Alarape
Alarape
Alarape
ON
STUDENT INDUSTRIAL WORK EXPERIENCE SCHEME (SIWES)
AT
PREPARED BY:
MATRICULATION NUMBER:
2022703020023
SUBMITTED TO:
IN BUILDING TECHNOLOGY
NOVEMBER, 2023
Table Of Contents
CERTIFICATION ....................................................................................... 3
APPROVAL PAGE ...................................................................................... 4
CHAPTER ONE ......................................................................................... 5
1.1 OBJECTIVES ...................................................................................... 6
1.2 BODIES INVOLVED IN THE MANAGEMENT OF SIWES................................. 7
1.3 BACKGROUND OF ESTABLISHMENT........................................................ 9
CHAPTER 2 ........................................................................................... 10
2.0 WORK EXPERIENCE DURING ATTACHMENT............................................ 10
CHAPTER THREE .................................................................................... 11
3.0 INTRODUCTION TO SITE MATERIALS EQUIPMENTS AND MACHINERIES. ..... 11
CHAPTER FOUR ...................................................................................... 19
4.0 PROBLEMS ENCOUNTERED DURING ATTACHMENT. ................................ 19
CONCLUSION ........................................................................................ 19
RECOMMENDATION ................................................................................ 21
REFRENCES........................................................................................... 23
CERTIFICATION
This is to clarify that the work during the four months industrial
Held at Ozeent Nigeria Limited, Shop 3/4 Kajola street Igbo Oloyin ,
training.
INTRODUCTION
BACKGROUND
1.1 OBJECTIVES
institutions
2002)
institutions
⚫ Supervise student at their places of attachment and sign their log
staff.
1.3 BACKGROUND OF ESTABLISHMENT
within the frame work of an approve master plan, the Unit prepares
development activities .
With its professional staff , the company reviews building stock and
building. They are the Arts-type of building and the Science and
buildings from the scratch which includes: site clearing, setting out,
setting out and digging of the septic and soak away tank, and also
the casting of slab cover for septic tank, block setting of the
activities and work progress carried out on site, and also to execute
MACHINERIES.
MATERIALS
follows ;
of pipes to rotary kiln which dry and burn the constituent in higher
This process changes the slurry to hard lumps called clinker, which
general purposes. There are other types of cement made for special
Fine aggregate; this should be clean, sharp and passes through the
1. Tape
2. Masonry Trowel
the work.
3. Head Pan
Materials
4. Plumb Bob
5. Digger
6. Wooden Float
7. Spade
8. Concrete Mixer
10. Drill
basic materials namely cement, the fine and coarse aggregates and
draught which can introduce moist air and cause air set of the
material. Cement should not be stored on the site for long period of
materials as follows.
mixer
The mode of transportation used was the manual method with the
movements.
(lubricant) was applied after the form-work was blown off of dust.
it a unit mass by eliminating voids within it. The method and type of
concrete.
moisture in the concrete. The concrete was watered 7days with use
material produced .
SETTING OUT
Refers to the act of measuring and marking out a full size plan of a
the weight of the structure (live,dead and other loads) to the earth.
BLOCKWORK
The walling system was mostly carried out using sand-crete hollow
The 6 inches blocks were used mostly for internal walls while the
9inches blocks were used in load bearing areas and external walling.
Bond; which is when the stretcher faces of the blocks appear on the
LINTELS
which supports the weight above it and transmits such weight of the
wooden mould while the cast in-situ lintel was used for the
the land.
CONCLUSION
effectively.
adequate social amenities for their workers and enhance the welfare
of their workers.
6. The management of Ozeent Nigeria Limited should try to
Grreno.
edition).