Power Plant Operation Turbine & Auxiliaries: 18 February 2013 PMI Revision 00 1
Power Plant Operation Turbine & Auxiliaries: 18 February 2013 PMI Revision 00 1
Power Plant Operation Turbine & Auxiliaries: 18 February 2013 PMI Revision 00 1
Presentation outline
CEP Starting
BFP Starting
VACUUM PULLING
18 February 2013
PMI Revision 00
CEP
For starting first CEP Checks at LOCAL No maintenance staff is working. CEP suction valves are OPEN. Hot well level is ADEQUATE Bearing temperature of CEPs is NOT HIGH 60 0 C. Condensate pump gland sealing water isolating valve is OPEN. Condensate pump priming (pressure equalizing) valve is OPEN. CEP bearing cooling water line isolating valve is OPEN. CEP bearing oil level is adequate. Emergency push button is released. ENSURE condensate system is lined up before starting CEP. Main ejectors inlet/outlet- valves are OPEN & Bypass valve is closed. Gland steam cooler inlet/outlet valves are open and bypass valve is CLOSED. LPHs (1-2-3) inlet/outlet valves are CLOSED. LPHs (1-2-3) bypass valves are OPEN. LPHs are bypassed initially to minimise corrosion.
18 February 2013 PMI Revision 00 3
18 February 2013
PMI Revision 00
CEP
START the CEP motor. CEP starting current comes down to 20A after 5 sec. CEP discharge pressure increases to 25 Kg/cm2. Approx. CEP's discharge valves open 100%. CLOSE the air vents on condensate lines. LOAD the condensate pump by opening V/V on condensate to D/A line. INSTRUCT the local operator to check bearing temperatures and vibrations. CHECK that the second condensate pump is ready for starting and is available on STANDBY. Breaker control switch is on Normal Pump OK standby - All permissive are SATISFIED. All local line ups are COMPLETE
18 February 2013
PMI Revision 00
CEP
For starting first CEP Checks at UCB CHECK if all start permissive for starting CEP is satisfied. Hot well level is ADEQUATE (UCB Indicator). Bearing temperature of CEPs is NOT HIGH 60 0 C.) UCB indications. CEP re-circulation valve is OPEN. Hotwell level controller output is zero. CEP electrical supply is AVAILABLE. Deaerator inlet valve is OPEN. CEP header vents and line vents OPEN. HW level controller, DA level controller and cycle make-up controller valves are CLOSED. Bypass valves of HW, DA and cycle make-up controllers are also CLOSED. Local operator intimated prior to starting of pump.
PMI Revision 00 6
18 February 2013
18 February 2013
PMI Revision 00
10
VACUUM PULLING
CHECK before starting vacuum pulling operation. Auxiliary steam header charged and its pressure ADEQUATE. Ejector PRDS is CHARGED and Ejector steam pressure is ADEQUATE ( 7.5 Kg/cm2) At least one condensate pump is ON. Main ejectors and GSC CHARGED from the waterside. Condenser air valve air valves to main ejectors are OPEN.
18 February 2013
PMI Revision 00
13
VACUUM PULLING
CHECK before starting vacuum pulling operation.
Surge tank level ADEQUATE. Condenser siphon filling COMPLETED. Condenser vacuum breaker valve must be CLOSED. Water sealing done. Condenser inlet & outlet valves are CLOSED. Steam line drains to flash tank, are CLOSED MOT level is NORMAL and "MOT level low" alarm is RESET. At least one MOT vapour extractor fan is ON. Generator hydrogen pressure must be 3.5 Kg/cm2. Generator hydrogen purity > 97%.
18 February 2013 PMI Revision 00 14
VACUUM PULLING
CHECK before starting vacuum pulling operation.
Hydrogen seal oil pressure should be more than 4.8 Kg/cm2. Seal oil to hydrogen DP is ADEQUATE, 1.2-1.5 kg/cm2. START AOP and one JOP. "Control oil pressure low" and "Lub. Oil pressure low" alarms get cleared off. Control oil pressure increases to 6.8 Kg/cm2. Jack oil pressure increases up to 130 Kg/cm2. "Jacking oil pressure low" alarm clears off.
