L2A.RIF.50 Clean-Agent System
L2A.RIF.50 Clean-Agent System
L2A.RIF.50 Clean-Agent System
LEVEL 2A
LEVEL 2A COMMISSIONING FORM
Record the equipment tag, manufacturer, ratings, attributes and note any additional arrangement details or spare parts received in the comments section C.
Complete the checklist below once the equipment is fixed in its final position.
EQUIPMENT TAG:
Power Rating kW
Ensure that the discharge nozzle and orifice unit have been installed in the accordance with
4
calculation and node diagram.
5 Actuation hose and discharge hose are rigidly fitted.
Check the cylinder guage to confirm that the pressure in the cylinder are in the acceptable
6
range.
7 The leak test of the piping has been complete and accepted
9 Check the cable termination of the all fire alarm and detection system.
C COMMENTS, DEFICIENCIES
Record any defect or deficiency of the equipment below to be notified to the manufacturer, GC coordinator or Construction Manager
Record any issues and resolutions on the construction snag list for tracking and close out
Additional Comments Below: