplier.
The following maintenance and inspections are recommended annually or during a Combustion Inspection,
whichever occurs first. The following recommendations are not in any particular order. Following a repair,
one or more of these recommendations may need to be performed again, in particular slew time and leak
tests.
1) Safety Shut Off Stop Valve (VS4-4)
It is important that a dial indicator be used to measure the shaft runout prior to and
following actuator mounting. The dial indicator shall be used to observe the shaft
runout as the valve is rotated from closed to open. The use of a dial indicator will
ensure that the actuator does not put excessive force on the valve bearings.
NOTE
It is important that a dial indicator be used to measure the shaft runout prior to and
following actuator mounting. The dial indicator shall be used to observe the shaft
runout as the valve is rotated from closed to open. The use of a dial indicator will
ensure that the actuator does not put excessive force on the valve bearings.
Refer to the Safety Shut Off Vent Valve Operations & Maintenance manual<394A5071> for
additional information regarding valve removal, installation, troubleshooting, inspection, and
refurbishment.
If the gas fuel strainer has signs of corrosion, tearing, or excessive debris this is indicative
of gas fuel that does not meet the cleanliness requirements of the applicable gas fuel
GEI/GEKs. The source of any corrosion, tearing, or debris should be identified and
removed prior to gas turbine operation.
It is important that a dial indicator be used to measure the shaft runout prior to and
following actuator mounting. The dial indicator shall be used to observe the shaft
runout as the valve is rotated from closed to open. The use of a dial indicator will
ensure that the actuator does not put excessive force on the valve bearings.
Refer to the Aux Stop Valve Operations & Maintenance manual<229A5100> for additional
information regarding valve removal, installation, troubleshooting, inspection, and refurbishment.
Refer to the Stop Ratio Valve Operations & Maintenance manual<229A5100> for
additional information regarding valve removal, installation, troubleshooting, inspection,
and refurbishment.
Changes in servo valve null bias, valve slew time, and valve dynamic response may be an
indication of hydraulic oil contamination or varnish. Refer to the applicable lube oil and
hydraulic oil GEK for additional information on contamination and varnish recognition
and mitigation. If contamination or varnish is a know site issue, a regular servo valve
replacement program is recommended.
Following any maintenance of the Stop Ratio Valve a LVDT calibration shall be
performed using the turbine control panel regulator calibration feature. If the site has
performance fuel heating it is recommend that a second calibration be performed at the
first hot restart.
Refer to the Gas Control Valve Operations & Maintenance manual<229A5102> for
additional information regarding valve removal, installation, troubleshooting, inspection,
and refurbishment instructions. Also, the Gas Control Valve Operations and Maintenance
manual contains refurbishment contact information. Following any maintenance of a Gas
Control Valve a LVDT calibration shall be performed using the turbine control panel
regulator calibration feature. If the site has performance fuel heating it is recommend that
a second calibration be performed at the first hot restart.
Refer to the Stop Ratio Valve Operations and Maintenance manual<229A5100> for
refurbishment contact information.
Refer to the Gas Control Valve Operations and Maintenance manual for refurbishment
contact information.
2.8.2 General
The Stop/Speed Ratio Valve (SRV) and the Gas Control Valves (GCVs) work in conjunction to regulate the
total fuel flow delivered to the gas turbine. This arrangement uses four separate Gas Control Valves to control
the distribution of the fuel flow to a multi-nozzle combustion system. (See Gas Fuel System schematic).
The GCVs control the desired fuel flow in response to a control system fuel command, Fuel Stroke Reference
(FSR). The response of the fuel flow to GCVs’ commands is made predictable by maintaining a
predetermined pressure upstream of the GCVs. The GCVs’ upstream pressure, P2, is controlled by
modulating the SRV based on turbine speed as a percentage of full speed, TNH, and feedback from the P2
pressure transducers, 96FG-2A, B, and C. Refer to the Gas Fuel System schematic.
In a Dry Low NOx 2.6 (DLN-2.6) combustion system there are four gas fuel system manifolds: Premix 1
(PM1), Premix 2 (PM2), Premix 3 (PM3), and Quarternary (Q). Each combustion chamber has a total of six
fuel nozzles. The PM1 gas fuel delivery system consists of one diffusion type fuel nozzle for each
combustion chamber. The PM2 gas fuel delivery system consists of two premix type fuel nozzles for each
combustion chamber. The Quarternary gas fuel delivery system consists of injection pegs located in each
combustion casing. The PM3 gas fuel delivery system consists of three premix type fuel nozzles for each
combustion chamber. The GCVs regulate the percentage of the total fuel flow delivered to each of the gas
fuel system manifolds.
The GCVs and SRV are actuated by hydraulic cylinders moving against spring loaded valve plugs. Three coil
servo valves are driven by electrical signals from the control system to regulate the hydraulic fluid in the
actuator cylinders. Redundant sensors in the form of Linear Variable Differential Transformers (LVDTs)
mounted on each valve provide the control system with valve position feedback for closed loop position
control.
A functional explanation of each part or subsystem is contained in subsequent paragraphs. For more detail on
the electro-hydraulic circuits see the SPEEDTRONIC* System text, Gas Fuel system schematics, and
Control Sequence Programs furnished to the site.
The control system’s fuel command, FSR, is the percentage of maximum fuel flow required by the control
system to maintain either speed, load, or another set-point. FSR is broken down into two parts which make
up the fuel split set-point, FSR1 and FSR2. FSR1 is the percentage of maximum fuel flow required from
the Liquid Fuel System and FSR2 is the percentage of maximum fuel flow required from the Gas Fuel
System. FSR2 is also broken down into four parts, FSRPM1, FSRPM2, FSRPM3 and FSRQT. FSRPM1 is
the percentage of FSR2 controlling the GCV1 gas fuel valve. FSRPM2 is the percentage of FSR2 to be
directed to the GCV2 gas fuel valves, and so on. FSRPM1is used as a reference to a servo amplifier which
drives the coils of GCV #1. FSRPM2 is used to drive the coils of GCV #2, and so on.
Each processor of the control system computes its own FSR2, FSRPM1, 2, 3 and FSRQT and each
processor drives one of the three servo valve coils. The GCVs’ position control loops function similarly to
the SRV’s position control loop.
The servo valves are furnished with a mechanical null offset bias which causes the GCVs or SRV to move
to the zero stroke position during a zero voltage input signal or an open circuiting of the servo valve coils.
During calibration, checks should be made to insure this feature is functioning properly.
The SRV and GCVs are equipped with hydraulically actuated spring return dump valves. The dump valves
are held in their normal operating state by a supply of hydraulic oil referred to as trip oil. The trip oil
system is triple redundant to ensure that no single device failure can disturb the operation of the power
generating unit.
It is this dc signal which is fed back and compared to FSR at the summing junction of an error amplifier in
the servo-driver circuitry. For stable control, the amplified error is properly proportioned to command the
integrating amplifier which drives the servovalve, 65GC. When the LVDT feedback equals the FSR input
signal the servo-drive amplifier summing junction is satisfied.
The Control Specifications give the correct position loop settings for a specific turbine.
E LVDT Oscillators
Excitation for each LVDT is provided by an oscillator in the SPEEDTRONIC*panel. The output of each
oscillator is 7.0 volts ac at a nominal frequency of 3000 Hz. The two oscillators, however, on the two
LVDTs can cause a beat frequency equal to the difference in the frequency of the two oscillators. Therefore,
one oscillator is set at 3200 Hz and the other oscillator is set at 2800 Hz to eliminate the effects of the beat
frequency in the same control loop.
The SRV and GCVs are equipped with hydraulic supply filters which have a high differential pressure
indicator for local indication.
While the SRV’s position control loop is considered an inner control loop, the pressure control loop is
considered an outer control loop. The control system computes a P2 pressure command, FPRGOUT. This
command is a linear function of TNH. Three pressure transducers are used to sense the intervalve pressure,
P2. Each channel of the control system computes its own FPRGOUT and each is wired to a single pressure
transducer. The pressure transducers are used to determine the error between desired P2 pressure,
FPRGOUT and actual P2 pressure. The resulting error is scaled through an integration algorithm which
uses the current gas FSR command, FSR2, to compute a valve position command. Two LVDTs sense SRV
stem position and their outputs are returned to each channel of the control system. The control system
selects the largest feedback signal in determining the error between desired SRV valve position command
and actual valve position. The error then becomes the input to the servo amplifier which drives the servo
valve in the direction required to decrease the position error.
The following conditions must be satisfied before the SRV can be opened: (Either a transfer to Gas fuel
must be occurring OR a 100% Liquid fuel split set-point must not exist) AND (the masterprotective circuit
must be enabled) AND (the Gas Fuel System purge valve(s) must be closed) AND (either flame detection
control must be enabled OR the ignition permissive circuit must be enabled).
The SRV will be closed automatically on flame failure, failure to ignite on start-up, or actuation of the fire
detection equipment. Following a unit trip the master protective and ignition permissive circuits are used
to prohibit starting until the conditions are acceptable.
In the event of an emergency trip or normal shutdown a negative P2 pressure is commanded by FPRGOUT.
This negative command drives the SRV servo valve into negative saturation and quickly closes the SRV.
However, in these situations the dumping of hydraulic fluid from the SRV actuator cylinder will allow the
SRV return spring to close the valve well before the servo valve can empty the cylinder.
H Valve Malfunction Alarms
In addition to being displayed, the feedback signals and the control signals of all valves are compared to
normal operating limits, and if they should go outside of these limits, there will be an alarm. The following
are typical alarms:
1. Loss of feedback.
2. Valve is open prior to permissive to open.
3. Loss of servo current signal.
4. P2 pressure (96FG) is zero during operation.
5. Valve not following command.
The servovalves are furnished with a mechanical null offset bias to cause the gas control valve or speed
ratio valve to go to the zero stroke position (fail safe condition) should the servovalve coil signals or power
be lost. During a trip or no run condition, a positive voltage bias is placed on the servo coils holding them
in the position calling for valve closed.
A diode is connected across the output of the transducer. This prevents any possibility of a spurious signal
driving the transducer amplifier negative, out of its normal operating range.
The transducer is factory adjusted and calibrated. Field calibration can be verified, however the
transducer´s zero and span are not adjustable.
J Gas Strainer
A strainer is provided in the fuel gas supply lines upstream of the stop/speed/ratio valve. The purpose of
the strainer is to stop foreign objects or materials that were not captured by the fuel gas conditioning
system from entering the fuel control and combustion system. The strainer utilizes a differential pressure
switch 63FGD-1 along with a differential pressure gauge installed across the strainer to monitor blockage.
The pressure switch or transducer initiates an alarm to the turbine control panel if the gas differential
pressure increases beyond a specified setting.
During operation the strainer differential pressure should be closely monitored. If an alarm is registered the
strainer should be inspected and if required cleaned. All strainer maintenance shall be performed in
accordance with the manufactures recommendations. Each strainer is equipped with a lockable vent valve
that vents to FG2, see MLI 0422 for additional information on location of strainer vent valve and
instructions for venting the fuel gas to a safe area.
Prior to strainer maintenance the upstream and downstream pressure shall be zero. To determine the down
stream pressure, utilize both pressure gauge FG-1 and pressure transducer 96FG-1. The upstream pressure
can be verified by using the differential pressure gauge FG-3 and differential pressure switch 63FGD-1 or
transmitter 96FGD-1. When using the differential pressure gauge/switch/transmitter to determine that the
upstream pressure is zero the downstream pressure shall be zero; the sensing lines to the differential
devices shall be open; and the pressure equalizer valve shall be closed.
K Pressure Gauges
One differential pressure gauge (PDI-FG-3) measures the difference between the inlet and outlet pressures
of the gas strainer.
Three pressure gauges, with hand valves, are installed in the fuel gas supply line. The upstream pressure
gauge (PI-FG-1) measures the pressure of the gas entering the stop/speed ratio valve; the intermediate
pressure gauge (PI-FG-2) measures P2 pressure ahead of the gas control valve; and the downstream gauges
(PI-PM-1, PI-PM-2, PI-PM-3, PI-Q) measures the pressure as the gas leaves the gas control valve.
The vent is open when the turbine is shut down because the stop/speed ratio and gas control valves have
metal plugs and metal seats and therefore, are not leak tight. The vent insures that during the shutdown
period, fuel gas pressure will not build up between the stop/speed ratio and gas control valves, and that no
fuel gas will leak past the closed gas control valve to collect in the combustors or exhaust.
If the vent valve fails during normal operation the SRV will continue to maintain constant pressure, P2.
This is accomplished by opening further, making up any lost flow through the vent valve.
The meter measure mass flow by taking advantage of the Coriolis Effect; the inertial effects that arise as a
fluid flows through a tube are directly proportional to the mass flow of the fluid. In a Coriolis flowmeter,
vibration is induced in the process-fluid-filled flow tube(s), then the mass flowrate is captured by
measuring the difference in the phase of vibration between one end of the flow tube and the other. The
flowrate is transmitted via flow transmitter 96FM-4.
Figure 1. Gas Control Valve Control Schematic
The fire protection system is comprised of a distribution system of piping for the delivery of CO2 from a low
pressure storage tank to the required gas turbine compartments in the event of a fire. This low pressure
storage tank is located on an off-base skid and maintains saturated liquid carbon dioxide at a storage pressure
of 300 psig (21.09 kg/cm2 or 2069 kPa) at 0°F (-18°C) by means of a refrigeration compressor.
The compressor is sized to keep the CO2 tank properly refrigerated to maintain the CO2 at the proper
pressure. If the pressure cannot be maintained by the refrigeration compressor, the CO2 tank is equipped with
a bleeder valve to release a small amount of CO2. This will act to lower the tank pressure and autorefrigerate
the CO2. A full port safety relief valve is fitted to the tank and will relieve pressure in the unlikely event than
the CO2 pressure continues to rise above the bleeder valve setpoint.
The CO2 tank supplier’s manual provides more information, and should be consulted for specific details.
The fire protection system control panel is usually mounted on the off-base skid (or in the turbine control
room if customer requested). The interconnecting field piping, which is usually supplied by the installer,
delivers the CO2 from the off-base skid to the gas turbine compartments, where it connects to the on-base
piping that distributes the CO2 into the compartments through nozzle orifices.
