2.1 Protection Development Branch: Industrial Training Report
2.1 Protection Development Branch: Industrial Training Report
2.1 Protection Development Branch: Industrial Training Report
2.1.1 Introduction
According to the schedule which was given by the Training Centre of Ceylon Electricity Board I
was appointed to the Protection Development Branch at Dematagoda for one week. This branch
stands for develop and monitor the protection system of the transmission network of CEB. This
branch is controlled by the Chief Engineer Mr.N.S.Wettasinghe and several Electrical Engineers
work under him. In the first day at the Protection Development Branch I gained a basic
knowledge about protection methods of transmission lines.
Tripping Time
Distance Protection
Distance of a transmission line is fixed and determined at the time commissioning. It remains
constant under all system conditions. Hence measurement of distance of a transmission line
is a good concept. If the distance measured is less than the “known”, that indicates a faulty
condition. If it is more than the “known” it indicates a healthy condition. In this method an
impedance relay is set to operate when the impedance measured is less than the preset value.
2.2.1 Introduction
Asset Management branch of CEB is situated in Kandy and it stands to handle and monitor the
protection of the generators of all CEB owned hydro power stations in Sri Lanka. Most of the
repairs and tests of protection equipments of the generators and relays are done in this branch.
This branch is supervised by a Deputy General Manager and I trained under the Chief Engineer
Mr. Tennakoon for one week.
2.3.1 Introduction
According to my schedule I was appointed to the Transmission Operation and Maintenance
Branch at Dematagoda in my third week of training. Chief Engineer of that branch assigns me to
train at Sapugaskanda Grid Substation for one week. Sapugaskanda grid substation is situated
near Kiribathgoda and it is supervised by an Electrical Superintendent. Four 132kV transmission
lines come to the substation from Biyagama and Kelanitissa while eleven feeders go out. This
substation consists of four 132kV/33kV power transformers and a Gas Insulated Switching (GIS)
system. Although it has 4 transformers 3 of them had been burnt and the total load was delivered
through one transformer which was running under full load when I arrived there. And there was
a newly installed transformer which had to be commissioned.
When I reached the substation the final oil filling process under vacuum of the transformer was
being performed. In the following days several tests of commissioning the transformer were
carried out. And I was also able to involve and observe Insulation resistance test, Polarity test
(Vector group), Ratio test, Short circuit test and Thermometer test which were done for the new
transformer.
The polarization index should be greater than 2 of a transformer which has a good insulation
level.
2.4.1 Introduction
Generation Planning Branch of CEB is situated in the CEB Head office building. This branch is
supervised by a DGM and I trained under the Electrical Engineer Mr.Anuradha for one week.
The major task done by this branch is planning the future electricity generation system of the
country in order to meet the future electricity demand. When planning this system primarily the
capability of the existing generating system is assessed. Then analyze whether it can meet the
energy demand in future. If the existing system fails to do that a candidate system should be
prepared to satisfy the demand. Details and costs of candidate thermal and hydro plants which
are to be considered for system addition are obtained from various pre-feasibility and feasibility
studies commissioned by the CEB in the recent past. Every year this branch publishes a Long
Term Generation Expansion Plan (LTGEP) for 10 years and I was able to study the LTGEP
2009-2022 plan when I was there.
2.5.1 Introduction
Transmission Planning Branch of CEB is situated in the CEB Head office building. This branch
is supervised by a DGM and I trained under the Electrical Engineer Mr.Priyadarshana for one
week. The major task done by this branch is designing of grid substation and transmission lines
according to the upcoming generation plans. Every year this branch publishes a Long Term
Transmission Development Plan for a time period of 8 years. This plan is prepared by analyzing
the Long Term Generation Expansion Plan, National Demand Forecast and Regional medium
voltage distribution plan. Preparing tender documents and shifting of transmission lines when
required are also functions of this branch. A schematic representation of the transmission process
is provided in the Annex A8,2,5,1.
2.6.1 Introduction
Sapugaskanda Deisel Power Station is supervised by its Chief Engineer and I trained under him
for one week.First stage of the Sapugaskanda Diesel Power Station was implemented in 1984
with four 20MW diesel generators. First expansion of the plant has been commissioned in 1998
with another four 10MW diesel generators. In the second expansion of the Sapugaskanda Diesel
Power Station four additional 10-MW diesel generator sets were installed, and commissioned in
1999 increasing the installed capacity from 120 MW to 160 MW. When I was there I was able to
obtain a fair knowledge about the process of generating power in the power plant.
2.7.1 Introduction
Kotmale Power Station is Supervised by its Chief Engineer and I trained under 4 Electrical
Engineers for one week. The Kotmale project was one of the first projects taken up under the
development of Mahaweli Complex. The Kotmale project was started with the construction of an
87 m high Rockfill dam across the Kotmale Oya. The water stored in the reservoir is conveyed
through an underground tunnel system to an underground power station situated in the belly of
the Atabage Mountains at about 7.2 km away from the dam for generation of electric power.
After power generation, this water is discharged through the outfall into the mahaweli ganga at
the Atabaghe Oya confluence.
Kotmale Power Station was commissioned in 1986 with three 67MW generators and still it
contributes about 445 GWh of power to the national grid annually. The underground power
station the power station consists of 3 vertical francis turbines which have the ratings of 67MW
at 201.5m head and at the speed of 375 rpm. Unlike the other power plants the power house,
administration office and the control room of Kotmale Power Station are located in 3 places far
apart from each other. Power house which contains turbines and generators are located
underground and there is a separate tunnel to enter that. The Administration building is situated
near that tunnel entrance while the Control room and the switch yard is situated top of the
Atabage Mountain.
2.8.1 Introduction
System Control Centre of CEB is situated in Dematagoda and it is supervised by a DGM. During
the one week period at there I trained under the Chief Engineer of that branch. Main task done by
this division is balancing the power generation and demand in the country to maintaining a high
quality power supply. It is done by controlling the output of all the generators in power plants by
communicating with the power plants. System Control Centre maintains a direct connection with
all the major electrical power generating stations via power line carrier system.
As well as this branch is responsible for the coordination and operation of the 220kV and 132kV
transmission network. The operation of the transmission system is planned by the System
Control Branch when an interruption is required in transmission lines.
System Voltage
As Normal Under emergency
220 kV ( ± 5% ) 220 kV ( + 5% or – 10% )
132 kV ( ± 10% ) 132 kV ( ± 10% )
33 kV ( ± 2% )
System Frequency
The statutory frequency limit is 50 Hz ±1%.
Spinning Reserve
Spinning Reserve Margin to be not less than 5% of gross generation.