FORM #E-002 (5/18/15)

SHT 1 of 2

SAUDI ARAMCO PRE-COMMISSIONING FORM


BLOWERS

EQUIPMENT TYPE:
EQUIPMENT TAG NO.:
BI/JO NO.:
REF. DRAWINGS & DOCUMENTS:
MANUFACTURER:
MODEL NO.:
COMMISSIONING DATE:
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16

17
18
19
20
21
22
23
24
25
26

USER REFERENCE:
DESCRIPTION:
PLANT NO. / LOCATION:
SERIAL NO.:

BASE PLATE CHECKED FOR LEVELING.


BASE PLATE CHECKED FOR GROUTING.
PROTECTIVE FLUID DRAINED OUT.
BEARING OIL FLUSH COMPLETED.
OILERS INSTALLED AND FILLED TO CORRECT LEVEL ( LUBE OIL USED).
COUPLING RUNOUT CHECKED ON ALL COUPLINGS. ( SHOULD BE WITHIN 0.001" )
COUPLING GAP CHECKED IN FOUR POSITIONS. ( SHOULD BE WITHIN 0.002" )
BLOWER AND DRIVER CHECKED FOR FREEDOM OF MOVEMENT.
SOFT FOOT CHECKED ON EACH HOLD DOWN BOLT. ( SHOULD BE WITHIN 0.002" )
COLD ALIGNMENT CHECKED AS PER REQUIRED.
JACKSCREWS REMOVED & FOUNDATION BOLTS TIGHTENED.
THE COLD ALIGNMENT RECHECKED.
SUCTION AND DISCHARGE PIPING CHECKED FOR CLEANLINESS.
PIPE SUPPORTS, SPECIFICALLY SPRING SUPPORTS, CHECKED TO BE WITHIN THE
LOAD RANGE SPECIFIED ON THE PIPING DRAWINGS.
SUCTION STRAINER OR FILTER INSTALLED.
FLANGE BOLT HOLE OFFSETS AND FACE PARALLELISM CHECKED.
- VERTICAL BOLT HOLE OFFSET
:
- HORIZONTAL BOLT HOLE OFFSET
:
- ROTATIONAL OFFSET
:
- FLANGE FACE PARALLELISM :
- FLANGE FACE SEPARATION
:

YES___ NO___
YES___ NO___
YES___ NO___
YES___ NO___
YES___ NO___
YES___ NO___
YES___ NO___
YES___ NO___
YES___ NO___
YES___ NO___
YES___ NO___
YES___ NO___
YES___ NO___
YES___ NO___

ALL PROCESS PIPING CONNECTED TO THE MACHINE AT THE SAME TIME.


( IT IS NOT ACCEPTABLE TO CONNECT ONE PIPE ONE DAY, ANOTHER
THE NEXT DAY, ETC.)
THE MAX MOVEMENT AT THE COUPLING DURING PIPING INSTALLATION IS 0.002".
BLOWER DOWELED TO BASE PLATE.
GROUNDING STRAPS INSTALLED.
DRIVER DIRECTION OF ROTATION CHECKED.
ROTOR FLOATS CHECKED TO BE WITHIN THE MANUFACTURERS TOLERANCES.
COUPLING LUBRICATION AS REQUIRED.
COUPLING HUB FIT ON THE SHAFTS CHECKED FOR DISTANCE PUSHED ONTO THE
SHAFT/ INTERFERENCE AND SQUARENESS TO THE SHAFT. ( FACE RUNOUT )
THE KEYS AND THE KEY WAYS CHECKED FOR THE CORRECT FIT.
MECHANICAL & ELECTRICAL RUNOUT CHECKED AT THE VIBRATION PROBE

YES___ NO___

YES___ NO___
YES___ NO___

YES___ NO___
YES___ NO___
YES___ NO___
YES___ NO___
YES___ NO___
YES___ NO___
YES___ NO___
YES___ NO___
YES___ NO___

NOTE: This non-mandatory form may be used as the starting point to assemble a pre-commissioning checklist.
Entries should be revised, added and deleted and approvals adjusted to reflect the needs of the Project
Acceptance Committee.

APPROVALS
Signature & Date

SAPMT

INSPECTION

CopyrightSaudi Aramco 2009. All rights reserved.

OTHER DEPT.

OPERATIONS

FORM #E-002 (5/18/15)

SHT 2 of 2

SAUDI ARAMCO PRE-COMMISSIONING FORM


BLOWERS

EQUIPMENT TYPE:
EQUIPMENT TAG NO.:
BI/JO NO.:
REF. DRAWINGS & DOCUMENTS:
MANUFACTURER:
MODEL NO.:
COMMISSIONING DATE:
27
_

USER REFERENCE:
DESCRIPTION:
PLANT NO. / LOCATION:
SERIAL NO.:

AREAS INCLUDING THE THRUST PROBES IF FITTED.


COUPLING GUARD INSTALLED.

YES___ NO___

NOTE: This non-mandatory form may be used as the starting point to assemble a pre-commissioning checklist.
Entries should be revised, added and deleted and approvals adjusted to reflect the needs of the Project
Acceptance Committee.

APPROVALS
Signature & Date

SAPMT

INSPECTION

CopyrightSaudi Aramco 2009. All rights reserved.

OTHER DEPT.

OPERATIONS