Two separate distribution systems are used: an initial discharge and an extended discharge. Within a few
seconds after actuation, sufficient CO2 flows from the initial discharge system into the gas turbine
compartments to rapidly build up an extinguishing concentration. A CO2 concentration is then maintained by
the gradual addition of more CO2 from the extended discharge system, compensating for compartment
leakage.
Carbon Dioxide flow rate is controlled by the size of the orifices in the discharge nozzles in each
compartment for both the initial and extended discharge systems. The orifices for the initial discharge system
are large, permitting the rapid discharge of CO2 to quickly obtain the extinguishing concentration mentioned
above. Orifices for the extended discharge system are smaller and permit a relatively slow discharge rate to
maintain an extinguishing concentration over a prolonged period of time (based on the turbine frame size’s
emergency roll down and cool down periods) to minimize the likelihood of a fire reigniting.
2.9.3 NOTE
It is important that a dial indicator be used to measure the shaft runout prior to and
following actuator mounting. The dial indicator shall be used to observe the shaft
runout as the valve is rotated from closed to open. The use of a dial indicator will
ensure that the actuator does not put excessive force on the valve bearings.
2.9.4 The unit has multiple zones of fire protection, with each zone consisting of an initial and an extended
discharge. This allows each zone to act independently of the other; a fire in one zone will not initiate a
discharge of CO2 in the other zones.
Protection/detection is achieved by using separate “A” and “B” loops of heat-sensitive fire detectors. Each
fire detector is wired into the fire protection control panel in such a way that a single detector will initiate the
alarms. However, a signal from both an “A-loop” and a “B-loop detector is required to initiate a CO2
discharge. Strobes and horns, as well as CO2 warning signs, are strategically positioned on the outside and/or
inside of the appropriate compartments to warn personnel of detected fires/CO2 discharges. Should a fire
occur in one of the protected compartments, the contacts of the heat sensitive fire detectors will close and
complete an electrical circuit that signals a pre-discharge sequence. The sequence includes starting an
electronic pre-discharge timer and charging a pneumatic timer (both are typically factory set for 30 seconds,
but are field adjustable to be set according to each site's specific egress time from each compartment). The
pneumatic sirens located in each zone annunciate during the time that the pneumatic timer operates to
provide an audible warning for anyone inside the compartment. The electronic strobe/horns also continue to
annunciate during this pre-discharge time.
After the pneumatic pre-discharge timer expires, CO2 pressure is directed to the correct pressure operated
valves on the tank's manifold. These valves then open and release CO2 into the inital and extended
interconnect piping for the particular compartment that is on fire. The system may also be manually actuated
by means of the manual toggle switches (43MRFP-x devices) located on the outside of the Electrical Control
Cabinet. If customer requested, there may also be manualrelease switches mounted on the enclosure external
walls of the protected zones. These devices, which will normally have 43MR nomenclature (refer to the
system schematic), are equipped with a pin which must be pulled before the pushbutton can be depressed to
activate the system and discharge the CO2. Actuation of the system, either automatically or manually, will
trip the turbine to shut down, shut off the ventilation system, trigger the electronic and pneumatic pre-charge
timers (beginning the sequence described above).
For the purpose of maintenance on the fire protection system or the gas turbine itself, the accidental discharge
of CO2 can be prevented by closing the main shut off valve/limit switch (33FP-1A) located on top of the
storage tank and by closing the ball valve/limit switch (33FP-2A) on the Pilot Vapor Line. If customer
requested, there may also be manual lockout valves/limit switches (which will normally have 33FP.X
nomenclature) mounted in the interconnect piping near the protected zones for remote lockout of CO2
discharge.
Initial and extended discharge timers, 2FP devices, are located in the electrical control cabinet and control the
length of time the solenoid valves are energized and thus the CO2 discharge time (these times are factory set
- refer to MLI 0426 for the specific times). After CO2 discharge, these timers must be reset by depressing the
timer reset buttons (62FP devices) located on the inside of the Electrical Control Cabinet (this will also serve
to shut off the alarms).
2.9.5 CAUTION
WARNING
2.9.6 To put the turbine in a safe condition upon detection of a fire, the following contacts provide signals to the
turbine motor control centers and/or turbine control panel to trip the unit prior to CO2 discharge. Each
protected zone is equipped with a contact (94F-xA) which is wired to the MCC to trip the ventilation system
prior to CO2 discharge. Each zone is also equipped with a contact (94F-xB) that is wired to the Turbine
Control Panel to trip the turbine prior to CO2 discharge. Finally, pressure switches are located in the pilot line
for each zone (63FP-xA devices). These switches sense when CO2 pressure isintroduced to the selector valve,
and they send a signal to the MCC to trip the ventilation and turbine operation upon CO2 release. This would
be considered a backup to the other contacts listed above. 33FP-1A, 33FP-2A, and 63FP-1D comprise the
supervisory circuit. If any of these switches sense the unit is not ready, contact 30FP-3A is a customer contact
which will change state to annunciate a “not-ready” condition. This would indicate that the CO2 tank has
been locked out. 30FP-1B is the same signal as 30FP-3A, but is wired to the turbine control panel.
Contact 30FP-2A is the trouble contact for customer use. This contact will change states if there is a problem
with any of the monitored devices, including: loss of AC power, short/open in a supervised circuit (heat
detectors, strobe/horns), ground fault, tank pressure, pilot solenoid circuit, tank pressure, refrigeration system,
etc. This contact annunciates a “fault condition” in the system, and action must be taken to remedy the fault.
30FP-1A is the same signal as 30FP-2A, but is wired to the turbine control panel.
The CO2 concentration test should be conducted per Fire Protections System Discharge Test Instructions
2.9.10 (MLI0113, 372A2460) and as follows:
1. Inspect the ventilation dampers in the accessory, turbine, load, and/or any additional compartments that are
being protected by CO2. They should all be latched in the OPEN position for the dampers that have CO2
operated latches.
2. Check to make sure the predischarge timers that are located in the control panel are set for the suggested
30 second time delay to allow personnel time to evacuate the compartment before CO2 is released. The
predischarge timers can be changed in the field if a different time delay is required. Z
3. Check to make sure all compartments protected by CO2 (except the bearing area where applicable) have a
minimum of two external CO2 warning signs applied, one on of each side of each compartment for personnel
warning.
4. Clear all personnel from the compartments and close all compartment doors. At this time, any obvious
cracks or leaks in the lagging should be sealed to ensure compartment integrity.
5. Initiate the release of the CO2 by electrical means within the fire protection control panel: for LP CO2
systems, toggle the control panel release switches to begin release of the CO2. Each zone should be tested
separately for both the initial and extended discharge. Upon initiating release of the CO2, the fire alarm
strobes and horns in the accessory compartment and in any other compartments should be activated and be
clearly heard. During the test, inspect the outside of each compartment to see if quantities of CO2 are leaking
out of cracks in the lagging, meaning compartment integrity has not yet been achieved.
6. After the CO2 discharge has stopped, the applicable switches should be reset. A compartment inspection
should be carried out to verify that all ventilation dampers have functioned properly. Once this operation has
been performed, the dampers should be reset to the OPEN position.
7. Upon successful completion of the CO2 concentration test, G.E. Design Engineering should be consulted
and the results of the concentration test should be sent to the appropriate design engineer for design
documentation purposes.
2.9.11 WARNING
CARBON DIOXIDE, IN A CONCENTRATION SUFFICIENT TO
EXTINGUISH FIRE, CREATES AN ATMOSPHERE THAT WILL NOT
SUPPORT LIFE. IT IS EXTREMELY HAZARDOUS TO ENTER THE
COMPARTMENTS AFTER THE CO2 SYSTEM HAS BEEN DISCHARGED.
ANYONE RENDERED UNCONSCIOUS BY CO2 SHOULD BE RESCUED AS
QUICKLY AS POSSIBLE AND RESUSCITATED IMMEDIATELY. IT IS
ESSENTIAL THAT PERSONNEL BE ADEQUATELY TRAINED AS TO THE
PROPER ACTION TO TAKE IN CASE OF SUCH AN EMERGENCY.
2.10.1 General
The Compressor Inlet Bleed Heating system recirculates a fraction of the hot compressor discharge airflow
into the compressor inlet Figure 1 is a top level summary diagram of the system. The system is used for the
following three main purposes:
1. To prevent conditions necessary for the formation of ice on the first stage stator blades
2. To extend emissions compliance to lower loads by allowing exhaust temperature control to occur at lower
inlet guide vane angles.
3. To provide sufficient compressor operating margin by reducing the compressor pressure ratio and by
heating the compressor inlet air. Gas turbine range may be restricted for cold compressor inlet temperatures
in order to protect the gas turbine compressor from exceeding its operating limit and/or inlet ice buildup. Gas
turbines that operate with the inlet guide vanes at restricted angles at low ambient temperatures are prone to
inlet ice formation and reduced compressor operating limit. With such designs, inlet heating becomes
necessary to guarantee full gas turbine operating range.
2. Inlet Bleed Heat Control Valve assembly (VA20-1) is a electrically actuated control valve. The following
components are mounted on the control valve:
a. Two inlet bleed heat quick exhauster valves (VA42-1, -5) alongwith associated needle valves which are
adjusted for quick exhaust valves.
b. Trip solenoid valve (20TH-1).
c. LVDT (96TH-1) for IBH Control Valve (VA20-1) position feedback.
3. Pressure transducer (96BH-1) measures the pressure upstream and similarly pressure transducer (96BH-2)
measures the pressure downstream of the inlet bleed heat control valve (VA20-1). These pressure transducers,
along with IBH control valve position and compressor discharge temperature, are used to compute inlet bleed
heat flow.
4. Pressure Regulator (VPR41-1) which has Instrument Air I/P from Turbine Inlet air heating control valve.
5. Electro-pneumatic transducer (65EP-3).
6. The Mark*1 VI VSVO Servo Board provides closed loop position control of the IBH valve.
2.10.3 OPERATION
For emissions turndown and compressor first stage icing prevention the amount of inlet bleed heat in terms of
percent compressor airflow is scheduled as a function of Inlet Guide Vane (IGV) angle.
GE gas turbine compressors are designed to operate below a compressor pressure ratio limit (CPRLIM) that
is a function of inlet guide vane angle (IGV) and temperature corrected rotor speed (TNHCOR).
Combinations of factors such as extreme cold ambient temperatures, low IGV angles, high combustion
reference temperature, low BTU gas fuel composition, online water wash, gas to liquid fuel transfers, and
high combustor diluent injection can cause the Mark* VIe controller to increase inlet bleed heat flow in order
to provide sufficient compressor operating margin.
The fail-safe position of the inlet bleed heat control valve (VA20-1) is the full open position. The valve will
fail open upon loss of electrical command signal to the servovalve.
The inlet bleed heat control valve (VA20-1) is tripped open by the Mark* VIe controller via the trip solenoid
(20TH-1) by means of electrical actuation. The IBH control valve is tripped open given one of the following
conditions:
1. The valve position feedback signal fails to follow command within a specified tolerance for greater than a
specified length of time.
2. The compressor pressure ratio (CPR) exceeds a maximum allowable limit (CPRLIM) for greater than a
specified length of time.
3. Ambient pressure (AFPAP) is above a high limit. The two alarms associated with the inlet bleed heat
system are ‘IBH CONTROL VALVE NOT TRACKING’ and ‘IBH PRESSURE TRANSDUCER FAULT’.
2.10.4
Figure 1. Top Level Summary Diagram
2.11.1 General
Heating and ventilation capabilities have been incorporated into the turbine compartment, accessory
compartment gas fuel region, accessory compartment lube and hydraulic oil region and load shaft
compartment. The purposes for ventilating the compartments are to dissipate heat generated inside the
compartment and to dilute any minor hazardous gas leakage. Each compartment is constructed with thermally
insulated side panels and roofs. The compartments are ventilated as shown in the schematic diagram in the
Reference Drawing section of this service manual.
Gravity operated inlet dampers and CO2 latched outlet dampers as shown on the reference schematic are
used in the system to automatically provide a tight enclosure when the fire protection system is activated. The
CO2 latched outlet dampers are normally held open by fire extinguishing agent pressure operated latches that
must be manually reset after damper release. When the agent is discharged, pressure on the latch forces a
piston against a spring, moving a locking lever that releases the latch allowing the damper to close.
2.11.2 NOTE
It is imperative that all Turbine Enclosure access doors remain closed during
operation of the compartment ventilation system. Operation of the compartment
ventilation system with any access door open could compromise the effectiveness of
the ventilation system and adversely affect safety systems such as hazardous gas
detection and CO2 fire protection systems.
The turbine compartment ventilation fan ventilates the gas fuel module region of the accessory
compartment. Ventilation air enters the gas fuel module through gravity-operated dampers in the
compartment side panels and exits the module through an opening to the turbine compartment.
Heater 23VS-3 is provided for humidity control in the gas fuel module region of the accessory
compartment when the ventilation system is not operating. The heater is energized based on the readings of
thermocouples AT-VS1/2.
Heater 23VS-1 is provided for freeze protection in the gas fuel module region of the accessory
compartment when the ventilation system is not operating. The heater has its own motor-driven blower and
is energized based on the readings of thermocouples AT-VS-1/2.
The ventilation system for the lube and hydraulic oil region consists of a fan driven by AC motor, 88BL-1
and 88BL-2. The fans are mounted on the roof of the lube and hydraulic oil region of the accessory
compartment.
Ventilation air enters the lube and hydraulic oil region through gravity-operated dampers on the discharge
side of the ventilation fan. Air exits the compartment through a discharge opening in the compartment roof.
A CO2-actuated damper is located at compartment ventilation discharge. This damper is held in a
normally-open position by a latch that is released when the fire protection system is activated. The closure
of this discharge damper, the automatic shutoff of the fans, and subsequent closure of the gravity dampers,
seal the lube and hydraulic oil region in the event the fire suppression system is activated. In a lead-lag
system, the gravity-operated backdraft damper located on each fan prevents backflow through the standby
fan.
During normal operation, the ventilation fan starts automatically when the lube oil pumps are running and
will continue to run when the unit fires. The fans are operated in a lead-lag configuration and if the
selected “lead” fan fails to operate as sensed by pressure differential switch 63AT-3 or 63AT-4, the
“standby” fan will start. When the unit is not firing, operation of the ventilation fan is controlled by
thermocouples AT-HL-1/2 located in the lube oil and hydraulic oil region of the accessory compartment.