18 February 2013 PMI Revision 00 15
VACUUM PULLING
SWITCH-ON SLCs of AOPs, JOPs, EOP, Gate valve gearing and the Lub. Oil temp controller. Turbine starts barring at 110 rpm approximately. Lub oil temperature controller modulates to maintain set lub oil temperature. CHARGE condenser priming ejector from steam & airside. Condenser water box priming initiated. INSTRUCT local operator to start one CW pump and CHARGE both condensers 50 % approx., to curb CW power consumption. CW header pressure increases, slightly. Condenser inlet & outlet valves are partially opened. Condenser flow starts increasing.
18 February 2013 PMI Revision 00 16
VACUUM PULLING
CUTOUT the priming ejector after CW water starts coming from the air vents of priming ejector. Priming ejector's steam airside valves are closed. OPEN seal steam line and header drains & CHARGE gland sealing steam into the turbine glands. Gland seal steam control opens up and gland steam header pressure starts increasing. TRANSFER seal steam control to auto. CHARGE starting ejector by opening ejectors steam supply & air suction valve. Condenser vacuum starts increasing to 0.7 Kg/cm2. OPEN steam supply valve to any one main ejector as per desired vacuum. Vacuum builds up to 0.92 Kg/cm2 i.e 72 mm Hg (approx) Turbine barring speed increases up to 220-RPM approx. "Condenser vacuum low" alarm gets cleared off.
18 February 2013 PMI Revision 00 17
VACUUM PULLING
ISOLATE starting ejector by closing air suction valve first and then steam supply valve. MAINTAIN rated condenser vacuum of 73 mm Hg (back pressure) Condenser vacuum is maintained at 0.92 Kg/cm2.
18 February 2013
PMI Revision 00
18
18 February 2013
18 February 2013
PMI Revision 00
20
ADJUST main steam pressure set point to obtain desired MS pressure. HP bypass valves open or close, depending on whether set point is less or more than the MS pressure respectively.
18 February 2013
PMI Revision 00
21
18 February 2013
PMI Revision 00
22
50KSC 350C
60 KSC 400C
85KSC 485C
SOAKING TIME
LOAD GRADIENT
18 February 2013
1HR
5MW/MIN
PMI Revision 00
15 MIN
10MW/MIN
10 MIN
15MW/M
23
TURBINE START- UP
CHECK that all the turbo-Supervisory instrumentations are functional. All UCB indicators and recorders are functional and healthy. All recorders are inked and all instruments are calibrated. CHECKS before starting the turbine run-up Electro-hydraulic controller for turbine is ON. EHC isolating valves on sec oil lines to control valves are open. Electro-hydraulic controller's output is zero. "EHC control fault" and "EHC Plunger coil off" alarms do not appear in the UCB. Speed reference set point for the Speed Controller is zero or less than the barring speed.
18 February 2013 PMI Revision 00 24
TURBINE START- UP
Load reference set point for the Load Controller and the load limiter output are zero. Speeder gear position is 100%. Starting device is at 0% position. The alarms "TSE influence off" "Turbine stress effects off" and "Turbine stress cubicle fault" are not on. TSE influence is ON. Unit trip relay (A & B) are in RESET condition "Turbine Trip" and "Turbine Trip gear operated" alarms are not on and Trip oil pressure > 5 Kg/cm2 All differential expansions of the turbine are NORMAL and within the alarms values.
