Ruslan Tech Services Clarification Letter
Ruslan Tech Services Clarification Letter
Ruslan Tech Services Clarification Letter
DXB/
M/s. Ruslan Technical services
Dear Sir,
MALEK MONAER
Managing Director
Ruslan Technical Services
PRICE ANALYSIS
please re-check the rates, the rate for floor slab is too low, while
03. Bill No.3 – Concrete
the rate for c/s plaster is too high, please clarify
• The quoted price for this bill is too high. It’s recommended to
07. Bill No. 7 – Electrical works
recheck the price.
Bill No. 8 – Fire Detection & Alarm • The quoted price for this bill is Low. It’s recommended to
08.
System recheck the price.
MALEK MONAER
Managing Director