As noted below, the same thermocouples are also used for activation of the humidity control heater. The
fan and heater are interlocked by thermocouples AT-HL-1/2 so that both the fan and heater will not be
energized simultaneously.
For humidity control during periods of shutdown and internal condensation during periods of shutdown,
the fan motor is equipped with heater 23BL-1 and 23BL-2.
Heater 23HL-3 is provided for humidity control in the lube oil and hydraulic oil region of the accessory
module when the unit is not operating. The heater is energized based on the readings of thermocouples AT-
HL-1/2.
Heater 23HL-1 is provided for freeze protection in the lube oil and hydraulic oil region of the accessory
compartment when the unit is not operating. The heater has its own motor-driven blower and is energized
based on the readings of thermocouples AT-HL-1/2.
B Turbine Compartment
The ventilation system for the turbine compartment consists of a fan driven by AC motor, 88BT-1 and
88BT-2. The fans are mounted on the roof of the GT compartment.
Ventilation air enters the turbine compartment through gravity-operated dampers in the compartment side
panels and from the gas fuel module region of the accessory compartment as described above. Air exits the
compartment via a discharge opening and a CO2-actuated damper on the compartment roof, a gravity
actuated damper, and the ventilation fan.
The CO2-actuated damper is held in a normally-open position by a latch that is released when the fire
protection system is activated. The closure of this discharge damper, the automatic shutoff of the fans, and
subsequent closure of the gravity dampers, seal the turbine compartment in the event the fire suppression
system is activated. In a lead-lag system, the gravity-operated backdraft damper located on each fan
prevents backflow through the standby fan.
The turbine compartment vent fans provide heat dissipation from the enclosure as well as sufficient
dilution ventilation of any small hazardous gas leaks; large leaks will be detected by the hazardous gas
detectors and require appropriate action. During normal operation, the ventilation fan starts automatically
when the unit fires during startup. The system is operated in a lead-lag configuration and if the selected
“lead” fan fails to operate as sensed by pressure differential switches 63AT-1A/1B/1C or 63AT-2A/2B/2C,
the “standby” fan will start.
Following a shutdown, thermocouples AT-TC-1/2, located in the turbine compartment, control the
operation of the fan, causing it to start when the temperature exceeds the high temperature set point and
causing it to stop when the compartment temperature drops below the reset setting. Thermocouples AT-TC-
1/2 will cause an alarm to occur if the turbine compartment temperature exceeds the high temperature
alarm setting.
For humidity control during periods of shutdown, the turbine compartment fan motor is equipped with
heater 23BT-1 and 23BT-2.
Heater 23HT-3A and 23HT-3B are provided for humidity control in the turbine compartment when the unit
is not operating. The heaters are energized based on the readings of thermocouples AT-TC-3/4.
Thermocouples AT-TC-3/4 are located in the turbine compartment below the gas turbine.
Heaters 23HT-1A/ 1B are provided for freeze protection in the turbine compartment when the unit is not
operating. The heaters have their own motor-driven fans (88HT-1A and 88HT-1B) and are energized based
on the readings of the thermocouples AT-TC-3/4.
Thermocouples AT-TC-3/4 will also cause an alarm to occur if the turbine compartment temperature drops
below the low temperature alarm setting to indicate the failure of the turbine compartment heaters.
Ventilation air enters the load shaft compartment through gravity-operated dampers on the discharge side
of the ventilation fan. Air exits the compartment through a discharge opening in the compartment roof. In
case of a compartment fire, the fan motor stops and the gravity damper close. In a lead-lag system, the
gravity-operated backdraft damper located on each fan prevents backflow through the standby fan.
The load compartment vent fans provide satisfactory heat dissipation from the enclosure as well as
sufficient dilution ventilation of any potential risk associated with close proximity to the hydrogen-cooled
generator. The load compartment ventilation system operates whenever the turbine is above turning gear
speed or when the hydrogen-cooled generator is pressurized. The fans are operated in a lead-lag
configuration and if the selected “lead” fan fails to operate as sensed by pressure differential switches
63AG-1A/1B/1C or 63AG-2A/2B/2C, the “standby” fan will start.
For humidity control during periods of shutdown, the load shaft compartment fan motor is equipped with
heater 23VG-1 and 23VG-2.
B Off–Base Equipment
The off-base portion of the water wash system, known as the water wash skid, contains both a watertank
and a detergent tank. The water tank is equipped with temperature sensors and electric heaters to maintain
proper water temperatures. The skid is equipped with a centrifugal water pump motor (88TW-1) and a
venturi used with the water pump to mix detergent solution. Also included on the skid are the various
control panels to initiate wash and to manually start/stop the appropriate devices. All equipment is made of
corrosion resistant material. Refer to the Water Wash Skid schematic for this on-base equipment.
All devices are set to give proper temperature, pressure, and flow. The settings for these devices can be
found in the device summary for the corresponding system.
C Functional Description
During the washing operation, water or wash solution is delivered through customer piping to the gas
turbine in the proper mix ratio. The wash water solution is delivered to the turbine unit at the proper
pressure, temperature, and flow rate to wash the gas turbine compressor. Refer to the system schematic for
proper pressure(s), temperature(s), and flow rate(s) for this gas turbine.
1) System Requirements
Water used for washing turbine parts should be reasonably clean so that it does not cause
fouling or corrosion in itself. Distilled or deionized water is recommended. Water quality
requirements are listed in Table 1 of GEK-111895 (Latest Revision). Oily or varnished oil
deposits on internal gas turbine parts require that a detergent solution be used during the
washing operation. The detergent shall meet the requirements of GEK-111895 (Latest
Revision), Appendix 1.
NOTE
It is imperative that all Turbine Enclosure access doors remain closed during
operation of the compartment ventilation system. Operation of the compartment
ventilation system with any access door open could compromise the effectiveness of
the ventilation system and adversely affect safety systems such as hazardous gas
detection and CO2 fire protection systems.
D System Operation
1) General
a. Off-line Water Wash
Off-line water washing should be scheduled during a normal shutdown, if possible. This
will allow enough time for the internal machine temperature to drop to the required levels
for the washing. The time required to cool the machine can be shortened by maintaining
the unit at crank speed. During this cooling of the turbine, the wash water may be heated
to the proper level.
Off-line wash water flow control is accomplished through a manual tuning valve installed
in the off-line supply line, and a local pressure gauge to allow the operator to set the
specified manifold supply pressure.
Refer to the system (MLI 0442) schematic for off-line wash operating parameters.
Refer to GEK-111895 (Latest Revision) for gas turbine compressor liquid washing
recommendations
The on–line compressor wash system allows an operator to water wash the turbine
compressor without having to shut down the turbine. The method of washing is similar in
many ways to the off–line system. Both systems use the same pump, 88TW-1, and piping
to supply high quality wash solution to the compressor. When the supply pipe reaches the
vicinity of the turbine base, it splits into two branches, one for the off–line system and one
for the on–line system. Each branch contains a stop valve, flow control orifice, manifold(s)
and spray nozzles.
There are significant differences, though, between the two systems. GE recommends
against the use of detergents during on-line washing, while the use of detergents during
off-line washing are encouraged. The on–line wash water requirements differ from that of
off–line wash solution and must meet the requirements of Table 1 of GEK-111895 (Latest
Revision) for on–line washing. Finally, the on–line system proceeds automatically after it
is manually initiated; whereas, the off–line system requires operator intervention before
and after the wash.
Per the latest on-line wash design improvements, the forward on-line wash manifold has
been removed to minimize the risk of blade root erosion. Therefore, only the outer, aft,
manifold is used during an on-line wash.
Also, the on-line flow control orifice plate has been replaced with a pressure regulator
(VPR74-1). A local pressure gauge is installed on the on-line circuit to make it easy for
the operator to set the specified manifold supply pressure for improved flow control. In
addition, a pressure transducer (96WW-3) is installed on the on-line aft manifold to
measure wash water pressure relative to ambient pressure. This transducer is wired to the
control system to monitor on-line wash water supply pressure.
Refer to the system (MLI 0442) schematic and the device summary for on-line wash
operating parameters and instrument settings and ratings.
NOTE
When using a detergent solution for on line washing, it is
recommended that the wash be followed by enough rinse water to
remove the detergent residue from the wash nozzles at the spray
manifold. This will prevent the detergent solutions from drying and
clogging the nozzles.
Several grid codes specify that at specific frequencies below normal, such as 50 Hz, power
delivered to the grid must meet or exceed a minimum power level. At very low grid frequencies,
water wash injection is used to reduce the net over firing of the gas turbine to conserve hot section
life.
For a GFC installation, the following components are added to on base piping (MLI 0953):
GFC control valve (VA16-4), manual tuning valve, GFC supply line pressure transducer (96WW-
4), GFC water manifold and nozzles with injection on inner cone of inlet plenum (MLI 1612).
The turbine control includes GFC software (MLI 210) to actuate control valves during an under
frequency event and perform a periodic self-test to verify that supply pressure to the GFC nozzles
exceeds the minimum allowable water pressure.
Refer to the system (MLI 0442) schematic and the device summary for GFC operating
parameters and instrument settings and ratings.
2) Mandatory Precautions
Before water washing of the compressor begins, the turbine blading temperature must be
low enough so that the water does not cause thermal shock.
CAUTION
The differential temperature between the washwater and the
interstage wheelspace temperature must not be greater than 120 F
(67 C) to prevent thermal shock to the hot gas parts. The maximum
wheelspace temperature as per TIL 1196-1 must be no greater than
150 F (65.5 C) as measured by the digital thermocouple readout
system on the turbine control panel.
To reduce this difference, the wash water may be heated and the turbine kept on crank until the
wheelspace temperatures drop to an acceptable level. The wheelspace temperatures are read in the
control room.
CAUTION
If, during operation, there has been an increase in exhaust
temperature spread above the normal 15 F to 30 F (8.3 C to
16.6 C), the thermocouples in the exhaust plenum should be
examined. If they are coated with ash, the ash should be removed.
Radiation shields should also be checked. If they are not radially
oriented relative to the turbine, they should be repositioned per
the appropriate drawing. If the thermocouples are coated with ash,
or if the radiation shields are not properly oriented, a correct
temperature reading will not be obtained.
If neither of the above conditions exists and there is no other explanation for the temperature
spread, consult the General Electric Service Engineering representative.
WARNING
THE WATER WASH OPERATION INVOLVES WATER UNDER
HIGH PRESSURE. CAUTION MUST BE EXERCISED TO ENSURE
THE PROPER POSITIONING OF ALL VALVES DURING THIS
OPERATION. SINCE THE WATER MAY ALSO BE HOT,
NECESSARY PRECAUTIONS SHOULD BE TAKEN IN HANDLING
VALVES, PIPES, AND POTENTIALLY HOT SURFACES.
NOTE
Before water washing the compressor, inspect the inlet plenum and
gas turbine
ellmouth for large accumulations of atmospheric contaminants that
could be washed into the compressor. The deposits can be removed by
washing with a garden hose.
2.13 GAS DETECTION SYSTEM
2.13.1 General
The gas protection system provides monitoring of the presence of combustible gas inside equipment areas for
protection of personnel and equipment. A brief description of the system’s overall purpose and peration is
provided below. For further details, refer to the gas protection schematic (MLI 0474), also called the
hazardous gas detection schematic, located in the Reference Drawings section of the Service Manuals.
Combustible gas detectors are placed in areas where combustible gases may be likely to be found in the
unlikely event of a gas release or leak:
• Gas turbine compartment, often near or inside the ventilation exhaust duct
• Fuel gas valve module, often near ventilation exhaust duct or air outlet
Secondly, the %LEL reading on a gas detector is a percentage of the LEL value. At 100%LEL, the minimum
level of gas to support ignition is present. Often, high alarms are set at 10%LEL or lower and high-high
alarms are set at 25%LEL or lower. This provides a safety margin and additional time before gas reaches
explosive concentrations. A common range for combustible gas detectors is from 0 to 100 %LEL Gas
detector readings may indicate higher or lower concentrations in other parts of the compartment. For example,
a 20% LEL reading in the extract duct may indicate that a 50% LEL cloud is present in an area inside the
compartment.
Other gas detectors may be provided for operator alarm only. These gas detectors will not be provided with
double or triple redundancy. When these detectors alarm, the operator will be alerted to the alarm on the
control system.
It is extremely important that gas turbine operators establish proper operating practices. We emphasize
adherence to the following:
• Respond to Annunciator Indicators—Investigate and correct the cause of the abnormal condition. This is
particularly true for the protection systems, such as low oil pressure, overtemperature, vibration, overspeed
etc.
• Check of Control Systems — After any type of control maintenance is completed, whether repair or
replacement of parts, functionally check control systems for proper operation. This should be done prior to
restart of the turbine. It should not be assumed that reassembly, “as taken apart” is adequate without the
functional test.
• Monitor Exhaust Temperature During All Phases of Startup — The operator is alerted to the following:
CAUTION
Over temperature can damage the turbine hot gas path parts
Recommendations
Mark VI
Mark VI Toolbox provides various privilege level access. Reference GEH 6403, Chapter 2, pg 2.8.
MARK Vie
Similar to the Mark VI, Mark VIe ToolboxST provides various ‘Access Rights.’ Reference GEH 6700A,
Chapter 1 pg 1-7.
Privilege level passwords are provided that allow the ability to force logic signals. It is intended that logic
forcing only be used for off-line software checkout procedures, while the unit is shut down, and in
conjunction with proper lockout / tag-out procedures. Customer personnel shall not force logic signals to
circumvent control and protection functions.
The customer is responsible for password-protecting privilege levels or access rights within the Mark VI
and Mark VIe to limit access to control settings and logic forcing to qualified personnel only.
The wheelspace thermocouples, identified together with their nomenclature, are on the
Device Summary. A bad thermocouple will cause a “High Wheelspace Differential
Temperature” alarm. The faulty thermocouple should be replaced at the earliest
convenience.
When the average temperature in any wheelspace is higher then the temperature limit set
forth in the table, it is an indication of trouble. High wheelspace temperature may be
caused by any of the following faults:
Check wheelspace temperatures very closely on initial startup. If consistently high, and a
check of the external cooling air circuits reveals nothing, it is permissible to increase the
size of the cooling air orifices slightly. Consult with a General Electric Company field
representative to obtain recommendations as to the size that an orifice should be increased.