18 February 2013 PMI Revision 00 25
TURBINE START- UP
Alarm Trip HPT IPT LPT
+4.5mm -2.5mm +5.0mm -2.0mm +25 mm - 5 mm +5.5mm -3.5mm +6.0mm -3.0mm +30 mm - 7mm
Condenser vacuum is NORMAL. 0.92 Kg/cm2 approx. Turbine SLC Drains is ON and NOT FAULTED. "SLC Drains fault" Alarm is not ON. Turbine stop valves (ESV-1&2, IV-1&2). Control valves (HPCV-1&2), IPCV1&2). Extraction block valves (ES-1,2,3,7,5,6) are CLOSED. Extraction NRV's (A2, A3,A4, A5) and CRH line NRV's L/R are CLOSED. The turbine is on BARRING and there is no abnormal sound from the turbine & bearings. The Speed of rotation of shaft is between 200 and 220 rpm. Turbine "Control oil pressure" is greater than 5 Kg/cm2 Turbine lub oil temperature after coolers is normal i.e. 45oC. Lub oil pr. is normal at 3.5 Kg/cm2 before coolers. Main oil tank level is NORMAL. 18 February 2013 Thrust bearing oil filters are NOT CHOKED. PMI Revision 00 26
TURBINE START- UP
CHECK that the entire turbine MS strainer drains CRH drains HRH strainer drains and ESV & IV before seat drains are open. CHECK that the generator seal oil and stator water system are in service and healthy Generator hydrogen pressure is NORMAL, more than 3 Kg/cm2 Seal oil pressure (turbine and exciter side) is more than 4.8 Kg/cm2 Seal oil to hydrogen DP is NORMAL (1.2 Kg/cm2) Stator water flow is more than 23 m3/Hr. Stator water specific conductivity is less than 1 micro mho/cm. Stator water pressure is NORMAL. (2.8 Kg/cm2) Generator and field breakers are in RESET condition.
18 February 2013
PMI Revision 00
27
TURBINE START- UP
TURBINE ROLLING PROCEDURE
CHECK turbine startup criteria as determined from the X-curves. Main steam, at the turbine inlet should have minimum of 50 oC superheat. M.S. pressure is 30 KSC approx. & temp. 280oC Criteria for Opening the ESVs. Max/Min. SH steam temp depending upon mid wall temp. of HPCV. (Start-up curves X- 1, X-2 and X-3.) Rolling to warm-up speed of 600 rpm. Max. MS temp depending upon saturated steam temp and mid body temperature of HP casing/ shaft. (Start-up curves X-4 and X- 5.) Rolling up to rated speed of 3000 rpm. Required minimum mean metal temp of H.P Shaft depending upon available MS temp. (Start-up curve X-6) Loading the turbine after synchronisation. Required minimum mean metal temp of IP shaft, depending upon the available HRH steam temp. (Start-up00 18 February 2013 PMI Revision curve X-7) 28
HPCASING X5 CURVE IS HRH TEMP BEFORE LP BYPASS/MIDWALL IP SHAFT X6 CURVE IS MAIN STEAM TEMP BEFORE HP BYPASS/MIDWALL
18 February 2013
PMI Revision 00
29
18 February 2013
PMI Revision 00
30
18 February 2013
PMI Revision 00
31
18 February 2013
PMI Revision 00
32
18 February 2013
PMI Revision 00
33
18 February 2013
PMI Revision 00
34
18 February 2013
PMI Revision 00
35
18 February 2013
PMI Revision 00
36
DESCRIPTION
UNIT
SAT STEAM TEMP. IN DRUM STEAM TEMPERATURE AT LTSH OUTLET STEAM TEMPERATURE AT SH PLATEN OUTLET STEAM TEMPERATURE AT FINAL SH OUTLET STEAM TEMP. AT RH INLET STEAM TEMP. AT RH OUTLET WATER TEMP. AT ECO INLET WATER TEMP. AT ECO OUTLET AMBIENT AIR TEMPERATURE AIR TEMPERATURE AT AH OUTLET (PRI. SIDE) AIR TEMPERATURE AT AH OUTLET (SEC. SIDE)
C C C C C C C C C C C
348 400 510 540 337 540 244 274 35 354 348
C
C C C C C C C
1165
1016 868 753 638 473 379 146
18 February 2013
PMI Revision 00
37
TURBINE ROLLING PROCEDURE Maintain boiler side steam parameters as required for turbine start-up. The MS/HRH temp and pressures are within the determined ranges. HRH steam pressure should not be more than 15 Kg/cm2 during rolling. RAISE starting device to 70% gradually. Start-up oil pr. Falls to 1.8 KSC and HP ESVs (1&2) open 100% at 42% position of starting device. Interceptor stop valves (1&2), open 100% at 56% position of starting device. Start-up oil pre. = 0 at 70% of starting device position. Aux Sec oil pressure increases up to 4 KSC.
18 February 2013 PMI Revision 00 38
18 February 2013
PMI Revision 00
40
THANK YOU
18 February 2013
PMI Revision 00
43