Tjc-Itp-Cwp-040506-L-2090
Tjc-Itp-Cwp-040506-L-2090
Tjc-Itp-Cwp-040506-L-2090
CONTENTS
STRUCTURAL WORKS
INSTALLATION OF FEED TUBE REFRACTORY LINING
DOC. NO: W-TJC-C3101-QAC-146- CWP-040506-L-2090 FURNACE#4 MAJOR REBUILD
PROJECT NAME : ELECTRIC FURNACE # 4 REBUILD MAIN CONSTRUCTION REFERENCES : Scope of work, Drawing, Site queries, PT. VALE Spec ,
OWNER : PT. Vale Indonesia - Sorowako
CLIENT : PT. Vale Indonesia - Sorowako
TJC JOB NO. : C-3101
DESCRIPTION : INSTALLATION OF FEED TUBE REFRACTORY LINING
II ABBREVIATIONS
AWS AMERICAN WELDING SOCIETY NCR NON CONFORMANCE REPORT RT RADIOGRAPHY TEST
ASTM AMERICAN SOCIETY TESTING OF MATERIAL RFI REQUEST FOR INFORMATION UT ULTRASONIC TEST
DIN DEUTCHES INSTITUT FUR NORMUNG MDR MANUFACTURER'S DATA REPORT PT PENETRANT TEST
WPS WELD PROCEDURE SPECIFICATION NDT NON DESTRUCTIVE TESTING MT MAGNETIC PART. TEST
PQR PROCEDURE QUALIFICATION RECORD PWHT POST WELD HEAT TREATMENT
WQTR WELDER QUALIFICATION TEST RECORD Proc. PROCEDURE
N/A NOT APPLICABLE
III REMARKS
1) Ref. Approval Section of Document.
a : Where there is a Subcontractor element, the Subcontractor involved will sign the approval of the activity.
b : Where there is no Subcontractor element, TJC will sign approval of activity and present to the Client.
2) Inspection and Test Plan (ITP) Status
It is to be understood that the Inspection and Test Plan forms an integeral part of the control/verification documentation.
However, where no other documents are required or exit " The Inspection and Test Plan " only will be understood to be
the control/verification document.
Page 3 of 6
REV. NO :
INSPECTION & TEST PLAN (ITP)
DATE : August, 9 2021
PROJECT NAME : ELECTRIC FURNACE # 4 REBUILD MAIN CONSTRUCTION REFERENCES :Scope of work, Drawing, Site queries, PT. VALE Spec ,
JOB NO : C-3101
1 Documentation Specification
Material Receiving
4 Verified BOM
Inspection & Storage
BOM, Mill certificate,
Material Receiving Correct as per BOM/
Mill Certificate Code/Standard, Mat’l QC,WH/MC H H, R & A
Inspection Report drawing
spec.
Packing list, etc.
Material Receiving
5 Inspection & Storage (if Verified BOM
supply by TJC) BOM, Mill certificate,
Material Receiving Correct as per BOM/
Code/Standard, Mat’l QC,WH/MC H H, R & A
Mill Certificate Inspection Report drawing
spec.
Inspection Activities
Inspection / Test Activities Verifying
Reference Acceptance Depart.
No Documents /
Process Operation/ Documents Criteria Involve TJC/or Subcon Vale/Client
Characteristic Reports*
Description
II General Works
1 Civil Works
1 Pre-Shutdown Work
Identify each of the feed tubes and Drawing, Scope of Work, Mechanical Checklist Correct as per
Cons., M M
check the dimensions. Site Query/CWP Report drawing/site query
Inspection Activities
Inspection / Test Activities Verifying
Reference Acceptance Depart.
No Documents /
Process Operation/ Documents Criteria Involve TJC/or Subcon Vale/Client
Characteristic Reports*
Description
Level the feed tube section so the top Drawing, Scope of Work, Correct as per
Inspection Report Cons.,QC W&R SW, R & A
flange is in the horizontal Site Query/CWP drawing/site query
position and install castable refractory
into the feed tube sections through one
continuous pour.
Dry out the feed tube sections as per Drawing, Scope of Work, Mechanical Checklist Correct as per
Cons.,QC W&R SW, R & A
the castable manufacturers dry Site Query/CWP Report drawing/site query
out schedule to remove all of the free
water and the majority of the
combined water.
2 Shutdown Work
Final
Pre-Handover Activities Scope of work, Inspection(inclu
IV Task completed Punch list Completed work
(Start up & Commisioning) Drawing ding as built
drawing)
W&R W, R & A
Page 6 of 6
Inspection Activities
Inspection / Test Activities Verifying
Reference Acceptance Depart.
No Documents /
Process Operation/ Documents Criteria Involve TJC/or Subcon Vale/Client
Characteristic Reports*
Description
W&R W, R & A
Up date all
records Review
for Compliance
forward to PM
Notes: * All Inspection Report/Checklist will be issued base on the Section II - Steel Structutal Works item (Civil/Structural Works) unless otherwise specified.