After a turbine overhaul, all orifices should be changed back to their original size,
assuming that all turbine clearances are returned to normal and all leakage paths are
corrected.
CAUTION
Wheelspace temperatures are read on the operators interface. Temperatures in
excess of the maximum are potentially harmful to turbine hot-gas-path parts
over a prolonged period of time. Excessive temperatures are annunciated but
will not cause the turbine to trip. High wheelspace temperature readings must
be reported to the General Electric technical representative as soon as possible.
2) Pressure limits
Refer to the Device Summary for actual pressure switch settings. Lube oil pressure in the
bearing feed header is a nominal value of 25 psig. The turbine will trip at 8 psig. Pressure
variations between these values will result from entrapped particulate matter within the
lube oil filtering system.
3) Vibration Limits
The maximum overall vibration velocity of the gas turbine should never exceed 1.0 inch
(2.54 cm) per second in either the vertical or horizontal direction. Corrective action
should be initiated when the vibration levels exceed 0.5 inch (1.27 cm) per second as
indicated on the control system <I>/HMI.
If doubt exists regarding the accuracy of the reading or if more accurate and specific
vibration readings are desired a vibration check is recommended using vibration test
equipment.
4) 4. Load Limit
The maximum load capability of the gas turbine is given in the control specification. For
the upper limits of generator capability, refer to the Reactive Capability Curve following
the GENERATOR tab.
So that maximum trouble-free operation can be secured, General Electric designs these
machines with more than ample margins on turbine bucket thermal and dynamic stresses,
compressor and turbine wheel stresses, generator ventilation, coolers, etc. As a result,
these machines are designed somewhat better than is strictly necessary, because of the
importance of reliability of these turbines to our customers and to the electrical industry.
It cannot be said, therefore, that these machines cannot be safely operated beyond the load
limits. Such operation, however, always encroaches upon the design margins of the
machines with a consequent reduction in reliability and increased maintenance.
Accordingly, any malfunction that occurs as a result of operation beyond contract limits
cannot be the responsibility of the General Electric Company.
The fact that a generator operates at temperature rises below the 185°F (85°C) for the
rotor and 140°F (60°C) for the stator permitted by the AIEE Standards does not mean that
it can be properly run with full safety up to these values by overloading beyond the
nameplate rating. These standards were primarily set up for the protection of insulation
from thermal deterioration on small machines. The imbedded temperature detectors of the
stator register a lower temperature than the copper because of the temperature drop
through the insulation from the copper to the outside of the insulation, where the
temperature detectors are located. There are also conditions of conductor expansion,
insulation stress, etc., which impose limitations. These factors have been anticipated in the
“Vee” curves and reactive capability curves which indicate recommended values
consistent with good operating practice. The “Vee” curves and reactive capability curves
form part of the operating instructions for the generator and it is considered unwise to
exceed the values given.
The gas turbines are mechanically designed so that (within prescribed limits), advantage
can be taken of the increased capability over nameplate rating, which is available at lower
ambient temperatures (because of increased air density), without exceeding the maximum
allowable turbine inlet temperature.
The load limit of the gas turbine-generator must not be exceeded, even when the ambient
temperature is lower than that at which the load limit of the gas turbine is reached. Under
these conditions, the gas turbine will operate at this load with a lower turbine inlet
temperature and the design stresses on the load coupling and turbine shaft will not be
exceeded.
If the turbine is overloaded so that the turbine exhaust temperature schedule is not
followed for reasons of malfunctioning or improper setting of the exhaust temperature
control system, the maximum allowable turbine inlet temperature or the maximum
allowable exhaust temperature, or both, will be exceeded and will result in a
corresponding increase in maintenance and, in extreme cases, might result in failure of the
turbine parts.
The exhaust temperature control system senses the turbine exhaust temperature and
introduces proper bias to limit the fuel flow so that neither the maximum allowable
turbine inlet temperature nor the maximum allowable turbine exhaust temperature is
exceeded.
The annunciator audible alarm may be silenced by clicking on the alarm SILENCE target.
The alarm message can be cleared from the ALARM list on the <I>/HMI after the
ACKNOWLEDGE target and the ALARM RESET target are actuated, but only after the
situation causing the alarm has been corrected.
The fire protection system must be replenished and reset before it can automatically react
to another fire. Reset must be made after each activation of the fire protection system
which includes an initial discharge followed by an extended discharge period of the fire
protection media.
Fire protection system reset is accomplished by resetting the pressure switch located on
the fire protection system.
Ventilation dampers, automatically closed by a signal received from the fire protection
system, must be reopened manually in all compartments before restarting the turbine.
CAUTION
Failure to reopen compartment ventilation dampers will severely shorten the
service life of major accessory equipment. Failure to reopen the load coupling
compartment dampers will materially reduce the performance of the generator.
To prevent the above described malfunctions the operator should keep the number of nonoperational
exhaust thermocouples to a maximum of two but no more than one of any three adjacent
thermocouples.
CAUTION
Operation of the gas turbine with a single faulty thermocouple should not be
neglected, as even one faulty thermocouple will increase the risk of an invalid
“combustion alarm” and/or “Trip”. The unit should not be shut down just for
replacement of a single faulty thermocouple. However, every effort should be
made to replace the faulty thermocouples when the machine is down for any
reason.
Adherence to the above criteria and early preventive maintenance should reduce distortions of the
control and protection functions and the number of unnecessary turbine trips.
8) Cooldown/Shutdown Precautions
CAUTION
In the event of an emergency shutdown in which internal damage of any
rotating equipment is suspected, do not turn the rotor after shutdown. Maintain
lube oil pump operation, since lack of circulating lube oil following a hot
shutdown will result in rising bearing temperatures which can result in
damaged bearing surfaces. If the malfunction that caused the shutdown can be
quickly repaired, or if a check reveals no internal damage affecting the rotating
parts, reinstate the cooldown cycle.
If there is an emergency shutdown and the turbine is not turned with the rotor turning device, the
following factors should be noted:
1. Within 20 minutes, maximum, following turbine shutdown, the gas turbine may be started without
cooldown rotation. Use the normal starting procedure.
2. Between 20 minutes and 48 hours after shutdown a restart should not be attempted unless the gas
turbine rotor has been turned for minimum four hours.
3. If the unit has been shut down and not turned at all, it must be shut down for approximately 48
hours before it can be restarted without danger of shaft bow.
CAUTION
Where the gas turbine has not been on rotor turning operation after shutdown
and a restart is attempted, as under conditions above, rotor bow restart
procedure should be followed:
If seismic vibration readings for both bearings are less than 0.1 in/sec, the start sequence may be
initiated.
CAUTION
If seizure occurs during the turning operation of the gas turbine, the turbine
should be shut down and remain idle for at least 30 hours, or until the rotor is
free. The turbine may be rotated at any time during the 30-hour period if it is
free; however, audible checks should be made for rubs.
NOTE
The vibration velocity must be measured at points near the gas turbine bearing caps.
1. Lube oil heaters, which when used in conjunction with the lube oil pumps, heat and circulate turbine
lube oil at low ambient temperatures to maintain proper oil viscosity.
3. *Generator heating.
4. Lube oil pumps. Auxiliary pump should be run at periodic intervals to prevent rust formation in the lube
oil system.
5. Fuel oil heaters, where used. These heaters used in conjunction with the fuel oil pumps, heat and
circulate fuel oil at low ambient temperatures to maintain proper fuel oil viscosity.
6. Compartment heating.
7. *Operation of control compartment air conditioner during periods of high ambient temperature to
maintain electrical equipment insulation within design temperature limits.
1. Check that all piping and turbine connections are securely fastened and that all blinds have been
removed. Most tube fittings incorporate a stop collar which insures proper torquing of the fittings at initial
fitting make up and at reassembly. These collars fit between the body of the fitting and the nut and contact
in tightening of the fitting. The stop collar is similar to a washer and can be rotated freely on unassembled
fittings. During initial assembly of a fitting with a stop collar, tighten the nut until it bottoms on the collar.
The fitting has to be sufficiently tightened until the collar cannot be rotated by hand. This is the inspection
for a proper fitting assembly. For each remake of the fitting, the nut should again be tightened until the
collar cannot be rotated.
2. Inlet and exhaust plenums and associated ducting are clean and rid of all foreign objects. All access
doors are secure.
3. Where fuel, air or lube oil filters have been replaced check that all covers are intact and tight.
4. Verify that the lube oil tank is within the operating level and if the tank has been drained that it has been
refilled with the recommended quality and quantity of lube oil. If lube oil flushing has been conducted
verify that all filters have been replaced and any blinds if used, removed.
5. Check operation of auxiliary and emergency equipment, such as lube oil pumps, water pumps, fuel
forwarding pumps, etc. Check for obvious leakage, abnormal vibration (maximum 3 mils), noise or
overheating.
6. Check lube oil piping for obvious leakage. Also using provided oil flow sights, check visually that oil is
flowing from the bearing drains. The turbine should not be started unless flow is visible at each flow sight.
7. Check condition of all thermocouples and/or resistance temperature detectors (RTDs) on the <I>/HMI.
Reading should be approximately ambient temperature.
8. Check spark plugs for proper arcing.
WARNING
DO NOT TEST SPARK PLUGS WHERE EXPLOSIVE ATMOSPHERE IS
PRESENT.
If the arc occurs anywhere other than directly across the gap at the tips of the electrodes, or if by
blowing on the arc it can be moved from this point, the plug should be cleaned and the tip clearance
adjusted. If necessary, the plug should be replaced. Verify the retracting piston for free operation.
10. Determine that the cooling water system has been properly flushed and filled with the
recommended coolant. Any fine powdery rust, which might form in the piping during short time
exposure to atmosphere, can be tolerated. If there is evidence of a scaly rust, the cooling system
should be power flushed until all scale is removed. If it is necessary to use a chemical cleaner, most
automobile cooling system cleaners are acceptable and will not damage the carbon and rubber parts
of the pump mechanical seals or rubber parts in the piping.
Refer to “Cooling Water Recommendations for Combustion Gas Turbine Closed Cooling Systems”.
Note the following regarding antifreeze.
Following the water system refill ensure that water system piping, primarily pumps and flexible
couplings, do not leak. It is wise not to add any corrosion inhibitors until after the water system is
found to be leak free.
CAUTION
Do not change from one type antifreeze to another without first flushing the
cooling system very thoroughly. Inhibitors used may not be compatible and can
cause formation of gums, in addition to destroying effectiveness as an inhibitor.
Consult the antifreeze vendor for specific recommendations.
• The Load Commutator Inverter (LCI) should be calibrated and tested as per GEH-6192.
• The use of radio transmitting equipment in the vicinity of open control panels is not recommended.
Prohibiting such use will assure that no extraneous signals are introduced into the control system that
might influence the normal operation of the equipment.
• Check the Cooling and Sealing Air Piping against the assembly drawing and piping schematic, to
ensure that all orifice plates are of designated size and in designated positions.
• At this time all annunciated ground faults should be cleared. It is recommended that units not be
operated when a ground fault is indicated. Immediate action should be taken to locate all grounds
and correct the problems.
CAUTION
Where an electric motor is used as the starting means refer to the Control
Specifications for maximum operating time.
When a unit has been overhauled those parts or components that have been removed and taken apart
for inspection/repair should be critically monitored during unit startup and operation. This inspection
should include: leakage check, vibration, unusual noise, overheating, lubrication.
1) Crank
a. Listen for rubbing noises in the turbine compartment especially in the load tunnel area.
A soundscope or some other listening type device is suggested. Shutdown and investigate
if unusual noise occurs
b. Check for unusual vibration.
c. Inspect for water system leakage.
2) Fire
WARNING
DUE TO THE COMPLEXITY OF GAS TURBINE FUEL SYSTEMS, IT IS
IMPERATIVE FOR EVERYONE TO EXERCISE EXTREME CAUTION IN
AND NEAR ANY TURBINECOMPARTMENT, FUEL HANDLING SYSTEM,
OR ANY OTHER ENCLOSURES OR AREAS CONTAINING FUEL PIPING
OR FUEL SYSTEM COMPONENTS.
Turbine Compartment
1. Bleed fuel oil filters, if appropriate. Then check entire fuel system and the area immediately
around the fuel nozzle for leaks. In particular check for leaks at the following points:
Accessory Module
- Flow divider (when used)
- Fuel and water pumps
- Filter covers and drains
CAUTION
• Elimination of fuel leakage in the turbine compartment is of extreme importance as
a fire preventive measure.
2. Monitor FLAME status on the <I> processor to verify all flame detectors are correctly indicating
flame.
3. Monitor the turbine control system readings on the <I> processor for unusual exhaust
thermocouple temperature, wheelspace temperature, lube oil drain temperature, highest to lowest
exhaust temperature spreads and “hot spots” i.e. combustion chamber(s) burning hotter than all the
others.
3) Automatic, Remote
On initial startup, permit the gas turbine to operate for a 30 to 60 minute period in a full
speed, no load condition. This time period allows for uniform and stabilized heating of the
parts and fluids. Tests and checks listed below are to supplement those recorded in
Control Specification—Control System Adjustments. Record all data for future
comparison and investigation.
1. Continue monitoring for unusual rubbing noises and shutdown immediately if noise
persists.
2. Monitor lube oil tank, header and bearing drain temperatures continually during the
heating period. Refer to the Schematic Piping Diagram — Summary Sheets for
temperature guidelines. Adjust VTRs if required.
3. At this time a thorough vibration check is recommended, using vibration test equipment
such as IRD equipment (IR DMechanalysis, Inc.) or equivalent with filtered or unfiltered
readings. It is suggested that horizontal, vertical and axial data be recorded for the:
a. all accessible bearing covers on the turbine
b. turbine forward compressor casing
c. turbine support legs
d. bearing covers on the load equipment
4. Check wheelspace, exhaust and control thermocouples for proper indication on the
<I>/HMI. Record these values for future reference.
5. Flame detector operation should be tested per the Control Specification — Control
System Adjustments.
6. Utilize all planned shutdowns in testing the Electronic and Mechanical Overspeed Trip
System per the Control Specifications — Control System Adjustments. Refer to Special
Operations section of this text.
Functional description of the <I>/HMI Main Display follows; however, panel installation, calibration, and
maintenance are not included.
