New Villa Quotation
New Villa Quotation
New Villa Quotation
boq
24,000.00
RCC Concrete
PCC m3 15 600.00 9,000.00
ploythebne sheet LS 1,000.00
RCC FOOTING M3 60 1,300.00 78,000.00
TIE BEAM RM 20 1,300.00 26,000.00
COLUMNS M3 25 1,300.00 32,500.00
slab on grade m3 35 650.00 22,750.00
169,250.00
Slabs 200 m3 1,300.00 260,000.00
Parapet 20 m3 1,200.00 24,000.00
Door Lintel 8.0 m3 1,300.00 10,400.00
Stair Case RCC LS LS 25,000.00 25,000.00
319,400.00
Block Works
Solid block 80 m2 100.00 8,000.00
Thermal block 800 m2 120.00 96,000.00
Normal block 750 m2 85.00 63,750.00
167,750.00
Plaster Works
Internal Plastering 2300 m2 35.00 80,500.00
external Plastering 1200 m2 40.00 48,000.00
128,500.00
tiling Finishing Works
boq
53,450.00
Date: 21/11/2023
boq
715,000.00
Block Works
Normal block 47 m2 80.00 3,780.00
Plaster Works
external Plastering 47 m2 40.00 1,890.00
Painting Works
External wall Paint Work 47 m2 30.00 1,417.50
boq
Discount - 135.00
Final construction amount 261,000.00