DIN GARDEN HOUSING SCHEME

SAHIANWALA, FAISALABAD

ESTIMATE FOR BOX CULVERT (01 NO) AT ROAD E-1 ADJACENT D-2 (40'-00'' LENGTH)

Sr.
Description Unit Qty. Rate Amount (Rs).
No.

1 Excavation Cft 3,658.20 5.00 18,291

2 P.C.C (1:4:8) Cft 245.42 245.00 60,127

3 R.C.C (1:2:4) Cft 1,024.72 360.00 368,899

4 R.C.C (1:1.5:3) Cft 740.00 450.00 333,000

5 PVC Water Stopper 8'' Rft 204.67 230.00 47,074

6 4" Dia PVC Pipe Rft 4.32 137.00 592

7 Steel Grade (Amreli Steel) Kg 5,161.87 285.00 1,471,134

Formwork with Steel Plate Folding Joint


8 Sft 875.00 115.00 100,625
Complete with all respects.

9 Manhole Grating LS 1.00 4,000.00 4,000

R.C.C Pipe 18'' for the purpose of Culvert


10 LS 1.00 15,000 15,000
Diversion Cost

Total Amount (Rs). 2,418,742

Quantity Surveyor Project Manager


M Jamal Abbas Jahangir Kamran
Din Garden Fsd Din Garden Fsd

Page 1 of 7
DIN GARDEN FAISALABAD

MEASUREMENT SHEET
BOX CULVERT (01) AT ROAD E-1 ADJACENT ROAD D-2 (SIZE 1X (40'x3'x4')

Length Width Height


Sr. No. Description Unit No. Quantity Remarks
(Ft) (Ft) (Ft)

1 Excavation

Box Culvert Cft 1 40.000 8.000 4.000 1,280.00

Wing Walls Cft 4 11.250 12.917 4.000 2,325.00

Apron Wall 01 (Culvert) Cft 1 5.000 1.330 4.000 26.60

Apron Wall 02 (Apron) Cft 1 5.000 1.330 4.000 26.60

Total = 3,658.200

2 Lean Concrete (1:4:8)

Box Culvert Bed Cft 1 40.000 5.667 0.333 75.56

W/Wall Base Slab Cft 4 11.250 9.917 0.333 148.75

Apron Cft 1 10.000 5.000 0.333 16.67

Apron Wall 01 (Culvert) Cft 1 5.000 1.333 0.333 2.22

Apron Wall 02 (Apron) Cft 1 5.000 1.333 0.333 2.22

Total = 245.417

3 RCC Concrete (1:2:4)

Wing Walls

Straight portion (V) Cft 4 11.167 1.042 12.617 587.06

Base Slab Cft 2 11.167 9.250 1.500 309.88

Apron Cft 2 10.000 5.000 0.500 50.00

Apron Wall 01 (Culvert) Cft 2 5.000 0.667 4.000 26.67

Apron Wall 02 (Apron) Cft 1 5.000 0.667 4.833 16.11

Head Wall Cft 2 5.000 1.000 3.500 35.00

Total = 1,024.721

4 RCC Concrete (1:1.5:3)

Top Slab Cft 1 40.000 5.000 1.000 200.00

Bottom Slab Cft 1 40.000 5.000 1.000 200.00

Walls Cft 2 40.000 1.000 4.000 320.00

Chamfer (6"x6") Upper Cft 2 40.000 Area (Sft)= 0.125 10.00

Chamfer (6"x6") Lower Cft 2 40.000 Area (Sft)= 0.125 10.00

Total = 740.000

Page 2 of 7
DIN GARDEN FAISALABAD

MEASUREMENT SHEET
BOX CULVERT (01) AT ROAD E-1 ADJACENT ROAD D-2 (SIZE 1X (40'x3'x4')

Length Width Height


Sr. No. Description Unit No. Quantity Remarks
(Ft) (Ft) (Ft)

5 PVC Water Stopper 8"

Drain Box Rft 4 40.000 160.00

Wing Walls Rft 4 11.167 44.67

Total = 204.668

7 4" Dia PVC Pipe

for Wing Wall Weep Rft 4 1.080 4.32

Total = 4.32

8 Steel Grade 60

Box Culvert Kg 3032.857

Apron & Apron Walls Kg 194.192

Head Wall Kg 232.431

Wing Walls Kg 1702.395

Total = 5,161.874