Operational information includes startup and shutdown sequencing in the AUTO mode of operation. The
most common causes of alarm messages can be found in the concluding section.
It is not intended to cover initial turbine operation herein; rather, it will be assumed that initial startup,
calibration and checkouts have been completed. The turbine is in the cooldown or standby mode ready for
normal operation with AC and DC power available for all pumps, motors, heaters, and controls and all
annunciator drops are cleared.
Refer to the Control Specifications (Control and Protection Systems) in this volume, and the previously
furnished Control Sequence Program (CSP) for additional operating sequence information and related
diagrams.
B Start-Up
1) General
Operation of a single turbine/generator unit may be accomplished either locally or
remotely.
The following description lists operator, control system and machine actions or events in
starting the gas turbine.
Reference the section “Description of Panels and Terms—Turbine Control Panel" for
description of turbine panel devices. The following assumes that the unit is off of
cooldown, and in a ready to start condition.
2) Starting Procedure
1. Using the cursor positioning device, select “MAIN” display from the DEMAND
DISPLAY menu.
a. The display will indicate speed, temperature, various conditions etc. Three lines
displayed on the <I> /HMI will read:
SHUTDOWN STATUS
OFF COOLDOWN
OFF
STARTUP STATUS
READY TO START
AUTO
a. Unit auxiliaries will be started including a motor driven lube oil pump used to establish
lube oil pressure. The <I>/HMI message SEQ IN PROGRESS will appear.
b. When permissives are satisfied, the master protective logic (L4) will be satisfied. The
<I>/HMI display will change to: STARTUP STATUS
STARTING
AUTO; START
c. The turbine shaft will begin to rotate on turning gear. The zero speed signal “14HR”
will be displayed. When the unit reaches approximately 6 rpm, the starting device will be
energized and accelerate the unit. The <I> /HMI display will change to START-UP
STATUS/CRANKING.
d. When the unit reaches approximately 15% speed, the minimum speed signal “14HM”
will be displayed on the <I>/HMI. (For machines with cooling water fan motors receiving
power from the generator terminals via the UCAT transformer, field flashing will be
initiated to build up generator voltage to power the fans; otherwise, field flashing to build
up generator voltage will occur at operating speed.)
e. If the unit configuration requires purging of the gas path prior to ignition, the starting
device will crank the gas turbine at purge speed for a period of time determined by the
setting of the purge timer. See Control Specifications-Settings Drawing for purge timer
settings.
f. FSR will be set to firing value. (FSR, Fuel Stroke Reference, is the electrical signal that
determines the amount of fuel delivered to the turbine combustion system.) Ignition
sequence is initiated. The <I>/HMI display will change to START UP STATUS/FIRING.
g. When flame is established, the <I>/HMI display will indicate flame in those
combustors equipped with flame detectors.
h. FSR is set back to warm-up value, and the <I> /HMI display will indicate STARTUP
STATUS/WARMING UP. If the flame goes out during the 60 second firing period, FSR
will be reset to firing value. (At the end of the ignition period, if flame has not been
established, the unit will remain at firing speed. Refer to operation 8 in the Special
Operations section for specific operating instructions for DLN 2.0 and DLN 2.6
configured machines.) At this time the operator may shut the unit down or attempt to fire
again. To fire again select CRANK on the Main Display. The purge timer and firing timer
are reinitialized. The purge timer will begin to time. Reselecting AUTO will cause the
ignition sequence to repeat itself after the purge timer has timed out. If the unit is being
operated remotely and multiple starts capability exists (REMOTE having previously been
selected on the Main Display), and no fire has been established at the end of the ignition
period, the unit will be purged of unburned fuel. At the end of the purge period ignition
will be attempted again. If flame is not established at this time, the starting sequence will
be terminated and the unit will shutdown. At the end of the warmup period, with flame
established, FSR will begin increasing. The <I>/HMI will indicate STARTUP
STATUS/ACCELERATING and the turbine will increase in speed. At approximately 50%
speed, the accelerating speed signal “14HA” will be displayed on the <I> /HMI.
i. The turbine will continue to accelerate. When it reaches 85-90% speed, the starting
device will disengage and shutdown. The <I>/HMI will indicate the change in status from
STARTUP CONTROL to SPEED CONTROL at approximately 60% speed.
j. When the turbine reaches operating speed, the operating speed signal “14HS” will be
displayed on the <I>/HMI. Field flashing is terminated. If the synchronizing selector
switch (43S) on the generator control panel is in the OFF position and REMOTE is not
selected on the <I>/HMI, as the turbine reaches operating speed, <I> /HMI will now read:
RUN STATUS
FULL SPEED NO LOAD
AUTO; START
If the synchronizing selector switch on the generator panel is in the AUTO position or
REMOTE is selected on the <I>/HMI automatic synchronizing is initiated. The <I>/HMI
will read SYNCHRONIZING. The turbine speed is matched to the system (to less than
1/3 Hz difference) and when the proper phase relationship is achieved the generator
breaker will close. The machine will load to Spinning Reserve unless a load control point
BASE, PEAK or PRESELECTED LOAD has been selected.
The <I>/HMI will display SPINNING RESERVE, once the unit has reached this load
point.
C Synchronizing
When a gas turbine-driven synchronous generator is connected into a power transmission system, the
phase angle of the generator going on-line must correspond to the phase angle of the existing line voltage
at the moment of its introduction into the system. This is called synchronizing.
CAUTION
Before initiating synchronization procedures, be sure that all synchronization
equipment is functioning properly, and that the phase sequence of the incoming
unit corresponds to the existing line phase sequence and the potential
transformers are connected correctly to proper phases. Initial synchronization
and checkout after performing maintenance to synchronizing equipment should
be performed with the breaker racked out.
NOTE
Synchronizing cannot take place unless AUTO or REMOTE has been selected on
the <I>/HMI Main Display and the turbine has reached full speed.
1) Manual Synchronization
1. Select MANUAL on <I>/HMI synchronization display.
2. Select AUTO on the <I>/HMI Main Display.
3. Select START and EXECUTE on the <I>/HMI Main Display. This will start the turbine
and accelerate it to full speed as previously described. At this point the CRT will indicate
RUN STATUS, FULL SPEED NO LOAD.
4. Compare the generator voltage with the line voltage. (These values are located on the
<I>/HMI synchronization display.)
5. Make any necessary voltage adjustment by operating the RAISE- LOWER buttons on
the <I>/HMI display until the generator voltage equals the line voltage.
6. Compare the generator and line frequency on the synchroscope (located on the
<I>/HMI display). If the pointer is rotating counterclockwise, the generator frequency is
lower than the line frequency and should be raised by increasing the turbine-generator
speed.
7. Adjust the speed until the synchroscope rotates clockwise at approximately five
seconds per revolution or slower.
8. The generator circuit breaker “close” signal should be given when it reaches a point
approximately one minute before the 12 o'clock position. This allows for a time lag for the
breaker contacts to close after receiving the close signal. Automatic synchronization is
accomplished by the following steps:
2) Automatic Synchronization
1. Select AUTO on the <I>/HMI synchronization display.
2. Select AUTO on the <I>/HMI Main Display.
3. Select START on the <I>/HMI Main Display.
This procedure will start the turbine, and upon attainment of “complete sequence”, match
generator voltage to line voltage, synchronize the generator to the line frequency, and load
the generator to the preselected value. A “breaker closed” indicator will actuate when the
generator circuit breaker has closed placing the synchronized unit on-line.
Once the generator has been connected to the power system, the turbine fuel flow may be
increased to pick up load, and the generator excitation may be adjusted to obtain the
desired KVAR value.
WARNING
FAILURE TO SYNCHRONIZE PROPERLY MAY RESULT IN EQUIPMENT
DAMAGE AND/OR FAILURE, OR THE CREATION OF CIRCUMSTANCES
WHICH COULD RESULT IN THE AUTOMATIC REMOVAL OF
GENERATING CAPACITY FROM THE POWER SYSTEM.
In those cases where out-of-phase breaker closures are not so serious as to cause immediate
equipment failure or system disruption, cumulative damage may result to the on-coming generator.
Repeated occurrences of out-of-phase breaker closures can eventually result in generator failure
because of the stresses created at the time of closure.
Out-of-phase breaker closure will result in abnormal generator noise and vibration at the
time of closure. If there is reason to suspect such breaker malclosure, the equipment
should be immediately inspected to determine the cause of the malclosure and for any
damage to the generator.
Refer to the “Control and Protection” section of this volume for additional information on
the synchronizing system.
Manual loading beyond the selected temperature control point BASE or PEAK is not
possible.
2) Automatic Loading
On startup if no load point is selected, the unit will load to the SPINNING RESERVE
load point. The SPINNING RESERVE load point is slightly greater than no load,
typically 8% of base rating. An intermediate load point, PRE-SELECTED load, and
temperature control load points BASE and PEAK can be selected anytime after a start
signal has been given. The selection will be displayed on the <I>/HMI. The unit will load
to the selected load point. PRESELECTED LOAD is a load point greater than SPINNING
RESERVE and less than BASE, typically 50%. The auto loading rate is shown in Control
Specification-Settings Drawing.
E Remote Operation
To transfer turbine control from the control compartment to remotely located equipment, select REMOTE
on the <I>/HMI Main Display. The turbine may then be started, automatically synchronized, and loaded by
the remote equipment.
2) Emergency Shutdown
Emergency shutdown is initiated by depressing the EMERGENCY STOP pushbutton.
Cooldown operation after emergency shutdown is also automatic provided the
permissives for this operation are met.
3) Cooldown
Immediately following a shutdown, after the turbine has been in the fired mode, the rotor
is turned to provide uniform cooling. Uniform cooling of the turbine rotor prevents rotor
bowing, resultant rubbing and imbalance, and related damage that might otherwise occur
when subsequent starts are attempted without cooldown. The turbine can be started and
loaded at any time during the cooldown cycle.
The cooldown cycle may be accelerated using the starting device; in which case it will be
operated at cranking speed.
A rotor turning device is provided for cooldown rotation. A description of rotor turning
operation and servicing can be found in the Starting System tab.
The minimum time required for turbine cooldown depends mainly on the turbine ambient
temperature. Other factors, such as wind direction and velocity in outdoor installations
and air drafts in indoor installations, can have an affect on the time required for cooldown.
The cooldown times recommended in the following paragraphs are the result of General
Electric Company operating experience in both factory and field testing of General
Electric gas turbines. The purchaser may find that these times can be modified as
experience is gained in operation of the gas turbine under his particular site conditions.
Cooldown times should not be accelerated by opening up the turbine compartment doors
or the lagging panels since uneven cooling of the outer casings may result in excessive
stress. The unit must be on rotor turning operation immediately following a shutdown for
at least 24 hours to ensure minimum protection against rubs and unbalance on a
subsequent starting attempt. The General Electric Company, however, recommends that
the rotor turning operation continue for 48 hours after shutdown to ensure uniform rotor
cooling.
G Special Operations
1) Testing the Emergency DC Lube Pump
The DC emergency pump may be tested using the test pushbutton on the motor starter.
NOTE
The turbine should be operated for at least 30 minutes at rated speed before checking
the overspeed settings.
Turbine speed is controlled by the turbine speed reference signal TNR. The maximum speed
called for by TNR is limited by the high speed stop control constant. This value is nominally set
at 107% of rated speed. It will be necessary to select the overspeed test function, which will
reprogram the 107% setpoint to 113%, in order to allow the speed to increase above the electrical
overspeed trip setting. With the high speed stop constant adjusted to be higher than the electrical
overspeed trip speed, raise unit speed gradually by using the SPEED SP RAISE target on the <I>
/HMI Main Display and observe speed at which the unit trips against the value tabulated in the
Control Specifications — Setting drawing. Once the unit trips, the speed setpoint is returned to
the 107% maximum value.
NOTE
The turbine should be operated for at least 30 minutes at rated speed before checking
the overspeed settings.
The fuel flow to the six fuel nozzles and quaternary pegs are controlled by four independent
control valves, each controlling flow split and unit load. The gas fuel system consists of the gas
fuel stop/ratio valve, gas control valve one, (PM1), gas control valve two (PM2), gas control
valve three, (PM3), and gas control valve four, (Quat). (Refer to figure 2.)
The stop/ratio valve (SRV) is designed to maintain a predetermined pressure, (P2), at the inlet of
the gas control valves. Gas control valves one through four, (GCV1–4), regulate the desired gas
fuel flow delivered to the turbine in response to the command signal FSR, (Fuel Stroke
Reference), from the SPEEDTRONIC panel. The DLN 2.6 control system is designed to ratio
FSR into a Flow Control Reference. This flow control philosophy is performed in a cascading
routine, scheduling a percentage flow reference for a particular valve, and driving the remainder
of the percentage to the next valve reference parenthetically downstream in the control software.
The stop ratio valve and gas control valves are monitored for their ability to track the command
setpoint. If the valve command setpoint differs from the actual valve position by a prescribed
amount for a period of time, an alarm will annunciate to warn the operator. If the condition
persists for an extended amount of time, the turbine will be tripped and another alarm will
annunciate the trip.
FIGURE 2. Gas Fuel System
DLN 2.6 operational mode is displayed on the main display as well as the DLN display.
Operational mode is defined as the sum of the nozzles being delivered fuel, therefore, if PM1 and
PM3 are fueled, the unit is in Mode 4, likewise, if PM2 and PM3 are fueled, the unit is in Mode 5.
When the quaternary passages are fueled, a Q is added to the mode number.
4. Chamber Arrangement
The 7F machine employs 14 combustors while the 9F employs 18 similar but slightly larger
combustors. For each machine there are two spark plugs and four flame detectors in selected
chambers with crossfire tubes connecting adjacent combustors. Each combustor consists of a six
nozzle/endcover assembly, forward and aft combustion casings, flow sleeve assembly, multi–
nozzle cap assembly, liner assembly, and transition piece assembly. A quaternary nozzle
arrangement penetrates the circumference of the combustion can, porting fuel to casing injection
pegs located radially around the casing. Figure 4 represents the chamber arrangement
Figure 4. 7FA DLN–2 Combustor
Inlet bleed heating, (IBH), through the use of recirculated compressor discharge airflow, is
necessary when operating with reduced IGV angles. Inlet heating protects the compressor from
stall by relieving the discharge pressure and by increasing the inlet air stream temperature. Other
benefits include anti–icing protection due to increased pressure drop across the IGV’s.
The inlet bleed heat system regulates compressor discharge bleed flow through a control valve
and into a manifold located in the compressor inlet air stream. The control valve varies the inlet
heating air flow as a function of IGV angle. At minimum IGV angles the inlet bleed flow is
controlled to a maximum of 5.0% of the total compressor discharge flow. As the IGV’s are
opened at higher loads, the inlet bleed flow will proportionally decrease until shut off.
The IBH control valve is monitored for its ability to track the command setpoint. If the valve
command setpoint differs from the actual valve position by a prescribed amount for a period of
time, an alarm will annunciate to warn the operator. If the condition persist for an additional
amount of time, the inlet bleed heat system will be tripped and the IGV’s minimum reference will
be raised to the default value.
The IBH system monitors the temperature rise in the compressor inlet airflow. This temperature
rise serves as an indication of bleed flow. Failure to detect a sufficient temperature rise in a set
amount of time will cause the inlet bleed heat system to be tripped and an alarm annunciated.
8. Flame Detection
Reliable detection of the flame location in the DLN–2.6 system is critical to the control of the
combustion process and to the protection of the gas turbine hardware. Four flame detectors in
separate combustion chambers around the gas turbine are mounted to detect flame in all modes of
operation. The signals from these flame detectors are processed in control logic and used for
various control and protection functions.
9. Ignition system
Two spark plugs located in different combustion chambers are used to ignite fuel flow. These
spark plugs are energized to ignite fuel during start–up only, at firing speed. Flame is propagated
to those combustion chambers without spark plugs through crossfire tubes that connect adjacent
combustion chambers around the gas turbine.
b. False Start
During a false start, where flame is not established in the four monitored combustion chambers
after 10 seconds, the stop ratio valve, (SRV) and gas control valves, (GCV’s) are shut and the unit
is run through a second unit purge cycle. At the end of this purge cycle, fuel is admitted and firing
is again attempted. If the second attempt is unsuccessful in maintaining flame, the unit is tripped
and the SRV and GCV’s close.
Mode 1 ( or M1)
Mode 2 ( or M2)
Mode 3 ( or M3)
Mode 4 ( or M4)
Mode 5 ( or M5)
Mode 5Q ( or M5Q)
Mode 6Q (or M6Q)
2. Mandatory Precautions
Before water washing of the compressor begins, the turbine blading temperature must be
low enough so that the water does not cause thermal shock
CAUTION
The differential temperature between the wash water and the interstage wheelspace
temperature must not be greater than 120°F (48.9°C) to prevent thermal shock to the
hot gas parts. For wash water of 180°F (82.2°C), the maximum wheelspace
temperature must be no greater than 300°F (148.9°C) as measured by the digital
thermocouple readout system on the turbine control panel.
To reduce this difference, the wash water may be heated and the turbine kept on crank until the
wheelspace temperatures drop to an acceptable level. The wheelspace temperatures are read in the
control room on the <I>/HMI.
CAUTION
If, during operation, there has been an increase in exhaust temperature spread above
the normal 15°F to 30°F (8.3°C to 16.6°C), the thermocouples in the exhaust plenum
should be examined. If they are coated with ash, the ash should be removed.
Radiation shields should also be checked.
If they are not radially oriented relative to the turbine, they should be repositioned
per the appropriate drawing. If the thermocouples are coated with ash, or if the
radiation shields are not properly oriented, a correct temperature reading will not be
obtained.
If neither of the above conditions exists and there is no other explanation for the temperature
spread, consult the General Electric Installation and Service Engineering representative.
WARNING
THE WATER WASH OPERATION INVOLVES WATER UNDER HIGH
PRESSURE. CAUTION MUST BE EXERCISED TO ENSURE THE PROPER
POSITIONING OF ALL VALVES DURING THIS OPERATION. SINCE THE
WATER MAY ALSO BE HOT, NECESSARY PRECAUTIONS SHOULD BE
TAKEN IN HANDLING VALVES, PIPES, AND POTENTIALLY HOT
SURFACES.
NOTE
Before water washing the compressor, inspect the inlet plenum and gas turbine
bellmouth for large accumulations of atmospheric contaminants which could be
washed into the compressor. These deposits can be removed by washing with a
garden hose.
B <I>/HMI
The <I>/HMI is a personal computer that directly interfaces to the turbine control panel. This is the
primary operator station. All operator commands can be issued from the <I>/HMI. Alarm management can
be performed and turbine parameters can be monitored. With the proper password, editing can also be
accomplished.
1. Main Display
Operator selector targets and master control selector targets can be actuated from the main display by using
the cursor positioning device (CPD). Operator selector targets include:
OFF:
Inhibits a start signal.
CRANK:
With crank selected, a start signal will bring the machine to purge speed.
FIRE:
With FIRE selected, a START signal will bring the machine to minimum speed and establish flame in the
combustors. Selecting FIRE while the machine is on CRANK will initiate the firing sequence and establish
flame in the combustors.
AUTO:
With AUTO selected, a START signal will bring the machine to operating speed. Changing selections from
FIRE to AUTO will allow the machine to accelerate to operating speed.
REMOTE:
With REMOTE selected, control for the unit is transferred to the remote control equipment. Master control
selector targets include:
START:
A START selection will cause the unit to start. With AUTO selected, the unit will load to the SPINNING
RESERVE load point.
FAST START:
A FAST START selection will cause the unit to start. With AUTO selected, the unit will load to the
PRESELECTED load point. The machine will load at the manual loading rate.
STOP:
A STOP selection will cause the unit to initiate a normal shutdown.
All operator selector switches and master control selector targets are green and are located on the right side
of the display. All green targets are the AUTO/EXECUTE type, which means that the target must be
selected with the CPD and then, within three seconds, the EXECUTE target at the bottom of the display
must also be selected in order to actuate that command.
PRESEL:
Select the preselected load point.
BASE:
Select base temperature control load point.
*PEAK:
Select peak temperature control load point.
GAS SELECT:
100% gas fuel operation.
DIST SELECT:
100% distillate fuel operation.
MIX SELECT:
Selecting MIX while on 100% single fuel will cause the machine to transfer to mixed fuel operation at a
preset mixture (not applicable on DLN units).
DROOP SELECT:
Used to select droop speed control.
ISOCH SELECT:
Used to select isochronous speed control.
6. Alarm Display
This screen displays the current un-reset alarms, the time when each alarm occurred, the alarm drop
number and a word description of the alarm. An “*” indicates that the alarm has not been acknowledged.
The “*” disappears after the alarm has been acknowledged. For more information, see the Turbine Control
System Users' Manual.
7. Auxiliary Display
COOLDOWN ON and COOLDOWN OFF can be selected from this display.
C Definition of Terms
SPINNING RESERVE:
The minimum load control point based on generator output. The spinning reserve magnitude in MWs can
be found in the control specifications (5-10% of rating is a typical value).
PRESELECTED LOAD:
A load control point based on generator output. The preselected load point is adjustable within a range
designated in the Control Specification. The preseelected load point is normally set below the base load
point (50-60% of rating is a typical value).
BASE LOAD:
This is the normal maximum loading for continuous turbine operation as determined by turbine exhaust
temperature levels.
Electromechanical auxiliary relays and lockouts are also included to facilitate tripping and alarm indication
to the Turbine Control Panel and customer (if required).
The panel also includes metering that measures typical generator electrical data. Available parameters
include voltage, current, kW, kVA, kVAR, Power Factor, frequency, kW/hr, kVA/hr & kVAR/hr.
G Annunciator System
Alarms are displayed on the <I>/HMI when the ALARM Display mode is selected. Before clearing an
alarm, action should be taken to determine the cause and perform the necessary corrective action. The
following is a list of annunciator messages along with suggested operator action.
NOTE
The alarm messages can be categorized as either “trip” or “alarm”. The “trip”
messages contain the word TRIP in the message. The “alarm” messages do not
indicate TRIP. For those alarms associated with permissive to start and trip logics
latched up through the MASTER RESET function, it will be necessary to call up the
<I>/HMI Display with the Master Reset target in order to unlatch and clear these
alarms.
SECTION 4. CONTROL AND PROTECTION
4 CONTROL AND PROTECTION
4.1 CONTROL AND PROTECTION
4.1.1 General
The gas turbine has a number of control and protection systems designed for the reliable and safe operation
of the unit. This section presents the general operating characteristics of turbine control and protection. For
settings and adjustments refer to the Control Specifications included in the manual. Additional information
will be provided in the SPEEDTRONIC* documentation.
Control of the turbine is done mainly by startup, speed, acceleration, synchronization, and temperature
control. Figure 1 illustrates the three control modes, and the means of fuel control in relation to the fuel
command signal. Sensors monitor the turbine speed, temperature, and compressor discharge pressure to
determine the operating conditions of the unit. When it is necessary for the turbine control to alter the turbine
operating conditions because of changes in load or ambient conditions, it is accomplished by modulating the
flow of fuel to the turbine. For example, if the exhaust temperature starts to exceed its permitted value for a
given operating condition, the temperature control circuit will cause a reduction in the fuel supplied to the
turbine and thereby limit the exhaust temperature.
Protection systems are provided to prevent abnormal conditions which could result in damage to the turbine.
The critical operating parameters monitored by the protection system are: temperature, speed, vibration,
flame, and compressor operating limit. Overtemperature and overspeed systems are provided as independent
backup systems for the temperature control and speed control systems. Vibration detection and protection is
activated by abnormal turbine vibration amplitude reaching a preset level. The flame detection and protection
system is activated if flame is not established during startup or if flame is lost during operation.
Each system operates independently and will trip the unit if its signal corresponds to a trip condition.
Operating conditions of the turbine are sensed and utilized as feedback signals to the SPEEDTRONIC*
control system. There are three major control loops — startup, speed and temperature, which may be in
control during turbine operation. These loops command Fuel Stroke Reference (FSR), the command signal
for fuel. The outputs of these control loops are connected to a minimum value select algorithm as shown in
Figure 1.
The minimum value select algorithm selects the lowest FSR called for by the control loops and passes the
result to the FSR controller. The action of this circuit is similar to a low-voltage selector. The lowest voltage
output of the control loops is allowed to pass the gate to the fuel control system as the controlling FSR
voltage. Fuel Stroke Reference (FSR) is the command signal for the fuel. Using this method of FSR selection,
switching between the control modes of speed, temperature and startup control takes place without any
discontinuity. The controlling FSR will establish the fuel input to the turbine at the value required by the
system which is in control. Displays on the turbine control panel CRT indicate which of the control systems
is controlling FSR. Figure 2 shows a more detailed schematic of the control loops.
This part of the service manual will explain the function of each control and protection system, with
descriptions of how electrical circuits and control devices operate together as systems. Reference to four sets
of control system documents is necessary for a complete understanding of turbine control. These are the
Control Specifications, the Device Summary, the Schematic Piping Diagrams and the SPEEDTRONIC*
documentation.
4.1.3 Control Specification
The Control Specifications consist of several multi-paged documents. The master document is Specification
Control - Control System Settings. It contains control settings defining the operational limits for each turbine,
calculated for the intended site conditions and fuel analysis submitted. The settings drawing reference the
other control specification drawings as well as the Device Summary and the Schematic Piping Diagrams. The
Control Specifications should be consulted before attempting to make adjustments or operate the gas turbine.
Users should therefore ensure that service manuals containing up-to-date revisions are available to operating
personnel.
During startup and shutdown sequence, these signals are critical because a large portion of the control logic
associated with actuating control devices, is also enabling protective circuits. These circuits are also utilizing
device status and condition as permissive to proceed with the starting of shutdown sequence.
Startup and shutdown cycles have been optimized to reduce low cycle fatigue on hot gas path components,
and provide customers with the ability to obtain additional benefits like “purge credits.”
Table-1 Detector/Relay Tags With Description And Speed Activation Set Point
4.2.3 The zero-speed detector, L14HR, provides the signal to the Turbine control system when the shaft line is at
standstill and as soon as the shaft line starts rotating. This signal plus L14HT speed relay - indicating that the
turning gear is running – forms the permissive for the LCI/Static Starter engagement and operation.
The minimum speed detector L14HM indicates that the turbine has reached the minimum firing speed and
also initiates the combustion system purge sequence prior to ignition. With these initiating signals and
permissives, the static starter is then given a command to go to purge speed. Once the purge sequence is
initiated, purge speed will be maintained until the purge timer has elapsed (times out). At this point in the
start sequence, the shaft–line will commence coasting down until the dropout of the L14HM (minimum-
speed relay).
4.2.4
NOTE
The dropout of 14HM provides several permissive functions in the startup of the gas
turbine after shutdown.
4.2.5 The acceleration speed relay L14HA pickup indicates that the turbine has reached approximately 50% in the
acceleration cycle. The high-speed sensor L14HS pickup indicates that the turbine is at 95% operating speed.
After the pickup of L14HS, the inlet guide vanes will open and the accelerating sequence is complete.
Should the gas turbine and generator bog down, after completing the start sequence and synchronization with
the Grid, the high speed relay L14HS will drop out at the under frequency speed setting.
At 95 % speed with the generator neutral in the correct verified position, the Exciter will “flash” the
generator field. The generator will start generating an output voltage which will rise to the nominal value on
the generator nameplate. The unit will now be at Full Speed No Load FSNL. At FSNL the digital set point is
100.3% speed with the Generator Circuit Breaker (GCB) open. At this point the startup sequence is virtually
complete since the unit is operating and ready to be synchronized to the HV network.
Approximately 0.5 second after 14HS drops out, the generator breaker will trip open and the digital setpoint
will be reset to 100.3%. After the opening of the generator breaker, the compressor bleed valves will open
and inlet guide vanes will close as a function of corrected speed. The actual settings of the speed relays are
programmed in the controllers as constants and are listed in the Control Specifications (MLI-A010).
4.2.6 Start up Control
The startup control operates as an open loop control in with the use of preset levels of the fuel command
signal, Fuel Stroke Reference, FSR. The levels set are “FIRE”, “WARMUP, and “”ACCELERATING”. The
Control Specifications provide the correct/acceptable settings calculated for the fuel anticipated from the fuel
wobbe index. For reliable startup, the FSR levels must be set in the turbine control system.
