Item Description Unit Quantity Material Unit Cost Total Material Cost Labor Unit Cost Total Labor Cost Total Cost
A. General Requirements:
1 Mobilization/Demobilization lot 1.00 50,000.00
2 Project Supervision Expenses lot 1.00 50,000.00
3
4
5
6
7
B Earth Works & Site preparation
1 Clearing lot 1.00 600.00 12,000.00 12,000.00
2 Excavation Works lot 1.00 600.00 12,000.00 12,000.00
3
4
5
C. Foundation Works
1 Rebar fabrication lot 1.00 432,000.00 64,000.00 496,000.00
2 Rebar Installation lot 1.00 20,000.00 48,000.00 68,000.00
3 Form Works lot 1.00 67,000.00 36,000.00 103,000.00
4 Concreting lot 1.00 225,000.00 50,400.00 275,400.00
5
D. Structural Steel Works
1 Layout lot 1.00 22,000.00 22,000.00
2 Rolling & Bending lot 1.00 963,200.00 45,000.00 1,008,200.00
3 Fit Up/ Assembly lot 1.00 120,000.00 120,000.00
4 Welding Works lot 1.00 63,000.00 98,000.00 161,000.00
5 Fabrication (others) lot 1.00 30,320.00 56,000.00 86,320.00
E. Others (Miscellaneous)
1 Equipment Rental (Tank Mobilization from Metalite to RBC Bukidnon) lot 1.00 - - 45,000.00
2 Equipment Rental (Tank Installation Works) lot 1.00 - - 65,000.00
3 Rehabilitation of Tank (Painting Works) lot 1.00 30,000.00
4 Testing and Commissioning lot 1.00 - - 32,122.00