Startup control FSR signals operate through the minimum value gate to insure that speed control and
temperature control can limit FSR if required. During the startup sequence, rates of increase in speed and
exhaust temperature are restricted to protect the turbine parts from excessive mechanical and thermal stresses.
The rates of acceleration and temperature rise are controlled independently by the closed loops of the speed
and temperature control systems.
The fuel command signals are generated by in the startup software. In addition to the three startup levels, the
software has the capability to set the maximum and minimum FSR with provisions for manual control of
FSR. The manual FSR control is accomplished via a FSR GAG pushbutton. When utilizing manual FSR
control, the operator can insert a value lower than the current FSR value to take control from the current
control command or a higher value to act as a not-to-exceed limit.
While the shaft line is at rest electronic system checks are performed on the stop/speed ratio valve, the gas
control valve, accessories, the voltage supplies, and Generator Protection Panel (GPP). If all systems are
“healthy” and functional without any system errors, trip latches or communicating errors at this time, the
operator display will be normal and the “SHUTDOWN STATUS” will be displayed on the Human Machine
Interface (HMI) screen.
Activating the Master Operation Switch from “OFF” to an operating mode will activate the ready circuit. If
all protective circuits and trip latches are cleared, the “STARTUP STATUS” and “READY TO START”
messages displayed to indicate the turbine will accept a start signal. Pressing the “START” Master Control
pushbutton will introduce the start signal to the panel.
The start signal energizes the Master Control and Protection circuits (the L4 circuit), and starts the necessary
auxiliary equipment. If the shaft line is at standstill, the turning gear will start. With the unit on turning gear
the start-up status message “STARTING” is displayed on the HMI screen. turning gear starting clutch from
the rotor The Static Starting System will engage, then continue accelerating the shaft line to purge speed.
Once the static starter has accelerated the shaft line to purge speed, the purge timer will start timing operation.
During the purge cycle, air flow through the turbine will purge the turbine and Heat Recovery Steam
Generator (HRSG) in combined cycle configuration of any residual combustible mixture by forcing
approximately four volume changes of air through the system, exhaust, out the stack. At the end of the purge
cycle, the LCI de-engerizes the generator and the turbine speed is allowed to decay below firing speed
(14HM drop-out speed). At this point the static starter maintains the turbine at the minimum firing speed.
When turbine speed reaches the firing level (14HM pickup), startup control FSR is set at the “FIRING” Level.
The firing timer, K2F, is started, and fuel flow is enabled. When flame detector output signals indicate the
establishment of flame – successful ignition and cross firing - in the combustion chambers, the warmup timer,
K2W, starts and the startup fuel command FSR is set to the “WARM UP” FSR level. If ignition and cross
firing is not achieved, before the 60 second cross firing timer times out, the control system will automatically
revert to the purge sequence and will attempt a second firing sequence. The warmup time is provided to
minimize thermal stresses during the initial part of the startup.
At the end of the warmup period, the startup control FSR command is ramped to the maximum allowable
startup value. that is defined as FSR acceleration control. At this point, the starting device is set at the
position to provide maximum acceleration torque. At about 80% speed, the turbine efficiency has increased
sufficiently to the point that the gas turbine is now self-sustaining and the static starter is no longer required.
The static starter begins to roll off to its reset sequence upon reaching 90% speed. At this point the IGV’s that
were closed during the startup to prevent compressor surge will be opened to the FSNL position.
It is important to mention that although startup control establishes the maximum FSR fuel command, other
controls may reduce FSR to perform their critical control functions that may cause the turbine to reach the
temperature control, speed control, or acceleration limit. However, the lowest FSR command is always
selected to control fuel. The limiting control parameter will always be displayed on the control panel.
4.2.7 NOTE
Time to FSNL and loading rates will depend on the system configuration (Simple or
Combined) in conjunction with the type/vintage of Dry Low NOx (DLN) system and
the type of fuel being used (cold or heated).
For these limitations, please refer to the Combustion System documentation for your
particular Gas Turbine
4.2.8
4.2.9 Control Model Display And Operating Condition
Display Condition
ACCEL Acceleration
The startup cycle has been designed to moderate the highest combustion reference during acceleration. by
programming a low acceleration rate control setting during startup. It also aids smooth transition to speed
control at the end of the startup sequence. The startup sequence time is extended to an optimum time to
minimize strains produced on hot gas path parts in mid-acceleration cycle.
The minimum FSR limit is incorporated into temperature, acceleration and speed control circuits. This
prevents these controllers from driving FSR below the value that would cause flameout during a transient
condition.
When the generator breaker closes, the startup control FSR command is quickly ramped to “MAX” FSR.
Refer to Figures 1 and 2 for startup sequence and control descriptions
After fuel is shut off, cooldown sequence logic ensures slow roll on turning gear until the cooldown time
expires.
4.2.11
On generator drive gas turbines the speed control system typically consists of the “HP Turbine Speed
Control”, FSRN algorithm in conjunction with the “Droop Speed/Load Setpoint”, TNR, and “Isochronous
Speed Control Setpoint”, TNRI (optional), alogorithms. The usual droop control system operates by
governing fuel flow. The droop relation is predictable only for a fuel of constant characteristics.
Constant settable droop control is a special speed control system capable of accommodating variation in gas
fuel heating values. When operating on droop speed control, this system maintains the droop relation even as
the heating value of the fuel changes. To do this a watts transducer and algorithms “Turbine Load Droop”,
DWDROOP, “Load Turbine Speed Reference”, TNRL and “Setpoint Tracking” L70TRACK are added to the
typical software program. Refer to the Control Sequence Program and Control Specifications for details of
the Constant Settable Droop Speed Control System.
A Speed Signal
The speed of the turbine is measured by three magnetic sensors. These magnetic pickup sensors (77NH–1,
2, 3) are high output devices, consisting of a permanent magnet, surrounded by a coil and hermetically
sealed case. The pickups are mounted in a ring around a 60–toothed wheel on the gas turbine compressor
rotor shaft. With the 60–tooth wheel, the frequency of the voltage output in Hertz is exactly equal to the
speed of the turbine in revolutions per minute. The voltage output is a direct function of the speed of the
wheel and is affected by the clearance between the teeth of the wheel and the tip of the magnetic pickup.
Clearance between the outside diameter of the toothed wheel and the tip of the magnetic pickup should be
kept within the limits specified on the Control Specifications. If the clearance is not maintained within the
specified limits, the pulse signal can be distorted causing generation of an erroneous speed signal. Turbine
speed control will then operate in response to the incorrect speed feedback signal.
B Droop Operation
If the power grid speed is held relatively constant at synchronous speed, fuel flow in excess of that
necessary to maintain full–speed–no–load, will result not in increased speed, but increased power
produced by the generator. Thus the speed control loop acts as a load control loop and the speed setpoint,
TNR, is a control of the desired load on the turbine–generator unit.
A watts transducer is used to measure the output of the generator. The droop characteristic is established
with respect to the watts transducer signal. Speed control is an integrating control acting in response to the
load signal from the watts transducer, the speed setpoint signal, a 100% speed signal and the turbine speed
signal. The integrating control will act in response to an error signal at the input to reduce the error signal
to zero. For example: if the turbine is operating at 100% speed (grid frequency) the speed control will
match the speed setpoint signal and the load signal.
Establishing the droop relationship using the load signal as the feedback, instead of the fuel command
signal FSR, permits FSR to change in response to fuel variation while maintaining the proportional droop
relationship.
Normally speed control is accomplished by using FSR feedback to the speed control software making it
control in proportion to fuel changes which are equivalent to power changes. The advantages of using
feedback (watts) in this system are twofold:
1. As fuel gas changes, the droop relation is preserved. The control automatically compensates for
variations in heating values by using the gas turbine itself as a calorimenter. Constant regulation could not
be maintained without power sensing.
2. As fuel gas changes the setpoint setting would cause a different load in proportion to the heating value.
Load margin, therefore, could not be maintained constant without power sensing. The speed control
changes FSR as it needs to change power (watts) in proportion to the difference between turbine speed and
the set point. Thus any change in actual speed (grid frequency) will also cause a proportionate change in
unit load. This proportionality is adjustable to the desired regulation or “Droop”.
If the entire grid system tends to be overloaded, grid frequency (or speed) will decrease and cause a FSR
increase in proportion to the droop setting. If all units have the same droop, all will share a load increase
equally. Load sharing is the main advantage of this method of speed control.
Another advantage of droop control is that the gain of the system is high. If 4% droop is selected, only a 1%
change in speed will produce a change in fuel flow equivalent to 25% of rated load. This results in fast
system response to transient changes and helps hold system frequency.
Normally 4% droop is selected and the speed set point is calibrated such that 104% set point will generate
a speed reference which will produce a FSR resulting in base load at design ambient temperature. On gas
turbines having a peak temperature control, 104% set point corresponds to peak load. The adjustments
required on the speed control loop are covered in the Control Specifications.
The speed control system can be readily switched to operate as an isochronous control since the control
algorithm is always operating as an integrator. The setpoint tracking algorithm L70TRACK raises and lowers
the droop setpoint TNR while in the isochronous mode to keep the setpoint within a deadband of the correct
setpoint for the actual load. This allows transfer to droop control with negligible load speed disturbances. See
Figures 1 and 2.
4.3.3
4.3.4 Isochronous Load Sharing
Isochronous load sharing (ILS) allows multiple turbines to operate together as though they were one,
isochronously controlled unit. When in this mode, the turbines will maintain constant system frequency and
share the existing system load amongst themselves in proportion to their individual unit ratings. The control
system is similar to a standard isochronous speed control but there is one additional input. The standard
inputs are speed reference and actual speed which feed an integrating type fuel controller. The additional
input, which is the output of the ILS control, is a load error signal. This signal, DWS, is the difference
between the particular unit’s load, DW, and the average of all the units tied together operating isochronously.
This latter signal is referred to as DWAVG. This is the means by which the units share the existing system
load.
There are five primary signals in the ILS control; DW, DWN, DWAVG, DWS, and DWLDDIV. Following is
a description of each of these signals.
DW – Unit load.
DWN – Normalized unit load. The unit’s load signal, DW, is normalized to its rated load value. Constant
DWKSGN performs this function. The normalized load signal, not the load signal, is used in the ILS control.
This way the control will cause the units to share normalized load equally. This is another way of saying the
units will share load in proportion to their individual unit ratings.
DWAVG – Average normalized unit load. The normalized unit load signals of all the units operating
isochronously are tied together through a resistor network to create this signal. To do this, a wire must
physically be run amongst all the units to tie the resistor networks together. The resultant voltage signal is
actually one half of the average normalized unit load because of the voltage division which occurs in the
resistor network. Consequently, the DWN signal is multiplied by one half before it is compared to this signal.
Constant DWKSGT in the DWSV1 algorithm performs this function.
DWS – Output signal of the ILS controller. This signal is fed to the summing junction of the isochronous
speed fuel controller. Whenever there is a difference between the DWN and DWAVG signals, the DWS
signal will change and cause the fuel flow to change in such a way as to make these signals equal again.
DWLDDIV – Average normalized load. This signal is used when a unit is being started up and added to a
group of isochronous load sharing units which are already running. It is used to load the unit at a normal rate
before placing it in to isochronous control.
DWLDDIV represents the average normalized load of the other units operating isochronously. Notice the
relationship of this signal, the DWAVG signal and the 83LS contact. When a unit is being started up and
isochronous control is selected prior to generator breaker closure, the unit will be in the droop speed/load
control mode and its 83LS contact will be open. After the generator breaker closes, the normalized load of
this unit, DWN, is compared to the average of the others operating isochronously, DWLDDIV. If an error
exists, the droop speed/load setpoint, TNR, is automatically raised at a normal loading rate until these two
signals are within a few per cent of each other, typically 3%. At that point, the unit will be automatically
switched to isochronous control. This automatic loading feature loads a unit at a normal rate, instead of the
much faster rate which the isochronous control would produce if it were in effect at the time the generator
breaker closed.
The differential signal, acceleration, is compared to a fixed signal at the summing junction to modulate FSR
if the acceleration rate specified in the Control Specifications is exceeded. See the Control Sequence Program
and Control Specifications. The acceleration control usually acts only during portions of startup but can act at
any time the acceleration rate is exceeded.
4.3.6 Synchronizing
Automatic synchronizing is accomplished using synchronizing algorithms programmed into the RST
software. The inputs are transmitted from an interface module. The interface module contains an isolation
transformer for the generator and line input signals and the breaker closing relay. The synchronizing software
is part of the SPEEDTRONIC . See Figure 3.
For synchronizing, the gas turbine is brought to 100.3% speed. The matching circuit in the synchronizer will
adjust the turbine speed to reduce the slip frequency and permit synchronizing, if the system frequency has
varied enough to cause an unacceptable high slip.
For added protection a synchronizing check relay is provided in the generator panel. It is used in series with
both the auto synchronizing relay and the manual breaker close switch to prevent large out-of-phase breaker
closures.
The exhaust temperature is determined as a function of compressor pressure ratio (CPR) across the
compressor. CPR is a function of the compressor discharge pressure (CPD) ambient pressure (AFPAP),
bellmouth differential pressure (AFPBD), and compressor inlet total pressure (AFPCS). The exhaust
temperature reference is also proportional to the fuel flow command Fuel Stroke Reference (FSR) and turbine
output. These parameters are used as a backup in case CPD measurement is lost. These relationships are
shown on Figure 1. The lines of constant firing temperature are used in the control system to limit gas turbine
operating temperatures. Compressor discharge pressure is measured by three 96CD pressure transducers.
Ambient pressure is measured with three 96AP transducers. Bellmouth differential pressure is measured by
the 96BD transducer. Compressor inlet total pressure is measured by the 96CS transducer.
An additional thermocouple junction is created where the thermocouple wires are connected to the
terminals on the isothermal module. A voltage, that is a function of the temperature at the connection
points and in opposition to the signal generated by the thermocouple, is generated at this junction. An RTD
is mounted on the isothermal module to measure this “cold junction” or connection point temperature.
These RTD’s are scanned with the thermocouples as part of the analog-input-scan program and the data.
Figure 2. Cold Junction Scan Program
Figure 4 is a graphical illustration of the control setpoints. The control constants are given by the Control
Specifications-Control System Settings drawing. The temperature control reference algorithm also selects
the isothermal setpoint TTK ( )___I. The minimum of the three setpoints, CPR bias, Backup bias, or the
Isotherm, is selected for the final exhaust temperature control reference. During normal operation with gas
or light distillate fuels, this selection results in a CPR bias control with an isothermal limit, as shown by
the heavy lines on Figure 4. The CPR bias setpoint is compared with the Backup bias setpoint and an alarm
occurs when the CPR setpoint is higher.
A ramp function is provided in the algorithm to limit the rate at which the setpoint can change. The ramp
rate (slope) is programmed in constant TTKRX1 for increasing rate and in TTKRX2 for decreasing rate.
Consult the Control Sequence Program and the Control Specifications drawing for the block diagram
illustration of this function and the value of the constants. Typical rate limit is 5 degrees F per second. The
output of the ramp function is the exhaust temperature control setpoint.
(Figure 4) to permit operation at approximately rated combustion reference temperature while the fault is
cleared. This feature is shown on Figure 7.
On some designs with redundant pressure transducers, the FSR temperature control backup curve is not
utilized. In these designs, the turbine is not allowed to operate with the loss of two 96CD pressure
transducers. On designs with constant settable droop, redundant watts transducers feedback Dwatt
(megawatts), and this is used as the temperature control backup curve in the event of 96CD failures.
Figure 4. Exhaust Temperature Control - Control Setpoint
Figure 5. Temperature Control Schematic
Figure 6. Temperature Control Ref. Setpoint
G Temperature Control Reference Speed Bias
On two-shaft gas turbines, fuel temperature reference is increased 8°F for each percent HP set speed below
100% rated. This feature allows LP governor speed control to increase exhaust temperature above that set
by inlet guide vanes and nozzles over an HP speed operating range of 95 to 100 percent. This feature is
shown on Figure 8.
H Temperature Feedback
The temperature control fuel stroke reference algorithm compares the exhaust temperature control set-
point with the measured gas turbine exhaust temperature as obtained from thermocouples mounted in the
exhaust plenum. These thermocouples are scanned and cold junction corrected. The exhaust temperature
vector algorithm (Figure 5) reads the exhaust thermocouple temperature values and sorts them from the
highest to the lowest. These signals are used in the combustion monitor algorithm as well as in the
temperature control system exhaust average algorithm. Each value is looked at and all thermocouple
signals below the second highest by a constant value are considered low, or from a computer to which
communications are lost, are rejected from the averaging. The remaining signals are looked at again, and
the highest and lowest are rejected. The remaining ones are averaged for the TTXC signal. The TTXC
signal is then used in the algorithm which calculates the exhaust temperature median feedback. Here all the
thermocouples are sorted again, highest to lowest. A median of the readings is selected and compared to
TTXC, which will produce a calculated exhaust temperature feedback (TTXM).
This calculation is based on an average, and a median is used to eliminate error due to bad thermocouples
or readings. If a Controller should fail, this algorithm will detect it and ignore the readings from the failing
Controller. The TTXM signal will be based on the remaining Controllers’ thermocouples and an alarm will
be generated.
The TTXM value is used as the feedback for the exhaust temperature comparator. This calculated feedback
is used because the value is not affected by extreme values that may be the result of faulty instrumentation.
Should one of the communication links fail between the Controllers, the Controller affected will freeze the
value of TTXC at the last healthy sample and compare it with the current sample of TTXM of the
Controller. This prevents large changes in the feedback signal. When the link becomes healthy again there
is a fixed rate of correction to prevent sudden bumps in the system. With three FSRT values most errors
can be removed to give more reliable gas turbine operation. This is true also with each Controller doing the
same calculations for TTXC and TTXM.
Figure 9b. Temperature Control Curve With Part Load IGV Control
This means of detecting abnormalities in the combustion system is effective only to the extent there is
incomplete mixing as the gases pass through the turbine, and an uneven inlet pattern will cause an uneven
exhaust pattern. The uneven inlet pattern could be caused by a rupture in a transition piece, loss of fuel or
flame in a combustor, or other combustion malfunctions. The usefulness and reliability of the combustion
monitor depends on the condition of the exhaust thermocouples. It is important that each of the
thermocouples is in good working condition.
SPREAD #1 (TTXSP1)--The difference between the highest and the lowest thermocouple reading;
SPREAD #2 (TTXSP2)--The difference between the highest and the 2nd lowest thermocouple reading;
and,
SPREAD #3 (TTXSP3)--The difference between the highest and the 3rd lowest thermocouple readings.
The nominal allowable spread is the steady state spread limit. It varies, typically, between 30 and 125°F as a
function of average exhaust temperature and compressor discharge temperature.
The bias is an adder to the nominal allowable spread which accounts for the temporary increase in actual
spreads that occur during transient operational periods. It is a temperature value which varies between 0 and
TTKSPL8 degrees F (typically, 100 to 200° F).
During steady state operation, the bias value is 0 degrees F. When a transient operational condition occurs,
such as a rapid change in load, the bias value steps to TTKSPL8 degrees F. It remains at that value until
K2SPMB2 seconds (typically, 15 to 60 seconds) after the transient condition ends. Its value then decays
exponentially to 0°F on a time constant of TTKSPL9 seconds (typically, 30 to 100 seconds). Refer to Figure
6.
The transient conditions which cause the bias to step to 200°F are: 1) fuel transfer, 2) turbine startup and
shutdown, 3) load changes produced by a governor RAISE or LOWER signal, and 4) load changes produced
by a rapid change in FSR.
Condition Figure
Only the TC Failure Alarm occurs 3
A General
The two main sources of alarm and trip signals being generated by the combustion monitor are failed
thermocouples and combustion system deterioration. Other causes include poor fuel distribution due to
plugged or worn fuel nozzles.
The tests for combustion alarm and trip action have been designed to minimize signals due to failed
thermocouples but it is impossible to always isolate this cause.
The best protection against shutdowns due to failed thermocouples is good thermocouple maintenance.
Replace failed thermocouples promptly during normal downtime so that the likelihood of operation with
more than one failed thermocouple is low.
The TC TROUBLE ALARM is intended to call attention to failed thermocouples so that they will be
promptly replaced. The TC ALARM will also be activated by the early stages of some combustion
problems.
If TC Alarm, Trip and Combustion Alarm occur and the gas turbine continues to run, monitor malfunction
has occurred. Attempt to reset monitor.
All possible problems cannot be foreseen and initiative and judgment may be required to troubleshoot.
Thermocouple malfunction may be detected by observing the monitor display. An open thermocouple will
indicate a value of -40°F. A thermocouple may be intermittently open if the display is erratic or cyclic. With
the turbine coasting down and the exhaust metal still hot, but the exhaust air cooler, a thermocouple that reads
significantly higher than the others is probably shorted in its junction box.
CAUTION
Follow the restart instructions carefully. It is impossible to be sure there is no
combustion problem from the tests referred to above. In case of doubt or if
failed thermocouple patterns are not found, it is recommended that the General
Electric Company Field Service Representative be consulted.
3. Collapsed Liner
B Fuel System
1. Break in Liquid Fuel Line
C Fuel Nozzle
1. Plugged Fuel Nozzle (Liquid or Gas)
2. Blown Gasket
WARNING
KEEP PERSONNEL AWAY FROM THE VICINITY OF THE
TURBINE AND ACCESSORY COMPARTMENTS UNTIL THE
PROBLEM HAS BEEN IDENTIFIED.
1. Look for abnormal smoke from the exhaust. Trip the turbine if abnormal smoke is observed.
CAUTION
During the troubleshooting period, watch the display of temperature spread closely
and trip the turbine in the event of a continuous or sudden increase.
2. Read and record the exhaust thermocouple temperatures using the display and the printer.
Proceed with the trouble shooting investigation to locate the problem. Perform the following steps:
7. If no evidence is discovered in (6), start the turbine in the crank position (unfired). Inspect the
turbine compartment for leaks or damage.
8. If no evidence is discovered in (7), fire the turbine and hold in a warm-up condition (do not permit
acceleration). Watch for an abnormal smoke condition from the exhaust.
TRIP THE TURBINE IF ABNORMAL SMOKE IS OBSERVED. This fired condition, while the
turbine is at low pressure, will permit personnel to read and record the individual fuel nozzle pressure
readings in the accessory compartment on liquid fuel fired gas turbines.
9. If an abnormal condition is observed, trip the turbine and take corrective action.
10. If no abnormal condition can be discovered at this point, the turbine should be shut down and a
combustion inspection performed. FURTHER ATTEMPTS AT DIAGNOSIS BY OPERATING THE
MACHINE ARE NOT RECOMMENDED.
11. Preliminary disassembly of the combustor end cover will permit inspection of the combustion
liner, a portion of the transition piece, the fuel nozzles and the crossfire tubes. The extent of the
inspection must be dictated by the nature of the problem.
12. The problem area discovered during the combustion inspection should be corrected and the
turbine should be returned to normal operation.
2. Combustion Alarm. Thermocouples show combustion alarm pattern, and the thermocouples have not
failed.
3. Thermocouple Alarm, Combustion Alarm and Trip. Trip pattern, and thermocouples have not failed.
4. Combustion Alarm and Trip. Trip pattern exists and thermocouples have not failed.
1. It is likely that an abnormal condition exists within the turbine and corrective action should be initiated.
3. Perform a combustion inspection. Inspect all combustor hardware including the transition piece for
signs of damage. Replace the damaged hardware and return the turbine to normal operation.
2. Open the turbine compartment doors and keep all personnel away from line-of-sight of the turbine
compartment.
3. Proceed with a normal start. If an abnormal smoke condition is observed from the exhaust stack, trip the
turbine and proceed with a complete combustion inspection of the liner, transition pieces, crossfire tubes
and fuel nozzles.
4. If no further alarms are noted by FSNL (full speed, no load), proceed with a normal loading procedure
and observe the temperature spread reading and exhaust smoke.
5. Any further trips due to the combustion monitor indicates an unsatisfactory condition, and a complete
combustion system inspection should be performed.
4.6.3 SYNCHRONIZING
Automatic synchronizing is accomplished using a microprocessor synchronizing circuit. The circuit inputs
are transmitted through an interface module. The interface module contains an isolation transformer for the
generator and line input signals and the breaker closing relay. The synchronizing software is part of the
SPEEDTRONIC Panel.
For synchronizing, the unit is brought to 100.3% of rated speed. If the system frequency has varied enough to
cause an unacceptably high slip frequency a speed matching circuit in the synchronizer will adjust the turbine
governor to reduce the slip frequency and permit synchronizing.
For added protection a synchronism check relay is provided. It is used in series with both the auto
synchronizing relay and the manual breaker close switch to prevent large out-of-phase breaker closures.
Once IPC is established, the DCS turns off the ‘‘Temp Match (ON/OFF)” signal, which will restore the IGVs
to the minimum position during a cold start. Once the exhaust temperature is matched and the IGVs are in
position the Speedtronic sends a ‘‘Temp Match Completed” signal to the DCS. At this point the unit is ready
for loading to proceed.
As the High Pressure Bypass (HPBP) becomes fully shut, the DCS sends a ‘‘Select IPC” signal to the
Speedtronic. The MCV transfer to IPC is then completed and the Speedtronic responds with an ‘‘On IPC
Status” signal to the DCS. At that point the DCS will complete the IP CRH admission valve transfer to
pressure control and close the IP bypass valve. The IP CRH admission valve is allowed to begin opening at
the same time as the MCV. When the MCV and IP CRH admission valves are in pressure control, IPC is
established and temperature matching may be turned off.
The DCS will control the transfer from auxiliary Low Pressure (LP) steam to HRSG LP steam by opening the
HRSG LP steam by opening the HRSG LP superheater shutoff. The LPBP valve closes down under pressure
control when this happens. When all three bypass valves are shut and all three admission valves are in
pressure control, the unit is in full combined cycle operating mode.
A Automatic Loading
The unit may be loaded automatically to either a preselected load or to base load. The preselected load
setpoint must be entered by the operator at the Speedtronic panel or DCS and will remain the setpoint until
another is entered. Base load is established by the turbine exhaust temperature control limit.
1. Preselected Load — This load is selected by giving the unit a second start signal after it is at spinning
reserve.
2. Load Limit — The load is not selectable but is an output protection beyond which the unit is not
permitted to operate. It is normally the material limit for the generator.
B Manual Load
The operator may increase or decrease load between no-load and base temperature control line. The
loading is accomplished by raising or lowering the digital setpoint.
4.7 OVER SPEED PROTECTION
4.7.1 General
The SPEEDTRONIC™ electronic overspeed system is designed to protect the gas turbine against possible
damage caused by overspeeding of the turbine shaft. Under normal operation, the speed of this shaft is under
the control of the speed loop, or temperature loop. This overspeed system would not be called on except after
the failure of these other systems.
The overspeed protection system consists of a primary electronic system and a secondary electronic system.
The primary electronic overspeed protection system is incorporated as part of the normal control system and
consists of magnetic pickups to sense turbine speed, speed detection software and associated logic circuits.
The level setting is made by adjustable constants. The secondary electronic overspeed protection system is
built into a separate module <P> in the SPEEDTRONIC™ panel. It is a triple redundant system. The speed
setting is set by <P> hardware and checked by the control system software. The fuel stop valve solenoids are
tripled directly with relays separate from the control system relays in <RST>.
The secondary electronic overspeed protection system is built into a separate module <P> in the
SPEEDTRONIC™ panel. It is a triple redundant system. The speed setting is set by hardware and checked
by the control system software. The fuel stop valve solenoids are tripled directly with relays separate from
the control system relays in <RST>.
A composite block diagram showing all components interconnected for overspeed protection, is shown in
Figure 1.
During test of the secondary electronic overspeed protection system, the primary electronic overspeed
setpoint is switched to a test setpoint (TNKHOST) to set the electronic overspeed trip speed slightly above
the mechanical overspeed trip speed setpoint.
The secondary overspeed protection system function is performed in a separate module within the
SPEEDTRONIC™ panel called the protection module <P> as diagrammed in Figure 1. This function
operates directly on the ETR relays. The magnetic pickup sensors (77HT-1, 2 and 3) are compared to the berg
jumper setpoints. When the turbine speed exceeds the berg jumper setpoints, the ETR relay driver de-
energizes the fuel stop valve solenoid.